Schedule Health DashboardDCMA 14-Point Assessment & Quality Compliance Analysis
remediation advised
Summary of Findings
This schedule cannot yet be relied on to forecast completion: it passes 4 of the 13 scored DCMA-14 checks (grade F, 31%), and four of its nine failures change its dates or its critical path.
As filed, it forecasts completion on 24 June 2026, 37 working days later than the baseline finish of 1 May 2026, but that forecast was calculated at a data date of 5 August 2025 while progress is recorded to 14 October 2025, so the date cannot be taken at face value. Against the contract finish of 1 May 2026 (A1050 Ready for Owner Takeover) it is 37 working days behind.
What is asked: the scheduler who prepares the update should re-issue it at a data date of 15 October 2025 and correct the items in section 2; the screen should then be run again before the forecast finish is used for any decision.
Negative float flags 123 of the 252 activities checked (48.8%), the largest share of any failing check
C4 relationship types and C13 CPLI fail on a ratio rather than a list of activities and are scored in section 3. An activity can be flagged by more than one check.
What Needs Fixing First
Four of the failing checks change the schedule’s dates or its critical path and come first: until these are corrected, neither the forecast finish nor the critical path can be relied on.
Status Recorded After the Data Date
61 activities carry dates on the wrong side of the data date of 5 August 2025: 53 actual starts and 54 actual finishes fall after it. The latest, 14 October 2025, is 48 working days after the data date. Inside one update that is a contradiction: the file reports work done after the date it says its status was taken.
102 activities that had not started were forecast to start before 15 October 2025: each is either late or missing its status.
To fix: re-issue the update with its data date moved to 15 October 2025 and the unstarted work re-forecast from that date.
For example:
- A1940 Metal deck Level 2 Zone B, started 14 October 2025
- A1960 Erect structural steel Level 2 Zone C, started 14 October 2025
- A2910 In-wall services inspection Level 1 Zone C, finished 14 October 2025
Every one is listed in the C9 register at A-06.
Critical Path Continuity
14 of 252 unfinished activities (5.6%, against a limit of 5%) are not on any path from the start to the finish. Of the 124 activities with zero or negative float, only 95 (76.6%) connect into one chain. The critical path the file reports cannot be followed from start to finish, and an activity off the path cannot move the finish however late it runs, so a delay to it would not show.
To fix: tie each listed activity to the work that drives it and the work it releases, then check the critical path again.
For example:
- A2230 Steel stairs and railings, no path to the finish
- A2280 Sealants and flashings, North elevation, no path to the finish
- A2320 Sealants and flashings, East elevation, no path to the finish
Every one is listed in the C12 register at A-06.
Excess Float
85 of 252 unfinished activities (33.7%, against a limit of 5%) carry more than 44 working days of total float, as much as 158 working days. Float that large usually means an activity is missing a successor: it could slip for weeks without moving the finish, so the critical path may be longer than the file shows.
To fix: check each listed activity for a missing successor and add it.
For example:
- A2520 Sprinkler mains and risers, 158 working days of float
- A4180 Site lighting bases and poles, 157 working days of float
- A2280 Sealants and flashings, North elevation, 151 working days of float
Every one is listed in the C6 register at A-06.
Leads
2 links carry a negative lag (a lead) of up to 2 working days. A lead overlaps two activities by a fixed amount instead of by logic, so the successor does not respond as it should when the predecessor changes.
To fix: replace each lead with a start-to-start link, or split the predecessor.
For example:
- A2380 Curtain wall and windows, West elevation, 2 working days of lead from Exterior sheathing and air/vapour barrier, West elevation
- A4100 Tape, mud and sand Level 3 Zone D, 1 working day of lead from Drywall board Level 3 Zone D
Every one is listed in the C2 register at A-06.
What the Dates Say About the Finish
Two further failures are not faults to correct in the file but readings of the finish. 123 activities carry negative float, as much as 37 working days, and the critical path length index is 0.83 against 0.95: as filed, the forecast finish of 24 June 2026 is 37 working days behind the contract finish of 1 May 2026. Both should be read again once the update is re-issued.
How the Schedule Scores
Of the 13 scored checks, 9 fail. The float and critical path checks fare worst, all four failing, and the duration and resource checks best, with none failing.
| Check | What it tests | Measured | Target | Result |
|---|---|---|---|---|
| LogicThree of the four checks fail: leads, lags and relationship types. | ||||
| C1 Logic | Every unfinished activity has a predecessor and a successor | 8 of 256 activities (3.1%) | 5% or fewer | Pass |
| C2 Leads | No link carries a negative lag (a lead) | 2 links | Zero | Fail |
| C3 Lags | Few links carry a positive lag (a waiting time) | 65 of 584 links (11.1%) | 5% or fewer | Fail |
| C4 Relationship types | Most links are finish-to-start | 88.2% finish-to-start | 90% or more | Fail |
| Dates and StatusTwo of the four checks fail: valid dates and missed tasks. | ||||
| C9 Valid dates | No actual date after the data date and no forecast date before it | 61 of 379 activities (16.1%) | 0% or fewer | Fail |
| C5 Hard constraints | Few dates are fixed by a hard constraint instead of by logic | 1 of 252 activities (0.4%) | 5% or fewer | Pass |
| C11 Missed tasks | Few activities due by the data date finished after the baseline date | 6 of 58 due (10.3%) | 5% or fewer | Fail |
| C14 BEI | The work the baseline planned by the data date is done | 0.97 | 0.95 or more | Pass |
| Float and the Critical PathAll four checks fail: critical path test, high float, negative float and CPLI. | ||||
| C12 Critical path test | The critical path runs as one chain from the start to the finish | 14 off the path to the finish; 95 of 124 critical activities in one chain | One chain from start to finish | Fail |
| C6 High float | Few unfinished activities carry more than 44 working days of float | 85 of 252 activities (33.7%) | 5% or fewer | Fail |
| C7 Negative float | No activity carries negative float | 123 of 252 activities | Zero | Fail |
| C13 CPLI | The remaining critical path can reach the contract finish | 0.83 | 0.95 or more | Fail |
| Durations and ResourcesThe check passes; the other is not scored on this file. | ||||
| C8 High duration | Few unfinished activities run longer than 44 working days | 2 of 252 activities (0.8%) | 5% or fewer | Pass |
| C10 Resources | Activities carry resources or cost | Not scored | 100% or more | Not scored |
The pass and fail thresholds are those of the DCMA 14-Point Assessment as this screen applies them; the A to F grade is CPP’s convention for summarising the scored checks, and DCMA does not grade a schedule.
How Far the Figures Can Be Relied On
Every figure here is read from the file exactly as filed, at a data date its own progress has overtaken: the figures describe the file, not yet the project.
Data date. The update reports its status at 5 August 2025 while its actual dates run to 14 October 2025, 48 working days later. Every forecast date, every float value and the negative float and CPLI results are read at the filed data date, so all of them move once the update is re-issued.
Read as filed. No network calculation was re-run. Dates and total float are taken as the source scheduler computed them, so a stale or overridden float value is reported as it stands rather than corrected.
Basis. Every duration, float and variance is in working days on each activity’s own P6 calendar; the movement of the finish is counted on the project calendar.
Scope of the file. The current schedule holds 379 activities and 584 relationships; the baseline holds 343, so the current schedule has 36 more.
What the checks cannot see. A DCMA-14 screen tests the structure and status of one file. It does not test whether the logic matches how the work is being built, whether durations are realistic, or why the finish moved. The critical path test here is a connectivity screen; the formal DCMA slip test is not performed. Resources were not scored: the file carries no resource assignments. These results have not been reviewed against the contract or the project records, and are not a delay analysis.
The basis of measurement and what has been validated are set out in full at A-01.1.
Analyst conclusion and next step
Analyst Conclusion and Next Step
Delay investigation warrantedThe finish has moved materially and the movement deserves a proper look at the update chain before anyone takes a position. The Preliminary Assessment, scoped and priced in writing before any work starts, is the next step.
Technical condition: the assessment grades this schedule F · 31% · RED; the forecast finish has moved 37 working days later than the baseline.
The movement is material and this pair of files cannot yet explain it. The forecast completion has moved 37 working days later than the baseline, and the schedule itself grades F on the DCMA screen, so both the dates and the instrument that produced them need attention before anyone takes a position.
The update was also filed with a data date of 05-Aug-2025 while its actual dates run to 14-Oct-2025, so the finish it reports is too early: the forecast has to be rebuilt at the correct data date before the movement is measured. A baseline and one update are endpoints. The causation story lives in the monthly chain between them and in the project record, and on this file only a small share of the moved activities have evidence paired to them. Examining the chain is the correct next step, and it is a bounded piece of work.
The Findings That Matter
| 1 | The forecast completion moved 37 working days later than the baseline, to 24-Jun-2026, as the file reports it. |
| 2 | The schedule grades F (31%) on the DCMA-14 screen, driven by high float on 34% of activities, 123 activities with negative float against the contract finish and 61 activities with actual dates after the data date: the instrument needs repair alongside the delay question. |
| 3 | Only 4.9% of the positive slips are evidence-supported in the records provided (the companion evidence workbench), so causation is asserted, not yet shown. |
Evidence Still Required
| • | The full monthly update chain (every XER between baseline and current, not just the endpoints) |
| • | Contract milestone dates and any amendments to them |
| • | Delay notices and the contractual notice log |
| • | Change orders and change directives with dates |
| • | Contemporaneous correspondence for the affected work fronts |
The Next Step
The Preliminary Assessment, scoped and priced in writing before any work starts, would cover:
| 1. | Reschedule the update at its correct data date, then ingest the full monthly update chain and rebuild the movement window by window on the project calendar. |
| 2. | Attribute each driving window to its cause using the schedule record and the documents listed above. |
| 3. | Screen the chain for baseline changes, logic revisions and calendar edits that move dates without progress. |
| 4. | Report whether a delay position is supportable, in which direction, and what a full analysis would cost if warranted. |
Conclusion written by Dana Fitkowski, Principal, Critical Path Partners on 2 October 2026. Every figure it cites was checked against this report (the file as filed) and the companion evidence workbench sample (data date corrected to 15-Oct-2025), both rebuilt on engine v2.10.13, and restated where a rebuild moved it, on 22 October 2026. The engine produced the files; the analyst produced this conclusion.
The Evidence
The exhibits behind these findings follow in full and unchanged, each under its drawing code; the registers at A-06 list every activity behind each failing check.
- A-01Executive Summary
- A-01.1Basis of Measurement
- A-02Key Performance Metrics
- A-03DCMA 14-Point Assessment
- A-04DCMA-14 Status by Criterion
- A-05Baseline vs Current Comparison
- A-06Failure Analysis & Registers
- A-06bDetailed Comparison
- A-07Schedule Exposure
- A-08Schedule Forecast
- A-09Path back to green
- A-10Report Information
Executive Summary
narrative · health score · findingsThe Larchmere Library and Community Hub (Demo Data) schedule passes 4 of 13 scored DCMA criteria, earning an overall grade of F (31% compliance) with a RED status band. Criteria clearing their thresholds: C1, C5, C8, C14.
The failing criteria are C2 Leads, C3 Lags, C4 Relationship Types, C6 High Float, C7 Negative Float, C9 Valid Dates, C11 Missed Tasks, C12 Critical Path Test, C13 CPLI. Both forward-looking indices read CPLI 0.83 and BEI 0.97, and the schedule is trending toward +37 working-day overrun to 24-Jun-2026.
finish drift +37 wd vs baseline
Summary of findings
what failed, and the grade it produced- Leads (2), 2 leads found (C2).
- Lags (11.1%), 65 of 584 relationships (11.1%) | 0 exceed 44 days (C3).
- Relationship Types (88% FS), Total: 584 | FS: 515 (88.2%), SS: 68 (11.6%), FF: 0 (0.0%), SF: 1 (0.2%) (C4).
- High Float (33.7% (85)), 85 activities with high float (33.7%) (C6).
- Negative Float (123), 123 activities with negative float (C7).
- Valid Dates (61), 61 activities with invalid dates (16.1%; 0 forecast, 61 actual) | Status date: 05-Aug-2025 | Latest actual: 14-Oct-2025 (+48 wd) | Actual>DD: start 53, finish 54 (C9).
- Missed Tasks (6), Missed: 6/58 (10.3%) | Missing baseline IDs from current: 2 (C11).
- Critical Path Test (124 activities), Orphans 5.6% > 5%; Fragmented critical network (76.6% in main chain) (C12).
- CPLI (0.83), CPLI: 0.834 | Contract: 01-May-2026 (A1050: Ready for Owner Takeover) | Forecast: 24-Jun-2026 (A1050: Ready for Owner Takeover) | Float: -37 wd (C13).
The schedule grades F (RED): 4 of 13 criteria pass. Failures cluster in C2, C3, C4, C6, C7, C9, C11, C12, C13. The registers under A-06 list every activity behind each failure.
Basis of Measurement
how to read these figures & what has been validatedKey Performance Metrics
14-criteria roll-upThe A to F grade and its bands are CPP’s convention for summarising the scored criteria. DCMA sets a pass or fail threshold for each criterion; it does not grade a schedule.
DCMA 14-Point Assessment
13 scored · 4 PASS / 9 FAIL · Grade FThe update was statused to 14-Oct-2025 (A2910 actual finish) but its data date was left at 05-Aug-2025. 102 activities that hadn't started were forecast to start before 15-Oct-2025: each is either late or missing its status. The CPP analysis tools move the data date to 15-Oct-2025 for their analysis.
DCMA-14 Status by Criterion
14 criteria · PASS / FAILBaseline vs Current Comparison
task · schedule · varianceFailure Analysis & Registers
9 failing criteria · severity profile · full activity registers| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A2380 | Curtain wall and windows, West elevation | ENV Building Envelope | 02-Dec-2025 | Lead (wd): 2 | Has 2 wd lead from "Exterior sheathing and air/vapour barrier, West elevation" |
| A4100 | Tape, mud and sand Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 08-Jan-2026 | Lead (wd): 1 | Has 1 wd lead from "Drywall board Level 3 Zone D" |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A1600 | Bulk excavation | Site Works | 04-Jul-2025 | Lag (wd): 3 | Positive lag of 3 wd from "Shoring along the north property line" (lag usage exceeds 5%) |
| A1610 | Storm sewer and catch basins | Site Works | 09-Jul-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Bulk excavation" (lag usage exceeds 5%) |
| A1620 | Sanitary service to property line | Site Works | 07-Jul-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Bulk excavation" (lag usage exceeds 5%) |
| A1630 | Water service and fire line | Site Works | 07-Jul-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Bulk excavation" (lag usage exceeds 5%) |
| A4670 | Masonry veneer, North elevation | ENV Building Envelope | 17-Sep-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Exterior sheathing and air/vapour barrier, North elevation" (lag usage exceeds 5%) |
| A4690 | Masonry veneer, East elevation | ENV Building Envelope | 29-Sep-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Exterior sheathing and air/vapour barrier, East elevation" (lag usage exceeds 5%) |
| A4710 | Masonry veneer, South elevation | ENV Building Envelope | 09-Oct-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Exterior sheathing and air/vapour barrier, South elevation" (lag usage exceeds 5%) |
| A4730 | Masonry veneer, West elevation | ENV Building Envelope | 22-Oct-2025 | Lag (wd): 5 | Positive lag of 5 wd from "Exterior sheathing and air/vapour barrier, West elevation" (lag usage exceeds 5%) |
| A2430 | Rooftop unit curbs | Roofing | 26-Sep-2025 | Lag (wd): 4 | Positive lag of 4 wd from "Roof insulation and membrane" (lag usage exceeds 5%) |
| A2450 | Roof drains and leaders | Roofing | 25-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Roof insulation and membrane" (lag usage exceeds 5%) |
| A2610 | Mechanical in-wall rough-in Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 13-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone A" (lag usage exceeds 5%) |
| A2620 | Plumbing in-wall rough-in Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 25-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone A" (lag usage exceeds 5%) |
| A2630 | Electrical in-wall rough-in Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 26-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone A" (lag usage exceeds 5%) |
| A2640 | Sprinkler branch piping Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 25-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone A" (lag usage exceeds 5%) |
| A2740 | Mechanical in-wall rough-in Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 10-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone B" (lag usage exceeds 5%) |
| A2750 | Plumbing in-wall rough-in Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 09-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone B" (lag usage exceeds 5%) |
| A2760 | Electrical in-wall rough-in Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 10-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone B" (lag usage exceeds 5%) |
| A2770 | Sprinkler branch piping Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 09-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone B" (lag usage exceeds 5%) |
| A2870 | Mechanical in-wall rough-in Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 10-Oct-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone C" (lag usage exceeds 5%) |
| A2880 | Plumbing in-wall rough-in Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 09-Oct-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone C" (lag usage exceeds 5%) |
| A2890 | Electrical in-wall rough-in Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 10-Oct-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone C" (lag usage exceeds 5%) |
| A2900 | Sprinkler branch piping Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 09-Oct-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone C" (lag usage exceeds 5%) |
| A3000 | Mechanical in-wall rough-in Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 14-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone D" (lag usage exceeds 5%) |
| A3010 | Plumbing in-wall rough-in Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 13-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone D" (lag usage exceeds 5%) |
| A3020 | Electrical in-wall rough-in Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 14-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone D" (lag usage exceeds 5%) |
| A3030 | Sprinkler branch piping Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 13-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 1 Zone D" (lag usage exceeds 5%) |
| A3130 | Mechanical in-wall rough-in Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 13-Feb-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone A" (lag usage exceeds 5%) |
| A3140 | Plumbing in-wall rough-in Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 12-Feb-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone A" (lag usage exceeds 5%) |
| A3150 | Electrical in-wall rough-in Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 13-Feb-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone A" (lag usage exceeds 5%) |
| A3160 | Sprinkler branch piping Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 12-Feb-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone A" (lag usage exceeds 5%) |
| A3260 | Mechanical in-wall rough-in Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 24-Feb-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone B" (lag usage exceeds 5%) |
| A3270 | Plumbing in-wall rough-in Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 23-Feb-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone B" (lag usage exceeds 5%) |
| A3280 | Electrical in-wall rough-in Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 24-Feb-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone B" (lag usage exceeds 5%) |
| A3290 | Sprinkler branch piping Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 23-Feb-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone B" (lag usage exceeds 5%) |
| A3390 | Mechanical in-wall rough-in Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 04-Mar-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone C" (lag usage exceeds 5%) |
| A3400 | Plumbing in-wall rough-in Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 03-Mar-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone C" (lag usage exceeds 5%) |
| A3410 | Electrical in-wall rough-in Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 04-Mar-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone C" (lag usage exceeds 5%) |
| A3420 | Sprinkler branch piping Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 03-Mar-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone C" (lag usage exceeds 5%) |
| A3520 | Mechanical in-wall rough-in Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 12-Mar-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone D" (lag usage exceeds 5%) |
| A3530 | Plumbing in-wall rough-in Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 11-Mar-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone D" (lag usage exceeds 5%) |
| A3540 | Electrical in-wall rough-in Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 12-Mar-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone D" (lag usage exceeds 5%) |
| A3550 | Sprinkler branch piping Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 11-Mar-2026 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 2 Zone D" (lag usage exceeds 5%) |
| A3650 | Mechanical in-wall rough-in Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 18-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone A" (lag usage exceeds 5%) |
| A3660 | Plumbing in-wall rough-in Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 08-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone A" (lag usage exceeds 5%) |
| A3670 | Electrical in-wall rough-in Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 09-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone A" (lag usage exceeds 5%) |
| A3680 | Sprinkler branch piping Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 08-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone A" (lag usage exceeds 5%) |
| A3780 | Mechanical in-wall rough-in Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 17-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone B" (lag usage exceeds 5%) |
| A3790 | Plumbing in-wall rough-in Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 16-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone B" (lag usage exceeds 5%) |
| A3800 | Electrical in-wall rough-in Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 17-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone B" (lag usage exceeds 5%) |
| A3810 | Sprinkler branch piping Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 16-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone B" (lag usage exceeds 5%) |
| A3910 | Mechanical in-wall rough-in Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 25-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone C" (lag usage exceeds 5%) |
| A3920 | Plumbing in-wall rough-in Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 24-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone C" (lag usage exceeds 5%) |
| A3930 | Electrical in-wall rough-in Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 25-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone C" (lag usage exceeds 5%) |
| A3940 | Sprinkler branch piping Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 24-Sep-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone C" (lag usage exceeds 5%) |
| A4040 | Mechanical in-wall rough-in Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 03-Oct-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone D" (lag usage exceeds 5%) |
| A4050 | Plumbing in-wall rough-in Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 02-Oct-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone D" (lag usage exceeds 5%) |
| A4060 | Electrical in-wall rough-in Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 03-Oct-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone D" (lag usage exceeds 5%) |
| A4070 | Sprinkler branch piping Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 02-Oct-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Layout and partition framing Level 3 Zone D" (lag usage exceeds 5%) |
| A4180 | Site lighting bases and poles | Exterior Works | 15-Aug-2025 | Lag (wd): 2 | Positive lag of 2 wd from "Granular base for parking and drive" (lag usage exceeds 5%) |
| A2230 | Steel stairs and railings | Structure | 07-Oct-2025 | Lag (wd): 7 | Positive lag of 7 wd from "Concrete topping Level 2 Zone D" (lag usage exceeds 5%) |
| A2230 | Steel stairs and railings | Structure | 07-Oct-2025 | Lag (wd): 7 | Positive lag of 7 wd from "Concrete topping Level 3 Zone D" (lag usage exceeds 5%) |
| A4680 | Metal panel cladding, North elevation | ENV Building Envelope | 18-Sep-2025 | Lag (wd): 3 | Positive lag of 3 wd from "Masonry veneer, North elevation" (lag usage exceeds 5%) |
| A4700 | Metal panel cladding, East elevation | ENV Building Envelope | 30-Sep-2025 | Lag (wd): 3 | Positive lag of 3 wd from "Masonry veneer, East elevation" (lag usage exceeds 5%) |
| A4720 | Metal panel cladding, South elevation | ENV Building Envelope | 10-Oct-2025 | Lag (wd): 3 | Positive lag of 3 wd from "Masonry veneer, South elevation" (lag usage exceeds 5%) |
| A4740 | Metal panel cladding, West elevation | ENV Building Envelope | 23-Oct-2025 | Lag (wd): 3 | Positive lag of 3 wd from "Masonry veneer, West elevation" (lag usage exceeds 5%) |
| Activity ID | Activity Name | WBS | Forecast Finish | Total Float (wd) | Issue |
|---|---|---|---|---|---|
| A1650 | Backfill and compact at foundations | Site Works | 05-Aug-2025 | 104 | Total float of 104 wd exceeds 44 wd |
| A1890 | Slab on grade Zone D | FDN Foundations | 05-Aug-2025 | 56 | Total float of 56 wd exceeds 44 wd |
| A1940 | Metal deck Level 2 Zone B | Structure | 05-Aug-2025 | 99 | Total float of 99 wd exceeds 44 wd |
| A1950 | Concrete topping Level 2 Zone B | Structure | 08-Aug-2025 | 99 | Total float of 99 wd exceeds 44 wd |
| A1970 | Metal deck Level 2 Zone C | Structure | 11-Aug-2025 | 101 | Total float of 101 wd exceeds 44 wd |
| A1980 | Concrete topping Level 2 Zone C | Structure | 14-Aug-2025 | 101 | Total float of 101 wd exceeds 44 wd |
| A2000 | Metal deck Level 2 Zone D | Structure | 15-Aug-2025 | 103 | Total float of 103 wd exceeds 44 wd |
| A2010 | Concrete topping Level 2 Zone D | Structure | 20-Aug-2025 | 103 | Total float of 103 wd exceeds 44 wd |
| A2030 | Metal deck Level 3 Zone A | Structure | 25-Aug-2025 | 73 | Total float of 73 wd exceeds 44 wd |
| A2040 | Concrete topping Level 3 Zone A | Structure | 28-Aug-2025 | 73 | Total float of 73 wd exceeds 44 wd |
| A2060 | Metal deck Level 3 Zone B | Structure | 29-Aug-2025 | 89 | Total float of 89 wd exceeds 44 wd |
| A2070 | Concrete topping Level 3 Zone B | Structure | 04-Sep-2025 | 89 | Total float of 89 wd exceeds 44 wd |
| A2090 | Metal deck Level 3 Zone C | Structure | 05-Sep-2025 | 91 | Total float of 91 wd exceeds 44 wd |
| A2100 | Concrete topping Level 3 Zone C | Structure | 10-Sep-2025 | 91 | Total float of 91 wd exceeds 44 wd |
| A2120 | Metal deck Level 3 Zone D | Structure | 11-Sep-2025 | 93 | Total float of 93 wd exceeds 44 wd |
| A2130 | Concrete topping Level 3 Zone D | Structure | 16-Sep-2025 | 93 | Total float of 93 wd exceeds 44 wd |
| A2230 | Steel stairs and railings | Structure | 07-Oct-2025 | 142 | Total float of 142 wd exceeds 44 wd |
| A2240 | Elevator shaft masonry | Structure | 05-Aug-2025 | 141 | Total float of 141 wd exceeds 44 wd |
| A2280 | Sealants and flashings, North elevation | ENV Building Envelope | 24-Sep-2025 | 151 | Total float of 151 wd exceeds 44 wd |
| A2320 | Sealants and flashings, East elevation | ENV Building Envelope | 06-Oct-2025 | 143 | Total float of 143 wd exceeds 44 wd |
| A2360 | Sealants and flashings, South elevation | ENV Building Envelope | 17-Oct-2025 | 135 | Total float of 135 wd exceeds 44 wd |
| A2400 | Sealants and flashings, West elevation | ENV Building Envelope | 29-Oct-2025 | 127 | Total float of 127 wd exceeds 44 wd |
| A2430 | Rooftop unit curbs | Roofing | 26-Sep-2025 | 86 | Total float of 86 wd exceeds 44 wd |
| A2440 | Set rooftop air handling units | Roofing | 01-Oct-2025 | 86 | Total float of 86 wd exceeds 44 wd |
| A2450 | Roof drains and leaders | Roofing | 25-Sep-2025 | 150 | Total float of 150 wd exceeds 44 wd |
| A2490 | Ductwork mains Level 2 | MEP Mechanical and Electrical Services | 10-Sep-2025 | 73 | Total float of 73 wd exceeds 44 wd |
| A2500 | Ductwork mains Level 3 | MEP Mechanical and Electrical Services | 11-Sep-2025 | 80 | Total float of 80 wd exceeds 44 wd |
| A2520 | Sprinkler mains and risers | MEP Mechanical and Electrical Services | 05-Aug-2025 | 158 | Total float of 158 wd exceeds 44 wd |
| A2580 | Elevator rails, machine and car install | Elevator | 03-Sep-2025 | 141 | Total float of 141 wd exceeds 44 wd |
| A2590 | Elevator inspection and licence (TSSA) | Elevator | 05-Sep-2025 | 141 | Total float of 141 wd exceeds 44 wd |
| A2990 | Layout and partition framing Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 13-Aug-2025 | 56 | Total float of 56 wd exceeds 44 wd |
| A3000 | Mechanical in-wall rough-in Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 14-Aug-2025 | 56 | Total float of 56 wd exceeds 44 wd |
| A3010 | Plumbing in-wall rough-in Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 13-Aug-2025 | 57 | Total float of 57 wd exceeds 44 wd |
| A3020 | Electrical in-wall rough-in Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 14-Aug-2025 | 56 | Total float of 56 wd exceeds 44 wd |
| A3030 | Sprinkler branch piping Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 13-Aug-2025 | 57 | Total float of 57 wd exceeds 44 wd |
| A3040 | In-wall services inspection Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 15-Aug-2025 | 56 | Total float of 56 wd exceeds 44 wd |
| A3640 | Layout and partition framing Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 08-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3650 | Mechanical in-wall rough-in Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 18-Sep-2025 | 80 | Total float of 80 wd exceeds 44 wd |
| A3660 | Plumbing in-wall rough-in Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 08-Sep-2025 | 88 | Total float of 88 wd exceeds 44 wd |
| A3670 | Electrical in-wall rough-in Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 09-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3680 | Sprinkler branch piping Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 08-Sep-2025 | 88 | Total float of 88 wd exceeds 44 wd |
| A3690 | In-wall services inspection Level 3 Zone A | Interiors / L3 Interiors - Level 3 | 19-Sep-2025 | 80 | Total float of 80 wd exceeds 44 wd |
| A3770 | Layout and partition framing Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 16-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3780 | Mechanical in-wall rough-in Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 17-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3790 | Plumbing in-wall rough-in Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 16-Sep-2025 | 88 | Total float of 88 wd exceeds 44 wd |
| A3800 | Electrical in-wall rough-in Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 17-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3810 | Sprinkler branch piping Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 16-Sep-2025 | 88 | Total float of 88 wd exceeds 44 wd |
| A3820 | In-wall services inspection Level 3 Zone B | Interiors / L3 Interiors - Level 3 | 18-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3900 | Layout and partition framing Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 24-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3910 | Mechanical in-wall rough-in Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 25-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3920 | Plumbing in-wall rough-in Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 24-Sep-2025 | 88 | Total float of 88 wd exceeds 44 wd |
| A3930 | Electrical in-wall rough-in Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 25-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A3940 | Sprinkler branch piping Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 24-Sep-2025 | 88 | Total float of 88 wd exceeds 44 wd |
| A3950 | In-wall services inspection Level 3 Zone C | Interiors / L3 Interiors - Level 3 | 26-Sep-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A4030 | Layout and partition framing Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 02-Oct-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A4040 | Mechanical in-wall rough-in Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 03-Oct-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A4050 | Plumbing in-wall rough-in Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 02-Oct-2025 | 88 | Total float of 88 wd exceeds 44 wd |
| A4060 | Electrical in-wall rough-in Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 03-Oct-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A4070 | Sprinkler branch piping Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 02-Oct-2025 | 88 | Total float of 88 wd exceeds 44 wd |
| A4080 | In-wall services inspection Level 3 Zone D | Interiors / L3 Interiors - Level 3 | 06-Oct-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| A4160 | Granular base for parking and drive | Exterior Works | 13-Aug-2025 | 104 | Total float of 104 wd exceeds 44 wd |
| A4170 | Concrete curbs and sidewalks | Exterior Works | 25-Aug-2025 | 104 | Total float of 104 wd exceeds 44 wd |
| A4180 | Site lighting bases and poles | Exterior Works | 15-Aug-2025 | 157 | Total float of 157 wd exceeds 44 wd |
| A4190 | Asphalt paving | Exterior Works | 29-Aug-2025 | 151 | Total float of 151 wd exceeds 44 wd |
| A4200 | Landscaping and sod | Exterior Works | 05-Sep-2025 | 104 | Total float of 104 wd exceeds 44 wd |
| A4210 | Line painting and signage | Exterior Works | 03-Sep-2025 | 151 | Total float of 151 wd exceeds 44 wd |
| A4220 | Exterior stairs and barrier-free ramp | Exterior Works | 21-Oct-2025 | 118 | Total float of 118 wd exceeds 44 wd |
| A4230 | Entrance canopy steel and soffit | Exterior Works | 20-Oct-2025 | 134 | Total float of 134 wd exceeds 44 wd |
| A4260 | Sprinkler flush and hydrostatic test | Commissioning and Closeout | 07-Oct-2025 | 117 | Total float of 117 wd exceeds 44 wd |
| A4270 | Test, adjust and balance | Commissioning and Closeout | 30-Oct-2025 | 95 | Total float of 95 wd exceeds 44 wd |
| A4280 | Building automation functional testing | Commissioning and Closeout | 11-Nov-2025 | 95 | Total float of 95 wd exceeds 44 wd |
| A4290 | Mechanical commissioning | Commissioning and Closeout | 16-Oct-2025 | 86 | Total float of 86 wd exceeds 44 wd |
| A4360 | Owner training | Commissioning and Closeout | 18-Nov-2025 | 113 | Total float of 113 wd exceeds 44 wd |
| A4390 | Landscape establishment and warranty maintenance | Exterior Works | 01-Dec-2025 | 104 | Total float of 104 wd exceeds 44 wd |
| A4400 | Seasonal commissioning of heating and cooling | Commissioning and Closeout | 29-Dec-2025 | 86 | Total float of 86 wd exceeds 44 wd |
| A4670 | Masonry veneer, North elevation | ENV Building Envelope | 17-Sep-2025 | 151 | Total float of 151 wd exceeds 44 wd |
| A4680 | Metal panel cladding, North elevation | ENV Building Envelope | 18-Sep-2025 | 151 | Total float of 151 wd exceeds 44 wd |
| A4690 | Masonry veneer, East elevation | ENV Building Envelope | 29-Sep-2025 | 143 | Total float of 143 wd exceeds 44 wd |
| A4700 | Metal panel cladding, East elevation | ENV Building Envelope | 30-Sep-2025 | 143 | Total float of 143 wd exceeds 44 wd |
| A4710 | Masonry veneer, South elevation | ENV Building Envelope | 09-Oct-2025 | 118 | Total float of 118 wd exceeds 44 wd |
| A4720 | Metal panel cladding, South elevation | ENV Building Envelope | 10-Oct-2025 | 118 | Total float of 118 wd exceeds 44 wd |
| A4730 | Masonry veneer, West elevation | ENV Building Envelope | 22-Oct-2025 | 127 | Total float of 127 wd exceeds 44 wd |
| A4740 | Metal panel cladding, West elevation | ENV Building Envelope | 23-Oct-2025 | 127 | Total float of 127 wd exceeds 44 wd |
| A4820 | ESA rough-in inspection Level 1 | MEP Mechanical and Electrical Services | 15-Aug-2025 | 56 | Total float of 56 wd exceeds 44 wd |
| A4840 | ESA rough-in inspection Level 3 | MEP Mechanical and Electrical Services | 06-Oct-2025 | 87 | Total float of 87 wd exceeds 44 wd |
| Activity ID | Activity Name | WBS | Forecast Finish | Total Float (wd) | Issue |
|---|---|---|---|---|---|
| A1960 | Erect structural steel Level 2 Zone C | Structure | 06-Aug-2025 | -37 | Total float -37 wd |
| A1990 | Erect structural steel Level 2 Zone D | Structure | 12-Aug-2025 | -37 | Total float -37 wd |
| A2020 | Erect structural steel Level 3 Zone A | Structure | 20-Aug-2025 | -37 | Total float -37 wd |
| A2050 | Erect structural steel Level 3 Zone B | Structure | 26-Aug-2025 | -26 | Total float -26 wd |
| A2080 | Erect structural steel Level 3 Zone C | Structure | 02-Sep-2025 | -15 | Total float -15 wd |
| A2110 | Erect structural steel Level 3 Zone D | Structure | 08-Sep-2025 | -9 | Total float -9 wd |
| A2140 | Erect structural steel Roof Zone A | Structure | 26-Aug-2025 | -37 | Total float -37 wd |
| A2160 | Erect structural steel Roof Zone B | Structure | 02-Sep-2025 | -26 | Total float -26 wd |
| A2180 | Erect structural steel Roof Zone C | Structure | 08-Sep-2025 | -15 | Total float -15 wd |
| A2190 | Metal deck Roof Zone C | Structure | 11-Sep-2025 | -1 | Total float -1 wd |
| A2200 | Erect structural steel Roof Zone D | Structure | 12-Sep-2025 | -9 | Total float -9 wd |
| A2210 | Metal deck Roof Zone D | Structure | 17-Sep-2025 | -2 | Total float -2 wd |
| A2250 | Exterior sheathing and air/vapour barrier, North elevation | ENV Building Envelope | 08-Sep-2025 | -37 | Total float -37 wd |
| A2260 | Curtain wall and windows, North elevation | ENV Building Envelope | 29-Sep-2025 | -37 | Total float -37 wd |
| A2290 | Exterior sheathing and air/vapour barrier, East elevation | ENV Building Envelope | 18-Sep-2025 | -30 | Total float -30 wd |
| A2300 | Curtain wall and windows, East elevation | ENV Building Envelope | 21-Oct-2025 | -37 | Total float -37 wd |
| A2330 | Exterior sheathing and air/vapour barrier, South elevation | ENV Building Envelope | 30-Sep-2025 | -23 | Total float -23 wd |
| A2340 | Curtain wall and windows, South elevation | ENV Building Envelope | 11-Nov-2025 | -37 | Total float -37 wd |
| A2370 | Exterior sheathing and air/vapour barrier, West elevation | ENV Building Envelope | 10-Oct-2025 | -21 | Total float -21 wd |
| A2380 | Curtain wall and windows, West elevation | ENV Building Envelope | 02-Dec-2025 | -37 | Total float -37 wd |
| A2410 | Roof insulation and membrane | Roofing | 03-Oct-2025 | -2 | Total float -2 wd |
| A2420 | Roof flashings and penetrations | Roofing | 14-Oct-2025 | -2 | Total float -2 wd |
| A2660 | Drywall board Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 09-Dec-2025 | -37 | Total float -37 wd |
| A2670 | Tape, mud and sand Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 15-Dec-2025 | -37 | Total float -37 wd |
| A2680 | Prime paint Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 17-Dec-2025 | -37 | Total float -37 wd |
| A2700 | Flooring Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 05-Jan-2026 | -28 | Total float -28 wd |
| A2710 | Doors, hardware and millwork Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 09-Jan-2026 | -28 | Total float -28 wd |
| A2720 | Final paint and finishes Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 14-Jan-2026 | -28 | Total float -28 wd |
| A2790 | Drywall board Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 16-Dec-2025 | -36 | Total float -36 wd |
| A2800 | Tape, mud and sand Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 22-Dec-2025 | -36 | Total float -36 wd |
| A2810 | Prime paint Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 24-Dec-2025 | -36 | Total float -36 wd |
| A2830 | Flooring Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 13-Jan-2026 | -31 | Total float -31 wd |
| A2840 | Doors, hardware and millwork Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 19-Jan-2026 | -31 | Total float -31 wd |
| A2850 | Final paint and finishes Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 22-Jan-2026 | -31 | Total float -31 wd |
| A2920 | Drywall board Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 23-Dec-2025 | -35 | Total float -35 wd |
| A2930 | Tape, mud and sand Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 31-Dec-2025 | -35 | Total float -35 wd |
| A2940 | Prime paint Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 05-Jan-2026 | -35 | Total float -35 wd |
| A2960 | Flooring Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 21-Jan-2026 | -34 | Total float -34 wd |
| A2970 | Doors, hardware and millwork Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 27-Jan-2026 | -34 | Total float -34 wd |
| A2980 | Final paint and finishes Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 30-Jan-2026 | -34 | Total float -34 wd |
| A3050 | Drywall board Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 02-Jan-2026 | -34 | Total float -34 wd |
| A3060 | Tape, mud and sand Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 08-Jan-2026 | -34 | Total float -34 wd |
| A3070 | Prime paint Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 12-Jan-2026 | -34 | Total float -34 wd |
| A3090 | Flooring Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 29-Jan-2026 | -37 | Total float -37 wd |
| A3100 | Doors, hardware and millwork Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 04-Feb-2026 | -37 | Total float -37 wd |
| A3110 | Final paint and finishes Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 09-Feb-2026 | -37 | Total float -37 wd |
| A3120 | Layout and partition framing Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 12-Feb-2026 | -37 | Total float -37 wd |
| A3130 | Mechanical in-wall rough-in Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 13-Feb-2026 | -30 | Total float -30 wd |
| A3140 | Plumbing in-wall rough-in Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 12-Feb-2026 | -29 | Total float -29 wd |
| A3150 | Electrical in-wall rough-in Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 13-Feb-2026 | -37 | Total float -37 wd |
| A3160 | Sprinkler branch piping Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 12-Feb-2026 | -29 | Total float -29 wd |
| A3170 | In-wall services inspection Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 17-Feb-2026 | -30 | Total float -30 wd |
| A3180 | Drywall board Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 05-Mar-2026 | -37 | Total float -37 wd |
| A3190 | Tape, mud and sand Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 11-Mar-2026 | -37 | Total float -37 wd |
| A3200 | Prime paint Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 13-Mar-2026 | -37 | Total float -37 wd |
| A3220 | Flooring Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 27-Mar-2026 | -22 | Total float -22 wd |
| A3230 | Doors, hardware and millwork Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 02-Apr-2026 | -22 | Total float -22 wd |
| A3240 | Final paint and finishes Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 08-Apr-2026 | -22 | Total float -22 wd |
| A3250 | Layout and partition framing Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 23-Feb-2026 | -30 | Total float -30 wd |
| A3260 | Mechanical in-wall rough-in Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 24-Feb-2026 | -30 | Total float -30 wd |
| A3270 | Plumbing in-wall rough-in Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 23-Feb-2026 | -29 | Total float -29 wd |
| A3280 | Electrical in-wall rough-in Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 24-Feb-2026 | -30 | Total float -30 wd |
| A3290 | Sprinkler branch piping Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 23-Feb-2026 | -29 | Total float -29 wd |
| A3300 | In-wall services inspection Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 25-Feb-2026 | -30 | Total float -30 wd |
| A3310 | Drywall board Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 12-Mar-2026 | -36 | Total float -36 wd |
| A3320 | Tape, mud and sand Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 18-Mar-2026 | -36 | Total float -36 wd |
| A3330 | Prime paint Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 20-Mar-2026 | -36 | Total float -36 wd |
| A3350 | Flooring Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 07-Apr-2026 | -25 | Total float -25 wd |
| A3360 | Doors, hardware and millwork Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 13-Apr-2026 | -25 | Total float -25 wd |
| A3370 | Final paint and finishes Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 16-Apr-2026 | -25 | Total float -25 wd |
| A3380 | Layout and partition framing Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 03-Mar-2026 | -30 | Total float -30 wd |
| A3390 | Mechanical in-wall rough-in Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 04-Mar-2026 | -30 | Total float -30 wd |
| A3400 | Plumbing in-wall rough-in Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 03-Mar-2026 | -29 | Total float -29 wd |
| A3410 | Electrical in-wall rough-in Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 04-Mar-2026 | -30 | Total float -30 wd |
| A3420 | Sprinkler branch piping Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 03-Mar-2026 | -29 | Total float -29 wd |
| A3430 | In-wall services inspection Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 05-Mar-2026 | -30 | Total float -30 wd |
| A3440 | Drywall board Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 19-Mar-2026 | -35 | Total float -35 wd |
| A3450 | Tape, mud and sand Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 25-Mar-2026 | -35 | Total float -35 wd |
| A3460 | Prime paint Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 27-Mar-2026 | -35 | Total float -35 wd |
| A3480 | Flooring Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 15-Apr-2026 | -28 | Total float -28 wd |
| A3490 | Doors, hardware and millwork Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 21-Apr-2026 | -28 | Total float -28 wd |
| A3500 | Final paint and finishes Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 24-Apr-2026 | -28 | Total float -28 wd |
| A3510 | Layout and partition framing Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 11-Mar-2026 | -30 | Total float -30 wd |
| A3520 | Mechanical in-wall rough-in Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 12-Mar-2026 | -30 | Total float -30 wd |
| A3530 | Plumbing in-wall rough-in Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 11-Mar-2026 | -29 | Total float -29 wd |
| A3540 | Electrical in-wall rough-in Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 12-Mar-2026 | -30 | Total float -30 wd |
| A3550 | Sprinkler branch piping Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 11-Mar-2026 | -29 | Total float -29 wd |
| A3560 | In-wall services inspection Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 13-Mar-2026 | -30 | Total float -30 wd |
| A3570 | Drywall board Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 26-Mar-2026 | -34 | Total float -34 wd |
| A3580 | Tape, mud and sand Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 01-Apr-2026 | -34 | Total float -34 wd |
| A3590 | Prime paint Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 06-Apr-2026 | -34 | Total float -34 wd |
| A3610 | Flooring Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 28-Apr-2026 | -37 | Total float -37 wd |
| A3620 | Doors, hardware and millwork Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 07-May-2026 | -37 | Total float -37 wd |
| A3630 | Final paint and finishes Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 14-May-2026 | -37 | Total float -37 wd |
| A4330 | Deficiency review with the consultant | Commissioning and Closeout | 27-May-2026 | -37 | Total float -37 wd |
| A4340 | Substantial performance certification | Commissioning and Closeout | 03-Jun-2026 | -37 | Total float -37 wd |
| A4370 | Operation and maintenance manuals | Commissioning and Closeout | 10-Jun-2026 | -27 | Total float -27 wd |
| A4380 | Deficiency correction | Commissioning and Closeout | 24-Jun-2026 | -37 | Total float -37 wd |
| A4410 | Owner furniture and fit-out (by others) | BYO Work by Others | 24-Jun-2026 | -37 | Total float -37 wd |
| A4420 | Owner IT and security installation (by others) | BYO Work by Others | 17-Jun-2026 | -32 | Total float -32 wd |
| A4430 | Ceiling grid Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 22-Dec-2025 | -37 | Total float -37 wd |
| A4440 | Ceiling MEP devices and tiles Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 29-Dec-2025 | -37 | Total float -37 wd |
| A4450 | Ceiling grid Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 02-Jan-2026 | -37 | Total float -37 wd |
| A4460 | Ceiling MEP devices and tiles Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 07-Jan-2026 | -37 | Total float -37 wd |
| A4470 | Ceiling grid Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 12-Jan-2026 | -37 | Total float -37 wd |
| A4480 | Ceiling MEP devices and tiles Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 15-Jan-2026 | -37 | Total float -37 wd |
| A4490 | Ceiling grid Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 20-Jan-2026 | -37 | Total float -37 wd |
| A4500 | Ceiling MEP devices and tiles Level 1 Zone D | Interiors / L1 Interiors - Level 1 | 23-Jan-2026 | -37 | Total float -37 wd |
| A4510 | Ceiling grid Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 18-Mar-2026 | -37 | Total float -37 wd |
| A4520 | Ceiling MEP devices and tiles Level 2 Zone A | Interiors / L2 Interiors - Level 2 | 23-Mar-2026 | -37 | Total float -37 wd |
| A4530 | Ceiling grid Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 26-Mar-2026 | -37 | Total float -37 wd |
| A4540 | Ceiling MEP devices and tiles Level 2 Zone B | Interiors / L2 Interiors - Level 2 | 31-Mar-2026 | -37 | Total float -37 wd |
| A4550 | Ceiling grid Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 06-Apr-2026 | -37 | Total float -37 wd |
| A4560 | Ceiling MEP devices and tiles Level 2 Zone C | Interiors / L2 Interiors - Level 2 | 09-Apr-2026 | -37 | Total float -37 wd |
| A4570 | Ceiling grid Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 14-Apr-2026 | -37 | Total float -37 wd |
| A4580 | Ceiling MEP devices and tiles Level 2 Zone D | Interiors / L2 Interiors - Level 2 | 17-Apr-2026 | -37 | Total float -37 wd |
| A4800 | Special inspection of Level 2 steel connections | Structure | 14-Aug-2025 | -37 | Total float -37 wd |
| A4810 | Roof membrane flood test | Roofing | 06-Oct-2025 | -2 | Total float -2 wd |
| A4830 | ESA rough-in inspection Level 2 | MEP Mechanical and Electrical Services | 13-Mar-2026 | -30 | Total float -30 wd |
| A4860 | Winter enclosure of open curtain wall openings | ENV Building Envelope | 20-Oct-2025 | -21 | Total float -21 wd |
| A4870 | Second framing crew mobilized for Level 2 | Interiors / L2 Interiors - Level 2 | 06-Feb-2026 | -20 | Total float -20 wd |
| A4880 | Owner audio-visual rough-in (by others) | BYO Work by Others | 26-Feb-2026 | -37 | Total float -37 wd |
| A4900 | Punch list Level 2 | Commissioning and Closeout | 20-May-2026 | -37 | Total float -37 wd |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A1030 | Permanent Power Available | MS Key Milestones | 18-Sep-2025 | Actual start (18-Sep-2025) after status date (05-Aug-2025) | Actual finish (18-Sep-2025) after status date (05-Aug-2025) | |
| A1170 | Structural steel: fabricate and deliver | PROC Submittals and Procurement | 20-Aug-2025 | Actual finish (20-Aug-2025) after status date (05-Aug-2025) | |
| A1230 | Curtain wall and windows: fabricate and deliver | PROC Submittals and Procurement | 23-Sep-2025 | Actual finish (23-Sep-2025) after status date (05-Aug-2025) | |
| A1290 | Rooftop air handling units: fabricate and deliver | PROC Submittals and Procurement | 27-Aug-2025 | Actual finish (27-Aug-2025) after status date (05-Aug-2025) | |
| A1350 | Switchgear and transformers: fabricate and deliver | PROC Submittals and Procurement | 04-Sep-2025 | Actual finish (04-Sep-2025) after status date (05-Aug-2025) | |
| A1380 | Elevator: fabricate and deliver | PROC Submittals and Procurement | 11-Sep-2025 | Actual finish (11-Sep-2025) after status date (05-Aug-2025) | |
| A1650 | Backfill and compact at foundations | Site Works | 05-Aug-2025 | Actual start (08-Oct-2025) after status date (05-Aug-2025) | |
| A1690 | Waterproofing and perimeter drainage Zone A | FDN Foundations | 07-Aug-2025 | Actual finish (07-Aug-2025) after status date (05-Aug-2025) | |
| A1700 | Underslab services Zone A | FDN Foundations | 08-Aug-2025 | Actual finish (08-Aug-2025) after status date (05-Aug-2025) | |
| A1710 | Slab on grade Zone A | FDN Foundations | 15-Aug-2025 | Actual start (11-Aug-2025) after status date (05-Aug-2025) | Actual finish (15-Aug-2025) after status date (05-Aug-2025) | |
| A1740 | Foundation walls Zone B | FDN Foundations | 15-Aug-2025 | Actual finish (15-Aug-2025) after status date (05-Aug-2025) | |
| A1750 | Waterproofing and perimeter drainage Zone B | FDN Foundations | 21-Aug-2025 | Actual start (18-Aug-2025) after status date (05-Aug-2025) | Actual finish (21-Aug-2025) after status date (05-Aug-2025) | |
| A1760 | Underslab services Zone B | FDN Foundations | 22-Aug-2025 | Actual start (18-Aug-2025) after status date (05-Aug-2025) | Actual finish (22-Aug-2025) after status date (05-Aug-2025) | |
| A1770 | Slab on grade Zone B | FDN Foundations | 29-Aug-2025 | Actual start (25-Aug-2025) after status date (05-Aug-2025) | Actual finish (29-Aug-2025) after status date (05-Aug-2025) | |
| A1780 | Footings Zone C | FDN Foundations | 29-Aug-2025 | Actual start (06-Aug-2025) after status date (05-Aug-2025) | Actual finish (29-Aug-2025) after status date (05-Aug-2025) | |
| A1790 | Footing inspection Zone C | FDN Foundations | 03-Sep-2025 | Actual start (03-Sep-2025) after status date (05-Aug-2025) | Actual finish (03-Sep-2025) after status date (05-Aug-2025) | |
| A1800 | Foundation walls Zone C | FDN Foundations | 17-Sep-2025 | Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (17-Sep-2025) after status date (05-Aug-2025) | |
| A1810 | Waterproofing and perimeter drainage Zone C | FDN Foundations | 23-Sep-2025 | Actual start (18-Sep-2025) after status date (05-Aug-2025) | Actual finish (23-Sep-2025) after status date (05-Aug-2025) | |
| A1820 | Underslab services Zone C | FDN Foundations | 24-Sep-2025 | Actual start (18-Sep-2025) after status date (05-Aug-2025) | Actual finish (24-Sep-2025) after status date (05-Aug-2025) | |
| A1830 | Slab on grade Zone C | FDN Foundations | 01-Oct-2025 | Actual start (25-Sep-2025) after status date (05-Aug-2025) | Actual finish (01-Oct-2025) after status date (05-Aug-2025) | |
| A1840 | Footings Zone D | FDN Foundations | 11-Sep-2025 | Actual start (02-Sep-2025) after status date (05-Aug-2025) | Actual finish (11-Sep-2025) after status date (05-Aug-2025) | |
| A1850 | Footing inspection Zone D | FDN Foundations | 12-Sep-2025 | Actual start (12-Sep-2025) after status date (05-Aug-2025) | Actual finish (12-Sep-2025) after status date (05-Aug-2025) | |
| A1860 | Foundation walls Zone D | FDN Foundations | 01-Oct-2025 | Actual start (18-Sep-2025) after status date (05-Aug-2025) | Actual finish (01-Oct-2025) after status date (05-Aug-2025) | |
| A1870 | Waterproofing and perimeter drainage Zone D | FDN Foundations | 07-Oct-2025 | Actual start (02-Oct-2025) after status date (05-Aug-2025) | Actual finish (07-Oct-2025) after status date (05-Aug-2025) | |
| A1880 | Underslab services Zone D | FDN Foundations | 08-Oct-2025 | Actual start (02-Oct-2025) after status date (05-Aug-2025) | Actual finish (08-Oct-2025) after status date (05-Aug-2025) | |
| A1890 | Slab on grade Zone D | FDN Foundations | 05-Aug-2025 | Actual start (09-Oct-2025) after status date (05-Aug-2025) | |
| A1900 | Erect structural steel Level 2 Zone A | Structure | 24-Sep-2025 | Actual start (19-Sep-2025) after status date (05-Aug-2025) | Actual finish (24-Sep-2025) after status date (05-Aug-2025) | |
| A1910 | Metal deck Level 2 Zone A | Structure | 29-Sep-2025 | Actual start (25-Sep-2025) after status date (05-Aug-2025) | Actual finish (29-Sep-2025) after status date (05-Aug-2025) | |
| A1920 | Concrete topping Level 2 Zone A | Structure | 02-Oct-2025 | Actual start (30-Sep-2025) after status date (05-Aug-2025) | Actual finish (02-Oct-2025) after status date (05-Aug-2025) | |
| A1930 | Erect structural steel Level 2 Zone B | Structure | 10-Oct-2025 | Actual start (25-Sep-2025) after status date (05-Aug-2025) | Actual finish (10-Oct-2025) after status date (05-Aug-2025) | |
| A1940 | Metal deck Level 2 Zone B | Structure | 05-Aug-2025 | Actual start (14-Oct-2025) after status date (05-Aug-2025) | |
| A1960 | Erect structural steel Level 2 Zone C | Structure | 06-Aug-2025 | Actual start (14-Oct-2025) after status date (05-Aug-2025) | |
| A2240 | Elevator shaft masonry | Structure | 05-Aug-2025 | Actual start (25-Aug-2025) after status date (05-Aug-2025) | |
| A2460 | Set boilers and pumps | MEP Mechanical and Electrical Services | 22-Aug-2025 | Actual start (18-Aug-2025) after status date (05-Aug-2025) | Actual finish (22-Aug-2025) after status date (05-Aug-2025) | |
| A2470 | Mechanical room piping | MEP Mechanical and Electrical Services | 10-Sep-2025 | Actual start (25-Aug-2025) after status date (05-Aug-2025) | Actual finish (10-Sep-2025) after status date (05-Aug-2025) | |
| A2480 | Ductwork mains Level 1 | MEP Mechanical and Electrical Services | 05-Aug-2025 | Actual start (03-Oct-2025) after status date (05-Aug-2025) | |
| A2510 | Domestic water risers | MEP Mechanical and Electrical Services | 10-Oct-2025 | Actual start (03-Oct-2025) after status date (05-Aug-2025) | Actual finish (10-Oct-2025) after status date (05-Aug-2025) | |
| A2520 | Sprinkler mains and risers | MEP Mechanical and Electrical Services | 05-Aug-2025 | Actual start (03-Oct-2025) after status date (05-Aug-2025) | |
| A2530 | Set switchgear and transformers | MEP Mechanical and Electrical Services | 11-Sep-2025 | Actual start (05-Sep-2025) after status date (05-Aug-2025) | Actual finish (11-Sep-2025) after status date (05-Aug-2025) | |
| A2540 | Utility connection and ESA inspection | MEP Mechanical and Electrical Services | 18-Sep-2025 | Actual start (12-Sep-2025) after status date (05-Aug-2025) | Actual finish (18-Sep-2025) after status date (05-Aug-2025) | |
| A2550 | Feeders and distribution panels | MEP Mechanical and Electrical Services | 29-Sep-2025 | Actual start (12-Sep-2025) after status date (05-Aug-2025) | Actual finish (29-Sep-2025) after status date (05-Aug-2025) | |
| A2570 | Building automation controls rough-in | MEP Mechanical and Electrical Services | 01-Oct-2025 | Actual start (11-Sep-2025) after status date (05-Aug-2025) | Actual finish (01-Oct-2025) after status date (05-Aug-2025) | |
| A2600 | Layout and partition framing Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 25-Aug-2025 | Actual start (18-Aug-2025) after status date (05-Aug-2025) | Actual finish (25-Aug-2025) after status date (05-Aug-2025) | |
| A2620 | Plumbing in-wall rough-in Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 25-Aug-2025 | Actual start (20-Aug-2025) after status date (05-Aug-2025) | Actual finish (25-Aug-2025) after status date (05-Aug-2025) | |
| A2630 | Electrical in-wall rough-in Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 26-Aug-2025 | Actual start (20-Aug-2025) after status date (05-Aug-2025) | Actual finish (26-Aug-2025) after status date (05-Aug-2025) | |
| A2640 | Sprinkler branch piping Level 1 Zone A | Interiors / L1 Interiors - Level 1 | 25-Aug-2025 | Actual start (20-Aug-2025) after status date (05-Aug-2025) | Actual finish (25-Aug-2025) after status date (05-Aug-2025) | |
| A2730 | Layout and partition framing Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 09-Sep-2025 | Actual start (02-Sep-2025) after status date (05-Aug-2025) | Actual finish (09-Sep-2025) after status date (05-Aug-2025) | |
| A2740 | Mechanical in-wall rough-in Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 10-Sep-2025 | Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (10-Sep-2025) after status date (05-Aug-2025) | |
| A2750 | Plumbing in-wall rough-in Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 09-Sep-2025 | Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (09-Sep-2025) after status date (05-Aug-2025) | |
| A2760 | Electrical in-wall rough-in Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 10-Sep-2025 | Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (10-Sep-2025) after status date (05-Aug-2025) | |
| A2770 | Sprinkler branch piping Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 09-Sep-2025 | Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (09-Sep-2025) after status date (05-Aug-2025) | |
| A2780 | In-wall services inspection Level 1 Zone B | Interiors / L1 Interiors - Level 1 | 11-Sep-2025 | Actual start (11-Sep-2025) after status date (05-Aug-2025) | Actual finish (11-Sep-2025) after status date (05-Aug-2025) | |
| A2860 | Layout and partition framing Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 09-Oct-2025 | Actual start (02-Oct-2025) after status date (05-Aug-2025) | Actual finish (09-Oct-2025) after status date (05-Aug-2025) | |
| A2870 | Mechanical in-wall rough-in Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 10-Oct-2025 | Actual start (06-Oct-2025) after status date (05-Aug-2025) | Actual finish (10-Oct-2025) after status date (05-Aug-2025) | |
| A2880 | Plumbing in-wall rough-in Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 09-Oct-2025 | Actual start (06-Oct-2025) after status date (05-Aug-2025) | Actual finish (09-Oct-2025) after status date (05-Aug-2025) | |
| A2890 | Electrical in-wall rough-in Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 10-Oct-2025 | Actual start (06-Oct-2025) after status date (05-Aug-2025) | Actual finish (10-Oct-2025) after status date (05-Aug-2025) | |
| A2900 | Sprinkler branch piping Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 09-Oct-2025 | Actual start (06-Oct-2025) after status date (05-Aug-2025) | Actual finish (09-Oct-2025) after status date (05-Aug-2025) | |
| A2910 | In-wall services inspection Level 1 Zone C | Interiors / L1 Interiors - Level 1 | 14-Oct-2025 | Actual start (14-Oct-2025) after status date (05-Aug-2025) | Actual finish (14-Oct-2025) after status date (05-Aug-2025) | |
| A4300 | Electrical commissioning | Commissioning and Closeout | 06-Oct-2025 | Actual start (30-Sep-2025) after status date (05-Aug-2025) | Actual finish (06-Oct-2025) after status date (05-Aug-2025) | |
| A4760 | CD-03 Atrium framing revision: re-detail and fabricate added steel | CO Change Orders | 18-Sep-2025 | Actual start (21-Aug-2025) after status date (05-Aug-2025) | Actual finish (18-Sep-2025) after status date (05-Aug-2025) | |
| A4790 | Footing re-inspection Zone C after engineered fill | FDN Foundations | 02-Sep-2025 | Actual start (02-Sep-2025) after status date (05-Aug-2025) | Actual finish (02-Sep-2025) after status date (05-Aug-2025) |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A1090 | Site survey and building layout | Preconstruction and Permits | 09-May-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (07-May-2025) |
| A1150 | Structural steel shop drawings: prepare and submit | PROC Submittals and Procurement | 16-Jun-2025 | Working days late: 10 wd | Actual finish 10 wd later than baseline (02-Jun-2025) |
| A1160 | Structural steel shop drawings: consultant review | PROC Submittals and Procurement | 30-Jun-2025 | Working days late: 10 wd | Actual finish 10 wd later than baseline (16-Jun-2025) |
| A1220 | Curtain wall and windows shop drawings: consultant review | PROC Submittals and Procurement | 11-Jul-2025 | Working days late: 18 wd | Actual finish 18 wd later than baseline (16-Jun-2025) |
| A1590 | Shoring along the north property line | Site Works | 26-Jun-2025 | Working days late: 21 wd | Actual finish 21 wd later than baseline (28-May-2025) |
| A1640 | Municipal service connection inspection | Site Works | 14-Jul-2025 | Working days late: 3 wd | Actual finish 3 wd later than baseline (09-Jul-2025) |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A2230 | Steel stairs and railings | Structure | 07-Oct-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A2280 | Sealants and flashings, North elevation | ENV Building Envelope | 24-Sep-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A2320 | Sealants and flashings, East elevation | ENV Building Envelope | 06-Oct-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A2360 | Sealants and flashings, South elevation | ENV Building Envelope | 17-Oct-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A2400 | Sealants and flashings, West elevation | ENV Building Envelope | 29-Oct-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A2450 | Roof drains and leaders | Roofing | 25-Sep-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A4230 | Entrance canopy steel and soffit | Exterior Works | 20-Oct-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A4420 | Owner IT and security installation (by others) | BYO Work by Others | 17-Jun-2026 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A4670 | Masonry veneer, North elevation | ENV Building Envelope | 17-Sep-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A4680 | Metal panel cladding, North elevation | ENV Building Envelope | 18-Sep-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A4690 | Masonry veneer, East elevation | ENV Building Envelope | 29-Sep-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A4700 | Metal panel cladding, East elevation | ENV Building Envelope | 30-Sep-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A4730 | Masonry veneer, West elevation | ENV Building Envelope | 22-Oct-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
| A4740 | Metal panel cladding, West elevation | ENV Building Envelope | 23-Oct-2025 | Connectivity: No finish path | Orphan activity cannot reach finish |
Detailed Comparison
baseline → current → variance| Metric | Baseline | Current | Variance |
|---|---|---|---|
| Total Tasks | 343 | 379 | +36 |
| Project Finish | 01-May-2026 | 24-Jun-2026 | +37 wd |
| Project Start | 05-May-2025 | 05-May-2025 | 0 wd |
| CPLI | n/a | 0.83 | below 0.95 |
| BEI | n/a | 0.97 | at/above 0.95 |
Schedule Exposure
measured figures only · derivations below- Finish drift: working days from the baseline finish (01-May-2026) to the current forecast finish (24-Jun-2026), counted on the project calendar. Positive = finishing later than baseline.
- CPLI 0.83:
(contract finish − data date) ÷ (forecast finish − data date). Below 1.00 = the forecast finish falls beyond the contract finish. Here: contract finish 01-May-2026, forecast finish 24-Jun-2026, measured from the data date 05-Aug-2025. - BEI 0.97:
baseline activities actually complete ÷ baseline activities planned complete at the data date. Below 1.00 = executing behind the baseline plan. Here: 58 complete ÷ 60 planned complete at the data date. - Drift direction: the sign of the finish drift. Positive drift (+37 wd), so the schedule is slipping against baseline.
- No resource figure is reported. The schedule carries no resource assignments (C10 not scored), so no resource-based risk or resource-increase percentage can be derived from this file.
Schedule Forecast
forward-pass dates as scheduled- These are the schedule’s own dates as read from the file: the forecast completion is the current schedule’s forward-pass finish, not a probabilistic projection. This screen models no delay probabilities and no resource requirements; a probabilistic finish-date forecast requires a schedule risk analysis (Monte Carlo), which is a separate deliverable.
Path back to green
grade re-scored per cleared criterion · 9 failing| Criterion cleared | Current metric | Grade | Compliance | Band |
|---|---|---|---|---|
| C7 Negative Float | 123 | F | 38% | RED |
| C9 Valid Dates | 61 | F | 38% | RED |
| C12 Critical Path Test | 124 activities | F | 38% | RED |
| C11 Missed Tasks | 6 | F | 38% | RED |
| C13 CPLI | 0.83 | F | 38% | RED |
| C2 Leads | 2 | F | 38% | RED |
| C3 Lags | 11.1% | F | 38% | RED |
| C4 Relationship Types | 88% FS | F | 38% | RED |
| C6 High Float | 33.7% (85) | F | 38% | RED |
| All 9 failing criteria cleared | all | A | 100% | GREEN |
- The grade is a pure function of the pass rate:
passed ÷ scored, graded A ≥90%, B ≥75%, C ≥60%, D ≥45%, else F, the same scoring the headline grade uses. Each row adds exactly one cleared criterion to the 4 currently passing of 13 scored. - Clearing a criterion means correcting its listed activities so the check passes (for example, clearing C9 means fixing every invalid date in its register). Other criteria are held at their computed results; knock-on effects of the corrections themselves are not modelled here.