Schedule settings disclosure
Source file: Ontario_Community_College_current.xer
Project: Georgian College (proj_id 4795)

This disclosure lists the P6 schedule calculation options stored in the SCHEDOPTIONS table of the file named above, so that another analyst can reproduce the schedule calculations with the same settings. Raw stored values are shown in parentheses.

SCHEDOPTIONS for proj_id 4795 (Georgian College)
------------------------------------------------
Schedule calculation method when progressed activities are out of sequence: Retained logic (sched_retained_logic=Y, sched_progress_override=N)
Calendar for scheduling relationship lag: Predecessor activity calendar (rcal_Predecessor)

All sched_ flags present in this row (raw values):
  sched_calendar_on_relationship_lag = 'rcal_Predecessor'
  sched_float_type = 'FT_FF'
  sched_lag_early_start_flag = 'Y'
  sched_open_critical_flag = 'N'
  sched_outer_depend_type = 'SD_Both'
  sched_progress_override = 'N'
  sched_retained_logic = 'Y'
  sched_setplantoforecast = 'N'
  sched_use_expect_end_flag = 'Y'
  sched_use_project_end_date_for_float = 'Y'

Other SCHEDOPTIONS fields present (raw values):
  LevelPriorityList = 'priority_type,ASC_BY_FIELD/ASC\x7f\x7f'
  enable_multiple_longest_path_calc = 'N'
  key_activity_for_multiple_longest_paths = ''
  level_all_rsrc_flag = 'Y'
  level_float_thrs_cnt = '0'
  level_keep_sched_date_flag = 'Y'
  level_outer_assign_flag = 'N'
  level_outer_assign_priority = '5'
  level_over_alloc_pct = '25'
  level_within_float_flag = 'N'
  limit_multiple_longest_path_calc = 'Y'
  max_multiple_longest_path = '10'
  use_total_float_multiple_longest_paths = 'Y'

