Executive Summary

ℹ️
Baseline Assessment Note This report is scored out of 13/14 criteria. Excluded: C10 (Resources) — marked N/A due to project phase or data availability. An approved baseline is available.
Only 5 of 13 criteria passed Schedule quality requires immediate attention with multiple critical deficiencies identified. (Note: Scored out of 13 criteria)
Feasibility gap vs baseline/contract finish CPLI 0.933 | Contract: 2026-08-31 | Forecast: 2026-09-30 | Float: -22d (22 days late vs baseline finish)
Lead relationships found 7 negative lag relationships detected. Leads create unrealistic schedule compression and should be eliminated. → Action: Replace leads with overlapping activities or adjust activity definitions.
Excessive lag usage 10.6% of relationships contain lags (target ≤5%). Review and justify each lag or break down activities. → Action: Create intermediate milestones instead of using lags where possible.
High float activities detected 149 activities with float >44 days indicate missing relationships or incorrect sequencing. → Action: Review high float activities to ensure proper integration into schedule logic.
Long duration activities 38 activities exceed 44 working days. Break down into smaller work packages for better control. → Action: Decompose long activities into 1-week activities for improved tracking.
Missed task dates 19 activities incomplete despite passing planned dates. Update actuals and reforecast remaining work. → Action: Mark completed activities and update progress on in-progress work immediately.
38%
Health Score
RED STATUS

Key Performance Metrics

Criteria Passed
5
of 13 total criteria
C10 N/A - scored out of 13
No criteria passed yet
Criteria Failed
8
requires attention
No criteria failed yet
%
Compliance Rate
38%
overall quality score
Load schedule to see breakdown
🎓
Overall Rating
F
assessment grade
Load schedule to see grading scale

DCMA 14-Point Assessment

Comprehensive evaluation of schedule quality based on Defense Contract Management Agency (DCMA) 14-Point Assessment criteria. Each criterion measures a critical aspect of schedule health and reliability.

Health Score Breakdown 👆 Click cards for details

🔗
Logic & Flow
2/4
Fair
Complete assessment to see breakdown
👥
Resources & Progress
0/2
Poor
Complete assessment to see breakdown
⚠️
Constraints & Float
2/4
Fair
Complete assessment to see breakdown
📊
Performance
1/3
Poor
Complete assessment to see breakdown

DCMA-14 Status by Criterion

Per-criterion DCMA-14 status — one row for each of the fourteen criteria, color-coded by result. PASS means the criterion met its threshold; FAIL means it did not; N/A applies to baseline-dependent criteria like CPLI and BEI when no baseline is loaded. Reading down the chart shows exactly which criteria failed without having to count slices in a doughnut.