Critical Path PartnersForensic schedule analysis
Forensic Delay Analysis

Ontario Community College 1 window analyzed: Baseline → Current

Project
Ontario Community College
Prepared By
CPP Lens · Critical Path Partners
Window Period
01-Apr-2025 → 01-Jul-2025
Generated
30-Aug-2026
Baseline → Final Slip (wd)
+21wd
Completion delay · 0 slip-days unattributed
Window Shifts
+21 wd
Windows
1
Attribution
100.0%
Findings

Scheduled completion slipped 21 working days, from 31-Aug-2026 to 30-Sep-2026, measured across 1 window (01-Apr-2025 to 01-Jul-2025). Of that movement, the slip registers attribute 9 wd to the Owner, 12 wd to the Contractor; nothing remains unattributed. The finish driver at the final data date is A4240 (Minor Deficiencies & Touch-ups), at the end of the driving critical-path chain. On the critical path, 6 activities grew in scheduler-estimated duration (+24 wd) and 9 reduced (-304 wd); the full per-activity tables follow. 309 activities moved their finish dates over the period; every one is listed in the registers below, none omitted.

Baseline → Final Slip (wd)
+21wd
Cumulative vs baseline completion (working days)
Sum of Window Shifts (wd)
+21wd
Signed shift across all windows (working days)
Windows Analyzed
1
Baseline → Current
Attribution Complete
100.0%
fully attributed
Basis of measurementHow to read the numbers in this report
Day unit
Working days
Every day count in this deliverable is in working days. No calendar-day figure is displayed. Where a contract clause is quoted verbatim in calendar days, the computed equivalent is given in working days alongside.
Calendar
The activity's own P6 calendar
Deltas are counted on the activity's own P6 calendar via work_day_delta. Where no project calendar is available the documented fallback is Monday to Friday with no holidays, and that fallback is disclosed on the affected figure.
Date fields read
P6 Start and Finish columns only
A negative number means the contractor lost time
Convention: contractor-loss: negative = the contractor lost time
Variance
How it is computed
A negative value means
Start variance
contract start - subject start
started later than contract, prep time lost
Finish variance
subject finish - contract finish
finished earlier than contract, buffer lost
Window variance
subject window - contract window
window compressed
Milestone variance
subject date - contract date
date pulled in ahead of contract
The subtraction order is deliberately opposite between start and finish, so that a negative value means lost time in both columns. Reversing either order to make them look consistent would invert the sign of every finish variance in this report.
A-01

Windows Overview

per-window shift and cumulative vs baseline, working days
WindowPeriodShift (wd)Cumulative vs Baseline (wd)CP ActivitiesCP Duration ChangesSlipped Activities
Baseline → Current01-Apr-2025 → 01-Jul-2025+21 wd+21 wd3915281
A-02

Window Shift Trend

signed completion shift per window (working days)
Window slip (working days)1 window
21 wd10 wd0 wd+21 wdBaseline → Current
Window slip (positive = delay)+21 wd total window shift
A-03

Cumulative Attribution Summary

party share of project slip-days
Attribution by responsible party (wd)21 wd total
Owner9 wdContractor12 wdConcurrent0 wdForce Majeure0 wdUnattributed0 wd
Attributed party share21 wd total project slip
Owner
9 wd
Contractor
12 wd
Concurrent
0 wd
Force Majeure
0 wd
A-04

Concurrent Delay Matrix

per-window × per-party attribution grid
Each cell = working days attributed to that party in that window (Window Shift (wd)). Column totals equal the cumulative party share across the project, which is a bookkeeping definition internal to this matrix rather than an AACE rule. The grand total equals the project completion shift in working days (CPP conservation check, per the AACE 29R-03 §3.3.E.13 requirement that the summed per-period net impacts equal the difference between the first and last schedule update in the evaluation). The Finish Driver column names the activity and date field the shift was measured on.
WindowPeriodOwnerContractorConcurrentForce MajeureUnattributedWindow Shift (wd)Finish Driver
Baseline → Current01-Apr-2025 → 01-Jul-2025+9 wd+12 wd+21 wdA4240
early_end_date
Cumulativeproject totals+9 wd+12 wd0 wd0 wd0 wd+21 wd
~CASCADE = window had no CP duration growth; attribution inferred from dominant CP slip party. !UNATTRIBUTED = the dominant share of the window shift dropped to Unattributed (no named responsible party). Reference: AACE RP 29R-03 §3.3.I (apportionment) · §4.2 (concurrency).
A-05

Slip Velocity & Acceleration

per-window slip-rate trend
Velocity = signed completion shift (working days) ÷ window duration (working days on the same calendar). Acceleration = change in velocity vs the prior window. Half-period estimate (working days) assumes uniform deterioration within the window.
Mean Velocity (wd/wd)
+0.339
working-days slip / working-day elapsed
Max-Velocity Window
fastest deterioration
Accelerating Windows
0
velocity increasing
Decelerating Windows
0
velocity decreasing
WindowPeriodDuration (wd)Shift (wd)Velocity (wd/wd)Δ AccelerationMidpoint DateHalf-Period Slip (wd)
Baseline → Current01-Apr-2025 → 01-Jul-202562 wd+21 wd+0.33916-May-2025+10.5 wd
Caveat (cite in any expert report): Slip velocity is a working-day/working-day rate: numerator = working-day completion shift, denominator = working days between data dates on the same calendar (see basis). Midpoint estimates assume uniform deterioration within the window. Actual slip events may have clustered at any point inside the window. The midpoint is a probabilistic centroid, not an observed event date. Cite this caveat in any expert report that quotes the half-period estimate. Velocity is a per-window average rate, not an instantaneous one; acceleration is a finite difference between successive averages and is sensitive to window-length disparity (sign and direction are reliable, magnitude less so).
Recovery windows (negative shift) detected: 0. Reference: AACE RP 29R-03 §3.3 (Windows Analysis: MIP 3.3 Observational / Dynamic).
A-06

WOET — Worked-vs-On-time Execution Timeline

4-state day classification
4-state day classification of as-built execution against the baseline plan. All day counts below are working days on each activity’s P6 calendar (weekends and holidays excluded). Reference date: 2025-07-01. Activities classified: 119. On-time-or-better: 20.1% (Progress 17.1% + Gain). Slipped: 80.0% (Extended + Void).
Progress (wd)
342 wd
17.1% on plan
Gain (wd)
3.0% ahead
Extended (wd)
440 wd
22.0% slipped
Void (wd)
1159 wd
58.0% unrecovered
A-06Worst-affected activities (sorted Extended → Void — full list)
119 classified activities — all listedExport CSV
CodeActivityBaseline PeriodActual PeriodProgress (wd)Gain (wd)Extended (wd)Void (wd)
A1160TPO Roofing Shop Drawings2025-06-05 → 2025-06-192025-07-09 → 2025-08-260 wd0 wd35 wd11 wd
A3930Interior Demolition2025-06-13 → 2025-07-072025-07-21 → 2025-09-020 wd0 wd31 wd16 wd
A146023 25 00 - Water Treatment (R0)2025-06-26 → 2025-07-042025-06-26 → 2025-08-126 wd0 wd27 wd0 wd
A1280ACT Data sheet and Sample2025-07-11 → 2025-07-252025-07-23 → 2025-08-273 wd0 wd23 wd8 wd
A2500Install Rebar for Piers2025-07-31 → 2025-08-082025-07-29 → 2025-09-087 wd2 wd20 wd0 wd
A1120Cold-formed Metal Framing Shop Drawings2025-06-05 → 2025-06-192025-06-26 → 2025-07-230 wd0 wd19 wd11 wd
A1100Structural Steel Framing and Steel Deck Shop Drawings (R0)2025-06-05 → 2025-06-192025-06-20 → 2025-07-140 wd0 wd16 wd11 wd
A1090Masonry and Mortar Samples & Data Sheets2025-07-11 → 2025-07-252025-06-10 → 2025-08-1811 wd22 wd16 wd0 wd
A2280Under Pinning Inspection2025-06-19 → 2025-06-202025-06-23 → 2025-07-140 wd0 wd15 wd2 wd
A2520Form and Pour Foundation Piers2025-08-08 → 2025-08-152025-08-11 → 2025-09-085 wd0 wd15 wd1 wd
A153020 05 10 - Electric Heat Tracing (R0)2025-07-09 → 2025-07-232025-07-09 → 2025-08-1211 wd0 wd14 wd0 wd
A2530Backfilling to U/S of Grade Beams2025-08-15 → 2025-08-222025-08-11 → 2025-09-126 wd4 wd14 wd0 wd
A1230Coiling Doors2025-07-11 → 2025-07-252025-08-05 → 2025-08-210 wd0 wd13 wd11 wd
A158026 50 00 - Lighting Fixtures2025-06-27 → 2025-07-142025-08-01 → 2025-08-180 wd0 wd12 wd11 wd
A159026 09 23 - Lighting Control (R0)2025-06-12 → 2025-06-262025-08-01 → 2025-08-180 wd0 wd12 wd11 wd
A1060Foundation Concrete Rebar Shop Drawing2025-06-05 → 2025-06-192025-05-29 → 2025-07-0811 wd5 wd12 wd0 wd
A147023 37 13 - Diffuser and Grilles Shop Drawings (R0)2025-07-15 → 2025-07-292025-07-15 → 2025-08-1411 wd0 wd12 wd0 wd
A1050Ductbank Underpinning Drawing2025-05-29 → 2025-06-122025-06-16 → 2025-06-300 wd0 wd11 wd11 wd
A156026 50 00 - Emergency Lighting & Exit Signs2025-06-27 → 2025-07-142025-06-27 → 2025-07-2911 wd0 wd11 wd0 wd
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes2025-06-11 → 2025-06-242025-06-11 → 2025-07-0810 wd0 wd9 wd0 wd
A1080Bentonite Waterstop Data Sheet2025-06-05 → 2025-06-192025-06-09 → 2025-07-029 wd0 wd8 wd2 wd
A137023 74 13 - Air Handling Units (R0)2025-06-26 → 2025-07-112025-06-26 → 2025-07-2111 wd0 wd6 wd0 wd
A1290Suspended Metal Soffits2025-07-11 → 2025-07-252025-08-28 → 2025-09-040 wd0 wd5 wd11 wd
A1660Bentonite Waterstop 2025-06-19 → 2025-06-262025-07-03 → 2025-07-090 wd0 wd5 wd6 wd
A142023 57 00 - Heat Exchangers2025-06-23 → 2025-06-252025-06-23 → 2025-07-033 wd0 wd5 wd0 wd
A157027 10 00 - Structural Cabling System (Fiber Optic Cable)2025-07-11 → 2025-07-152025-07-11 → 2025-07-223 wd0 wd5 wd0 wd
A1070Foundation Concrete Mix Design2025-06-05 → 2025-06-192025-06-13 → 2025-06-255 wd0 wd4 wd6 wd
A151023 00 00 - Wall Fin Heater2025-07-22 → 2025-08-062025-07-22 → 2025-08-1212 wd0 wd4 wd0 wd
A154022 40 00 - Plumbing Fixtures (R0)2025-07-11 → 2025-07-252025-07-11 → 2025-07-3111 wd0 wd4 wd0 wd
A1190Fire-resistive Material Data Sheet2025-06-19 → 2025-07-042025-06-27 → 2025-07-095 wd0 wd3 wd6 wd
A1150Built-up Roofing Shop Drawings2025-06-19 → 2025-07-042025-06-19 → 2025-07-0911 wd0 wd3 wd0 wd
A139023 25 00 - Buffer Tanks2025-06-24 → 2025-06-272025-06-24 → 2025-07-034 wd0 wd3 wd0 wd
A140023 21 16 - Air Separator2025-06-24 → 2025-06-272025-06-24 → 2025-07-034 wd0 wd3 wd0 wd
A141023 21 16 - Expansion Tanks2025-06-24 → 2025-06-272025-06-24 → 2025-07-034 wd0 wd3 wd0 wd
A1220Flush Wood Doors Sample2025-07-11 → 2025-07-252025-08-26 → 2025-08-270 wd0 wd2 wd11 wd
A2240Construction Site Setup. Fencing and Temp Facilities2025-06-05 → 2025-06-122025-06-10 → 2025-06-163 wd0 wd2 wd3 wd
A2260Top Soil Stripping2025-06-13 → 2025-06-182025-06-18 → 2025-06-201 wd0 wd2 wd3 wd
A2300Setup Hoarding @ Vestibule F1002025-06-12 → 2025-06-162025-06-17 → 2025-06-180 wd0 wd2 wd3 wd
A2290Existing Structure Under Pinning2025-06-19 → 2025-07-112025-06-24 → 2025-07-1513 wd0 wd2 wd3 wd
A2330Gas Meter and Pipe Relocation Investigation2025-06-12 → 2025-06-172025-06-17 → 2025-06-191 wd0 wd2 wd3 wd
A2340Gas Meter and pipe Relocation2025-06-17 → 2025-06-192025-06-20 → 2025-06-230 wd0 wd2 wd3 wd
A2350Daylighting of Existing Hydro Ductbank & Services2025-06-18 → 2025-07-032025-06-23 → 2025-07-078 wd0 wd2 wd3 wd
A1020Subcontract Award2025-04-30 → 2025-05-292025-05-05 → 2025-06-0218 wd0 wd2 wd3 wd
A1650Foundation Concrete Mix Design2025-06-19 → 2025-06-232025-06-26 → 2025-06-270 wd0 wd2 wd3 wd
A2370Bulk Excavation to U/S of Footings2025-07-11 → 2025-07-182025-07-16 → 2025-07-223 wd0 wd2 wd3 wd
A2320Demolition of Existing Vestibule F1002025-06-16 → 2025-06-232025-06-18 → 2025-06-254 wd0 wd2 wd2 wd
A2230Ontario Community College Auto Show2025-04-30 → 2025-06-052025-06-09 → 2025-06-090 wd0 wd1 wd26 wd
A1680 IN-PROGRESSStructural Steel 2025-06-19 → 2025-07-252025-09-04 → —0 wd0 wd1 wd26 wd
A1130 IN-PROGRESSMisc. Metals Shop Drawings2025-07-04 → 2025-07-182025-08-26 → —0 wd0 wd1 wd11 wd
A1330 IN-PROGRESSFall Arrest Anchors and Horizontal Lines2025-07-11 → 2025-07-252025-08-14 → —0 wd0 wd1 wd11 wd
A1110Structural Reinforcement + Decking Shop Drawings2025-06-05 → 2025-06-192025-08-01 → 2025-08-010 wd0 wd1 wd11 wd
A1500 IN-PROGRESS23 52 16 - Heating Boilers2025-07-09 → 2025-07-232025-09-12 → —0 wd0 wd1 wd11 wd
A1040Permit (Not Required Per Ontario Community College)2025-05-12 → 2025-05-132025-05-16 → 2025-05-160 wd0 wd1 wd2 wd
A1010Contract Award2025-04-29 → 2025-04-302025-05-02 → 2025-05-020 wd0 wd1 wd2 wd
A1030IFC Drawings Released2025-05-09 → 2025-05-122025-05-15 → 2025-05-150 wd0 wd1 wd2 wd
A2270Excavation for Under Pinning2025-06-18 → 2025-06-192025-06-23 → 2025-06-230 wd0 wd1 wd2 wd
A2250Tree Removal, Protection and Equipment Mobilization2025-06-12 → 2025-06-132025-06-17 → 2025-06-170 wd0 wd1 wd2 wd
A2310Relocate FAA2025-06-12 → 2025-06-162025-06-16 → 2025-06-171 wd0 wd1 wd2 wd
A3920Setup Temporary Hoarding2025-06-12 → 2025-06-132025-07-04 → 2025-07-040 wd0 wd1 wd2 wd
A3780Layout for Elevator Cylinder2025-06-18 → 2025-06-192025-06-23 → 2025-06-230 wd0 wd1 wd2 wd
A3790Drilling Elevator Cylinder from Grade2025-06-19 → 2025-06-202025-06-24 → 2025-06-240 wd0 wd1 wd2 wd
A3800Install Steel Casing into the ground2025-06-20 → 2025-06-232025-06-25 → 2025-06-250 wd0 wd1 wd2 wd
A2380Bulk Excavation to U/S North Stair Footing2025-07-18 → 2025-07-212025-07-23 → 2025-07-230 wd0 wd1 wd2 wd
A2510Supply of Embedment & Ankors2025-06-19 → 2025-06-202025-08-22 → 2025-08-220 wd0 wd1 wd2 wd
A2600Compaction Inspection2025-04-01 → 2025-09-192025-08-15 → 2025-08-151 wd0 wd0 wd95 wd
A2390Subgrade Inspection2025-04-01 → 2025-07-252025-07-22 → 2025-07-221 wd0 wd0 wd77 wd
A3320Blocking Installation2025-04-01 → 2026-04-09— → —0 wd0 wd0 wd63 wd
A3480Blocking Installation2025-04-01 → 2026-04-23— → —0 wd0 wd0 wd63 wd
A3610Blocking Installation2025-04-01 → 2026-05-04— → —0 wd0 wd0 wd63 wd
A2660Install Temporary Hoarding for Slab on Deck2025-04-01 → 2025-11-03— → —0 wd0 wd0 wd63 wd
A3180Roof Inspection2025-04-01 → 2025-12-19— → —0 wd0 wd0 wd63 wd
A2620Structural Steel Inspection2025-04-01 → 2025-10-20— → —0 wd0 wd0 wd63 wd
A3080L1, L2 & L3 Air Vapor Barrier Inspection2025-04-01 → 2026-02-25— → —0 wd0 wd0 wd63 wd
A3250Fire Spraying & Intumescent Paint Inspection2025-04-01 → 2026-02-25— → —0 wd0 wd0 wd63 wd
A2540Compaction Inspection2025-04-01 → 2025-08-22— → —0 wd0 wd0 wd63 wd
A2150 IN-PROGRESS26 50 00 - Lighting Fixtures2025-07-14 → 2025-11-202025-08-19 → —1 wd0 wd0 wd26 wd
A1180 IN-PROGRESSExterior Wall Cladding Shop Drawings2025-07-25 → 2025-08-112025-08-11 → —1 wd0 wd0 wd11 wd
A2450Rebar for Pad Footings2025-07-08 → 2025-07-292025-07-23 → 2025-07-242 wd0 wd0 wd11 wd
A1210 IN-PROGRESSInterior Aluminum Screen2025-07-11 → 2025-07-252025-07-25 → —1 wd0 wd0 wd10 wd
A1170Air Barrier System Data Sheet and Mockup2025-06-19 → 2025-07-04— → —0 wd0 wd0 wd8 wd
A1700Cold-formed Metal Framing 2025-06-19 → 2025-07-04— → —0 wd0 wd0 wd8 wd
A1740TPO Roofing (Bridge)2025-06-19 → 2025-08-04— → —0 wd0 wd0 wd8 wd
A1690Structural Reinforcement2025-06-19 → 2025-09-16— → —0 wd0 wd0 wd8 wd
A2140 IN-PROGRESS26 27 26 - Wiring Devices, Service Poles, & Floor Boxes2025-06-26 → 2025-11-052025-07-09 → —1 wd0 wd0 wd8 wd
A3940Existing Slab Removal and Trenching2025-06-12 → 2025-06-19— → —0 wd0 wd0 wd6 wd
A2160 IN-PROGRESS27 10 00 - Structural Cabling System (Fiber Optic Cable)2025-07-15 → 2026-04-212025-07-23 → —1 wd0 wd0 wd6 wd
A2420 IN-PROGRESSForm and Pour North Exit Stair2025-07-29 → 2025-09-252025-08-04 → —1 wd0 wd0 wd4 wd
A1350Sprinkler & Standpipe Shop Drawings2025-06-26 → 2025-07-11— → —0 wd0 wd0 wd3 wd
A218026 09 23 - Lighting Control2025-06-26 → 2025-11-05— → —0 wd0 wd0 wd3 wd
A2220Testing and Inspection Cash Allowance Expenditure2025-05-12 → 2025-05-13— → —0 wd0 wd0 wd2 wd
A1000Tender Closing2025-04-01 → 2025-04-292025-04-01 → 2025-04-2920 wd0 wd0 wd0 wd
A2360Ductbank Shoring 2025-07-03 → 2025-07-172025-06-23 → 2025-07-084 wd7 wd0 wd0 wd
A3960Vinyl Flooring Abatement (Cash Allowance)2025-07-07 → 2025-07-142025-07-07 → 2025-07-115 wd0 wd0 wd0 wd
A1340Hydraulic Lift Shop Drawings2025-06-26 → 2025-07-112025-06-26 → 2025-07-099 wd0 wd0 wd0 wd
A1630Ductbank Underpinning 2025-06-12 → 2025-06-192025-05-28 → 2025-05-280 wd1 wd0 wd0 wd
A1640Foundation Concrete Rebar 2025-06-19 → 2025-07-042025-06-13 → 2025-06-130 wd1 wd0 wd0 wd
A136023 82 19 - Fan Coil Units (R0)2025-06-19 → 2025-07-042025-06-19 → 2025-07-0310 wd0 wd0 wd0 wd
A138023 21 23 - Pumps (R0)2025-06-24 → 2025-07-092025-06-24 → 2025-07-048 wd0 wd0 wd0 wd
A143022 33 00 - Electric Domestic Water Heaters2025-06-19 → 2025-07-032025-06-19 → 2025-07-0310 wd0 wd0 wd0 wd
A144023 81 26 - Split System2025-06-12 → 2025-06-302025-06-12 → 2025-06-3013 wd0 wd0 wd0 wd
A145022 13 29 - Sump Pumps (R0)2025-06-09 → 2025-06-202025-05-27 → 2025-06-020 wd5 wd0 wd0 wd
A148023 00 00 - Exhaust Fans (R0)2025-07-22 → 2025-08-062025-07-22 → 2025-07-221 wd0 wd0 wd0 wd
A149023 00 00 - Unit Heater2025-07-22 → 2025-08-062025-07-22 → 2025-07-221 wd0 wd0 wd0 wd
A1520 IN-PROGRESS23 74 13 - Air Source Heat Pump2025-06-26 → 2025-07-102025-06-26 → —3 wd0 wd0 wd0 wd
A1980 IN-PROGRESS23 25 00 - Buffer Tanks2025-07-04 → 2025-12-242025-07-04 → —1 wd0 wd0 wd0 wd
A1990 IN-PROGRESS23 21 16 - Air Separator2025-07-04 → 2025-11-112025-07-04 → —1 wd0 wd0 wd0 wd
A2000 IN-PROGRESS23 21 16 - Expansion Tanks2025-07-04 → 2025-11-112025-07-04 → —1 wd0 wd0 wd0 wd
A2010 IN-PROGRESS23 57 00 - Heat Exchangers2025-07-04 → 2025-11-112025-07-04 → —1 wd0 wd0 wd0 wd
A2020 IN-PROGRESS22 33 00 - Electric Domestic Water Heaters2025-07-04 → 2025-11-122025-07-04 → —1 wd0 wd0 wd0 wd
A2030 IN-PROGRESS23 81 26 - Split System2025-07-10 → 2025-11-182025-07-10 → —1 wd0 wd0 wd0 wd
A2040 IN-PROGRESS22 13 29 - Sump Pumps2025-06-19 → 2025-08-082025-06-19 → —8 wd0 wd0 wd0 wd
A160028 31 00 - Fire Alarm Shop Drawings and Data Sheets2025-06-11 → 2025-06-242025-06-11 → 2025-06-175 wd0 wd0 wd0 wd
A2190 IN-PROGRESS28 31 00 - Fire Alarm2025-06-26 → 2025-11-052025-06-18 → —3 wd6 wd0 wd0 wd
A2400Subgrade Preparation2025-07-25 → 2025-07-282025-07-23 → 2025-07-230 wd1 wd0 wd0 wd
A2410Soil Bearing Capacity Inspection2025-07-28 → 2025-07-292025-07-24 → 2025-07-240 wd1 wd0 wd0 wd
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)2025-07-25 → 2025-07-282025-07-23 → 2025-07-230 wd1 wd0 wd0 wd
A2460Rebar Inspection2025-07-29 → 2025-07-302025-07-25 → 2025-07-250 wd1 wd0 wd0 wd
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)2025-07-30 → 2025-07-312025-07-28 → 2025-07-280 wd1 wd0 wd0 wd
A2490Concrete Field Testing2025-07-30 → 2025-07-312025-07-28 → 2025-07-280 wd1 wd0 wd0 wd
119 classified activities — full list shown. Reference: Per-day execution-classification overlay on AACE RP 29R-03 §3.3 (Windows Analysis, MIP 3.3). A CPP-disclosed enhancement, NOT itself AACE-defined. Day counts are working days on each activity P6 calendar (weekends and holidays excluded), not calendar days.
A-07

Float Burndown Across Windows

per-activity float-erosion register, drawing-sheet exhibit
A-07

Criticality predates the window: 38 of 99 activities opened at TF ≤ 0 at Baseline, and 14 more demonstrably burned their float to zero as completion moved 21 working days later

Total float in working days (wd), read from the schedule of record at 2 CPM snapshots, Baseline through Current spanning 1 window, day math on the project working calendar. Criticality test: TF ≤ 0. Sign convention: negative Δ = float lost across the window. Finish driver A4240; completion Baseline → Current: 21 wd later. Register bands: TF ≤ 0 · 1-5 wd (near-critical) · 6-20 wd · over 20 wd.

FirmCritical Path Partners
ExhibitFloat erosion register
Generated30-Aug-2026
UnitsWorking days
BasisAACE RP 29R-03
Snapshots2
ScaleBroken at 40 wd
Critical at Baseline
38
at TF ≤ 0 when the first window opened · no in-window crossing is claimed for them
Demonstrably lost float in window
14
a TF > 0 observation followed by TF ≤ 0 at a later snapshot
Never reached TF ≤ 0
11
positive float at every observation
Single-observation entrants: 36

36 further activities first appear with one observation only. No second reading exists, so a loss of float cannot be demonstrated for them and is not claimed here.

conservation: 38 + 14 + 36 + 11 = 99 · reconciles to the register below

KEYTF at first observationfloat lostfloat gainedTF ≤ 0 at last observation (critical)TF > 0 at last observation
TF = 0 (critical)near-critical band ≤ 5 wd, per register bandingFloat lost across the window · 15 activities, sorted by lossFloat gained across the window · 35 activities, sorted by gainA4050A4070A4060A4030A4040A4080A4090A4100A4110A4120A4170A1690A3240A3250A3260A2480A2560A2570A3210A3220A2540A2590A3290A3450A3580A3590A3610A3630A3640A3650A3660A3670A3710A3720A3750A3760A2550A2580A2610A2620A2650A2660A2670A2680A2690A2700A2710A3280A2440A3070−133 wd−128 wd−119 wd−12 wd−12 wd+310 wd · 5 → 315Δ −184 wd · largest loss in the windowA4050 · TF 184 → 0 · first at TF ≤ 0: Current010203040100200300Total float at snapshot, working days · axis breaks at 40 wd (section break marked): 1 wd ≈ 18.6 px left of the break, ≈ 1.0 px right · nothing clipped
All 99 activities by float band · Baseline vs Current
counts of activities per register band at the first and last observation
BaselineCurrent
2040606249TF ≤ 0Δ −1325151-5 wdΔ −108306-20 wdΔ +2245> 20 wdΔ +1

Reading notes

  1. Not plotted above: 49 activities with zero net float movement · 35 held TF ≤ 0 at every observation (11 observed at multiple snapshots, 24 single-observation) · 14 held constant positive float. All 99 appear in the register below.
  2. Baseline band counts in the inset carry the register convention: the 36 single-observation entrants are imputed at their only reading. The movement panel plots observed pairs only.
  3. The horizontal scale breaks at 40 wd, marked with a drafting section break. Nothing is clipped: A2480 reaches 315 wd on the compressed segment.
  4. Band deltas conserve across the population: −13 − 10 + 22 + 1 = 0 over 99 activities.
  5. Engine-reported recovery events (TF increase between consecutive snapshots): 35.
  6. Method caveat (cite in any expert report): Float burndown is post-processing of analyst-supplied CPM snapshots. Accuracy depends on the quality of the underlying schedule updates. Recovery events (TF increase) may reflect legitimate scope removal, schedule optimization, or activity deletion, and the analyst must verify which. Slip velocity is a linear average; actual burndown may be non-linear. The per-activity float-timeline presentation is not yet published in AACE/SCL literature; it is disclosed here as a CPP enhancement to the cited observational method.
SOURCE · activity float register, 99 activities · CPM snapshots (data dates of record): Baseline → Current (2 snapshots / 1 window) · float and Δ in working days on the project working calendar · observational window basis per AACE RP 29R-03 · criticality counts analyst-verified only · finish driver A4240 · completion Baseline → Current: 21 wd later · buckets reconcile: 38 + 14 + 36 + 11 = 99 · method: compute_float_burndown v2.9.42
Activity register · all 99 activities TF FIRST / LAST · Δ · FIRST AT TF ≤ 0
ActivityTF at Baseline (wd)TF at Current (wd)Δ (wd)First at TF ≤ 0Movement
A1000220neversingle observation
A1010220neversingle observation
A1020220neversingle observation
A1060220neversingle observation
A1110.1000Currentsingle observation
A1640220neversingle observation
A169070−7Currentlost
A2230550neversingle observation
A2240550neversingle observation
A2290550neversingle observation
A2300550neversingle observation
A2310550neversingle observation
A2320550neversingle observation
A2370550neversingle observation
A2390000Baselinesingle observation
A2400000Baselinesingle observation
A2430000Baselinesingle observation
A2440514+9nevergained
A2450000Baselinesingle observation
A2460000Baselinesingle observation
A2470000Baselinesingle observation
A24805315+310nevergained
A2490000Baselinesingle observation
A2500000Baselinesingle observation
A2520000Baselinesingle observation
A2530000Baselinesingle observation
A2540020+20Baselinegained
A2550014+14Baselinegained
A2560342+39nevergained
A2570039+39Baselinegained
A2580416+12nevergained
A2590016+16Baselinegained
A2610012+12Baselinegained
A2620012+12Baselinegained
A2650012+12Baselinegained
A2660012+12Baselinegained
A2670012+12Baselinegained
A2680012+12Baselinegained
A2690012+12Baselinegained
A2700012+12Baselinegained
A2710012+12Baselinegained
A2740440neverno movement
A2750000Baselineno movement
A2880000Baselineno movement
A2970000Baselineno movement
A3060000Baselineno movement
A3070510+5nevergained
A3210021+21Baselinegained
A3220021+21Baselinegained
A324050−5Currentlost
A325050−5Currentlost
A326050−5Currentlost
A3280515+10nevergained
A3290015+15Baselinegained
A3450015+15Baselinegained
A3580015+15Baselinegained
A3590015+15Baselinegained
A3610015+15Baselinegained
A3630015+15Baselinegained
A3640015+15Baselinegained
A3650015+15Baselinegained
A3660520+15nevergained
A3670015+15Baselinegained
A3710015+15Baselinegained
A3720520+15nevergained
A3750015+15Baselinegained
A3760015+15Baselinegained
A40301190−119Currentlost
A4040120−12Currentlost
A4040x000Currentsingle observation
A40501840−184Currentlost
A40601280−128Currentlost
A40701330−133Currentlost
A4080120−12Currentlost
A4090120−12Currentlost
A4100120−12Currentlost
A4110120−12Currentlost
A4120120−12Currentlost
A4170165−11neverlost
A4180000Baselineno movement
A4190000Baselineno movement
A4200000Baselineno movement
A4210000Baselineno movement
A4220550neverno movement
A4240000Baselineno movement
A4250000Baselineno movement
A4260000Baselineno movement
A4400000Currentsingle observation
A4420000Currentsingle observation
A4430000Currentsingle observation
A4450000Currentsingle observation
A4460000Currentsingle observation
A4470000Currentsingle observation
A4480000Currentsingle observation
A4490000Currentsingle observation
A4500000Currentsingle observation
A4520000Currentsingle observation
A4590000Currentsingle observation
A4820000Currentsingle observation
NOTE · for the 36 single-observation rows the register carries the only reading in both float columns; no other observation exists for them · engine order preserved (activity code ascending) · compute_float_burndown v2.9.42
A-08

Cumulative Activity Slip Register

sum of signed slip across all windows
A-08Most-slipped first — full list (309 activities)
309 rows — all listedExport CSV
Sum of signed slip across all windows per activity. Most-slipped first. Activities whose signed slip sums to zero working days are not listed here; the per-window registers (A-09 onward) list every mover, including 0 wd rows.
CodeActivityTotal SlipWindows Touched
A4070 CPFrames installation+182 wd1
A4060 CPBlocking+169 wd1
A4050 CPSprinkler Rough-ins+162 wd1
A4030 CPNew Partition Framing+136 wd1
A3850Foundations+126 wd1
A3860Concrete Vertical Piers+126 wd1
A3870Removal of Existing Facade for Tie In+126 wd1
A3880Structural Steel erection including expansion plates +94 wd1
A3890Envelope +94 wd1
A4150New Exterior Paved Areas and Sidewalks +94 wd1
A4160Landscape Installations+94 wd1
A3940Existing Slab Removal and Trenching+90 wd1
A3900Interior M&E Rough in +84 wd1
A209023 52 16 - Heating Boilers+71 wd1
A3910Interior Finishes+65 wd1
A2730Stairs B Installation @ North Side+62 wd1
A1710Misc. Metals +62 wd1
A2720Tactile Attention Indicators Mock-up+62 wd1
A150023 52 16 - Heating Boilers+62 wd1
A195023 82 19 - Fan Coil Units+62 wd1
A205023 25 00 - Water Treatment+61 wd1
A206023 37 13 - Diffuser and Grilles+60 wd1
A3270New Stair A Installation+59 wd1
A2540Compaction Inspection+58 wd1
A218026 09 23 - Lighting Control+55 wd1
A3170Install Built-up Roof+54 wd1
A1130Misc. Metals Shop Drawings+53 wd1
A3180Roof Inspection+52 wd1
A1680Structural Steel +48 wd1
A1160TPO Roofing Shop Drawings+47 wd1
A1740TPO Roofing (Bridge)+46 wd1
A1330Fall Arrest Anchors and Horizontal Lines+45 wd1
A2640Install Roof Decking+44 wd1
A2630Install Roof Anchors +44 wd1
A1920Fall Arrest Anchors and Horizontal Lines+44 wd1
A3150Roof Parapet Framing+44 wd1
A3160Roof Penetration Layout+44 wd1
A2510Supply of Embedment & Ankors+44 wd1
A2580Underground Drainage+43 wd1
A213022 40 00 - Plumbing Fixtures+42 wd1
A3930Interior Demolition+40 wd1
A2590Backfilling to U/S of SOG+39 wd1
A197023 21 23 - Pumps+38 wd1
A159026 09 23 - Lighting Control (R0)+36 wd1
A215026 50 00 - Lighting Fixtures+35 wd1
A2220Testing and Inspection Cash Allowance Expenditure+34 wd1
A196023 74 13 - Air Handling Units+34 wd1
A2440Formwork Remaining Pad Footing (Ramp)+34 wd1
A4040 CPMEP Rough-ins+33 wd1
A4080 CPDrywall/Sheathing Installation+33 wd1
A4090 CPTaping and mudding+33 wd1
A4110 CPTile and Rubber Flooring Installation+33 wd1
A4100 CPPainting+33 wd1
A4120 CPFinal Terminations and Fixtures Installation+33 wd1
A212020 05 10 - Electric Heat Tracing+33 wd1
A4170Fire Alarm Verification+32 wd1
A1110Structural Reinforcement + Decking Shop Drawings+30 wd1
A1290Suspended Metal Soffits+28 wd1
A1820Coiling Doors+28 wd1
A1870ACT & ACB +27 wd1
A146023 25 00 - Water Treatment (R0)+27 wd1
A158026 50 00 - Lighting Fixtures+25 wd1
A1700Cold-formed Metal Framing +24 wd1
A1120Cold-formed Metal Framing Shop Drawings+23 wd1
A1220Flush Wood Doors Sample+23 wd1
A1280ACT Data sheet and Sample+23 wd1
A4240 CPMinor Deficiencies & Touch-ups+22 wd1
A1810Flush Wood Doors +22 wd1
A4260 CPTotal Completion +21 wd1
A4220Final Cleaning +21 wd1
A4180 CPMechanical, Electrical and Elevator Commissioning+21 wd1
A4190 CPIntegrated Testing+21 wd1
A4250 CPReady-To-Take Over+21 wd1
A4230Close-out Documents & Training+21 wd1
A4210 CPOccupancy+20 wd1
A2500Install Rebar for Piers+20 wd1
A4200 CPSubstantial Performance+19 wd1
A1230Coiling Doors+19 wd1
A1180Exterior Wall Cladding Shop Drawings+18 wd1
A1210Interior Aluminum Screen+18 wd1
A1760Exterior Wall Cladding+18 wd1
A1800Interior Aluminum Screens+17 wd1
A1090Masonry and Mortar Samples & Data Sheets+16 wd1
A1100Structural Steel Framing and Steel Deck Shop Drawings (R0)+16 wd1
A2550Form and Pour Grade Beams+16 wd1
A2560Below Grade Vapour Barrier Mock-up+16 wd1
A2570Footing Vapor Barrier & Insulation+16 wd1
A2750 CPL1, L2 & L3 Framing and Sheathing Installation+15 wd1
A2880 CPL1, L2 & L3 Framing and Sheathing Installation+15 wd1
A2890L1 Masonry Wall Installation+15 wd1
A2770L1 Masonry Wall installation+15 wd1
A2790L1, L2 & L3 Air Vapour Barrier Installation+15 wd1
A3260 CPSeal Concrete Floor+15 wd1
A3430Seal concrete Floor+15 wd1
A3280New partition framing+15 wd1
A3330Door frames Installation+15 wd1
A3440New partition framing+15 wd1
A3560Seal concrete Floor+15 wd1
A1670Masonry and Mortar+15 wd1
A3420Fire Spraying & Intumescent Paint+15 wd1
A3550Fire Spraying & Intumescent Paint+15 wd1
A2820Glazing Site Measure and Scanning+15 wd1
A2280Under Pinning Inspection+15 wd1
A2760Masonry Mock-up+15 wd1
A2740Cold-Formed Metal Framing Mock+15 wd1
A3680Misc. Metals Mock-up+15 wd1
A2780Above Grade Vapour Mock-up+15 wd1
A2800AVB Inspection+15 wd1
A3250 CPFire Spraying & Intumescent Paint Inspection+15 wd1
A2520Form and Pour Foundation Piers+15 wd1
A3490Door frames Installation+14 wd1
A3520Door and Hardware Installation+14 wd1
A3620Door frames Installation+14 wd1
A3570New wall partition framing+14 wd1
A3920Setup Temporary Hoarding+14 wd1
A3240 CPFire Spraying & Intumescent Paint+14 wd1
A3210Electrical and Mechanical Room +14 wd1
A3690Misc. Metals installation+14 wd1
A3220Mech. and Elec. Equipment Installation+14 wd1
A153020 05 10 - Electric Heat Tracing (R0)+14 wd1
A2530Backfilling to U/S of Grade Beams+14 wd1
A1060Foundation Concrete Rebar Shop Drawing+12 wd1
A1050Ductbank Underpinning Drawing+12 wd1
A147023 37 13 - Diffuser and Grilles Shop Drawings (R0)+12 wd1
A3410Painting+11 wd1
A3300Electrical, FA & Comms rough-ins+11 wd1
A3320Blocking Installation+11 wd1
A3350Gypsum board Installation+11 wd1
A3360Drywall Taping and Mudding+11 wd1
A3390Interior Aluminum/Glazing Screens Installation+11 wd1
A3370Door and Hardware Installation+11 wd1
A3810Install Controller at Machine Room+11 wd1
A3820Rails and Elevator Car installation+11 wd1
A3830Power to controller, Phone lines and Comms+11 wd1
A3840Elevator Testing and Commissioning+11 wd1
A3380Interior Aluminum/Glazing Screens Mock-up+11 wd1
A3340ACT Baffles Mock-ups+11 wd1
A3400Paint Mock-up+11 wd1
A156026 50 00 - Emergency Lighting & Exit Signs+11 wd1
A3290Mech. & Plumbing rough-ins+10 wd1
A3310Sprinkler Rough-ins+10 wd1
A3540Painting+9 wd1
A2610Erect Structural Steel+9 wd1
A2650Install Level 2 & 3 Decking+9 wd1
A3450Mech. & Plumbing rough-ins+9 wd1
A3480Blocking Installation+9 wd1
A3500Gypsum board Installation+9 wd1
A3460Electrical, FA & Comms rough-ins+9 wd1
A3510Drywall Taping and Mudding+9 wd1
A3530Interior Glazing Installation+9 wd1
A3590Electrical, FA & Comms rough-ins+9 wd1
A3580Mech. & Plumbing rough-ins+9 wd1
A3610Blocking Installation+9 wd1
A3470Sprinkler Rough-ins+9 wd1
A3600Sprinkler Rough-ins+9 wd1
A2660Install Temporary Hoarding for Slab on Deck+9 wd1
A2620Structural Steel Inspection+9 wd1
A1080Bentonite Waterstop Data Sheet+8 wd1
A1660Bentonite Waterstop +8 wd1
A214026 27 26 - Wiring Devices, Service Poles, & Floor Boxes+8 wd1
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes+7 wd1
A3750Washroom Partitions and Accessories Installation+6 wd1
A2670Rebar and Prep Work for Slab on Deck+6 wd1
A3110L1, L2 & L3 Exterior Glazing Installation (W09a, W09b)+6 wd1
A2930L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)+6 wd1
A2840L1, L2, L3 Exterior Glazing Installation (W05)+6 wd1
A3010L2 & L3 Exterior Glazing Installation (W08a, W08b)+6 wd1
A3720Ceiling/Wall Fixtures Installation+6 wd1
A3740Millwork Installation+6 wd1
A3710Tiling and rubber flooring Installation+6 wd1
A3670Painting+6 wd1
A3770Corner Guards and Wall Protection Installation+6 wd1
A3660Interior Glazing Installation+6 wd1
A3650Door and Hardware Installation+6 wd1
A3630Gypsum board Installation+6 wd1
A3640Drywall Taping and Mudding+6 wd1
A2850Exterior Cladding Site Measure and Scanning+6 wd1
A2940Exterior Cladding Site Measure and Scanning+6 wd1
A3020Exterior Cladding Site Measure and Scanning+6 wd1
A3100Glazing Shop Fabrication+6 wd1
A3120Exterior Cladding Site Measure and Scanning+6 wd1
A3760Plumbing Washroom Fixtures Installation+6 wd1
A3730Millwork Mock-up+6 wd1
A2810Aluminum & Metal Panel Cladding Mock-up+6 wd1
A3700Tiling & Rubber & Carpet Flooring Mock-up+6 wd1
A137023 74 13 - Air Handling Units (R0)+6 wd1
A203023 81 26 - Split System+6 wd1
A216027 10 00 - Structural Cabling System (Fiber Optic Cable)+6 wd1
A2680Concrete pour for slab on deck level 2 & 3+5 wd1
A2960L2 & L3 Cladding Installation (EW2)+5 wd1
A2870L1, L2 & L3 Cladding Installation (EW2a)+5 wd1
A3040L2 & L3 Cladding Installation (EW2)+5 wd1
A3050Horizontal Shading Louvers+5 wd1
A2900Air Vapor Barrier Installation+5 wd1
A3140L1, L2 & L3 Cladding Installation (EW2, EW2A)+5 wd1
A3070L1, L2 & L3 Air Vapor Barrier Installation+5 wd1
A2690Final Grading and Vapor Barrier for SOG+5 wd1
A2860Exterior Cladding Shop Fabrication+5 wd1
A2910Glazing Site Measure and Scanning+5 wd1
A2950Exterior Cladding Shop Fabrication+5 wd1
A3000Glazing Shop Fabrication+5 wd1
A3030Exterior Cladding Shop Fabrication+5 wd1
A3130Exterior Cladding Shop Fabrication+5 wd1
A3080L1, L2 & L3 Air Vapor Barrier Inspection+5 wd1
A142023 57 00 - Heat Exchangers+5 wd1
A157027 10 00 - Structural Cabling System (Fiber Optic Cable)+5 wd1
A2970 CPL2 & L3 Framing and Sheathing Installation+4 wd1
A3060 CPL1, L2 & L3 Framing and Sheathing Installation+4 wd1
A2980L2 & L3 Air Vapor Barrier Installation+4 wd1
A1070Foundation Concrete Mix Design+4 wd1
A1650Foundation Concrete Mix Design+4 wd1
A2830Glazing Shop Fabrication+4 wd1
A2920Glazing Shop Fabrication+4 wd1
A2990Glazing Site Measure and Scanning+4 wd1
A3090Glazing Site Measure and Scanning+4 wd1
A3230Fire Spraying & Intumescent Paint Mock-up+4 wd1
A151023 00 00 - Wall Fin Heater+4 wd1
A154022 40 00 - Plumbing Fixtures (R0)+4 wd1
A210023 00 00 - Wall Fin Heater+4 wd1
A1040Permit (Not Required Per Ontario Community College)+3 wd1
A1030IFC Drawings Released+3 wd1
A1150Built-up Roofing Shop Drawings+3 wd1
A1170Air Barrier System Data Sheet and Mockup+3 wd1
A1190Fire-resistive Material Data Sheet+3 wd1
A1350Sprinkler & Standpipe Shop Drawings+3 wd1
A1730Built-up Roofing +3 wd1
A1750Air Barrier System+3 wd1
A1770Fire-resistive Material +3 wd1
A1940Sprinkler & Standpipe Shop Drawings+3 wd1
A2710Concrete Pour and Curing for SOG+3 wd1
A2700Rebar Installation for SOG+3 wd1
A3190Hoisting Roof Equipment+3 wd1
A3200Roof Anchor System Installation+3 wd1
A139023 25 00 - Buffer Tanks+3 wd1
A140023 21 16 - Air Separator+3 wd1
A141023 21 16 - Expansion Tanks+3 wd1
A152023 74 13 - Air Source Heat Pump+3 wd1
A211023 74 13 - Air Source Heat Pump+3 wd1
A2240Construction Site Setup. Fencing and Temp Facilities+2 wd1
A1010Contract Award+2 wd1
A2230Ontario Community College Auto Show+2 wd1
A2270Excavation for Under Pinning+2 wd1
A2250Tree Removal, Protection and Equipment Mobilization+2 wd1
A2260Top Soil Stripping+2 wd1
A2300Setup Hoarding @ Vestibule F100+2 wd1
A2320Demolition of Existing Vestibule F100+2 wd1
A2290Existing Structure Under Pinning+2 wd1
A2330Gas Meter and Pipe Relocation Investigation+2 wd1
A2340Gas Meter and pipe Relocation+2 wd1
A2350Daylighting of Existing Hydro Ductbank & Services+2 wd1
A1020Subcontract Award+2 wd1
A1140Millwork Shop Drawings+2 wd1
A1200Hollow Metal Frames & Doors Shop Drawings+2 wd1
A1240Aluminum Framed Glazing System Shop Drawings+2 wd1
A1250Finished Hardware Schedule+2 wd1
A1260Stud framing and Gypsum Board Data Sheets+2 wd1
A1270Tiling Data sheet and samples+2 wd1
A1300Flooring Data Sheets and Samples+2 wd1
A1310Paint Drawdowns+2 wd1
A1320Washroom accessories and Partitions Shop Drawings+2 wd1
A1610Concrete Mix for Hardscapes+2 wd1
A1620Landscape Shop Drawings+2 wd1
A1720Millwork +2 wd1
A1780Hollow Metal Frames+2 wd1
A1830Aluminum Framed Glazing Systems+2 wd1
A1840Finished Hardware +2 wd1
A1850Stud framing & gypsum board+2 wd1
A1860Tiling +2 wd1
A1890Flooring +2 wd1
A1900Paint Drawdowns+2 wd1
A1910Washroom accessories and Partitions +2 wd1
A2200Concrete for Hardscape+2 wd1
A2210Landscape (unit pavers, furniture, etc)+2 wd1
A3780Layout for Elevator Cylinder+2 wd1
A3790Drilling Elevator Cylinder from Grade+2 wd1
A3800Install Steel Casing into the ground+2 wd1
A1690 CPStructural Reinforcement+2 wd1
A1790Hollow Metal Doors+2 wd1
A2370Bulk Excavation to U/S of Footings+2 wd1
A2380Bulk Excavation to U/S North Stair Footing+2 wd1
A2310Relocate FAA+1 wd1
A3960Vinyl Flooring Abatement (Cash Allowance)-1 wd1
A136023 82 19 - Fan Coil Units (R0)-1 wd1
A1340Hydraulic Lift Shop Drawings-2 wd1
A1930Hydraulic Lift -2 wd1
A4010Underground Plumbing Rough-ins-3 wd1
A138023 21 23 - Pumps (R0)-3 wd1
A2390Subgrade Inspection-3 wd1
A2400Subgrade Preparation-3 wd1
A2410Soil Bearing Capacity Inspection-3 wd1
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)-3 wd1
A2450Rebar for Pad Footings-3 wd1
A2460Rebar Inspection-3 wd1
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)-3 wd1
A2490Concrete Field Testing-3 wd1
A204022 13 29 - Sump Pumps-4 wd1
A2360Ductbank Shoring -7 wd1
A160028 31 00 - Fire Alarm Shop Drawings and Data Sheets-7 wd1
A219028 31 00 - Fire Alarm-7 wd1
A148023 00 00 - Exhaust Fans (R0)-11 wd1
A149023 00 00 - Unit Heater-11 wd1
A1640Foundation Concrete Rebar -14 wd1
A2420Form and Pour North Exit Stair-14 wd1
A1630Ductbank Underpinning -16 wd1
A145022 13 29 - Sump Pumps (R0)-16 wd1
A2480Concrete for Remaining Pad Footings (Ramp)-21 wd1
A208023 00 00 - Unit Heater-23 wd1
A2600Compaction Inspection-24 wd1
A207023 00 00 - Exhaust Fans-29 wd1
309 rows — full list shown.
A-09

Window 1 — Baseline → Current

01-Apr-2025 → 01-Jul-2025 · shift +21 wd
Window Shift (wd)+21 wd · CRITICALPeriod01-Apr-2025 → 01-Jul-2025
Newly Critical
activities added to CP
No Longer Critical
activities left CP
Slipped Activities
281
finish dates later (slip > 0 wd) · 28 recovered
CP Duration Changes
6 grew · 9 reduced
Completion-shift basis
The window shift is measured on the finish driver shown below. Scheduled finish (scd_end_date) is cross-checked but never used as the shift basis.
Shift basis
Latest activity finish
Finish activity
A4240
Date field used
early_end_date
Window shift (working days)
21 wd
Cumulative vs baseline (working days)
21 wd
Scheduled finish (prior)
31-Aug-2026
Scheduled finish (later)
30-Sep-2026
Basis vs project finish
Consistent
Critical-path duration changes (full list)
Each day of duration growth on a CP activity adds a day of direct delay to the project; a duration reduction recovers time. Growth rows and reduction rows are both listed, largest growth first.
CodeActivityPrior DurationLater DurationChange (wd)
A3240Fire Spraying & Intumescent Paint5.0 wd15.0 wd+10.0 wd
A4040MEP Rough-ins19.0 wd23.0 wd+4.0 wd
A4030New Partition Framing10.0 wd13.0 wd+3.0 wd
A4070Frames installation5.0 wd8.0 wd+3.0 wd
A4050Sprinkler Rough-ins10.0 wd13.0 wd+3.0 wd
A4240Minor Deficiencies & Touch-ups10.0 wd11.0 wd+1.0 wd
A4200Substantial Performance1.0 wd0.0 wd-1.0 wd
A4260Total Completion 1.0 wd0.0 wd-1.0 wd
A4210Occupancy1.0 wd0.0 wd-1.0 wd
A4250Ready-To-Take Over1.0 wd0.0 wd-1.0 wd
A4060Blocking10.0 wd7.0 wd-3.0 wd
A2970L2 & L3 Framing and Sheathing Installation25.0 wd14.0 wd-11.0 wd
A4080Drywall/Sheathing Installation38.0 wd10.0 wd-28.0 wd
A1690Structural Reinforcement61.0 wd30.0 wd-31.0 wd
A3250Fire Spraying & Intumescent Paint Inspection228.0 wd1.0 wd-227.0 wd
Newly Critical (28)
A1110.1Structural Reinforcement + Decking Shop Drawings (R1)
A1690Structural Reinforcement
A3240Fire Spraying & Intumescent Paint
A3250Fire Spraying & Intumescent Paint Inspection
A3260Seal Concrete Floor
A4030New Partition Framing
A4040MEP Rough-ins
A4040xMEP Rough-ins + Sprinkler
A4050Sprinkler Rough-ins
A4060Blocking
A4070Frames installation
A4080Drywall/Sheathing Installation
A4090Taping and mudding
A4100Painting
A4110Tile and Rubber Flooring Installation
A4120Final Terminations and Fixtures Installation
A4400Existing Columns Reinforcement
A4420Steel Joist Reinforcement Installation
A4430Stud Framing
A4450Plywood Blocking
A4460Drywall Installation
A4470Taping Drywall
A4480Paint
A4490Finishes
A4500CNC Machine Relocation (Cash Allowance)
A4520Setup Temporary Hoarding
A4590Steel Joist Reinforcement Installation
A4820Concrete Floor Sealer
No Longer Critical (37)
A2390Subgrade Inspection
A2400Subgrade Preparation
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)
A2450Rebar for Pad Footings
A2460Rebar Inspection
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)
A2490Concrete Field Testing
A2500Install Rebar for Piers
A2520Form and Pour Foundation Piers
A2530Backfilling to U/S of Grade Beams
A2540Compaction Inspection
A2550Form and Pour Grade Beams
A2570Footing Vapor Barrier & Insulation
A2590Backfilling to U/S of SOG
A2610Erect Structural Steel
A2620Structural Steel Inspection
A2650Install Level 2 & 3 Decking
A2660Install Temporary Hoarding for Slab on Deck
A2670Rebar and Prep Work for Slab on Deck
A2680Concrete pour for slab on deck level 2 & 3
A2690Final Grading and Vapor Barrier for SOG
A2700Rebar Installation for SOG
A2710Concrete Pour and Curing for SOG
A3210Electrical and Mechanical Room
A3220Mech. and Elec. Equipment Installation
A3290Mech. & Plumbing rough-ins
A3450Mech. & Plumbing rough-ins
A3580Mech. & Plumbing rough-ins
A3590Electrical, FA & Comms rough-ins
A3610Blocking Installation
A3630Gypsum board Installation
A3640Drywall Taping and Mudding
A3650Door and Hardware Installation
A3670Painting
A3710Tiling and rubber flooring Installation
A3750Washroom Partitions and Accessories Installation
A3760Plumbing Washroom Fixtures Installation
Logic changes
Added
Removed
Type Changed
Lag Changed
Activity set changes
Added (87)
217026 50 00 - Emergency Lighting & Exit Signs
A1100.1Structural Steel Framing and Steel Deck Shop Drawings (R1)
A1100.2Structural Steel Framing and Steel Deck Shop Drawings (R2)
A1110.1Structural Reinforcement + Decking Shop Drawings (R1)
A12380.123 21 23 - Pumps (R1)
A1280.1ACB Data sheet and Sample
A1360.123 82 19 - Fan Coil Units (R1)
A1360.223 82 19 - Fan Coil Units (R2)
A1370,123 74 13 - Air Handling Units (R1)
A1370xMetal Shelving
A1380xMetal Shelving (R1)
A1450.122 13 29 - Sump Pumps (R1)
A1460.123 25 00 - Water Treatment (R1)
A1470.123 37 13 - Diffuser and Grilles Shop Drawings (R1)
A1480.123 00 00 - Exhaust Fans (R1)
A1530.120 05 10 - Electric Heat Tracing (R1)
A1540.122 40 00 - Plumbing Fixtures (R1)
A1590.126 09 23 - Lighting Control (R1)
A2090xMetal Shelving
A2410xRFI #17 Demo Clarification
A2420xPC-002 Demo Clarification Issuance
A2430xPCO-008 (Quote) Submission
A2440xCO-005 Issuance
A2450xCD-01 Water Room Demo (Elec. FACP) Issuance
A2460xCD-01 Fire Alarm Panel Relocation
A2470xWater Room Block Wall Demo
A2480xExisting Vestibule Slab Cutting
A2490xExisting Vestibule Slab Removal
A2500xR1 - RFI #19 & 20 - Existing DCW and Sanitary Line
A2510xR2 - RFI 06 - SI-002 Existing Gas Piping and Meter Relocation
A2520xR3 - RFI 45 - City of Barrie Water Department - Request to Review Drawings
A2530.1Backfilling to U/S of Grade Beams (GL AA)
A2530xR4 - PC-004 Grade Beam Rebar
A2540xR5 - RFI #39R2 Jewelery Workshop Interior Fitout
A2550xR6 - RFI 60 Sprinkler Diesel Pump
A2560xR7 - SP 3 & 4 - 3rd Floor Fan Coil Units Scope
A4040xMEP Rough-ins + Sprinkler
A4310Mobilize Temporary Student Washrooms
A4340Electrical and Mechanical Make Safe
A4370Underground Mechanical Installation (DCW, Sprinkler)
A4380Backfilling and Concrete for SOG
A4390Review Interferences with Steel Joist
A4400Existing Columns Reinforcement
A4410Joist Interferences Relocation
A4420Steel Joist Reinforcement Installation
A4430Stud Framing
A4450Plywood Blocking
A4460Drywall Installation
A4470Taping Drywall
A4480Paint
A4490Finishes
A4500CNC Machine Relocation (Cash Allowance)
A4510Metal Shelving Installation
A4520Setup Temporary Hoarding
A4530Electrical and Mechanical Make Safe
A4540Interior Demolition
A4550Existing Exterior Wall Demo (New Building Must be Erected and Enclosed)
A4560Review Interferences with Steel Joist
A4570Joist Interferences Relocation
A4580New Columns Installation
A4590Steel Joist Reinforcement Installation
A4600Stud Framing
A4610MEP Rough-ins
A4620Plywood Blocking
A4630Drywall Installation
A4640Taping Drywall
A4650Painting
A4660Setup Temporary Hoarding
A4670Electrical and Mechanical Make Safe
A4680Interior Demolition
A4690Electrical Fixtures
A4700Review Interferences with Steel Joist
A4710Relocation of Interferences
A4720Existing Column Reinforcement
A4730Steel Joist Reinforcement Installation
A4740Concrete Scanning & Cutting
A4760Trench Backfill
A4770Concrete Slab Infill
A4780New Columns Installation
A4790Existing Column Reinforcement
A4800Flatness Survey @ Floor Slab
A4810Self Levelling
A4820Concrete Floor Sealer
A5070Removal of Existing Water and Sanitary
A5220Weather Impact (Rain) - August 28, 2025
A5230Footings and Piers Along GL-B.1 (Successor to CO-005)
A5250Weather Impact (Rain) - September 04, 2025
Removed (10)
A1880Suspended Metal Soffits
A217026 50 00 - Lighting Fixtures & Controls
A3950Relocation of Interferences with Structural Reinforcement (Cash Allowance)
A3970Existing Roof Demolition
A3980Structural Joist and Column Reinforcement
A3990Fire Spraying
A4000New Roof Installation
A4020Concrete Patching and infills
A4130Equipment Relocation to final location
A4140Removal & Disposal of Existing HRAC Equipment
A-09Slip register — 309 activities (full list)
309 activities — all listedExport CSV
Movement split: 281 slipped (slip > 0 wd) · 28 recovered (negative slip). All 309 rows listed.
Attribution basis complete: every root-cause slip carries a responsible party. Cascade recipients of the same events are listed without independent attribution.
CodeActivityPrior FinishLater FinishSlipResponsible PartyCause Notes
A4070 CPFrames installation30-Sep-202519-Jun-2026+182 wdContractorFrame installation at the end of the delayed interior chain
A4060 CPBlocking07-Oct-202509-Jun-2026+169 wdContractorBlocking follows sprinkler rough-in in the interior chain
A4050 CPSprinkler Rough-ins07-Oct-202529-May-2026+162 wdContractorSprinkler rough-in follows partition framing; trade stacking on remobilization
A4030 CPNew Partition Framing23-Sep-202508-Apr-2026+136 wdContractorFraming crew availability following remobilization
A3850Foundations22-Aug-202523-Feb-2026+126 wdOwnerDiffering site condition at the existing facade tie-in
A3860Concrete Vertical Piers29-Aug-202502-Mar-2026+126 wdOwnerFollows delayed foundations at the tie-in
A3870Removal of Existing Facade for Tie In03-Sep-202505-Mar-2026+126 wdOwnerExisting facade removal held for tie-in condition resolution
A3880Structural Steel erection including expansion plates 10-Nov-202526-Mar-2026+94 wd
A3890Envelope 15-Dec-202530-Apr-2026+94 wd
A4150New Exterior Paved Areas and Sidewalks 14-Jan-202629-May-2026+94 wd
A4160Landscape Installations28-Jan-202612-Jun-2026+94 wd
A3940Existing Slab Removal and Trenching19-Jun-202528-Oct-2025+90 wdContractorResequenced slab removal and trenching
A3900Interior M&E Rough in 14-Jan-202614-May-2026+84 wd
A209023 52 16 - Heating Boilers01-Dec-202516-Mar-2026+71 wd
A3910Interior Finishes11-Feb-202615-May-2026+65 wd
A2730Stairs B Installation @ North Side19-Nov-202518-Feb-2026+62 wd
A1710Misc. Metals 29-Oct-202527-Jan-2026+62 wd
A2720Tactile Attention Indicators Mock-up30-Oct-202528-Jan-2026+62 wd
A150023 52 16 - Heating Boilers23-Jul-202521-Oct-2025+62 wd
A195023 82 19 - Fan Coil Units26-Nov-202525-Feb-2026+62 wd
A205023 25 00 - Water Treatment12-Nov-202509-Feb-2026+61 wd
A206023 37 13 - Diffuser and Grilles05-Dec-202505-Mar-2026+60 wd
A3270New Stair A Installation17-Nov-202510-Feb-2026+59 wd
A2540Compaction Inspection22-Aug-202514-Nov-2025+58 wd
A218026 09 23 - Lighting Control05-Nov-202523-Jan-2026+55 wd
A3170Install Built-up Roof17-Dec-202509-Mar-2026+54 wd
A1130Misc. Metals Shop Drawings18-Jul-202502-Oct-2025+53 wdContractorLate misc. metals submittal
A3180Roof Inspection19-Dec-202509-Mar-2026+52 wd
A1680Structural Steel 25-Jul-202502-Oct-2025+48 wd
A1160TPO Roofing Shop Drawings19-Jun-202526-Aug-2025+47 wdOwnerOwner-directed revision to the roofing assembly; resubmittal and re-review cycle
A1740TPO Roofing (Bridge)04-Aug-202508-Oct-2025+46 wd
A1330Fall Arrest Anchors and Horizontal Lines25-Jul-202529-Sep-2025+45 wd
A2640Install Roof Decking12-Nov-202515-Jan-2026+44 wd
A2630Install Roof Anchors 05-Nov-202508-Jan-2026+44 wd
A1920Fall Arrest Anchors and Horizontal Lines22-Oct-202523-Dec-2025+44 wd
A3150Roof Parapet Framing19-Nov-202522-Jan-2026+44 wd
A3160Roof Penetration Layout14-Nov-202519-Jan-2026+44 wd
A2510Supply of Embedment & Ankors20-Jun-202522-Aug-2025+44 wd
A2580Underground Drainage08-Sep-202507-Nov-2025+43 wd
A213022 40 00 - Plumbing Fixtures03-Dec-202503-Feb-2026+42 wd
A3930Interior Demolition07-Jul-202502-Sep-2025+40 wd
A2590Backfilling to U/S of SOG19-Sep-202514-Nov-2025+39 wd
A197023 21 23 - Pumps17-Nov-202512-Jan-2026+38 wd
A159026 09 23 - Lighting Control (R0)26-Jun-202518-Aug-2025+36 wd
A215026 50 00 - Lighting Fixtures20-Nov-202512-Jan-2026+35 wd
A2220Testing and Inspection Cash Allowance Expenditure13-May-202502-Jul-2025+34 wd
A196023 74 13 - Air Handling Units30-Mar-202615-May-2026+34 wd
A2440Formwork Remaining Pad Footing (Ramp)30-Jul-202517-Sep-2025+34 wd
A4040 CPMEP Rough-ins25-Mar-202611-May-2026+33 wdContractorMEP rough-in trade coordination; stacked trades after remobilization
A4080 CPDrywall/Sheathing Installation19-May-202606-Jul-2026+33 wd
A4090 CPTaping and mudding02-Jun-202620-Jul-2026+33 wd
A4110 CPTile and Rubber Flooring Installation12-Jun-202630-Jul-2026+33 wd
A4100 CPPainting05-Jun-202623-Jul-2026+33 wd
A4120 CPFinal Terminations and Fixtures Installation19-Jun-202606-Aug-2026+33 wd
A212020 05 10 - Electric Heat Tracing01-Dec-202519-Jan-2026+33 wd
A4170Fire Alarm Verification07-Jul-202620-Aug-2026+32 wd
A1110Structural Reinforcement + Decking Shop Drawings19-Jun-202501-Aug-2025+30 wd
A1290Suspended Metal Soffits25-Jul-202504-Sep-2025+28 wd
A1820Coiling Doors03-Dec-202514-Jan-2026+28 wd
A1870ACT & ACB 09-Sep-202517-Oct-2025+27 wd
A146023 25 00 - Water Treatment (R0)04-Jul-202512-Aug-2025+27 wd
A158026 50 00 - Lighting Fixtures14-Jul-202518-Aug-2025+25 wd
A1700Cold-formed Metal Framing 04-Jul-202507-Aug-2025+24 wd
A1120Cold-formed Metal Framing Shop Drawings19-Jun-202523-Jul-2025+23 wd
A1220Flush Wood Doors Sample25-Jul-202527-Aug-2025+23 wd
A1280ACT Data sheet and Sample25-Jul-202527-Aug-2025+23 wd
A4240 CPMinor Deficiencies & Touch-ups28-Aug-202630-Sep-2026+22 wdContractorDeficiency and touch-up re-work extended by finishing crew quality issues
A1810Flush Wood Doors 12-Nov-202512-Dec-2025+22 wd
A4260 CPTotal Completion 31-Aug-202630-Sep-2026+21 wd
A4220Final Cleaning 05-Aug-202603-Sep-2026+21 wd
A4180 CPMechanical, Electrical and Elevator Commissioning29-Jul-202627-Aug-2026+21 wd
A4190 CPIntegrated Testing12-Aug-202611-Sep-2026+21 wd
A4250 CPReady-To-Take Over31-Aug-202630-Sep-2026+21 wd
A4230Close-out Documents & Training05-Aug-202603-Sep-2026+21 wd
A4210 CPOccupancy13-Aug-202611-Sep-2026+20 wd
A2500Install Rebar for Piers08-Aug-202508-Sep-2025+20 wd
A4200 CPSubstantial Performance14-Aug-202611-Sep-2026+19 wd
A1230Coiling Doors25-Jul-202521-Aug-2025+19 wd
A1180Exterior Wall Cladding Shop Drawings11-Aug-202505-Sep-2025+18 wd
A1210Interior Aluminum Screen25-Jul-202520-Aug-2025+18 wd
A1760Exterior Wall Cladding05-Nov-202501-Dec-2025+18 wd
A1800Interior Aluminum Screens03-Dec-202529-Dec-2025+17 wd
A1090Masonry and Mortar Samples & Data Sheets25-Jul-202518-Aug-2025+16 wd
A1100Structural Steel Framing and Steel Deck Shop Drawings (R0)19-Jun-202514-Jul-2025+16 wd
A2550Form and Pour Grade Beams08-Sep-202530-Sep-2025+16 wd
A2560Below Grade Vapour Barrier Mock-up09-Sep-202501-Oct-2025+16 wd
A2570Footing Vapor Barrier & Insulation12-Sep-202506-Oct-2025+16 wd
A2750 CPL1, L2 & L3 Framing and Sheathing Installation05-Dec-202529-Dec-2025+15 wd
A2880 CPL1, L2 & L3 Framing and Sheathing Installation19-Dec-202513-Jan-2026+15 wd
A2890L1 Masonry Wall Installation29-Dec-202520-Jan-2026+15 wd
A2770L1 Masonry Wall installation09-Dec-202531-Dec-2025+15 wd
A2790L1, L2 & L3 Air Vapour Barrier Installation12-Dec-202506-Jan-2026+15 wd
A3260 CPSeal Concrete Floor04-Mar-202625-Mar-2026+15 wd
A3430Seal concrete Floor06-Mar-202627-Mar-2026+15 wd
A3280New partition framing18-Mar-202608-Apr-2026+15 wd
A3330Door frames Installation25-Mar-202615-Apr-2026+15 wd
A3440New partition framing01-Apr-202622-Apr-2026+15 wd
A3560Seal concrete Floor12-Mar-202602-Apr-2026+15 wd
A1670Masonry and Mortar04-Aug-202525-Aug-2025+15 wd
A3420Fire Spraying & Intumescent Paint04-Mar-202625-Mar-2026+15 wd
A3550Fire Spraying & Intumescent Paint11-Mar-202601-Apr-2026+15 wd
A2820Glazing Site Measure and Scanning08-Dec-202530-Dec-2025+15 wd
A2280Under Pinning Inspection20-Jun-202514-Jul-2025+15 wd
A2760Masonry Mock-up08-Dec-202530-Dec-2025+15 wd
A2740Cold-Formed Metal Framing Mock01-Dec-202522-Dec-2025+15 wd
A3680Misc. Metals Mock-up02-Apr-202623-Apr-2026+15 wd
A2780Above Grade Vapour Mock-up08-Dec-202530-Dec-2025+15 wd
A2800AVB Inspection08-Dec-202530-Dec-2025+15 wd
A3250 CPFire Spraying & Intumescent Paint Inspection25-Feb-202619-Mar-2026+15 wd
A2520Form and Pour Foundation Piers15-Aug-202508-Sep-2025+15 wd
A3490Door frames Installation07-Apr-202627-Apr-2026+14 wd
A3520Door and Hardware Installation21-Apr-202611-May-2026+14 wd
A3620Door frames Installation23-Apr-202613-May-2026+14 wd
A3570New wall partition framing16-Apr-202606-May-2026+14 wd
A3920Setup Temporary Hoarding13-Jun-202504-Jul-2025+14 wd
A3240 CPFire Spraying & Intumescent Paint25-Feb-202618-Mar-2026+14 wdOwnerFire-spray application held for owner inspector availability
A3210Electrical and Mechanical Room 04-Mar-202624-Mar-2026+14 wd
A3690Misc. Metals installation29-May-202618-Jun-2026+14 wd
A3220Mech. and Elec. Equipment Installation18-Mar-202607-Apr-2026+14 wd
A153020 05 10 - Electric Heat Tracing (R0)23-Jul-202512-Aug-2025+14 wd
A2530Backfilling to U/S of Grade Beams22-Aug-202512-Sep-2025+14 wd
A1060Foundation Concrete Rebar Shop Drawing19-Jun-202508-Jul-2025+12 wd
A1050Ductbank Underpinning Drawing12-Jun-202530-Jun-2025+12 wd
A147023 37 13 - Diffuser and Grilles Shop Drawings (R0)29-Jul-202514-Aug-2025+12 wd
A3410Painting07-May-202625-May-2026+11 wd
A3300Electrical, FA & Comms rough-ins06-Apr-202621-Apr-2026+11 wd
A3320Blocking Installation09-Apr-202624-Apr-2026+11 wd
A3350Gypsum board Installation16-Apr-202601-May-2026+11 wd
A3360Drywall Taping and Mudding30-Apr-202615-May-2026+11 wd
A3390Interior Aluminum/Glazing Screens Installation07-May-202625-May-2026+11 wd
A3370Door and Hardware Installation07-May-202625-May-2026+11 wd
A3810Install Controller at Machine Room08-May-202626-May-2026+11 wd
A3820Rails and Elevator Car installation25-May-202609-Jun-2026+11 wd
A3830Power to controller, Phone lines and Comms01-Jun-202616-Jun-2026+11 wd
A3840Elevator Testing and Commissioning22-Jun-202608-Jul-2026+11 wd
A3380Interior Aluminum/Glazing Screens Mock-up01-May-202619-May-2026+11 wd
A3340ACT Baffles Mock-ups10-Apr-202627-Apr-2026+11 wd
A3400Paint Mock-up05-May-202621-May-2026+11 wd
A156026 50 00 - Emergency Lighting & Exit Signs14-Jul-202529-Jul-2025+11 wd
A3290Mech. & Plumbing rough-ins01-Apr-202615-Apr-2026+10 wd
A3310Sprinkler Rough-ins01-Apr-202615-Apr-2026+10 wd
A3540Painting20-May-202602-Jun-2026+9 wd
A2610Erect Structural Steel20-Oct-202531-Oct-2025+9 wd
A2650Install Level 2 & 3 Decking03-Nov-202514-Nov-2025+9 wd
A3450Mech. & Plumbing rough-ins16-Apr-202629-Apr-2026+9 wd
A3480Blocking Installation23-Apr-202606-May-2026+9 wd
A3500Gypsum board Installation30-Apr-202613-May-2026+9 wd
A3460Electrical, FA & Comms rough-ins20-Apr-202601-May-2026+9 wd
A3510Drywall Taping and Mudding14-May-202628-May-2026+9 wd
A3530Interior Glazing Installation22-May-202604-Jun-2026+9 wd
A3590Electrical, FA & Comms rough-ins27-Apr-202608-May-2026+9 wd
A3580Mech. & Plumbing rough-ins09-Apr-202622-Apr-2026+9 wd
A3610Blocking Installation04-May-202615-May-2026+9 wd
A3470Sprinkler Rough-ins16-Apr-202629-Apr-2026+9 wd
A3600Sprinkler Rough-ins09-Apr-202622-Apr-2026+9 wd
A2660Install Temporary Hoarding for Slab on Deck03-Nov-202514-Nov-2025+9 wd
A2620Structural Steel Inspection20-Oct-202531-Oct-2025+9 wd
A1080Bentonite Waterstop Data Sheet19-Jun-202502-Jul-2025+8 wd
A1660Bentonite Waterstop 26-Jun-202509-Jul-2025+8 wd
A214026 27 26 - Wiring Devices, Service Poles, & Floor Boxes05-Nov-202517-Nov-2025+8 wd
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes26-Jun-202508-Jul-2025+7 wd
A3750Washroom Partitions and Accessories Installation08-Jul-202616-Jul-2026+6 wd
A2670Rebar and Prep Work for Slab on Deck10-Nov-202518-Nov-2025+6 wd
A3110L1, L2 & L3 Exterior Glazing Installation (W09a, W09b)26-Mar-202603-Apr-2026+6 wd
A2930L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)12-Mar-202620-Mar-2026+6 wd
A2840L1, L2, L3 Exterior Glazing Installation (W05)05-Mar-202613-Mar-2026+6 wd
A3010L2 & L3 Exterior Glazing Installation (W08a, W08b)05-Mar-202613-Mar-2026+6 wd
A3720Ceiling/Wall Fixtures Installation30-Jun-202609-Jul-2026+6 wd
A3740Millwork Installation23-Jun-202602-Jul-2026+6 wd
A3710Tiling and rubber flooring Installation30-Jun-202609-Jul-2026+6 wd
A3670Painting16-Jun-202624-Jun-2026+6 wd
A3770Corner Guards and Wall Protection Installation06-Jul-202614-Jul-2026+6 wd
A3660Interior Glazing Installation09-Jun-202617-Jun-2026+6 wd
A3650Door and Hardware Installation16-Jun-202624-Jun-2026+6 wd
A3630Gypsum board Installation19-May-202627-May-2026+6 wd
A3640Drywall Taping and Mudding02-Jun-202610-Jun-2026+6 wd
A2850Exterior Cladding Site Measure and Scanning06-Mar-202616-Mar-2026+6 wd
A2940Exterior Cladding Site Measure and Scanning13-Mar-202623-Mar-2026+6 wd
A3020Exterior Cladding Site Measure and Scanning06-Mar-202616-Mar-2026+6 wd
A3100Glazing Shop Fabrication19-Mar-202627-Mar-2026+6 wd
A3120Exterior Cladding Site Measure and Scanning27-Mar-202606-Apr-2026+6 wd
A3760Plumbing Washroom Fixtures Installation08-Jul-202616-Jul-2026+6 wd
A3730Millwork Mock-up17-Jun-202625-Jun-2026+6 wd
A2810Aluminum & Metal Panel Cladding Mock-up06-Mar-202616-Mar-2026+6 wd
A3700Tiling & Rubber & Carpet Flooring Mock-up17-Jun-202625-Jun-2026+6 wd
A137023 74 13 - Air Handling Units (R0)11-Jul-202521-Jul-2025+6 wd
A203023 81 26 - Split System18-Nov-202526-Nov-2025+6 wd
A216027 10 00 - Structural Cabling System (Fiber Optic Cable)21-Apr-202629-Apr-2026+6 wd
A2680Concrete pour for slab on deck level 2 & 313-Nov-202520-Nov-2025+5 wd
A2960L2 & L3 Cladding Installation (EW2)11-May-202619-May-2026+5 wd
A2870L1, L2 & L3 Cladding Installation (EW2a)04-May-202611-May-2026+5 wd
A3040L2 & L3 Cladding Installation (EW2)04-May-202611-May-2026+5 wd
A3050Horizontal Shading Louvers11-May-202619-May-2026+5 wd
A2900Air Vapor Barrier Installation13-Jan-202620-Jan-2026+5 wd
A3140L1, L2 & L3 Cladding Installation (EW2, EW2A)02-Jun-202609-Jun-2026+5 wd
A3070L1, L2 & L3 Air Vapor Barrier Installation25-Feb-202605-Mar-2026+5 wd
A2690Final Grading and Vapor Barrier for SOG18-Nov-202525-Nov-2025+5 wd
A2860Exterior Cladding Shop Fabrication06-Apr-202613-Apr-2026+5 wd
A2910Glazing Site Measure and Scanning07-Jan-202614-Jan-2026+5 wd
A2950Exterior Cladding Shop Fabrication13-Apr-202620-Apr-2026+5 wd
A3000Glazing Shop Fabrication26-Feb-202606-Mar-2026+5 wd
A3030Exterior Cladding Shop Fabrication06-Apr-202613-Apr-2026+5 wd
A3130Exterior Cladding Shop Fabrication27-Apr-202604-May-2026+5 wd
A3080L1, L2 & L3 Air Vapor Barrier Inspection25-Feb-202605-Mar-2026+5 wd
A142023 57 00 - Heat Exchangers25-Jun-202503-Jul-2025+5 wd
A157027 10 00 - Structural Cabling System (Fiber Optic Cable)15-Jul-202522-Jul-2025+5 wd
A2970 CPL2 & L3 Framing and Sheathing Installation27-Jan-202602-Feb-2026+4 wd
A3060 CPL1, L2 & L3 Framing and Sheathing Installation18-Feb-202624-Feb-2026+4 wd
A2980L2 & L3 Air Vapor Barrier Installation03-Feb-202609-Feb-2026+4 wd
A1070Foundation Concrete Mix Design19-Jun-202525-Jun-2025+4 wd
A1650Foundation Concrete Mix Design23-Jun-202527-Jun-2025+4 wd
A2830Glazing Shop Fabrication21-Jan-202627-Jan-2026+4 wd
A2920Glazing Shop Fabrication04-Feb-202610-Feb-2026+4 wd
A2990Glazing Site Measure and Scanning28-Jan-202603-Feb-2026+4 wd
A3090Glazing Site Measure and Scanning19-Feb-202625-Feb-2026+4 wd
A3230Fire Spraying & Intumescent Paint Mock-up19-Feb-202625-Feb-2026+4 wd
A151023 00 00 - Wall Fin Heater06-Aug-202512-Aug-2025+4 wd
A154022 40 00 - Plumbing Fixtures (R0)25-Jul-202531-Jul-2025+4 wd
A210023 00 00 - Wall Fin Heater12-Dec-202518-Dec-2025+4 wd
A1040Permit (Not Required Per Ontario Community College)13-May-202516-May-2025+3 wd
A1030IFC Drawings Released12-May-202515-May-2025+3 wd
A1150Built-up Roofing Shop Drawings04-Jul-202509-Jul-2025+3 wd
A1170Air Barrier System Data Sheet and Mockup04-Jul-202509-Jul-2025+3 wd
A1190Fire-resistive Material Data Sheet04-Jul-202509-Jul-2025+3 wd
A1350Sprinkler & Standpipe Shop Drawings11-Jul-202516-Jul-2025+3 wd
A1730Built-up Roofing 18-Aug-202521-Aug-2025+3 wd
A1750Air Barrier System18-Jul-202523-Jul-2025+3 wd
A1770Fire-resistive Material 04-Aug-202507-Aug-2025+3 wd
A1940Sprinkler & Standpipe Shop Drawings04-Aug-202507-Aug-2025+3 wd
A2710Concrete Pour and Curing for SOG28-Nov-202503-Dec-2025+3 wd
A2700Rebar Installation for SOG21-Nov-202526-Nov-2025+3 wd
A3190Hoisting Roof Equipment09-Jun-202612-Jun-2026+3 wd
A3200Roof Anchor System Installation16-Jun-202619-Jun-2026+3 wd
A139023 25 00 - Buffer Tanks27-Jun-202503-Jul-2025+3 wd
A140023 21 16 - Air Separator27-Jun-202503-Jul-2025+3 wd
A141023 21 16 - Expansion Tanks27-Jun-202503-Jul-2025+3 wd
A152023 74 13 - Air Source Heat Pump14-Jul-202517-Jul-2025+3 wd
A211023 74 13 - Air Source Heat Pump02-Jun-202605-Jun-2026+3 wd
A2240Construction Site Setup. Fencing and Temp Facilities12-Jun-202516-Jun-2025+2 wd
A1010Contract Award30-Apr-202502-May-2025+2 wd
A2230Ontario Community College Auto Show05-Jun-202509-Jun-2025+2 wd
A2270Excavation for Under Pinning19-Jun-202523-Jun-2025+2 wd
A2250Tree Removal, Protection and Equipment Mobilization13-Jun-202517-Jun-2025+2 wd
A2260Top Soil Stripping18-Jun-202520-Jun-2025+2 wd
A2300Setup Hoarding @ Vestibule F10016-Jun-202518-Jun-2025+2 wd
A2320Demolition of Existing Vestibule F10023-Jun-202525-Jun-2025+2 wd
A2290Existing Structure Under Pinning11-Jul-202515-Jul-2025+2 wd
A2330Gas Meter and Pipe Relocation Investigation17-Jun-202519-Jun-2025+2 wd
A2340Gas Meter and pipe Relocation19-Jun-202523-Jun-2025+2 wd
A2350Daylighting of Existing Hydro Ductbank & Services03-Jul-202507-Jul-2025+2 wd
A1020Subcontract Award29-May-202502-Jun-2025+2 wd
A1140Millwork Shop Drawings25-Jul-202529-Jul-2025+2 wd
A1200Hollow Metal Frames & Doors Shop Drawings25-Jul-202529-Jul-2025+2 wd
A1240Aluminum Framed Glazing System Shop Drawings04-Aug-202506-Aug-2025+2 wd
A1250Finished Hardware Schedule25-Jul-202529-Jul-2025+2 wd
A1260Stud framing and Gypsum Board Data Sheets25-Jul-202529-Jul-2025+2 wd
A1270Tiling Data sheet and samples25-Jul-202529-Jul-2025+2 wd
A1300Flooring Data Sheets and Samples25-Jul-202529-Jul-2025+2 wd
A1310Paint Drawdowns25-Jul-202529-Jul-2025+2 wd
A1320Washroom accessories and Partitions Shop Drawings25-Jul-202529-Jul-2025+2 wd
A1610Concrete Mix for Hardscapes04-Aug-202506-Aug-2025+2 wd
A1620Landscape Shop Drawings04-Aug-202506-Aug-2025+2 wd
A1720Millwork 07-Oct-202509-Oct-2025+2 wd
A1780Hollow Metal Frames23-Sep-202525-Sep-2025+2 wd
A1830Aluminum Framed Glazing Systems26-Nov-202528-Nov-2025+2 wd
A1840Finished Hardware 03-Dec-202505-Dec-2025+2 wd
A1850Stud framing & gypsum board04-Aug-202506-Aug-2025+2 wd
A1860Tiling 09-Sep-202511-Sep-2025+2 wd
A1890Flooring 22-Oct-202524-Oct-2025+2 wd
A1900Paint Drawdowns11-Aug-202513-Aug-2025+2 wd
A1910Washroom accessories and Partitions 02-Sep-202504-Sep-2025+2 wd
A2200Concrete for Hardscape11-Aug-202513-Aug-2025+2 wd
A2210Landscape (unit pavers, furniture, etc)29-Oct-202531-Oct-2025+2 wd
A3780Layout for Elevator Cylinder19-Jun-202523-Jun-2025+2 wd
A3790Drilling Elevator Cylinder from Grade20-Jun-202524-Jun-2025+2 wd
A3800Install Steel Casing into the ground23-Jun-202525-Jun-2025+2 wd
A1690 CPStructural Reinforcement16-Sep-202518-Sep-2025+2 wd
A1790Hollow Metal Doors22-Oct-202524-Oct-2025+2 wd
A2370Bulk Excavation to U/S of Footings18-Jul-202522-Jul-2025+2 wd
A2380Bulk Excavation to U/S North Stair Footing21-Jul-202523-Jul-2025+2 wd
A2310Relocate FAA16-Jun-202517-Jun-2025+1 wd
A3960Vinyl Flooring Abatement (Cash Allowance)14-Jul-202511-Jul-2025-1 wd
A136023 82 19 - Fan Coil Units (R0)04-Jul-202503-Jul-2025-1 wd
A1340Hydraulic Lift Shop Drawings11-Jul-202509-Jul-2025-2 wd
A1930Hydraulic Lift 03-Dec-202501-Dec-2025-2 wd
A4010Underground Plumbing Rough-ins21-Jul-202516-Jul-2025-3 wd
A138023 21 23 - Pumps (R0)09-Jul-202504-Jul-2025-3 wd
A2390Subgrade Inspection25-Jul-202522-Jul-2025-3 wd
A2400Subgrade Preparation28-Jul-202523-Jul-2025-3 wd
A2410Soil Bearing Capacity Inspection29-Jul-202524-Jul-2025-3 wd
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)28-Jul-202523-Jul-2025-3 wd
A2450Rebar for Pad Footings29-Jul-202524-Jul-2025-3 wd
A2460Rebar Inspection30-Jul-202525-Jul-2025-3 wd
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)31-Jul-202528-Jul-2025-3 wd
A2490Concrete Field Testing31-Jul-202528-Jul-2025-3 wd
A204022 13 29 - Sump Pumps14-Aug-202508-Aug-2025-4 wd
A2360Ductbank Shoring 17-Jul-202508-Jul-2025-7 wd
A160028 31 00 - Fire Alarm Shop Drawings and Data Sheets26-Jun-202517-Jun-2025-7 wd
A219028 31 00 - Fire Alarm05-Nov-202527-Oct-2025-7 wd
A148023 00 00 - Exhaust Fans (R0)06-Aug-202522-Jul-2025-11 wd
A149023 00 00 - Unit Heater06-Aug-202522-Jul-2025-11 wd
A1640Foundation Concrete Rebar 04-Jul-202513-Jun-2025-14 wd
A2420Form and Pour North Exit Stair25-Sep-202505-Sep-2025-14 wd
A1630Ductbank Underpinning 19-Jun-202528-May-2025-16 wd
A145022 13 29 - Sump Pumps (R0)24-Jun-202502-Jun-2025-16 wd
A2480Concrete for Remaining Pad Footings (Ramp)01-Aug-202503-Jul-2025-21 wd
A208023 00 00 - Unit Heater12-Dec-202511-Nov-2025-23 wd
A2600Compaction Inspection19-Sep-202515-Aug-2025-24 wd
A207023 00 00 - Exhaust Fans12-Dec-202503-Nov-2025-29 wd
A-10

Provenance & Method

reproducibility manifest
Generated
30-Aug-2026
Method
Windows Analysis — AACE MIP 3.3
Engine
CPP cpm-engine v2.9.42