Schedule Health Dashboard
DCMA 14-Point Assessment & Quality Compliance Analysis
Executive Summary
Baseline Assessment Note
This report is scored out of 13/14 criteria. Excluded: C10 (Resources) — marked N/A due to project phase or data availability. An approved baseline is available.
Only 5 of 13 criteria passed
Schedule quality requires immediate attention with multiple critical deficiencies identified. (Note: Scored out of 13 criteria)
Feasibility gap vs baseline/contract finish
CPLI 0.933 | Contract: 2026-08-31 | Forecast: 2026-09-30 | Float: -22d (22 days late vs baseline finish)
Lead relationships found
7 negative lag relationships detected. Leads create unrealistic schedule compression and should be eliminated. → Action: Replace leads with overlapping activities or adjust activity definitions.
Excessive lag usage
10.6% of relationships contain lags (target ≤5%). Review and justify each lag or break down activities. → Action: Create intermediate milestones instead of using lags where possible.
High float activities detected
149 activities with float >44 days indicate missing relationships or incorrect sequencing. → Action: Review high float activities to ensure proper integration into schedule logic.
Long duration activities
38 activities exceed 44 working days. Break down into smaller work packages for better control. → Action: Decompose long activities into 1-week activities for improved tracking.
Missed task dates
19 activities incomplete despite passing planned dates. Update actuals and reforecast remaining work. → Action: Mark completed activities and update progress on in-progress work immediately.
38%
Health Score
RED STATUS
Key Performance Metrics
Criteria Passed
5
of 13 total criteria
C10 N/A - scored out of 13
›
No criteria passed yet
Criteria Failed
8
requires attention
›
No criteria failed yet
Compliance Rate
38%
overall quality score
›
Load schedule to see breakdown
Overall Rating
F
assessment grade
›
Load schedule to see grading scale
DCMA 14-Point Assessment
Comprehensive evaluation of schedule quality based on Defense Contract Management Agency (DCMA) 14-Point Assessment criteria. Each criterion measures a critical aspect of schedule health and reliability.
Health Score Breakdown 👆 Click cards for details
Logic & Flow
2/4
Fair
›
Complete assessment to see breakdown
Resources & Progress
0/2
Poor
›
Complete assessment to see breakdown
Constraints & Float
2/4
Fair
›
Complete assessment to see breakdown
Performance
1/3
Poor
›
Complete assessment to see breakdown
DCMA-14 Status by Criterion
Per-criterion DCMA-14 status — one row for each of the fourteen criteria, color-coded by result. PASS means the criterion met its threshold; FAIL means it did not; N/A applies to baseline-dependent criteria like CPLI and BEI when no baseline is loaded. Reading down the chart shows exactly which criteria failed without having to count slices in a doughnut.