Schedule Health DashboardDCMA 14-Point Assessment & Quality Compliance Analysis
remediation advised
Executive Summary
narrative · health score · findingsThe Ontario Community College Building F Expansion (CURRENT - FIXED) schedule passes 5 of 13 scored DCMA criteria, earning an overall grade of F (38% compliance) with a RED status band. Criteria clearing their thresholds: C1, C4, C5, C7, C12.
The failing criteria are C2 Leads, C3 Lags, C6 High Float, C8 High Duration, C9 Valid Dates, C11 Missed Tasks, C13 CPLI, C14 BEI. Both forward-looking indices read CPLI 0.93 and BEI 0.58, and the schedule is trending toward +21 working-day overrun to 30-Sep-2026.
finish drift +21 wd vs baseline
Summary of findings
what failed, and the grade it produced- Leads (7), 7 leads found (C2).
- Lags (10.6%), 69 of 653 relationships (10.6%) | 1 exceed 44 days (C3).
- High Float (53.0% (152)), 152 activities with high float (53.0%) (C6).
- High Duration (13.2% (38)), 38 activities with high duration (13.2%) (C8).
- Valid Dates (103), 103 activities with invalid dates (26.1%; 0 forecast, 103 actual) | Status date: 2025-07-01 | Latest actual: 2025-09-16 (+54 wd) | Actual>DD: start 78, finish 80 (C9).
- Missed Tasks (38), Missed: 38/43 (88.4%) | Missing baseline IDs from current: 0 (C11).
- CPLI (0.93), CPLI: 0.934 | Contract: 2026-08-31 (A4260: Total Completion) | Forecast: 2026-09-30 (A4260: Total Completion) | Float: -21 wd (C13).
- BEI (0.58), BEI: 0.581 (25 complete / 43 planned complete) (C14).
The schedule grades F (RED): 5 of 13 criteria pass. Failures cluster in C2, C3, C6, C8, C9, C11, C13, C14. The registers under A-06 list every activity behind each failure.
Basis of Measurement
how to read these figures & what has been validatedKey Performance Metrics
14-criteria roll-upDCMA 14-Point Assessment
13 scored · 5 PASS / 8 FAIL · Grade FDCMA-14 Status by Criterion
14 criteria · PASS / FAILBaseline vs Current Comparison
task · schedule · varianceFailure Analysis & Registers
8 failing criteria · severity profile · full activity registers| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A2290 | Existing Structure Under Pinning | 1.4.5.1 Phase 1 - Early Works | 15-Jul-2025 | Lead (wd): 2 | Has 2 wd lead from "Demolition of Existing Vestibule F100" |
| A2650 | Install Level 2 & 3 Decking | 1.4.5.3 Phase 3 - Building Erection | 14-Nov-2025 | Lead (wd): 5 | Has 5 wd lead from "Erect Structural Steel" |
| A3580 | Mech. & Plumbing rough-ins | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.5 Level 3 | 22-Apr-2026 | Lead (wd): 15 | Has 15 wd lead from "Mech. & Plumbing rough-ins" |
| A3290 | Mech. & Plumbing rough-ins | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.3 Level 1 | 15-Apr-2026 | Lead (wd): 5 | Has 5 wd lead from "New partition framing" |
| A3180 | Roof Inspection | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing | 09-Mar-2026 | Lead (wd): 1 | Has 1 wd lead from "Install Built-up Roof" |
| A2620 | Structural Steel Inspection | 1.4.5.3 Phase 3 - Building Erection | 31-Oct-2025 | Lead (wd): 1 | Has 1 wd lead from "Erect Structural Steel" |
| A2580 | Underground Drainage | 1 Phase 2 - Foundation Work | 07-Nov-2025 | Lead (wd): 10 | Has 10 wd lead from "Erect Structural Steel" |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A1370x | Metal Shelving | 1.2 Shop Drawings | 23-Jun-2025 | Lag (wd): 60 | Lag of 60 wd from "Subcontract Award" exceeds 44 wd |
| A1060 | Foundation Concrete Rebar Shop Drawing | 1.2 Shop Drawings | 08-Jul-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1070 | Foundation Concrete Mix Design | 1.2 Shop Drawings | 25-Jun-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1080 | Bentonite Waterstop Data Sheet | 1.2 Shop Drawings | 02-Jul-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1090 | Masonry and Mortar Samples & Data Sheets | 1.2 Shop Drawings | 18-Aug-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | 1.2 Shop Drawings | 14-Jul-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1120 | Cold-formed Metal Framing Shop Drawings | 1.2 Shop Drawings | 23-Jul-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1130 | Misc. Metals Shop Drawings | 1.2 Shop Drawings | 02-Oct-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Structural Steel Framing and Steel Deck Shop Drawings (R0)" (lag usage exceeds 5%) |
| A1140 | Millwork Shop Drawings | 1.2 Shop Drawings | 29-Jul-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1150 | Built-up Roofing Shop Drawings | 1.2 Shop Drawings | 09-Jul-2025 | Lag (wd): 15 | Positive lag of 15 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1160 | TPO Roofing Shop Drawings | 1.2 Shop Drawings | 26-Aug-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1170 | Air Barrier System Data Sheet and Mockup | 1.2 Shop Drawings | 09-Jul-2025 | Lag (wd): 15 | Positive lag of 15 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1180 | Exterior Wall Cladding Shop Drawings | 1.2 Shop Drawings | 05-Sep-2025 | Lag (wd): 40 | Positive lag of 40 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1190 | Fire-resistive Material Data Sheet | 1.2 Shop Drawings | 09-Jul-2025 | Lag (wd): 15 | Positive lag of 15 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1200 | Hollow Metal Frames & Doors Shop Drawings | 1.2 Shop Drawings | 29-Jul-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1210 | Interior Aluminum Screen | 1.2 Shop Drawings | 20-Aug-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1220 | Flush Wood Doors Sample | 1.2 Shop Drawings | 27-Aug-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1230 | Coiling Doors | 1.2 Shop Drawings | 21-Aug-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1240 | Aluminum Framed Glazing System Shop Drawings | 1.2 Shop Drawings | 06-Aug-2025 | Lag (wd): 35 | Positive lag of 35 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1250 | Finished Hardware Schedule | 1.2 Shop Drawings | 29-Jul-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1260 | Stud framing and Gypsum Board Data Sheets | 1.2 Shop Drawings | 29-Jul-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1270 | Tiling Data sheet and samples | 1.2 Shop Drawings | 29-Jul-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1280 | ACT Data sheet and Sample | 1.2 Shop Drawings | 27-Aug-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1290 | Suspended Metal Soffits | 1.2 Shop Drawings | 04-Sep-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1300 | Flooring Data Sheets and Samples | 1.2 Shop Drawings | 29-Jul-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1310 | Paint Drawdowns | 1.2 Shop Drawings | 29-Jul-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1320 | Washroom accessories and Partitions Shop Drawings | 1.2 Shop Drawings | 29-Jul-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1330 | Fall Arrest Anchors and Horizontal Lines | 1.2 Shop Drawings | 29-Sep-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1340 | Hydraulic Lift Shop Drawings | 1.2 Shop Drawings | 09-Jul-2025 | Lag (wd): 20 | Positive lag of 20 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1350 | Sprinkler & Standpipe Shop Drawings | 1.2 Shop Drawings | 16-Jul-2025 | Lag (wd): 20 | Positive lag of 20 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1610 | Concrete Mix for Hardscapes | 1.2 Shop Drawings | 06-Aug-2025 | Lag (wd): 35 | Positive lag of 35 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1620 | Landscape Shop Drawings | 1.2 Shop Drawings | 06-Aug-2025 | Lag (wd): 35 | Positive lag of 35 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A3460 | Electrical, FA & Comms rough-ins | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.4 Level 2 | 01-May-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Mech. & Plumbing rough-ins" (lag usage exceeds 5%) |
| A3300 | Electrical, FA & Comms rough-ins | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.3 Level 1 | 21-Apr-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Mech. & Plumbing rough-ins" (lag usage exceeds 5%) |
| A3590 | Electrical, FA & Comms rough-ins | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.5 Level 3 | 08-May-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Mech. & Plumbing rough-ins" (lag usage exceeds 5%) |
| A3480 | Blocking Installation | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.4 Level 2 | 06-May-2026 | Lag (wd): 3 | Positive lag of 3 wd from "Electrical, FA & Comms rough-ins" (lag usage exceeds 5%) |
| A3610 | Blocking Installation | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.5 Level 3 | 15-May-2026 | Lag (wd): 5 | Positive lag of 5 wd from "Electrical, FA & Comms rough-ins" (lag usage exceeds 5%) |
| A1110 | Structural Reinforcement + Decking Shop Drawings | 1.2 Shop Drawings | 01-Aug-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1030 | IFC Drawings Released | 1.1 Preconstruction | 15-May-2025 | Lag (wd): 7 | Positive lag of 7 wd from "Contract Award" (lag usage exceeds 5%) |
| A4240 | Minor Deficiencies & Touch-ups | 1.4 Construction / 1.4.8 Closeout and Commissioing | 30-Sep-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Substantial Performance" (lag usage exceeds 5%) |
| A1360 | 23 82 19 - Fan Coil Units (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1370 | 23 74 13 - Air Handling Units (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 21-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1380 | 23 21 23 - Pumps (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 04-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1390 | 23 25 00 - Buffer Tanks | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1400 | 23 21 16 - Air Separator | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1410 | 23 21 16 - Expansion Tanks | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1420 | 23 57 00 - Heat Exchangers | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1430 | 22 33 00 - Electric Domestic Water Heaters | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1440 | 23 81 26 - Split System | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 30-Jun-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1450 | 22 13 29 - Sump Pumps (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 02-Jun-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1460 | 23 25 00 - Water Treatment (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 14-Aug-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1480 | 23 00 00 - Exhaust Fans (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 22-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1490 | 23 00 00 - Unit Heater | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 22-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1500 | 23 52 16 - Heating Boilers | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 21-Oct-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1510 | 23 00 00 - Wall Fin Heater | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1520 | 23 74 13 - Air Source Heat Pump | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 17-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 31-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 08-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 29-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 22-Jul-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1580 | 26 50 00 - Lighting Fixtures | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 18-Aug-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1590 | 26 09 23 - Lighting Control (R0) | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 18-Aug-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 17-Jun-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A1130 | Misc. Metals Shop Drawings | 1.2 Shop Drawings | 02-Oct-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Structural Steel Framing and Steel Deck Shop Drawings (R1)" (lag usage exceeds 5%) |
| A1130 | Misc. Metals Shop Drawings | 1.2 Shop Drawings | 02-Oct-2025 | Lag (wd): 10 | Positive lag of 10 wd from "Structural Steel Framing and Steel Deck Shop Drawings (R2)" (lag usage exceeds 5%) |
| A1280.1 | ACB Data sheet and Sample | 1.2 Shop Drawings | 04-Sep-2025 | Lag (wd): 30 | Positive lag of 30 wd from "Subcontract Award" (lag usage exceeds 5%) |
| A2550 | Form and Pour Grade Beams | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 30-Sep-2025 | Lag (wd): 3 | Positive lag of 3 wd from "Backfilling to U/S of Grade Beams (GL AA)" (lag usage exceeds 5%) |
| Activity ID | Activity Name | WBS | Forecast Finish | Total Float (wd) | Issue |
|---|---|---|---|---|---|
| A3850 | Foundations | 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 23-Feb-2026 | 57 | Total float of 57d exceeds 44 days |
| A3860 | Concrete Vertical Piers | 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 02-Mar-2026 | 57 | Total float of 57d exceeds 44 days |
| A3870 | Removal of Existing Facade for Tie In | 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 05-Mar-2026 | 57 | Total float of 57d exceeds 44 days |
| A3880 | Structural Steel erection including expansion plates | 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 26-Mar-2026 | 57 | Total float of 57d exceeds 44 days |
| A3890 | Envelope | 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 30-Apr-2026 | 57 | Total float of 57d exceeds 44 days |
| A3900 | Interior M&E Rough in | 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 14-May-2026 | 57 | Total float of 57d exceeds 44 days |
| A3910 | Interior Finishes | 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 15-May-2026 | 57 | Total float of 57d exceeds 44 days |
| A4150 | New Exterior Paved Areas and Sidewalks | 1.4 Construction / 1.4.7 Exterior Works | 29-May-2026 | 58 | Total float of 58d exceeds 44 days |
| A4160 | Landscape Installations | 1.4 Construction / 1.4.7 Exterior Works | 12-Jun-2026 | 58 | Total float of 58d exceeds 44 days |
| A3110 | L1, L2 & L3 Exterior Glazing Installation (W09a, W09b) | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation | 03-Apr-2026 | 61 | Total float of 61d exceeds 44 days |
| A2930 | L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 20-Mar-2026 | 76 | Total float of 76d exceeds 44 days |
| A2890 | L1 Masonry Wall Installation | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 20-Jan-2026 | 158 | Total float of 158d exceeds 44 days |
| A2770 | L1 Masonry Wall installation | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 31-Dec-2025 | 166 | Total float of 166d exceeds 44 days |
| A2840 | L1, L2, L3 Exterior Glazing Installation (W05) | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 13-Mar-2026 | 81 | Total float of 81d exceeds 44 days |
| A2960 | L2 & L3 Cladding Installation (EW2) | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 19-May-2026 | 76 | Total float of 76d exceeds 44 days |
| A2870 | L1, L2 & L3 Cladding Installation (EW2a) | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 11-May-2026 | 81 | Total float of 81d exceeds 44 days |
| A3010 | L2 & L3 Exterior Glazing Installation (W08a, W08b) | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 13-Mar-2026 | 76 | Total float of 76d exceeds 44 days |
| A3040 | L2 & L3 Cladding Installation (EW2) | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 11-May-2026 | 76 | Total float of 76d exceeds 44 days |
| A3050 | Horizontal Shading Louvers | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 19-May-2026 | 76 | Total float of 76d exceeds 44 days |
| A3140 | L1, L2 & L3 Cladding Installation (EW2, EW2A) | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation | 09-Jun-2026 | 61 | Total float of 61d exceeds 44 days |
| A3740 | Millwork Installation | 1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes | 02-Jul-2026 | 50 | Total float of 50d exceeds 44 days |
| A3520 | Door and Hardware Installation | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.4 Level 2 | 11-May-2026 | 46 | Total float of 46d exceeds 44 days |
| A4540 | Interior Demolition | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 24-Dec-2025 | 193 | Total float of 193d exceeds 44 days |
| A3940 | Existing Slab Removal and Trenching | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 28-Oct-2025 | 219 | Total float of 219d exceeds 44 days |
| A4010 | Underground Plumbing Rough-ins | 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 16-Jul-2025 | 135 | Total float of 135d exceeds 44 days |
| A4760 | Trench Backfill | 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 23-Jul-2025 | 135 | Total float of 135d exceeds 44 days |
| A1140 | Millwork Shop Drawings | 1.2 Shop Drawings | 29-Jul-2025 | 228 | Total float of 228d exceeds 44 days |
| A1170 | Air Barrier System Data Sheet and Mockup | 1.2 Shop Drawings | 09-Jul-2025 | 144 | Total float of 144d exceeds 44 days |
| A1180 | Exterior Wall Cladding Shop Drawings | 1.2 Shop Drawings | 05-Sep-2025 | 172 | Total float of 172d exceeds 44 days |
| A1200 | Hollow Metal Frames & Doors Shop Drawings | 1.2 Shop Drawings | 29-Jul-2025 | 162 | Total float of 162d exceeds 44 days |
| A1210 | Interior Aluminum Screen | 1.2 Shop Drawings | 20-Aug-2025 | 133 | Total float of 133d exceeds 44 days |
| A1240 | Aluminum Framed Glazing System Shop Drawings | 1.2 Shop Drawings | 06-Aug-2025 | 131 | Total float of 131d exceeds 44 days |
| A1250 | Finished Hardware Schedule | 1.2 Shop Drawings | 29-Jul-2025 | 132 | Total float of 132d exceeds 44 days |
| A1260 | Stud framing and Gypsum Board Data Sheets | 1.2 Shop Drawings | 29-Jul-2025 | 95 | Total float of 95d exceeds 44 days |
| A1270 | Tiling Data sheet and samples | 1.2 Shop Drawings | 29-Jul-2025 | 213 | Total float of 213d exceeds 44 days |
| A1300 | Flooring Data Sheets and Samples | 1.2 Shop Drawings | 29-Jul-2025 | 183 | Total float of 183d exceeds 44 days |
| A1310 | Paint Drawdowns | 1.2 Shop Drawings | 29-Jul-2025 | 212 | Total float of 212d exceeds 44 days |
| A1320 | Washroom accessories and Partitions Shop Drawings | 1.2 Shop Drawings | 29-Jul-2025 | 228 | Total float of 228d exceeds 44 days |
| A1350 | Sprinkler & Standpipe Shop Drawings | 1.2 Shop Drawings | 16-Jul-2025 | 191 | Total float of 191d exceeds 44 days |
| A1610 | Concrete Mix for Hardscapes | 1.2 Shop Drawings | 06-Aug-2025 | 238 | Total float of 238d exceeds 44 days |
| A1620 | Landscape Shop Drawings | 1.2 Shop Drawings | 06-Aug-2025 | 203 | Total float of 203d exceeds 44 days |
| A1670 | Masonry and Mortar | 1.3 Procurement | 25-Aug-2025 | 253 | Total float of 253d exceeds 44 days |
| A1700 | Cold-formed Metal Framing | 1.3 Procurement | 07-Aug-2025 | 94 | Total float of 94d exceeds 44 days |
| A1720 | Millwork | 1.3 Procurement | 09-Oct-2025 | 228 | Total float of 228d exceeds 44 days |
| A1730 | Built-up Roofing | 1.3 Procurement | 21-Aug-2025 | 127 | Total float of 127d exceeds 44 days |
| A1740 | TPO Roofing (Bridge) | 1.3 Procurement | 08-Oct-2025 | 173 | Total float of 173d exceeds 44 days |
| A1750 | Air Barrier System | 1.3 Procurement | 23-Jul-2025 | 144 | Total float of 144d exceeds 44 days |
| A1760 | Exterior Wall Cladding | 1.3 Procurement | 01-Dec-2025 | 172 | Total float of 172d exceeds 44 days |
| A1770 | Fire-resistive Material | 1.3 Procurement | 07-Aug-2025 | 138 | Total float of 138d exceeds 44 days |
| A1780 | Hollow Metal Frames | 1.3 Procurement | 25-Sep-2025 | 162 | Total float of 162d exceeds 44 days |
| A1800 | Interior Aluminum Screens | 1.3 Procurement | 29-Dec-2025 | 133 | Total float of 133d exceeds 44 days |
| A1810 | Flush Wood Doors | 1.3 Procurement | 12-Dec-2025 | 127 | Total float of 127d exceeds 44 days |
| A1820 | Coiling Doors | 1.3 Procurement | 14-Jan-2026 | 106 | Total float of 106d exceeds 44 days |
| A1830 | Aluminum Framed Glazing Systems | 1.3 Procurement | 28-Nov-2025 | 131 | Total float of 131d exceeds 44 days |
| A1840 | Finished Hardware | 1.3 Procurement | 05-Dec-2025 | 132 | Total float of 132d exceeds 44 days |
| A1850 | Stud framing & gypsum board | 1.3 Procurement | 06-Aug-2025 | 95 | Total float of 95d exceeds 44 days |
| A1860 | Tiling | 1.3 Procurement | 11-Sep-2025 | 213 | Total float of 213d exceeds 44 days |
| A1870 | ACT & ACB | 1.3 Procurement | 17-Oct-2025 | 156 | Total float of 156d exceeds 44 days |
| A1890 | Flooring | 1.3 Procurement | 24-Oct-2025 | 183 | Total float of 183d exceeds 44 days |
| A1900 | Paint Drawdowns | 1.3 Procurement | 13-Aug-2025 | 212 | Total float of 212d exceeds 44 days |
| A1910 | Washroom accessories and Partitions | 1.3 Procurement | 04-Sep-2025 | 228 | Total float of 228d exceeds 44 days |
| A1930 | Hydraulic Lift | 1.3 Procurement | 01-Dec-2025 | 141 | Total float of 141d exceeds 44 days |
| A1940 | Sprinkler & Standpipe Shop Drawings | 1.3 Procurement | 07-Aug-2025 | 191 | Total float of 191d exceeds 44 days |
| A2200 | Concrete for Hardscape | 1.3 Procurement | 13-Aug-2025 | 238 | Total float of 238d exceeds 44 days |
| A2210 | Landscape (unit pavers, furniture, etc) | 1.3 Procurement | 31-Oct-2025 | 203 | Total float of 203d exceeds 44 days |
| A4530 | Electrical and Mechanical Make Safe | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 10-Dec-2025 | 193 | Total float of 193d exceeds 44 days |
| A1790 | Hollow Metal Doors | 1.3 Procurement | 24-Oct-2025 | 162 | Total float of 162d exceeds 44 days |
| A2850 | Exterior Cladding Site Measure and Scanning | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 16-Mar-2026 | 81 | Total float of 81d exceeds 44 days |
| A2820 | Glazing Site Measure and Scanning | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 30-Dec-2025 | 91 | Total float of 91d exceeds 44 days |
| A2830 | Glazing Shop Fabrication | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 27-Jan-2026 | 91 | Total float of 91d exceeds 44 days |
| A2860 | Exterior Cladding Shop Fabrication | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 13-Apr-2026 | 81 | Total float of 81d exceeds 44 days |
| A2910 | Glazing Site Measure and Scanning | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 14-Jan-2026 | 76 | Total float of 76d exceeds 44 days |
| A2920 | Glazing Shop Fabrication | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 10-Feb-2026 | 76 | Total float of 76d exceeds 44 days |
| A2940 | Exterior Cladding Site Measure and Scanning | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 23-Mar-2026 | 76 | Total float of 76d exceeds 44 days |
| A2950 | Exterior Cladding Shop Fabrication | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 20-Apr-2026 | 76 | Total float of 76d exceeds 44 days |
| A3000 | Glazing Shop Fabrication | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 06-Mar-2026 | 76 | Total float of 76d exceeds 44 days |
| A2990 | Glazing Site Measure and Scanning | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 03-Feb-2026 | 76 | Total float of 76d exceeds 44 days |
| A3020 | Exterior Cladding Site Measure and Scanning | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 16-Mar-2026 | 76 | Total float of 76d exceeds 44 days |
| A3030 | Exterior Cladding Shop Fabrication | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 13-Apr-2026 | 76 | Total float of 76d exceeds 44 days |
| A3090 | Glazing Site Measure and Scanning | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation | 25-Feb-2026 | 61 | Total float of 61d exceeds 44 days |
| A3100 | Glazing Shop Fabrication | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation | 27-Mar-2026 | 61 | Total float of 61d exceeds 44 days |
| A3120 | Exterior Cladding Site Measure and Scanning | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation | 06-Apr-2026 | 61 | Total float of 61d exceeds 44 days |
| A3130 | Exterior Cladding Shop Fabrication | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation | 04-May-2026 | 61 | Total float of 61d exceeds 44 days |
| A3200 | Roof Anchor System Installation | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing | 19-Jun-2026 | 58 | Total float of 58d exceeds 44 days |
| A2220 | Testing and Inspection Cash Allowance Expenditure | 1.3 Procurement | 02-Jul-2025 | 316 | Total float of 316d exceeds 44 days |
| A2760 | Masonry Mock-up | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 30-Dec-2025 | 167 | Total float of 167d exceeds 44 days |
| A3680 | Misc. Metals Mock-up | 1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes | 23-Apr-2026 | 73 | Total float of 73d exceeds 44 days |
| A3730 | Millwork Mock-up | 1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes | 25-Jun-2026 | 54 | Total float of 54d exceeds 44 days |
| A2780 | Above Grade Vapour Mock-up | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 30-Dec-2025 | 152 | Total float of 152d exceeds 44 days |
| A2810 | Aluminum & Metal Panel Cladding Mock-up | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 16-Mar-2026 | 81 | Total float of 81d exceeds 44 days |
| A3230 | Fire Spraying & Intumescent Paint Mock-up | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.3 Level 1 | 25-Feb-2026 | 45 | Total float of 45d exceeds 44 days |
| A3180 | Roof Inspection | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing | 09-Mar-2026 | 101 | Total float of 101d exceeds 44 days |
| A2800 | AVB Inspection | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 30-Dec-2025 | 110 | Total float of 110d exceeds 44 days |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation | 05-Mar-2026 | 77 | Total float of 77d exceeds 44 days |
| A1960 | 23 74 13 - Air Handling Units | 1.3 Procurement / 1.3.34 Mechanical Equipment | 15-May-2026 | 52 | Total float of 52d exceeds 44 days |
| A1970 | 23 21 23 - Pumps | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Jan-2026 | 70 | Total float of 70d exceeds 44 days |
| A1980 | 23 25 00 - Buffer Tanks | 1.3 Procurement / 1.3.34 Mechanical Equipment | 24-Dec-2025 | 71 | Total float of 71d exceeds 44 days |
| A1990 | 23 21 16 - Air Separator | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | 111 | Total float of 111d exceeds 44 days |
| A2000 | 23 21 16 - Expansion Tanks | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | 111 | Total float of 111d exceeds 44 days |
| A2010 | 23 57 00 - Heat Exchangers | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | 111 | Total float of 111d exceeds 44 days |
| A2020 | 22 33 00 - Electric Domestic Water Heaters | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | 111 | Total float of 111d exceeds 44 days |
| A2030 | 23 81 26 - Split System | 1.3 Procurement / 1.3.34 Mechanical Equipment | 26-Nov-2025 | 101 | Total float of 101d exceeds 44 days |
| A2040 | 22 13 29 - Sump Pumps | 1.3 Procurement / 1.3.34 Mechanical Equipment | 08-Aug-2025 | 177 | Total float of 177d exceeds 44 days |
| A2070 | 23 00 00 - Exhaust Fans | 1.3 Procurement / 1.3.34 Mechanical Equipment | 03-Nov-2025 | 187 | Total float of 187d exceeds 44 days |
| A2080 | 23 00 00 - Unit Heater | 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | 112 | Total float of 112d exceeds 44 days |
| A2100 | 23 00 00 - Wall Fin Heater | 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Dec-2025 | 85 | Total float of 85d exceeds 44 days |
| A2120 | 20 05 10 - Electric Heat Tracing | 1.3 Procurement / 1.3.34 Mechanical Equipment | 19-Jan-2026 | 134 | Total float of 134d exceeds 44 days |
| A2130 | 22 40 00 - Plumbing Fixtures | 1.3 Procurement / 1.3.34 Mechanical Equipment | 03-Feb-2026 | 54 | Total float of 54d exceeds 44 days |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 17-Nov-2025 | 108 | Total float of 108d exceeds 44 days |
| A2190 | 28 31 00 - Fire Alarm | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 27-Oct-2025 | 123 | Total float of 123d exceeds 44 days |
| A2150 | 26 50 00 - Lighting Fixtures | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 25-Dec-2025 | 80 | Total float of 80d exceeds 44 days |
| A2180 | 26 09 23 - Lighting Control | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 23-Jan-2026 | 71 | Total float of 71d exceeds 44 days |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Apr-2026 | 69 | Total float of 69d exceeds 44 days |
| 2170 | 26 50 00 - Emergency Lighting & Exit Signs | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 08-Dec-2025 | 103 | Total float of 103d exceeds 44 days |
| A1480.1 | 23 00 00 - Exhaust Fans (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 07-Oct-2025 | 248 | Total float of 248d exceeds 44 days |
| A1530.1 | 20 05 10 - Electric Heat Tracing (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 26-Aug-2025 | 134 | Total float of 134d exceeds 44 days |
| A1540.1 | 22 40 00 - Plumbing Fixtures (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 11-Sep-2025 | 54 | Total float of 54d exceeds 44 days |
| A1590.1 | 26 09 23 - Lighting Control (R1) | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 02-Sep-2025 | 71 | Total float of 71d exceeds 44 days |
| A4370 | Underground Mechanical Installation (DCW, Sprinkler) | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 11-Nov-2025 | 219 | Total float of 219d exceeds 44 days |
| A4380 | Backfilling and Concrete for SOG | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 18-Nov-2025 | 219 | Total float of 219d exceeds 44 days |
| A4510 | Metal Shelving Installation | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 19-Aug-2025 | 75 | Total float of 75d exceeds 44 days |
| A4560 | Review Interferences with Steel Joist | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 09-Jul-2025 | 104 | Total float of 104d exceeds 44 days |
| A4570 | Joist Interferences Relocation | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 18-Aug-2025 | 283 | Total float of 283d exceeds 44 days |
| A4600 | Stud Framing | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 23-Jan-2026 | 109 | Total float of 109d exceeds 44 days |
| A4610 | MEP Rough-ins | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 29-Jan-2026 | 109 | Total float of 109d exceeds 44 days |
| A4620 | Plywood Blocking | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 03-Feb-2026 | 109 | Total float of 109d exceeds 44 days |
| A4630 | Drywall Installation | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 06-Feb-2026 | 109 | Total float of 109d exceeds 44 days |
| A4640 | Taping Drywall | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 13-Feb-2026 | 109 | Total float of 109d exceeds 44 days |
| A4550 | Existing Exterior Wall Demo (New Building Must be Erected and Enclosed) | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 20-Jan-2026 | 109 | Total float of 109d exceeds 44 days |
| A4660 | Setup Temporary Hoarding | 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area | 19-Feb-2026 | 109 | Total float of 109d exceeds 44 days |
| A4670 | Electrical and Mechanical Make Safe | 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area | 23-Feb-2026 | 109 | Total float of 109d exceeds 44 days |
| A4680 | Interior Demolition | 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area | 04-Mar-2026 | 109 | Total float of 109d exceeds 44 days |
| A4700 | Review Interferences with Steel Joist | 1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area | 11-Aug-2025 | 72 | Total float of 72d exceeds 44 days |
| A4730 | Steel Joist Reinforcement Installation | 1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area | 24-Oct-2025 | 55 | Total float of 55d exceeds 44 days |
| A4770 | Concrete Slab Infill | 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 07-Aug-2025 | 135 | Total float of 135d exceeds 44 days |
| A4580 | New Columns Installation | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 02-Oct-2025 | 45 | Total float of 45d exceeds 44 days |
| A4720 | Existing Column Reinforcement | 1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area | 02-Oct-2025 | 55 | Total float of 55d exceeds 44 days |
| A4780 | New Columns Installation | 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 14-Aug-2025 | 135 | Total float of 135d exceeds 44 days |
| A4790 | Existing Column Reinforcement | 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 21-Aug-2025 | 135 | Total float of 135d exceeds 44 days |
| A4800 | Flatness Survey @ Floor Slab | 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 25-Aug-2025 | 135 | Total float of 135d exceeds 44 days |
| A4810 | Self Levelling | 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 04-Sep-2025 | 135 | Total float of 135d exceeds 44 days |
| A2090x | Metal Shelving | 1.3 Procurement | 14-Aug-2025 | 75 | Total float of 75d exceeds 44 days |
| A4650 | Painting | 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 18-Feb-2026 | 109 | Total float of 109d exceeds 44 days |
| A4690 | Electrical Fixtures | 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area | 11-Mar-2026 | 109 | Total float of 109d exceeds 44 days |
| A4710 | Relocation of Interferences | 1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area | 25-Aug-2025 | 72 | Total float of 72d exceeds 44 days |
| A2550x | R6 - RFI 60 Sprinkler Diesel Pump | 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 21-Oct-2025 | 219 | Total float of 219d exceeds 44 days |
| A1380x | Metal Shelving (R1) | 1.2 Shop Drawings | 16-Jul-2025 | 75 | Total float of 75d exceeds 44 days |
| A2560x | R7 - SP 3 & 4 - 3rd Floor Fan Coil Units Scope | 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 13-Aug-2025 | 65 | Total float of 65d exceeds 44 days |
| A1460.1 | 23 25 00 - Water Treatment (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 17-Sep-2025 | 50 | Total float of 50d exceeds 44 days |
| A2050 | 23 25 00 - Water Treatment | 1.3 Procurement / 1.3.34 Mechanical Equipment | 09-Feb-2026 | 50 | Total float of 50d exceeds 44 days |
| A2420 | Form and Pour North Exit Stair | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 05-Sep-2025 | 119 | Total float of 119d exceeds 44 days |
| A2480 | Concrete for Remaining Pad Footings (Ramp) | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 03-Jul-2025 | 315 | Total float of 315d exceeds 44 days |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A3850 | Foundations | 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 23-Feb-2026 | Duration (wd): 116 | Duration of 116d exceeds 44 days |
| A1710 | Misc. Metals | 1.3 Procurement | 27-Jan-2026 | Duration (wd): 80 | Duration of 80d exceeds 44 days |
| A1720 | Millwork | 1.3 Procurement | 09-Oct-2025 | Duration (wd): 51 | Duration of 51d exceeds 44 days |
| A1760 | Exterior Wall Cladding | 1.3 Procurement | 01-Dec-2025 | Duration (wd): 60 | Duration of 60d exceeds 44 days |
| A1800 | Interior Aluminum Screens | 1.3 Procurement | 29-Dec-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A1810 | Flush Wood Doors | 1.3 Procurement | 12-Dec-2025 | Duration (wd): 75 | Duration of 75d exceeds 44 days |
| A1820 | Coiling Doors | 1.3 Procurement | 14-Jan-2026 | Duration (wd): 100 | Duration of 100d exceeds 44 days |
| A1830 | Aluminum Framed Glazing Systems | 1.3 Procurement | 28-Nov-2025 | Duration (wd): 80 | Duration of 80d exceeds 44 days |
| A1840 | Finished Hardware | 1.3 Procurement | 05-Dec-2025 | Duration (wd): 91 | Duration of 91d exceeds 44 days |
| A1890 | Flooring | 1.3 Procurement | 24-Oct-2025 | Duration (wd): 61 | Duration of 61d exceeds 44 days |
| A1920 | Fall Arrest Anchors and Horizontal Lines | 1.3 Procurement | 23-Dec-2025 | Duration (wd): 60 | Duration of 60d exceeds 44 days |
| A1930 | Hydraulic Lift | 1.3 Procurement | 01-Dec-2025 | Duration (wd): 101 | Duration of 101d exceeds 44 days |
| A2210 | Landscape (unit pavers, furniture, etc) | 1.3 Procurement | 31-Oct-2025 | Duration (wd): 60 | Duration of 60d exceeds 44 days |
| A1790 | Hollow Metal Doors | 1.3 Procurement | 24-Oct-2025 | Duration (wd): 61 | Duration of 61d exceeds 44 days |
| A1950 | 23 82 19 - Fan Coil Units | 1.3 Procurement / 1.3.34 Mechanical Equipment | 25-Feb-2026 | Duration (wd): 109 | Duration of 109d exceeds 44 days |
| A1960 | 23 74 13 - Air Handling Units | 1.3 Procurement / 1.3.34 Mechanical Equipment | 15-May-2026 | Duration (wd): 180 | Duration of 180d exceeds 44 days |
| A1970 | 23 21 23 - Pumps | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Jan-2026 | Duration (wd): 100 | Duration of 100d exceeds 44 days |
| A1980 | 23 25 00 - Buffer Tanks | 1.3 Procurement / 1.3.34 Mechanical Equipment | 24-Dec-2025 | Duration (wd): 120 | Duration of 120d exceeds 44 days |
| A1990 | 23 21 16 - Air Separator | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2000 | 23 21 16 - Expansion Tanks | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2010 | 23 57 00 - Heat Exchangers | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2020 | 22 33 00 - Electric Domestic Water Heaters | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2030 | 23 81 26 - Split System | 1.3 Procurement / 1.3.34 Mechanical Equipment | 26-Nov-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2060 | 23 37 13 - Diffuser and Grilles | 1.3 Procurement / 1.3.34 Mechanical Equipment | 05-Mar-2026 | Duration (wd): 100 | Duration of 100d exceeds 44 days |
| A2070 | 23 00 00 - Exhaust Fans | 1.3 Procurement / 1.3.34 Mechanical Equipment | 03-Nov-2025 | Duration (wd): 72 | Duration of 72d exceeds 44 days |
| A2080 | 23 00 00 - Unit Heater | 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Duration (wd): 78 | Duration of 78d exceeds 44 days |
| A2090 | 23 52 16 - Heating Boilers | 1.3 Procurement / 1.3.34 Mechanical Equipment | 16-Mar-2026 | Duration (wd): 100 | Duration of 100d exceeds 44 days |
| A2100 | 23 00 00 - Wall Fin Heater | 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Dec-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2110 | 23 74 13 - Air Source Heat Pump | 1.3 Procurement / 1.3.34 Mechanical Equipment | 05-Jun-2026 | Duration (wd): 224 | Duration of 224d exceeds 44 days |
| A2120 | 20 05 10 - Electric Heat Tracing | 1.3 Procurement / 1.3.34 Mechanical Equipment | 19-Jan-2026 | Duration (wd): 100 | Duration of 100d exceeds 44 days |
| A2130 | 22 40 00 - Plumbing Fixtures | 1.3 Procurement / 1.3.34 Mechanical Equipment | 03-Feb-2026 | Duration (wd): 100 | Duration of 100d exceeds 44 days |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 17-Nov-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2190 | 28 31 00 - Fire Alarm | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 27-Oct-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2150 | 26 50 00 - Lighting Fixtures | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 25-Dec-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2180 | 26 09 23 - Lighting Control | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 23-Jan-2026 | Duration (wd): 100 | Duration of 100d exceeds 44 days |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Apr-2026 | Duration (wd): 183 | Duration of 183d exceeds 44 days |
| 2170 | 26 50 00 - Emergency Lighting & Exit Signs | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 08-Dec-2025 | Duration (wd): 90 | Duration of 90d exceeds 44 days |
| A2050 | 23 25 00 - Water Treatment | 1.3 Procurement / 1.3.34 Mechanical Equipment | 09-Feb-2026 | Duration (wd): 100 | Duration of 100d exceeds 44 days |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| 2170 | 26 50 00 - Emergency Lighting & Exit Signs | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 08-Dec-2025 | Actual start (2025-07-30) after status date (2025-07-01) | |
| A1060 | Foundation Concrete Rebar Shop Drawing | 1.2 Shop Drawings | 08-Jul-2025 | Actual finish (2025-07-08) after status date (2025-07-01) | |
| A1080 | Bentonite Waterstop Data Sheet | 1.2 Shop Drawings | 02-Jul-2025 | Actual finish (2025-07-02) after status date (2025-07-01) | |
| A1090 | Masonry and Mortar Samples & Data Sheets | 1.2 Shop Drawings | 18-Aug-2025 | Actual finish (2025-08-18) after status date (2025-07-01) | |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | 1.2 Shop Drawings | 14-Jul-2025 | Actual finish (2025-07-14) after status date (2025-07-01) | |
| A1100.1 | Structural Steel Framing and Steel Deck Shop Drawings (R1) | 1.2 Shop Drawings | 25-Aug-2025 | Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-25) after status date (2025-07-01) | |
| A1100.2 | Structural Steel Framing and Steel Deck Shop Drawings (R2) | 1.2 Shop Drawings | 04-Sep-2025 | Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A1110 | Structural Reinforcement + Decking Shop Drawings | 1.2 Shop Drawings | 01-Aug-2025 | Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-01) after status date (2025-07-01) | |
| A1120 | Cold-formed Metal Framing Shop Drawings | 1.2 Shop Drawings | 23-Jul-2025 | Actual finish (2025-07-23) after status date (2025-07-01) | |
| A1130 | Misc. Metals Shop Drawings | 1.2 Shop Drawings | 02-Oct-2025 | Actual start (2025-08-26) after status date (2025-07-01) | |
| A1150 | Built-up Roofing Shop Drawings | 1.2 Shop Drawings | 09-Jul-2025 | Actual finish (2025-07-09) after status date (2025-07-01) | |
| A1160 | TPO Roofing Shop Drawings | 1.2 Shop Drawings | 26-Aug-2025 | Actual start (2025-07-09) after status date (2025-07-01) | Actual finish (2025-08-26) after status date (2025-07-01) | |
| A1180 | Exterior Wall Cladding Shop Drawings | 1.2 Shop Drawings | 05-Sep-2025 | Actual start (2025-08-11) after status date (2025-07-01) | |
| A1190 | Fire-resistive Material Data Sheet | 1.2 Shop Drawings | 09-Jul-2025 | Actual finish (2025-07-09) after status date (2025-07-01) | |
| A1210 | Interior Aluminum Screen | 1.2 Shop Drawings | 20-Aug-2025 | Actual start (2025-07-25) after status date (2025-07-01) | |
| A1220 | Flush Wood Doors Sample | 1.2 Shop Drawings | 27-Aug-2025 | Actual start (2025-08-26) after status date (2025-07-01) | Actual finish (2025-08-27) after status date (2025-07-01) | |
| A1230 | Coiling Doors | 1.2 Shop Drawings | 21-Aug-2025 | Actual start (2025-08-05) after status date (2025-07-01) | Actual finish (2025-08-21) after status date (2025-07-01) | |
| A12380.1 | 23 21 23 - Pumps (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 19-Aug-2025 | Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-19) after status date (2025-07-01) | |
| A1280 | ACT Data sheet and Sample | 1.2 Shop Drawings | 27-Aug-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-08-27) after status date (2025-07-01) | |
| A1280.1 | ACB Data sheet and Sample | 1.2 Shop Drawings | 04-Sep-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A1290 | Suspended Metal Soffits | 1.2 Shop Drawings | 04-Sep-2025 | Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A1330 | Fall Arrest Anchors and Horizontal Lines | 1.2 Shop Drawings | 29-Sep-2025 | Actual start (2025-08-14) after status date (2025-07-01) | |
| A1340 | Hydraulic Lift Shop Drawings | 1.2 Shop Drawings | 09-Jul-2025 | Actual finish (2025-07-09) after status date (2025-07-01) | |
| A1360 | 23 82 19 - Fan Coil Units (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1360.1 | 23 82 19 - Fan Coil Units (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A1360.2 | 23 82 19 - Fan Coil Units (R2) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 19-Sep-2025 | Actual start (2025-08-25) after status date (2025-07-01) | |
| A1370 | 23 74 13 - Air Handling Units (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 21-Jul-2025 | Actual finish (2025-07-21) after status date (2025-07-01) | |
| A1370,1 | 23 74 13 - Air Handling Units (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 28-Aug-2025 | Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-28) after status date (2025-07-01) | |
| A1380 | 23 21 23 - Pumps (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 04-Jul-2025 | Actual finish (2025-07-04) after status date (2025-07-01) | |
| A1390 | 23 25 00 - Buffer Tanks | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1400 | 23 21 16 - Air Separator | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1410 | 23 21 16 - Expansion Tanks | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1420 | 23 57 00 - Heat Exchangers | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1430 | 22 33 00 - Electric Domestic Water Heaters | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1460 | 23 25 00 - Water Treatment (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A1460.1 | 23 25 00 - Water Treatment (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 17-Sep-2025 | Actual start (2025-08-22) after status date (2025-07-01) | |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 14-Aug-2025 | Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-08-14) after status date (2025-07-01) | |
| A1470.1 | 23 37 13 - Diffuser and Grilles Shop Drawings (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 09-Oct-2025 | Actual start (2025-09-05) after status date (2025-07-01) | |
| A1480.1 | 23 00 00 - Exhaust Fans (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 07-Oct-2025 | Actual start (2025-09-16) after status date (2025-07-01) | |
| A1500 | 23 52 16 - Heating Boilers | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 21-Oct-2025 | Actual start (2025-09-12) after status date (2025-07-01) | |
| A1510 | 23 00 00 - Wall Fin Heater | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Actual start (2025-07-09) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 31-Jul-2025 | Actual start (2025-07-11) after status date (2025-07-01) | Actual finish (2025-07-31) after status date (2025-07-01) | |
| A1540.1 | 22 40 00 - Plumbing Fixtures (R1) | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 11-Sep-2025 | Actual start (2025-08-14) after status date (2025-07-01) | |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 08-Jul-2025 | Actual finish (2025-07-08) after status date (2025-07-01) | |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 29-Jul-2025 | Actual finish (2025-07-29) after status date (2025-07-01) | |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 22-Jul-2025 | Actual start (2025-07-11) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) | |
| A1580 | 26 50 00 - Lighting Fixtures | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 18-Aug-2025 | Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-18) after status date (2025-07-01) | |
| A1590 | 26 09 23 - Lighting Control (R0) | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 18-Aug-2025 | Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-18) after status date (2025-07-01) | |
| A1660 | Bentonite Waterstop | 1.3 Procurement | 09-Jul-2025 | Actual start (2025-07-03) after status date (2025-07-01) | Actual finish (2025-07-09) after status date (2025-07-01) | |
| A1680 | Structural Steel | 1.3 Procurement | 01-Oct-2025 | Actual start (2025-09-04) after status date (2025-07-01) | |
| A1980 | 23 25 00 - Buffer Tanks | 1.3 Procurement / 1.3.34 Mechanical Equipment | 24-Dec-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A1990 | 23 21 16 - Air Separator | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A2000 | 23 21 16 - Expansion Tanks | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A2010 | 23 57 00 - Heat Exchangers | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A2020 | 22 33 00 - Electric Domestic Water Heaters | 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Nov-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A2030 | 23 81 26 - Split System | 1.3 Procurement / 1.3.34 Mechanical Equipment | 26-Nov-2025 | Actual start (2025-07-10) after status date (2025-07-01) | |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 17-Nov-2025 | Actual start (2025-07-09) after status date (2025-07-01) | |
| A2150 | 26 50 00 - Lighting Fixtures | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 25-Dec-2025 | Actual start (2025-08-19) after status date (2025-07-01) | |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Apr-2026 | Actual start (2025-07-23) after status date (2025-07-01) | |
| A2280 | Under Pinning Inspection | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 14-Jul-2025 | Actual finish (2025-07-14) after status date (2025-07-01) | |
| A2290 | Existing Structure Under Pinning | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 15-Jul-2025 | Actual finish (2025-07-15) after status date (2025-07-01) | |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 07-Jul-2025 | Actual finish (2025-07-07) after status date (2025-07-01) | |
| A2360 | Ductbank Shoring | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 08-Jul-2025 | Actual finish (2025-07-08) after status date (2025-07-01) | |
| A2370 | Bulk Excavation to U/S of Footings | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 22-Jul-2025 | Actual start (2025-07-16) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) | |
| A2380 | Bulk Excavation to U/S North Stair Footing | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 23-Jul-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) | |
| A2390 | Subgrade Inspection | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 22-Jul-2025 | Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) | |
| A2400 | Subgrade Preparation | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 23-Jul-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) | |
| A2410 | Soil Bearing Capacity Inspection | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 24-Jul-2025 | Actual start (2025-07-24) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) | |
| A2410x | RFI #17 Demo Clarification | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 11-Jul-2025 | Actual finish (2025-07-11) after status date (2025-07-01) | |
| A2420 | Form and Pour North Exit Stair | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 05-Sep-2025 | Actual start (2025-08-04) after status date (2025-07-01) | |
| A2420x | PC-002 Demo Clarification Issuance | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 14-Jul-2025 | Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-14) after status date (2025-07-01) | |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 23-Jul-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) | |
| A2430x | PCO-008 (Quote) Submission | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 24-Jul-2025 | Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) | |
| A2440x | CO-005 Issuance | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 07-Aug-2025 | Actual start (2025-07-25) after status date (2025-07-01) | Actual finish (2025-08-07) after status date (2025-07-01) | |
| A2450 | Rebar for Pad Footings | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 24-Jul-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) | |
| A2450x | CD-01 Water Room Demo (Elec. FACP) Issuance | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 18-Jul-2025 | Actual start (2025-07-18) after status date (2025-07-01) | Actual finish (2025-07-18) after status date (2025-07-01) | |
| A2460 | Rebar Inspection | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 25-Jul-2025 | Actual start (2025-07-25) after status date (2025-07-01) | Actual finish (2025-07-25) after status date (2025-07-01) | |
| A2460x | CD-01 Fire Alarm Panel Relocation | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 24-Jul-2025 | Actual start (2025-07-24) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) | |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 28-Jul-2025 | Actual start (2025-07-28) after status date (2025-07-01) | Actual finish (2025-07-28) after status date (2025-07-01) | |
| A2470x | Water Room Block Wall Demo | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 12-Aug-2025 | Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A2480x | Existing Vestibule Slab Cutting | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 13-Aug-2025 | Actual start (2025-08-13) after status date (2025-07-01) | Actual finish (2025-08-13) after status date (2025-07-01) | |
| A2490 | Concrete Field Testing | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 28-Jul-2025 | Actual start (2025-07-28) after status date (2025-07-01) | Actual finish (2025-07-28) after status date (2025-07-01) | |
| A2490x | Existing Vestibule Slab Removal | 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 14-Aug-2025 | Actual start (2025-08-14) after status date (2025-07-01) | Actual finish (2025-08-14) after status date (2025-07-01) | |
| A2500 | Install Rebar for Piers | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 08-Sep-2025 | Actual start (2025-07-29) after status date (2025-07-01) | Actual finish (2025-09-08) after status date (2025-07-01) | |
| A2500x | R1 - RFI #19 & 20 - Existing DCW and Sanitary Line | 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 27-Aug-2025 | Actual finish (2025-08-27) after status date (2025-07-01) | |
| A2510 | Supply of Embedment & Ankors | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 22-Aug-2025 | Actual start (2025-08-22) after status date (2025-07-01) | Actual finish (2025-08-22) after status date (2025-07-01) | |
| A2520 | Form and Pour Foundation Piers | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 08-Sep-2025 | Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-09-08) after status date (2025-07-01) | |
| A2520x | R3 - RFI 45 - City of Barrie Water Department - Request to Review Drawings | 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 04-Sep-2025 | Actual start (2025-07-31) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A2530 | Backfilling to U/S of Grade Beams | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 12-Sep-2025 | Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-09-12) after status date (2025-07-01) | |
| A2530x | R4 - PC-004 Grade Beam Rebar | 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 10-Sep-2025 | Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-09-10) after status date (2025-07-01) | |
| A2540x | R5 - RFI #39R2 Jewelery Workshop Interior Fitout | 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 04-Sep-2025 | Actual start (2025-07-17) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A2550x | R6 - RFI 60 Sprinkler Diesel Pump | 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 21-Oct-2025 | Actual start (2025-08-21) after status date (2025-07-01) | |
| A2600 | Compaction Inspection | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 15-Aug-2025 | Actual start (2025-08-15) after status date (2025-07-01) | Actual finish (2025-08-15) after status date (2025-07-01) | |
| A3920 | Setup Temporary Hoarding | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 04-Jul-2025 | Actual start (2025-07-04) after status date (2025-07-01) | Actual finish (2025-07-04) after status date (2025-07-01) | |
| A3930 | Interior Demolition | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 02-Sep-2025 | Actual start (2025-07-21) after status date (2025-07-01) | Actual finish (2025-09-02) after status date (2025-07-01) | |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 11-Jul-2025 | Actual start (2025-07-07) after status date (2025-07-01) | Actual finish (2025-07-11) after status date (2025-07-01) | |
| A4340 | Electrical and Mechanical Make Safe | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 18-Jul-2025 | Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-18) after status date (2025-07-01) | |
| A4390 | Review Interferences with Steel Joist | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 15-Aug-2025 | Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-08-15) after status date (2025-07-01) | |
| A4410 | Joist Interferences Relocation | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 22-Aug-2025 | Actual start (2025-08-16) after status date (2025-07-01) | Actual finish (2025-08-22) after status date (2025-07-01) | |
| A5070 | Removal of Existing Water and Sanitary | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 14-Jul-2025 | Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-14) after status date (2025-07-01) | |
| A5220 | Weather Impact (Rain) - August 28, 2025 | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 28-Aug-2025 | Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-08-28) after status date (2025-07-01) | |
| A5250 | Weather Impact (Rain) - September 04, 2025 | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 04-Sep-2025 | Actual start (2025-09-04) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A3780 | Layout for Elevator Cylinder | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.16 New Hydraulic Elevator | 23-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-19) |
| A3790 | Drilling Elevator Cylinder from Grade | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.16 New Hydraulic Elevator | 24-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-20) |
| A3800 | Install Steel Casing into the ground | 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.16 New Hydraulic Elevator | 25-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-23) |
| A1110 | Structural Reinforcement Shop Drawings | 1.2 Shop Drawings | 01-Aug-2025 | Working days late: 30 wd | Actual finish 30 wd later than baseline (2025-06-19) |
| A2220 | Testing and Inspection Cash Allowance Expenditure | 1.3 Procurement | 02-Jul-2025 | Working days late: 34 wd | Forecast finish 34 wd later than baseline (2025-05-13) |
| A2280 | Under Pinning Inspection | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 14-Jul-2025 | Working days late: 15 wd | Actual finish 15 wd later than baseline (2025-06-20) |
| A1390 | 23 25 00 - Buffer Tanks | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Working days late: 3 wd | Actual finish 3 wd later than baseline (2025-06-27) |
| A1400 | 23 21 16 - Air Separator | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Working days late: 3 wd | Actual finish 3 wd later than baseline (2025-06-27) |
| A1410 | 23 21 16 - Expansion Tanks | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Working days late: 3 wd | Actual finish 3 wd later than baseline (2025-06-27) |
| A1420 | 23 57 00 - Heat Exchangers | 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Working days late: 5 wd | Actual finish 5 wd later than baseline (2025-06-25) |
| A2510 | Supply of Embedment & Ankors | 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 22-Aug-2025 | Working days late: 44 wd | Actual finish 44 wd later than baseline (2025-06-20) |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 08-Jul-2025 | Working days late: 9 wd | Actual finish 9 wd later than baseline (2025-06-24) |
| A1590 | 26 09 23 - Lighting Control | 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 18-Aug-2025 | Working days late: 36 wd | Actual finish 36 wd later than baseline (2025-06-26) |
| A2240 | Construction Site Setup. Fencing and Temp Facilities | 1.4 Construction | 16-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-12) |
| A1040 | Permit (Not Required Per Ontario Community College) | 1.1 Preconstruction | 16-May-2025 | Working days late: 3 wd | Actual finish 3 wd later than baseline (2025-05-13) |
| A1010 | Contract Award | 1.1 Preconstruction | 02-May-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-04-30) |
| A1030 | IFC Drawings Released | 1.1 Preconstruction | 15-May-2025 | Working days late: 3 wd | Actual finish 3 wd later than baseline (2025-05-12) |
| A1060 | Foundation Concrete Rebar Shop Drawing | 1.2 Shop Drawings | 08-Jul-2025 | Working days late: 12 wd | Actual finish 12 wd later than baseline (2025-06-19) |
| A2230 | Ontario Community College Auto Show | 1.4 Construction | 09-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-05) |
| A2270 | Excavation for Under Pinning | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 23-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-19) |
| A2250 | Tree Removal, Protection and Equipment Mobilization | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 17-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-13) |
| A2260 | Top Soil Stripping | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 20-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-18) |
| A2300 | Setup Hoarding @ Vestibule F100 | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 18-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-16) |
| A2310 | Relocate FAA | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 17-Jun-2025 | Working days late: 1 wd | Actual finish 1 wd later than baseline (2025-06-16) |
| A2320 | Demolition of Existing Vestibule F100 | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 25-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-23) |
| A2330 | Gas Meter and Pipe Relocation Investigation | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 19-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-17) |
| A2340 | Gas Meter and pipe Relocation | 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 23-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-19) |
| A1020 | Subcontract Award | 1.1 Preconstruction | 02-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-05-29) |
| A3920 | Setup Hoarding at Existing Areas | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 04-Jul-2025 | Working days late: 14 wd | Actual finish 14 wd later than baseline (2025-06-13) |
| A3940 | Existing Slab Removal and Trenching | 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 28-Oct-2025 | Working days late: 90 wd | Forecast finish 90 wd later than baseline (2025-06-19) |
| A1050 | Ductbank Underpinning Drawing | 1.2 Shop Drawings | 30-Jun-2025 | Working days late: 12 wd | Actual finish 12 wd later than baseline (2025-06-12) |
| A1070 | Foundation Concrete Mix Design | 1.2 Shop Drawings | 25-Jun-2025 | Working days late: 4 wd | Actual finish 4 wd later than baseline (2025-06-19) |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings | 1.2 Shop Drawings | 14-Jul-2025 | Working days late: 16 wd | Actual finish 16 wd later than baseline (2025-06-19) |
| A1120 | Cold-formed Metal Framing Shop Drawings | 1.2 Shop Drawings | 23-Jul-2025 | Working days late: 23 wd | Actual finish 23 wd later than baseline (2025-06-19) |
| A1080 | Bentonite Waterstop Data Sheet | 1.2 Shop Drawings | 02-Jul-2025 | Working days late: 8 wd | Actual finish 8 wd later than baseline (2025-06-19) |
| A1160 | TPO Roofing Shop Drawings | 1.2 Shop Drawings | 26-Aug-2025 | Working days late: 47 wd | Actual finish 47 wd later than baseline (2025-06-19) |
| A1650 | Foundation Concrete Mix Design | 1.3 Procurement | 27-Jun-2025 | Working days late: 4 wd | Actual finish 4 wd later than baseline (2025-06-23) |
| A1660 | Bentonite Waterstop | 1.3 Procurement | 09-Jul-2025 | Working days late: 8 wd | Actual finish 8 wd later than baseline (2025-06-26) |
Detailed Comparison
baseline → current → variance| Metric | Baseline | Current | Variance |
|---|---|---|---|
| Total Tasks | 327 | 405 | +78 |
| Project Finish | 31-Aug-2026 | 30-Sep-2026 | +21 wd |
| Project Start | 01-Apr-2025 | 01-Apr-2025 | 0 wd |
| CPLI | n/a | 0.93 | below 0.95 |
| BEI | n/a | 0.58 | below 0.95 |
Schedule Exposure
measured figures only · derivations below- Finish drift: working days from the baseline finish (31-Aug-2026) to the current forecast finish (30-Sep-2026), counted on the project calendar. Positive = finishing later than baseline.
- CPLI 0.93:
(contract finish − data date) ÷ (forecast finish − data date). Below 1.00 = the forecast finish falls beyond the contract finish. Here: contract finish 31-Aug-2026, forecast finish 30-Sep-2026, measured from the data date 01-Jul-2025. - BEI 0.58:
baseline activities actually complete ÷ baseline activities planned complete at the data date. Below 1.00 = executing behind the baseline plan. Here: 25 complete ÷ 43 planned complete at the data date. - Drift direction: the sign of the finish drift. Positive drift (+21 wd), so the schedule is slipping against baseline.
- No resource figure is reported. The schedule carries no resource assignments (C10 not scored), so no resource-based risk or resource-increase percentage can be derived from this file.
Schedule Forecast
forward-pass dates as scheduled- These are the schedule’s own dates as read from the file: the forecast completion is the current schedule’s forward-pass finish, not a probabilistic projection. This screen models no delay probabilities and no resource requirements; a probabilistic finish-date forecast requires a schedule risk analysis (Monte Carlo), which is a separate deliverable.
Path back to green
grade re-scored per cleared criterion · 8 failing| Criterion cleared | Current metric | Grade | Compliance | Band |
|---|---|---|---|---|
| C9 Valid Dates | 103 | D | 46% | RED |
| C11 Missed Tasks | 38 | D | 46% | RED |
| C13 CPLI | 0.93 | D | 46% | RED |
| C14 BEI | 0.58 | D | 46% | RED |
| C2 Leads | 7 | D | 46% | RED |
| C3 Lags | 10.6% | D | 46% | RED |
| C6 High Float | 53.0% (152) | D | 46% | RED |
| C8 High Duration | 13.2% (38) | D | 46% | RED |
| All 8 failing criteria cleared | — | A | 100% | GREEN |
- The grade is a pure function of the pass rate:
passed ÷ scored, graded A ≥90%, B ≥75%, C ≥60%, D ≥45%, else F, the same scoring the headline grade uses. Each row adds exactly one cleared criterion to the 5 currently passing of 13 scored. - Clearing a criterion means correcting its listed activities so the check passes (for example, clearing C9 means fixing every invalid date in its register). Other criteria are held at their computed results; knock-on effects of the corrections themselves are not modelled here.
Report Information
provenance & reproducibilityAnalyst conclusion and next step
What this schedule can and cannot prove
Delay investigation warrantedThe finish has moved materially and the movement deserves a proper look at the update chain before anyone takes a position. The Preliminary Assessment, scoped and priced in writing before any work starts, is the next step.
Technical condition: the assessment grades this schedule F · 38% · RED; the forecast finish has moved 21 working days later than the baseline.
The movement is material and this pair of files cannot yet explain it. The forecast completion has moved 21 working days later than the baseline, and the schedule itself grades F on the DCMA screen, so both the dates and the instrument that produced them need attention before anyone takes a position.
A baseline and one update are endpoints. The causation story lives in the monthly chain between them and in the project record, and on this file only a minority of the moved activities have evidence artifacts paired to them. Examining the chain is the correct next step, and it is a bounded piece of work.
The findings that actually matter
| 1 | The forecast completion moved 21 working days later than the baseline, to 30-Sep-2026. |
| 2 | The schedule grades F (38%) on the DCMA-14 screen, driven by high float on 53% of activities and 103 activities with invalid dates: the instrument needs repair alongside the delay question. |
| 3 | Only 10.3% of the positive slips are evidence-supported in the records provided, so causation is asserted, not yet shown. |
Evidence still required
| • | The full monthly update chain (every XER between baseline and current, not just the endpoints) |
| • | Contract milestone dates and any amendments to them |
| • | Delay notices and the contractual notice log |
| • | Change orders and change directives with dates |
| • | Contemporaneous correspondence for the affected work fronts |
The next step, precisely
The Preliminary Assessment, scoped and priced in writing before any work starts, would cover:
| 1. | Ingest the full monthly update chain and rebuild the 21 working days of movement window by window on the project calendars. |
| 2. | Attribute each driving window to its cause using the schedule record and the documents listed above. |
| 3. | Screen the chain for baseline changes, logic revisions and calendar edits that move dates without progress. |
| 4. | Report whether a delay position is supportable, in which direction, and what a full analysis would cost if warranted. |
Conclusion written by Dana Fitkowski, Principal, Critical Path Partners on 1 September 2026. The engine produced the files; the analyst produced this conclusion.