Schedule Health Review

Schedule Health DashboardDCMA 14-Point Assessment & Quality Compliance Analysis

Project
Larchmere Library and Community Hub (Demo Data)
Data date
05-Aug-2025
Baseline
05-May-2025
Activities
379
Overall quality grade
F
Critical
remediation advised
Status
RED
DCMA-14
4 / 13
Compliance
31%
1

Summary of Findings

This schedule cannot yet be relied on to forecast completion: it passes 4 of the 13 scored DCMA-14 checks (grade F, 31%), and four of its nine failures change its dates or its critical path.

As filed, it forecasts completion on 24 June 2026, 37 working days later than the baseline finish of 1 May 2026, but that forecast was calculated at a data date of 5 August 2025 while progress is recorded to 14 October 2025, so the date cannot be taken at face value. Against the contract finish of 1 May 2026 (A1050 Ready for Owner Takeover) it is 37 working days behind.

What is asked: the scheduler who prepares the update should re-issue it at a data date of 15 October 2025 and correct the items in section 2; the screen should then be run again before the forecast finish is used for any decision.

Grade
F (31%)
4 of 13 scored checks pass; the A to F grade is CPP’s convention
Forecast finish, as filed
24 June 2026
37 working days later than the baseline, 1 May 2026
Data date
5 August 2025
progress recorded to 14 October 2025
Negative float
123 activities
of 252 checked, as much as 37 working days behind

Negative float flags 123 of the 252 activities checked (48.8%), the largest share of any failing check

Changes the dates or the critical path: fix firstReads the finish against the contractOther failing checksThe check’s limit
C7Negative float
48.8%, 123 of 252 activities
C6High float
33.7%, 85 of 252 activities
C9Valid dates
16.1%, 61 of 379 activities
C3Lags
11.1%, 65 of 584 links
C11Missed tasks
10.3%, 6 of 58 activities due
C12Critical path test
5.6%, 14 of 252 unfinished activities
C2Leads
0.3%, 2 of 584 links

C4 relationship types and C13 CPLI fail on a ratio rather than a list of activities and are scored in section 3. An activity can be flagged by more than one check.

2

What Needs Fixing First

Four of the failing checks change the schedule’s dates or its critical path and come first: until these are corrected, neither the forecast finish nor the critical path can be relied on.

Status Recorded After the Data Date

61 activities carry dates on the wrong side of the data date of 5 August 2025: 53 actual starts and 54 actual finishes fall after it. The latest, 14 October 2025, is 48 working days after the data date. Inside one update that is a contradiction: the file reports work done after the date it says its status was taken.

102 activities that had not started were forecast to start before 15 October 2025: each is either late or missing its status.

To fix: re-issue the update with its data date moved to 15 October 2025 and the unstarted work re-forecast from that date.

For example:

  • A1940 Metal deck Level 2 Zone B, started 14 October 2025
  • A1960 Erect structural steel Level 2 Zone C, started 14 October 2025
  • A2910 In-wall services inspection Level 1 Zone C, finished 14 October 2025

Every one is listed in the C9 register at A-06.

61activities with dates on the wrong side of the data date

Critical Path Continuity

14 of 252 unfinished activities (5.6%, against a limit of 5%) are not on any path from the start to the finish. Of the 124 activities with zero or negative float, only 95 (76.6%) connect into one chain. The critical path the file reports cannot be followed from start to finish, and an activity off the path cannot move the finish however late it runs, so a delay to it would not show.

To fix: tie each listed activity to the work that drives it and the work it releases, then check the critical path again.

For example:

  • A2230 Steel stairs and railings, no path to the finish
  • A2280 Sealants and flashings, North elevation, no path to the finish
  • A2320 Sealants and flashings, East elevation, no path to the finish

Every one is listed in the C12 register at A-06.

14unfinished activities with no path to the finish

Excess Float

85 of 252 unfinished activities (33.7%, against a limit of 5%) carry more than 44 working days of total float, as much as 158 working days. Float that large usually means an activity is missing a successor: it could slip for weeks without moving the finish, so the critical path may be longer than the file shows.

To fix: check each listed activity for a missing successor and add it.

For example:

  • A2520 Sprinkler mains and risers, 158 working days of float
  • A4180 Site lighting bases and poles, 157 working days of float
  • A2280 Sealants and flashings, North elevation, 151 working days of float

Every one is listed in the C6 register at A-06.

85activities with more than 44 working days of float

Leads

2 links carry a negative lag (a lead) of up to 2 working days. A lead overlaps two activities by a fixed amount instead of by logic, so the successor does not respond as it should when the predecessor changes.

To fix: replace each lead with a start-to-start link, or split the predecessor.

For example:

  • A2380 Curtain wall and windows, West elevation, 2 working days of lead from Exterior sheathing and air/vapour barrier, West elevation
  • A4100 Tape, mud and sand Level 3 Zone D, 1 working day of lead from Drywall board Level 3 Zone D

Every one is listed in the C2 register at A-06.

2links with a lead

What the Dates Say About the Finish

Two further failures are not faults to correct in the file but readings of the finish. 123 activities carry negative float, as much as 37 working days, and the critical path length index is 0.83 against 0.95: as filed, the forecast finish of 24 June 2026 is 37 working days behind the contract finish of 1 May 2026. Both should be read again once the update is re-issued.

3

How the Schedule Scores

Of the 13 scored checks, 9 fail. The float and critical path checks fare worst, all four failing, and the duration and resource checks best, with none failing.

CheckWhat it testsMeasuredTargetResult
LogicThree of the four checks fail: leads, lags and relationship types.
C1 LogicEvery unfinished activity has a predecessor and a successor8 of 256 activities (3.1%)5% or fewerPass
C2 LeadsNo link carries a negative lag (a lead)2 linksZeroFail
C3 LagsFew links carry a positive lag (a waiting time)65 of 584 links (11.1%)5% or fewerFail
C4 Relationship typesMost links are finish-to-start88.2% finish-to-start90% or moreFail
Dates and StatusTwo of the four checks fail: valid dates and missed tasks.
C9 Valid datesNo actual date after the data date and no forecast date before it61 of 379 activities (16.1%)0% or fewerFail
C5 Hard constraintsFew dates are fixed by a hard constraint instead of by logic1 of 252 activities (0.4%)5% or fewerPass
C11 Missed tasksFew activities due by the data date finished after the baseline date6 of 58 due (10.3%)5% or fewerFail
C14 BEIThe work the baseline planned by the data date is done0.970.95 or morePass
Float and the Critical PathAll four checks fail: critical path test, high float, negative float and CPLI.
C12 Critical path testThe critical path runs as one chain from the start to the finish14 off the path to the finish; 95 of 124 critical activities in one chainOne chain from start to finishFail
C6 High floatFew unfinished activities carry more than 44 working days of float85 of 252 activities (33.7%)5% or fewerFail
C7 Negative floatNo activity carries negative float123 of 252 activitiesZeroFail
C13 CPLIThe remaining critical path can reach the contract finish0.830.95 or moreFail
Durations and ResourcesThe check passes; the other is not scored on this file.
C8 High durationFew unfinished activities run longer than 44 working days2 of 252 activities (0.8%)5% or fewerPass
C10 ResourcesActivities carry resources or costNot scored100% or moreNot scored

The pass and fail thresholds are those of the DCMA 14-Point Assessment as this screen applies them; the A to F grade is CPP’s convention for summarising the scored checks, and DCMA does not grade a schedule.

4

How Far the Figures Can Be Relied On

Every figure here is read from the file exactly as filed, at a data date its own progress has overtaken: the figures describe the file, not yet the project.

Data date. The update reports its status at 5 August 2025 while its actual dates run to 14 October 2025, 48 working days later. Every forecast date, every float value and the negative float and CPLI results are read at the filed data date, so all of them move once the update is re-issued.

Read as filed. No network calculation was re-run. Dates and total float are taken as the source scheduler computed them, so a stale or overridden float value is reported as it stands rather than corrected.

Basis. Every duration, float and variance is in working days on each activity’s own P6 calendar; the movement of the finish is counted on the project calendar.

Scope of the file. The current schedule holds 379 activities and 584 relationships; the baseline holds 343, so the current schedule has 36 more.

What the checks cannot see. A DCMA-14 screen tests the structure and status of one file. It does not test whether the logic matches how the work is being built, whether durations are realistic, or why the finish moved. The critical path test here is a connectivity screen; the formal DCMA slip test is not performed. Resources were not scored: the file carries no resource assignments. These results have not been reviewed against the contract or the project records, and are not a delay analysis.

The basis of measurement and what has been validated are set out in full at A-01.1.

Analyst conclusion and next step

Analyst Conclusion and Next Step

Delay investigation warranted

The finish has moved materially and the movement deserves a proper look at the update chain before anyone takes a position. The Preliminary Assessment, scoped and priced in writing before any work starts, is the next step.

Technical condition: the assessment grades this schedule F · 31% · RED; the forecast finish has moved 37 working days later than the baseline.

The movement is material and this pair of files cannot yet explain it. The forecast completion has moved 37 working days later than the baseline, and the schedule itself grades F on the DCMA screen, so both the dates and the instrument that produced them need attention before anyone takes a position.

The update was also filed with a data date of 05-Aug-2025 while its actual dates run to 14-Oct-2025, so the finish it reports is too early: the forecast has to be rebuilt at the correct data date before the movement is measured. A baseline and one update are endpoints. The causation story lives in the monthly chain between them and in the project record, and on this file only a small share of the moved activities have evidence paired to them. Examining the chain is the correct next step, and it is a bounded piece of work.

The Findings That Matter

1The forecast completion moved 37 working days later than the baseline, to 24-Jun-2026, as the file reports it.
2The schedule grades F (31%) on the DCMA-14 screen, driven by high float on 34% of activities, 123 activities with negative float against the contract finish and 61 activities with actual dates after the data date: the instrument needs repair alongside the delay question.
3Only 4.9% of the positive slips are evidence-supported in the records provided (the companion evidence workbench), so causation is asserted, not yet shown.

Evidence Still Required

•The full monthly update chain (every XER between baseline and current, not just the endpoints)
•Contract milestone dates and any amendments to them
•Delay notices and the contractual notice log
•Change orders and change directives with dates
•Contemporaneous correspondence for the affected work fronts

The Next Step

The Preliminary Assessment, scoped and priced in writing before any work starts, would cover:

1.Reschedule the update at its correct data date, then ingest the full monthly update chain and rebuild the movement window by window on the project calendar.
2.Attribute each driving window to its cause using the schedule record and the documents listed above.
3.Screen the chain for baseline changes, logic revisions and calendar edits that move dates without progress.
4.Report whether a delay position is supportable, in which direction, and what a full analysis would cost if warranted.

Conclusion written by Dana Fitkowski, Principal, Critical Path Partners on 2 October 2026. Every figure it cites was checked against this report (the file as filed) and the companion evidence workbench sample (data date corrected to 15-Oct-2025), both rebuilt on engine v2.10.13, and restated where a rebuild moved it, on 22 October 2026. The engine produced the files; the analyst produced this conclusion.

A-01

Executive Summary

narrative · health score · findings
Key Findings

The Larchmere Library and Community Hub (Demo Data) schedule passes 4 of 13 scored DCMA criteria, earning an overall grade of F (31% compliance) with a RED status band. Criteria clearing their thresholds: C1, C5, C8, C14.

The failing criteria are C2 Leads, C3 Lags, C4 Relationship Types, C6 High Float, C7 Negative Float, C9 Valid Dates, C11 Missed Tasks, C12 Critical Path Test, C13 CPLI. Both forward-looking indices read CPLI 0.83 and BEI 0.97, and the schedule is trending toward +37 working-day overrun to 24-Jun-2026.

Passed
4
Failed
9
Compliance
31%
Finish Var.
+37 wd
Health Score
31%Grade F
RED
Trend watch · BEI 0.97, CPLI 0.83
finish drift +37 wd vs baseline
A-01b

Summary of findings

what failed, and the grade it produced
What failed, and by how much
  • Leads (2), 2 leads found (C2).
  • Lags (11.1%), 65 of 584 relationships (11.1%) | 0 exceed 44 days (C3).
  • Relationship Types (88% FS), Total: 584 | FS: 515 (88.2%), SS: 68 (11.6%), FF: 0 (0.0%), SF: 1 (0.2%) (C4).
  • High Float (33.7% (85)), 85 activities with high float (33.7%) (C6).
  • Negative Float (123), 123 activities with negative float (C7).
  • Valid Dates (61), 61 activities with invalid dates (16.1%; 0 forecast, 61 actual) | Status date: 05-Aug-2025 | Latest actual: 14-Oct-2025 (+48 wd) | Actual>DD: start 53, finish 54 (C9).
  • Missed Tasks (6), Missed: 6/58 (10.3%) | Missing baseline IDs from current: 2 (C11).
  • Critical Path Test (124 activities), Orphans 5.6% > 5%; Fragmented critical network (76.6% in main chain) (C12).
  • CPLI (0.83), CPLI: 0.834 | Contract: 01-May-2026 (A1050: Ready for Owner Takeover) | Forecast: 24-Jun-2026 (A1050: Ready for Owner Takeover) | Float: -37 wd (C13).
A-01.1

Basis of Measurement

how to read these figures & what has been validated
Basis of measurementHow to read the numbers in this report
Day unit
Working days
Every day count in this assessment is in working days. Where a criterion threshold is written in calendar days in DCMA-14, the computed figure is stated in working days alongside.
Calendar
The activity’s own P6 calendar
Durations and float are read as the source scheduler computed them, on each activity’s assigned calendar. This screen does not recompute the network.
Date fields read
P6 Start and Finish columns only
Float basis
Total float as computed by the source scheduler
Taken from the file as submitted. No forward or backward pass is re-run, so a stale or overridden float value is reported as it stands rather than corrected.
Excluded
Level-of-effort and WBS-summary activities
Excluded from the criteria where the check does not apply, per DCMA-14.
This is a screening assessment, and its validation boundary is narrower than the engine’s
The figures here are counts, percentages and float in days. No signed variance against a contract is reported, so there is no loss-direction convention to apply; where a forensic deliverable is needed, those skills state their own sign convention on their own page one.
What has been validated, in two separate layers: first, the CPP CPM engine’s JavaScript and Python implementations agree on all 22,189 field comparisons across 233 fixtures (none skipped); both are by the same author, so this layer catches port drift, not a shared misreading of P6. Second, 13 of 13 comparison cases scheduled in Primavera P6 Professional 23.12 now match the engine’s dates and float, a fitted result after a first capture of 6 of 13, not a blind one. History and limits of both are at criticalpathpartners.ca/validation.html. Both layers cover the ENGINE. Neither covers this DCMA-14 screen, which is computed in the browser from the file as submitted. These results have not been reviewed against the contract, the project records, or an AACE 29R-03 source validation, and they are not a delay analysis or an entitlement finding.
A-02

Key Performance Metrics

14-criteria roll-up
Criteria Passed
4
of 13 scored criteria
Criteria Failed
9
requires attention
Compliance Rate
31%
overall quality score
Overall Rating
F
assessment grade
A
≥90 Excellent
B
≥75 Good
C
≥60 Acceptable
D
≥45 Below Std
F
<45 Critical

The A to F grade and its bands are CPP’s convention for summarising the scored criteria. DCMA sets a pass or fail threshold for each criterion; it does not grade a schedule.

A-03

DCMA 14-Point Assessment

13 scored · 4 PASS / 9 FAIL · Grade F
Logic & FlowC1–C4 · 1 PASS / 3 FAIL
C1
Logic
Activities missing a predecessor or successor
Missing Logic · ≤5%
3.1% (8)
PASS
0 w/o predecessors (0.0%), 8 w/o successors (3.1%)
C2
Leads
Relationships with a negative lag (lead)
Leads · target 0
2
FAIL
2 leads found see register A-06
C3
Lags
Relationships carrying a positive lag
Rels w/ Lag · ≤5%
11.1%
FAIL
65 of 584 relationships (11.1%) | 0 exceed 44 days see register A-06
C4
Relationship Types
Share of links that are Finish-to-Start
FS Share · ≥90%
88% FS
FAIL
Total: 584 | FS: 515 (88.2%), SS: 68 (11.6%), FF: 0 (0.0%), SF: 1 (0.2%)
Constraints & FloatC5–C7 · 1 PASS / 2 FAIL
C5
Hard Constraints
Mandatory / fixed-date constraints in the network
Hard Constraints · ≤5%
1
PASS
1 hard constraints (0.4%)
C6
High Float
Incomplete activities with total float > 44 wd
High Float · ≤5%
33.7% (85)
FAIL
85 activities with high float (33.7%) see register A-06
C7
Negative Float
Activities with total float below zero
Negative Float · target 0
123
FAIL
123 activities with negative float see register A-06
Resources & ProgressC9–C11 · 2 FAIL / 1 N/A
C9
Valid Dates
Forecast dates before, or actual dates after, the data date
Invalid Dates · target 0
61
FAIL
61 activities with invalid dates (16.1%; 0 forecast, 61 actual) | Status date: 05-Aug-2025 | Latest actual: 14-Oct-2025 (+48 wd) | Actual>DD: start 53, finish 54 see register A-06

The update was statused to 14-Oct-2025 (A2910 actual finish) but its data date was left at 05-Aug-2025. 102 activities that hadn't started were forecast to start before 15-Oct-2025: each is either late or missing its status. The CPP analysis tools move the data date to 15-Oct-2025 for their analysis.

C10
Resources
Activities with a resource or cost loaded
Resourced · 100%
N/A
N/A
Not scored - TASKRSRC section not found in XER export. (252 eligible activities ≥1d)
C11
Missed Tasks
Activities that slipped past baseline finish
Missed Tasks · ≤5%
6
FAIL
Missed: 6/58 (10.3%) | Missing baseline IDs from current: 2 see register A-06
PerformanceC8, C12–C14 · 2 PASS / 2 FAIL
C8
High Duration
Incomplete activities with duration > 44 wd
High Duration · ≤5%
0.8% (2)
PASS
2 activities with high duration (0.8%)
C12
Critical Path Test
Screening only: connected, unbroken critical chain. A clean screen is not scored; the formal DCMA slip test is not performed
Critical Path
124 activities
FAIL
Orphans 5.6% > 5%; Fragmented critical network (76.6% in main chain) see register A-06
C13
CPLI
Critical Path Length Index, pace to finish
CPLI · ≥0.95
0.83
FAIL
CPLI: 0.834 | Contract: 01-May-2026 (A1050: Ready for Owner Takeover) | Forecast: 24-Jun-2026 (A1050: Ready for Owner Takeover) | Float: -37 wd
C14
BEI
Baseline Execution Index, tasks earned vs planned
BEI · ≥0.95
0.97
PASS
BEI: 0.967 (58 complete / 60 planned complete) | 2 planned-complete baseline IDs missing from current
Pass and fail thresholds per the DCMA 14-Point Assessment. The A to F grade is CPP’s convention, not DCMA’s4 PASS  /  9 FAIL  →  Grade F · 31% · RED
A-04

DCMA-14 Status by Criterion

14 criteria · PASS / FAIL
Per-criterion compliance, full result vs threshold toleranceC1 → C14
C1 · LogicC2 · LeadsC3 · LagsC4 · Relationship TypesC5 · Hard ConstraintsC6 · High FloatC7 · Negative FloatC8 · High DurationC9 · Valid DatesC10 · ResourcesC11 · Missed TasksC12 · Critical Path TestC13 · CPLIC14 · BEIPASS · 3.1% (8)FAIL · 2FAIL · 11.1%FAIL · 88% FSPASS · 1FAIL · 33.7% (85)FAIL · 123PASS · 0.8% (2)FAIL · 61N/AFAIL · 6FAIL · 124 activitiesFAIL · 0.83PASS · 0.97
PASS · within tolerance FAIL · exceeds threshold4 PASS  /  9 FAIL
A-05

Baseline vs Current Comparison

task · schedule · variance
Task Metrics
Baseline Tasks343
Current Tasks379
Tasks Added+36
Scope Growth10.5%
Schedule Metrics
Baseline Start05-May-2025
Current Start05-May-2025
Baseline Finish01-May-2026
Current Finish24-Jun-2026
Variance Analysis
Start Delay0 wd
Finish Variance+37 wd
Duration Variance+37 wd
Scope Growth+10.5%
A-06

Failure Analysis & Registers

9 failing criteria · severity profile · full activity registers
C2Leads Register, all flagged activities
2 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A2380Curtain wall and windows, West elevationENV Building Envelope02-Dec-2025Lead (wd): 2Has 2 wd lead from "Exterior sheathing and air/vapour barrier, West elevation"
A4100Tape, mud and sand Level 3 Zone DInteriors / L3 Interiors - Level 308-Jan-2026Lead (wd): 1Has 1 wd lead from "Drywall board Level 3 Zone D"
WBS shown relative to the common root: Larchmere Library and Community Hub (Demo Data). Full paths are in the tooltip and the CSV export.
C3Lags Register, all flagged activities
65 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A1600Bulk excavationSite Works04-Jul-2025Lag (wd): 3Positive lag of 3 wd from "Shoring along the north property line" (lag usage exceeds 5%)
A1610Storm sewer and catch basinsSite Works09-Jul-2025Lag (wd): 5Positive lag of 5 wd from "Bulk excavation" (lag usage exceeds 5%)
A1620Sanitary service to property lineSite Works07-Jul-2025Lag (wd): 5Positive lag of 5 wd from "Bulk excavation" (lag usage exceeds 5%)
A1630Water service and fire lineSite Works07-Jul-2025Lag (wd): 5Positive lag of 5 wd from "Bulk excavation" (lag usage exceeds 5%)
A4670Masonry veneer, North elevationENV Building Envelope17-Sep-2025Lag (wd): 5Positive lag of 5 wd from "Exterior sheathing and air/vapour barrier, North elevation" (lag usage exceeds 5%)
A4690Masonry veneer, East elevationENV Building Envelope29-Sep-2025Lag (wd): 5Positive lag of 5 wd from "Exterior sheathing and air/vapour barrier, East elevation" (lag usage exceeds 5%)
A4710Masonry veneer, South elevationENV Building Envelope09-Oct-2025Lag (wd): 5Positive lag of 5 wd from "Exterior sheathing and air/vapour barrier, South elevation" (lag usage exceeds 5%)
A4730Masonry veneer, West elevationENV Building Envelope22-Oct-2025Lag (wd): 5Positive lag of 5 wd from "Exterior sheathing and air/vapour barrier, West elevation" (lag usage exceeds 5%)
A2430Rooftop unit curbsRoofing26-Sep-2025Lag (wd): 4Positive lag of 4 wd from "Roof insulation and membrane" (lag usage exceeds 5%)
A2450Roof drains and leadersRoofing25-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Roof insulation and membrane" (lag usage exceeds 5%)
A2610Mechanical in-wall rough-in Level 1 Zone AInteriors / L1 Interiors - Level 113-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone A" (lag usage exceeds 5%)
A2620Plumbing in-wall rough-in Level 1 Zone AInteriors / L1 Interiors - Level 125-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone A" (lag usage exceeds 5%)
A2630Electrical in-wall rough-in Level 1 Zone AInteriors / L1 Interiors - Level 126-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone A" (lag usage exceeds 5%)
A2640Sprinkler branch piping Level 1 Zone AInteriors / L1 Interiors - Level 125-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone A" (lag usage exceeds 5%)
A2740Mechanical in-wall rough-in Level 1 Zone BInteriors / L1 Interiors - Level 110-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone B" (lag usage exceeds 5%)
A2750Plumbing in-wall rough-in Level 1 Zone BInteriors / L1 Interiors - Level 109-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone B" (lag usage exceeds 5%)
A2760Electrical in-wall rough-in Level 1 Zone BInteriors / L1 Interiors - Level 110-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone B" (lag usage exceeds 5%)
A2770Sprinkler branch piping Level 1 Zone BInteriors / L1 Interiors - Level 109-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone B" (lag usage exceeds 5%)
A2870Mechanical in-wall rough-in Level 1 Zone CInteriors / L1 Interiors - Level 110-Oct-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone C" (lag usage exceeds 5%)
A2880Plumbing in-wall rough-in Level 1 Zone CInteriors / L1 Interiors - Level 109-Oct-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone C" (lag usage exceeds 5%)
A2890Electrical in-wall rough-in Level 1 Zone CInteriors / L1 Interiors - Level 110-Oct-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone C" (lag usage exceeds 5%)
A2900Sprinkler branch piping Level 1 Zone CInteriors / L1 Interiors - Level 109-Oct-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone C" (lag usage exceeds 5%)
A3000Mechanical in-wall rough-in Level 1 Zone DInteriors / L1 Interiors - Level 114-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone D" (lag usage exceeds 5%)
A3010Plumbing in-wall rough-in Level 1 Zone DInteriors / L1 Interiors - Level 113-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone D" (lag usage exceeds 5%)
A3020Electrical in-wall rough-in Level 1 Zone DInteriors / L1 Interiors - Level 114-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone D" (lag usage exceeds 5%)
A3030Sprinkler branch piping Level 1 Zone DInteriors / L1 Interiors - Level 113-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 1 Zone D" (lag usage exceeds 5%)
A3130Mechanical in-wall rough-in Level 2 Zone AInteriors / L2 Interiors - Level 213-Feb-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone A" (lag usage exceeds 5%)
A3140Plumbing in-wall rough-in Level 2 Zone AInteriors / L2 Interiors - Level 212-Feb-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone A" (lag usage exceeds 5%)
A3150Electrical in-wall rough-in Level 2 Zone AInteriors / L2 Interiors - Level 213-Feb-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone A" (lag usage exceeds 5%)
A3160Sprinkler branch piping Level 2 Zone AInteriors / L2 Interiors - Level 212-Feb-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone A" (lag usage exceeds 5%)
A3260Mechanical in-wall rough-in Level 2 Zone BInteriors / L2 Interiors - Level 224-Feb-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone B" (lag usage exceeds 5%)
A3270Plumbing in-wall rough-in Level 2 Zone BInteriors / L2 Interiors - Level 223-Feb-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone B" (lag usage exceeds 5%)
A3280Electrical in-wall rough-in Level 2 Zone BInteriors / L2 Interiors - Level 224-Feb-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone B" (lag usage exceeds 5%)
A3290Sprinkler branch piping Level 2 Zone BInteriors / L2 Interiors - Level 223-Feb-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone B" (lag usage exceeds 5%)
A3390Mechanical in-wall rough-in Level 2 Zone CInteriors / L2 Interiors - Level 204-Mar-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone C" (lag usage exceeds 5%)
A3400Plumbing in-wall rough-in Level 2 Zone CInteriors / L2 Interiors - Level 203-Mar-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone C" (lag usage exceeds 5%)
A3410Electrical in-wall rough-in Level 2 Zone CInteriors / L2 Interiors - Level 204-Mar-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone C" (lag usage exceeds 5%)
A3420Sprinkler branch piping Level 2 Zone CInteriors / L2 Interiors - Level 203-Mar-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone C" (lag usage exceeds 5%)
A3520Mechanical in-wall rough-in Level 2 Zone DInteriors / L2 Interiors - Level 212-Mar-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone D" (lag usage exceeds 5%)
A3530Plumbing in-wall rough-in Level 2 Zone DInteriors / L2 Interiors - Level 211-Mar-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone D" (lag usage exceeds 5%)
A3540Electrical in-wall rough-in Level 2 Zone DInteriors / L2 Interiors - Level 212-Mar-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone D" (lag usage exceeds 5%)
A3550Sprinkler branch piping Level 2 Zone DInteriors / L2 Interiors - Level 211-Mar-2026Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 2 Zone D" (lag usage exceeds 5%)
A3650Mechanical in-wall rough-in Level 3 Zone AInteriors / L3 Interiors - Level 318-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone A" (lag usage exceeds 5%)
A3660Plumbing in-wall rough-in Level 3 Zone AInteriors / L3 Interiors - Level 308-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone A" (lag usage exceeds 5%)
A3670Electrical in-wall rough-in Level 3 Zone AInteriors / L3 Interiors - Level 309-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone A" (lag usage exceeds 5%)
A3680Sprinkler branch piping Level 3 Zone AInteriors / L3 Interiors - Level 308-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone A" (lag usage exceeds 5%)
A3780Mechanical in-wall rough-in Level 3 Zone BInteriors / L3 Interiors - Level 317-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone B" (lag usage exceeds 5%)
A3790Plumbing in-wall rough-in Level 3 Zone BInteriors / L3 Interiors - Level 316-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone B" (lag usage exceeds 5%)
A3800Electrical in-wall rough-in Level 3 Zone BInteriors / L3 Interiors - Level 317-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone B" (lag usage exceeds 5%)
A3810Sprinkler branch piping Level 3 Zone BInteriors / L3 Interiors - Level 316-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone B" (lag usage exceeds 5%)
A3910Mechanical in-wall rough-in Level 3 Zone CInteriors / L3 Interiors - Level 325-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone C" (lag usage exceeds 5%)
A3920Plumbing in-wall rough-in Level 3 Zone CInteriors / L3 Interiors - Level 324-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone C" (lag usage exceeds 5%)
A3930Electrical in-wall rough-in Level 3 Zone CInteriors / L3 Interiors - Level 325-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone C" (lag usage exceeds 5%)
A3940Sprinkler branch piping Level 3 Zone CInteriors / L3 Interiors - Level 324-Sep-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone C" (lag usage exceeds 5%)
A4040Mechanical in-wall rough-in Level 3 Zone DInteriors / L3 Interiors - Level 303-Oct-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone D" (lag usage exceeds 5%)
A4050Plumbing in-wall rough-in Level 3 Zone DInteriors / L3 Interiors - Level 302-Oct-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone D" (lag usage exceeds 5%)
A4060Electrical in-wall rough-in Level 3 Zone DInteriors / L3 Interiors - Level 303-Oct-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone D" (lag usage exceeds 5%)
A4070Sprinkler branch piping Level 3 Zone DInteriors / L3 Interiors - Level 302-Oct-2025Lag (wd): 2Positive lag of 2 wd from "Layout and partition framing Level 3 Zone D" (lag usage exceeds 5%)
A4180Site lighting bases and polesExterior Works15-Aug-2025Lag (wd): 2Positive lag of 2 wd from "Granular base for parking and drive" (lag usage exceeds 5%)
A2230Steel stairs and railingsStructure07-Oct-2025Lag (wd): 7Positive lag of 7 wd from "Concrete topping Level 2 Zone D" (lag usage exceeds 5%)
A2230Steel stairs and railingsStructure07-Oct-2025Lag (wd): 7Positive lag of 7 wd from "Concrete topping Level 3 Zone D" (lag usage exceeds 5%)
A4680Metal panel cladding, North elevationENV Building Envelope18-Sep-2025Lag (wd): 3Positive lag of 3 wd from "Masonry veneer, North elevation" (lag usage exceeds 5%)
A4700Metal panel cladding, East elevationENV Building Envelope30-Sep-2025Lag (wd): 3Positive lag of 3 wd from "Masonry veneer, East elevation" (lag usage exceeds 5%)
A4720Metal panel cladding, South elevationENV Building Envelope10-Oct-2025Lag (wd): 3Positive lag of 3 wd from "Masonry veneer, South elevation" (lag usage exceeds 5%)
A4740Metal panel cladding, West elevationENV Building Envelope23-Oct-2025Lag (wd): 3Positive lag of 3 wd from "Masonry veneer, West elevation" (lag usage exceeds 5%)
WBS shown relative to the common root: Larchmere Library and Community Hub (Demo Data). Full paths are in the tooltip and the CSV export.
C6High-Float Register, incomplete activities with total float > 44 wd
85 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishTotal Float (wd)Issue
A1650Backfill and compact at foundationsSite Works05-Aug-2025104Total float of 104 wd exceeds 44 wd
A1890Slab on grade Zone DFDN Foundations05-Aug-202556Total float of 56 wd exceeds 44 wd
A1940Metal deck Level 2 Zone BStructure05-Aug-202599Total float of 99 wd exceeds 44 wd
A1950Concrete topping Level 2 Zone BStructure08-Aug-202599Total float of 99 wd exceeds 44 wd
A1970Metal deck Level 2 Zone CStructure11-Aug-2025101Total float of 101 wd exceeds 44 wd
A1980Concrete topping Level 2 Zone CStructure14-Aug-2025101Total float of 101 wd exceeds 44 wd
A2000Metal deck Level 2 Zone DStructure15-Aug-2025103Total float of 103 wd exceeds 44 wd
A2010Concrete topping Level 2 Zone DStructure20-Aug-2025103Total float of 103 wd exceeds 44 wd
A2030Metal deck Level 3 Zone AStructure25-Aug-202573Total float of 73 wd exceeds 44 wd
A2040Concrete topping Level 3 Zone AStructure28-Aug-202573Total float of 73 wd exceeds 44 wd
A2060Metal deck Level 3 Zone BStructure29-Aug-202589Total float of 89 wd exceeds 44 wd
A2070Concrete topping Level 3 Zone BStructure04-Sep-202589Total float of 89 wd exceeds 44 wd
A2090Metal deck Level 3 Zone CStructure05-Sep-202591Total float of 91 wd exceeds 44 wd
A2100Concrete topping Level 3 Zone CStructure10-Sep-202591Total float of 91 wd exceeds 44 wd
A2120Metal deck Level 3 Zone DStructure11-Sep-202593Total float of 93 wd exceeds 44 wd
A2130Concrete topping Level 3 Zone DStructure16-Sep-202593Total float of 93 wd exceeds 44 wd
A2230Steel stairs and railingsStructure07-Oct-2025142Total float of 142 wd exceeds 44 wd
A2240Elevator shaft masonryStructure05-Aug-2025141Total float of 141 wd exceeds 44 wd
A2280Sealants and flashings, North elevationENV Building Envelope24-Sep-2025151Total float of 151 wd exceeds 44 wd
A2320Sealants and flashings, East elevationENV Building Envelope06-Oct-2025143Total float of 143 wd exceeds 44 wd
A2360Sealants and flashings, South elevationENV Building Envelope17-Oct-2025135Total float of 135 wd exceeds 44 wd
A2400Sealants and flashings, West elevationENV Building Envelope29-Oct-2025127Total float of 127 wd exceeds 44 wd
A2430Rooftop unit curbsRoofing26-Sep-202586Total float of 86 wd exceeds 44 wd
A2440Set rooftop air handling unitsRoofing01-Oct-202586Total float of 86 wd exceeds 44 wd
A2450Roof drains and leadersRoofing25-Sep-2025150Total float of 150 wd exceeds 44 wd
A2490Ductwork mains Level 2MEP Mechanical and Electrical Services10-Sep-202573Total float of 73 wd exceeds 44 wd
A2500Ductwork mains Level 3MEP Mechanical and Electrical Services11-Sep-202580Total float of 80 wd exceeds 44 wd
A2520Sprinkler mains and risersMEP Mechanical and Electrical Services05-Aug-2025158Total float of 158 wd exceeds 44 wd
A2580Elevator rails, machine and car installElevator03-Sep-2025141Total float of 141 wd exceeds 44 wd
A2590Elevator inspection and licence (TSSA)Elevator05-Sep-2025141Total float of 141 wd exceeds 44 wd
A2990Layout and partition framing Level 1 Zone DInteriors / L1 Interiors - Level 113-Aug-202556Total float of 56 wd exceeds 44 wd
A3000Mechanical in-wall rough-in Level 1 Zone DInteriors / L1 Interiors - Level 114-Aug-202556Total float of 56 wd exceeds 44 wd
A3010Plumbing in-wall rough-in Level 1 Zone DInteriors / L1 Interiors - Level 113-Aug-202557Total float of 57 wd exceeds 44 wd
A3020Electrical in-wall rough-in Level 1 Zone DInteriors / L1 Interiors - Level 114-Aug-202556Total float of 56 wd exceeds 44 wd
A3030Sprinkler branch piping Level 1 Zone DInteriors / L1 Interiors - Level 113-Aug-202557Total float of 57 wd exceeds 44 wd
A3040In-wall services inspection Level 1 Zone DInteriors / L1 Interiors - Level 115-Aug-202556Total float of 56 wd exceeds 44 wd
A3640Layout and partition framing Level 3 Zone AInteriors / L3 Interiors - Level 308-Sep-202587Total float of 87 wd exceeds 44 wd
A3650Mechanical in-wall rough-in Level 3 Zone AInteriors / L3 Interiors - Level 318-Sep-202580Total float of 80 wd exceeds 44 wd
A3660Plumbing in-wall rough-in Level 3 Zone AInteriors / L3 Interiors - Level 308-Sep-202588Total float of 88 wd exceeds 44 wd
A3670Electrical in-wall rough-in Level 3 Zone AInteriors / L3 Interiors - Level 309-Sep-202587Total float of 87 wd exceeds 44 wd
A3680Sprinkler branch piping Level 3 Zone AInteriors / L3 Interiors - Level 308-Sep-202588Total float of 88 wd exceeds 44 wd
A3690In-wall services inspection Level 3 Zone AInteriors / L3 Interiors - Level 319-Sep-202580Total float of 80 wd exceeds 44 wd
A3770Layout and partition framing Level 3 Zone BInteriors / L3 Interiors - Level 316-Sep-202587Total float of 87 wd exceeds 44 wd
A3780Mechanical in-wall rough-in Level 3 Zone BInteriors / L3 Interiors - Level 317-Sep-202587Total float of 87 wd exceeds 44 wd
A3790Plumbing in-wall rough-in Level 3 Zone BInteriors / L3 Interiors - Level 316-Sep-202588Total float of 88 wd exceeds 44 wd
A3800Electrical in-wall rough-in Level 3 Zone BInteriors / L3 Interiors - Level 317-Sep-202587Total float of 87 wd exceeds 44 wd
A3810Sprinkler branch piping Level 3 Zone BInteriors / L3 Interiors - Level 316-Sep-202588Total float of 88 wd exceeds 44 wd
A3820In-wall services inspection Level 3 Zone BInteriors / L3 Interiors - Level 318-Sep-202587Total float of 87 wd exceeds 44 wd
A3900Layout and partition framing Level 3 Zone CInteriors / L3 Interiors - Level 324-Sep-202587Total float of 87 wd exceeds 44 wd
A3910Mechanical in-wall rough-in Level 3 Zone CInteriors / L3 Interiors - Level 325-Sep-202587Total float of 87 wd exceeds 44 wd
A3920Plumbing in-wall rough-in Level 3 Zone CInteriors / L3 Interiors - Level 324-Sep-202588Total float of 88 wd exceeds 44 wd
A3930Electrical in-wall rough-in Level 3 Zone CInteriors / L3 Interiors - Level 325-Sep-202587Total float of 87 wd exceeds 44 wd
A3940Sprinkler branch piping Level 3 Zone CInteriors / L3 Interiors - Level 324-Sep-202588Total float of 88 wd exceeds 44 wd
A3950In-wall services inspection Level 3 Zone CInteriors / L3 Interiors - Level 326-Sep-202587Total float of 87 wd exceeds 44 wd
A4030Layout and partition framing Level 3 Zone DInteriors / L3 Interiors - Level 302-Oct-202587Total float of 87 wd exceeds 44 wd
A4040Mechanical in-wall rough-in Level 3 Zone DInteriors / L3 Interiors - Level 303-Oct-202587Total float of 87 wd exceeds 44 wd
A4050Plumbing in-wall rough-in Level 3 Zone DInteriors / L3 Interiors - Level 302-Oct-202588Total float of 88 wd exceeds 44 wd
A4060Electrical in-wall rough-in Level 3 Zone DInteriors / L3 Interiors - Level 303-Oct-202587Total float of 87 wd exceeds 44 wd
A4070Sprinkler branch piping Level 3 Zone DInteriors / L3 Interiors - Level 302-Oct-202588Total float of 88 wd exceeds 44 wd
A4080In-wall services inspection Level 3 Zone DInteriors / L3 Interiors - Level 306-Oct-202587Total float of 87 wd exceeds 44 wd
A4160Granular base for parking and driveExterior Works13-Aug-2025104Total float of 104 wd exceeds 44 wd
A4170Concrete curbs and sidewalksExterior Works25-Aug-2025104Total float of 104 wd exceeds 44 wd
A4180Site lighting bases and polesExterior Works15-Aug-2025157Total float of 157 wd exceeds 44 wd
A4190Asphalt pavingExterior Works29-Aug-2025151Total float of 151 wd exceeds 44 wd
A4200Landscaping and sodExterior Works05-Sep-2025104Total float of 104 wd exceeds 44 wd
A4210Line painting and signageExterior Works03-Sep-2025151Total float of 151 wd exceeds 44 wd
A4220Exterior stairs and barrier-free rampExterior Works21-Oct-2025118Total float of 118 wd exceeds 44 wd
A4230Entrance canopy steel and soffitExterior Works20-Oct-2025134Total float of 134 wd exceeds 44 wd
A4260Sprinkler flush and hydrostatic testCommissioning and Closeout07-Oct-2025117Total float of 117 wd exceeds 44 wd
A4270Test, adjust and balanceCommissioning and Closeout30-Oct-202595Total float of 95 wd exceeds 44 wd
A4280Building automation functional testingCommissioning and Closeout11-Nov-202595Total float of 95 wd exceeds 44 wd
A4290Mechanical commissioningCommissioning and Closeout16-Oct-202586Total float of 86 wd exceeds 44 wd
A4360Owner trainingCommissioning and Closeout18-Nov-2025113Total float of 113 wd exceeds 44 wd
A4390Landscape establishment and warranty maintenanceExterior Works01-Dec-2025104Total float of 104 wd exceeds 44 wd
A4400Seasonal commissioning of heating and coolingCommissioning and Closeout29-Dec-202586Total float of 86 wd exceeds 44 wd
A4670Masonry veneer, North elevationENV Building Envelope17-Sep-2025151Total float of 151 wd exceeds 44 wd
A4680Metal panel cladding, North elevationENV Building Envelope18-Sep-2025151Total float of 151 wd exceeds 44 wd
A4690Masonry veneer, East elevationENV Building Envelope29-Sep-2025143Total float of 143 wd exceeds 44 wd
A4700Metal panel cladding, East elevationENV Building Envelope30-Sep-2025143Total float of 143 wd exceeds 44 wd
A4710Masonry veneer, South elevationENV Building Envelope09-Oct-2025118Total float of 118 wd exceeds 44 wd
A4720Metal panel cladding, South elevationENV Building Envelope10-Oct-2025118Total float of 118 wd exceeds 44 wd
A4730Masonry veneer, West elevationENV Building Envelope22-Oct-2025127Total float of 127 wd exceeds 44 wd
A4740Metal panel cladding, West elevationENV Building Envelope23-Oct-2025127Total float of 127 wd exceeds 44 wd
A4820ESA rough-in inspection Level 1MEP Mechanical and Electrical Services15-Aug-202556Total float of 56 wd exceeds 44 wd
A4840ESA rough-in inspection Level 3MEP Mechanical and Electrical Services06-Oct-202587Total float of 87 wd exceeds 44 wd
WBS shown relative to the common root: Larchmere Library and Community Hub (Demo Data). Full paths are in the tooltip and the CSV export.
C7Negative-Float Register, all activities with total float < 0
123 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishTotal Float (wd)Issue
A1960Erect structural steel Level 2 Zone CStructure06-Aug-2025-37Total float -37 wd
A1990Erect structural steel Level 2 Zone DStructure12-Aug-2025-37Total float -37 wd
A2020Erect structural steel Level 3 Zone AStructure20-Aug-2025-37Total float -37 wd
A2050Erect structural steel Level 3 Zone BStructure26-Aug-2025-26Total float -26 wd
A2080Erect structural steel Level 3 Zone CStructure02-Sep-2025-15Total float -15 wd
A2110Erect structural steel Level 3 Zone DStructure08-Sep-2025-9Total float -9 wd
A2140Erect structural steel Roof Zone AStructure26-Aug-2025-37Total float -37 wd
A2160Erect structural steel Roof Zone BStructure02-Sep-2025-26Total float -26 wd
A2180Erect structural steel Roof Zone CStructure08-Sep-2025-15Total float -15 wd
A2190Metal deck Roof Zone CStructure11-Sep-2025-1Total float -1 wd
A2200Erect structural steel Roof Zone DStructure12-Sep-2025-9Total float -9 wd
A2210Metal deck Roof Zone DStructure17-Sep-2025-2Total float -2 wd
A2250Exterior sheathing and air/vapour barrier, North elevationENV Building Envelope08-Sep-2025-37Total float -37 wd
A2260Curtain wall and windows, North elevationENV Building Envelope29-Sep-2025-37Total float -37 wd
A2290Exterior sheathing and air/vapour barrier, East elevationENV Building Envelope18-Sep-2025-30Total float -30 wd
A2300Curtain wall and windows, East elevationENV Building Envelope21-Oct-2025-37Total float -37 wd
A2330Exterior sheathing and air/vapour barrier, South elevationENV Building Envelope30-Sep-2025-23Total float -23 wd
A2340Curtain wall and windows, South elevationENV Building Envelope11-Nov-2025-37Total float -37 wd
A2370Exterior sheathing and air/vapour barrier, West elevationENV Building Envelope10-Oct-2025-21Total float -21 wd
A2380Curtain wall and windows, West elevationENV Building Envelope02-Dec-2025-37Total float -37 wd
A2410Roof insulation and membraneRoofing03-Oct-2025-2Total float -2 wd
A2420Roof flashings and penetrationsRoofing14-Oct-2025-2Total float -2 wd
A2660Drywall board Level 1 Zone AInteriors / L1 Interiors - Level 109-Dec-2025-37Total float -37 wd
A2670Tape, mud and sand Level 1 Zone AInteriors / L1 Interiors - Level 115-Dec-2025-37Total float -37 wd
A2680Prime paint Level 1 Zone AInteriors / L1 Interiors - Level 117-Dec-2025-37Total float -37 wd
A2700Flooring Level 1 Zone AInteriors / L1 Interiors - Level 105-Jan-2026-28Total float -28 wd
A2710Doors, hardware and millwork Level 1 Zone AInteriors / L1 Interiors - Level 109-Jan-2026-28Total float -28 wd
A2720Final paint and finishes Level 1 Zone AInteriors / L1 Interiors - Level 114-Jan-2026-28Total float -28 wd
A2790Drywall board Level 1 Zone BInteriors / L1 Interiors - Level 116-Dec-2025-36Total float -36 wd
A2800Tape, mud and sand Level 1 Zone BInteriors / L1 Interiors - Level 122-Dec-2025-36Total float -36 wd
A2810Prime paint Level 1 Zone BInteriors / L1 Interiors - Level 124-Dec-2025-36Total float -36 wd
A2830Flooring Level 1 Zone BInteriors / L1 Interiors - Level 113-Jan-2026-31Total float -31 wd
A2840Doors, hardware and millwork Level 1 Zone BInteriors / L1 Interiors - Level 119-Jan-2026-31Total float -31 wd
A2850Final paint and finishes Level 1 Zone BInteriors / L1 Interiors - Level 122-Jan-2026-31Total float -31 wd
A2920Drywall board Level 1 Zone CInteriors / L1 Interiors - Level 123-Dec-2025-35Total float -35 wd
A2930Tape, mud and sand Level 1 Zone CInteriors / L1 Interiors - Level 131-Dec-2025-35Total float -35 wd
A2940Prime paint Level 1 Zone CInteriors / L1 Interiors - Level 105-Jan-2026-35Total float -35 wd
A2960Flooring Level 1 Zone CInteriors / L1 Interiors - Level 121-Jan-2026-34Total float -34 wd
A2970Doors, hardware and millwork Level 1 Zone CInteriors / L1 Interiors - Level 127-Jan-2026-34Total float -34 wd
A2980Final paint and finishes Level 1 Zone CInteriors / L1 Interiors - Level 130-Jan-2026-34Total float -34 wd
A3050Drywall board Level 1 Zone DInteriors / L1 Interiors - Level 102-Jan-2026-34Total float -34 wd
A3060Tape, mud and sand Level 1 Zone DInteriors / L1 Interiors - Level 108-Jan-2026-34Total float -34 wd
A3070Prime paint Level 1 Zone DInteriors / L1 Interiors - Level 112-Jan-2026-34Total float -34 wd
A3090Flooring Level 1 Zone DInteriors / L1 Interiors - Level 129-Jan-2026-37Total float -37 wd
A3100Doors, hardware and millwork Level 1 Zone DInteriors / L1 Interiors - Level 104-Feb-2026-37Total float -37 wd
A3110Final paint and finishes Level 1 Zone DInteriors / L1 Interiors - Level 109-Feb-2026-37Total float -37 wd
A3120Layout and partition framing Level 2 Zone AInteriors / L2 Interiors - Level 212-Feb-2026-37Total float -37 wd
A3130Mechanical in-wall rough-in Level 2 Zone AInteriors / L2 Interiors - Level 213-Feb-2026-30Total float -30 wd
A3140Plumbing in-wall rough-in Level 2 Zone AInteriors / L2 Interiors - Level 212-Feb-2026-29Total float -29 wd
A3150Electrical in-wall rough-in Level 2 Zone AInteriors / L2 Interiors - Level 213-Feb-2026-37Total float -37 wd
A3160Sprinkler branch piping Level 2 Zone AInteriors / L2 Interiors - Level 212-Feb-2026-29Total float -29 wd
A3170In-wall services inspection Level 2 Zone AInteriors / L2 Interiors - Level 217-Feb-2026-30Total float -30 wd
A3180Drywall board Level 2 Zone AInteriors / L2 Interiors - Level 205-Mar-2026-37Total float -37 wd
A3190Tape, mud and sand Level 2 Zone AInteriors / L2 Interiors - Level 211-Mar-2026-37Total float -37 wd
A3200Prime paint Level 2 Zone AInteriors / L2 Interiors - Level 213-Mar-2026-37Total float -37 wd
A3220Flooring Level 2 Zone AInteriors / L2 Interiors - Level 227-Mar-2026-22Total float -22 wd
A3230Doors, hardware and millwork Level 2 Zone AInteriors / L2 Interiors - Level 202-Apr-2026-22Total float -22 wd
A3240Final paint and finishes Level 2 Zone AInteriors / L2 Interiors - Level 208-Apr-2026-22Total float -22 wd
A3250Layout and partition framing Level 2 Zone BInteriors / L2 Interiors - Level 223-Feb-2026-30Total float -30 wd
A3260Mechanical in-wall rough-in Level 2 Zone BInteriors / L2 Interiors - Level 224-Feb-2026-30Total float -30 wd
A3270Plumbing in-wall rough-in Level 2 Zone BInteriors / L2 Interiors - Level 223-Feb-2026-29Total float -29 wd
A3280Electrical in-wall rough-in Level 2 Zone BInteriors / L2 Interiors - Level 224-Feb-2026-30Total float -30 wd
A3290Sprinkler branch piping Level 2 Zone BInteriors / L2 Interiors - Level 223-Feb-2026-29Total float -29 wd
A3300In-wall services inspection Level 2 Zone BInteriors / L2 Interiors - Level 225-Feb-2026-30Total float -30 wd
A3310Drywall board Level 2 Zone BInteriors / L2 Interiors - Level 212-Mar-2026-36Total float -36 wd
A3320Tape, mud and sand Level 2 Zone BInteriors / L2 Interiors - Level 218-Mar-2026-36Total float -36 wd
A3330Prime paint Level 2 Zone BInteriors / L2 Interiors - Level 220-Mar-2026-36Total float -36 wd
A3350Flooring Level 2 Zone BInteriors / L2 Interiors - Level 207-Apr-2026-25Total float -25 wd
A3360Doors, hardware and millwork Level 2 Zone BInteriors / L2 Interiors - Level 213-Apr-2026-25Total float -25 wd
A3370Final paint and finishes Level 2 Zone BInteriors / L2 Interiors - Level 216-Apr-2026-25Total float -25 wd
A3380Layout and partition framing Level 2 Zone CInteriors / L2 Interiors - Level 203-Mar-2026-30Total float -30 wd
A3390Mechanical in-wall rough-in Level 2 Zone CInteriors / L2 Interiors - Level 204-Mar-2026-30Total float -30 wd
A3400Plumbing in-wall rough-in Level 2 Zone CInteriors / L2 Interiors - Level 203-Mar-2026-29Total float -29 wd
A3410Electrical in-wall rough-in Level 2 Zone CInteriors / L2 Interiors - Level 204-Mar-2026-30Total float -30 wd
A3420Sprinkler branch piping Level 2 Zone CInteriors / L2 Interiors - Level 203-Mar-2026-29Total float -29 wd
A3430In-wall services inspection Level 2 Zone CInteriors / L2 Interiors - Level 205-Mar-2026-30Total float -30 wd
A3440Drywall board Level 2 Zone CInteriors / L2 Interiors - Level 219-Mar-2026-35Total float -35 wd
A3450Tape, mud and sand Level 2 Zone CInteriors / L2 Interiors - Level 225-Mar-2026-35Total float -35 wd
A3460Prime paint Level 2 Zone CInteriors / L2 Interiors - Level 227-Mar-2026-35Total float -35 wd
A3480Flooring Level 2 Zone CInteriors / L2 Interiors - Level 215-Apr-2026-28Total float -28 wd
A3490Doors, hardware and millwork Level 2 Zone CInteriors / L2 Interiors - Level 221-Apr-2026-28Total float -28 wd
A3500Final paint and finishes Level 2 Zone CInteriors / L2 Interiors - Level 224-Apr-2026-28Total float -28 wd
A3510Layout and partition framing Level 2 Zone DInteriors / L2 Interiors - Level 211-Mar-2026-30Total float -30 wd
A3520Mechanical in-wall rough-in Level 2 Zone DInteriors / L2 Interiors - Level 212-Mar-2026-30Total float -30 wd
A3530Plumbing in-wall rough-in Level 2 Zone DInteriors / L2 Interiors - Level 211-Mar-2026-29Total float -29 wd
A3540Electrical in-wall rough-in Level 2 Zone DInteriors / L2 Interiors - Level 212-Mar-2026-30Total float -30 wd
A3550Sprinkler branch piping Level 2 Zone DInteriors / L2 Interiors - Level 211-Mar-2026-29Total float -29 wd
A3560In-wall services inspection Level 2 Zone DInteriors / L2 Interiors - Level 213-Mar-2026-30Total float -30 wd
A3570Drywall board Level 2 Zone DInteriors / L2 Interiors - Level 226-Mar-2026-34Total float -34 wd
A3580Tape, mud and sand Level 2 Zone DInteriors / L2 Interiors - Level 201-Apr-2026-34Total float -34 wd
A3590Prime paint Level 2 Zone DInteriors / L2 Interiors - Level 206-Apr-2026-34Total float -34 wd
A3610Flooring Level 2 Zone DInteriors / L2 Interiors - Level 228-Apr-2026-37Total float -37 wd
A3620Doors, hardware and millwork Level 2 Zone DInteriors / L2 Interiors - Level 207-May-2026-37Total float -37 wd
A3630Final paint and finishes Level 2 Zone DInteriors / L2 Interiors - Level 214-May-2026-37Total float -37 wd
A4330Deficiency review with the consultantCommissioning and Closeout27-May-2026-37Total float -37 wd
A4340Substantial performance certificationCommissioning and Closeout03-Jun-2026-37Total float -37 wd
A4370Operation and maintenance manualsCommissioning and Closeout10-Jun-2026-27Total float -27 wd
A4380Deficiency correctionCommissioning and Closeout24-Jun-2026-37Total float -37 wd
A4410Owner furniture and fit-out (by others)BYO Work by Others24-Jun-2026-37Total float -37 wd
A4420Owner IT and security installation (by others)BYO Work by Others17-Jun-2026-32Total float -32 wd
A4430Ceiling grid Level 1 Zone AInteriors / L1 Interiors - Level 122-Dec-2025-37Total float -37 wd
A4440Ceiling MEP devices and tiles Level 1 Zone AInteriors / L1 Interiors - Level 129-Dec-2025-37Total float -37 wd
A4450Ceiling grid Level 1 Zone BInteriors / L1 Interiors - Level 102-Jan-2026-37Total float -37 wd
A4460Ceiling MEP devices and tiles Level 1 Zone BInteriors / L1 Interiors - Level 107-Jan-2026-37Total float -37 wd
A4470Ceiling grid Level 1 Zone CInteriors / L1 Interiors - Level 112-Jan-2026-37Total float -37 wd
A4480Ceiling MEP devices and tiles Level 1 Zone CInteriors / L1 Interiors - Level 115-Jan-2026-37Total float -37 wd
A4490Ceiling grid Level 1 Zone DInteriors / L1 Interiors - Level 120-Jan-2026-37Total float -37 wd
A4500Ceiling MEP devices and tiles Level 1 Zone DInteriors / L1 Interiors - Level 123-Jan-2026-37Total float -37 wd
A4510Ceiling grid Level 2 Zone AInteriors / L2 Interiors - Level 218-Mar-2026-37Total float -37 wd
A4520Ceiling MEP devices and tiles Level 2 Zone AInteriors / L2 Interiors - Level 223-Mar-2026-37Total float -37 wd
A4530Ceiling grid Level 2 Zone BInteriors / L2 Interiors - Level 226-Mar-2026-37Total float -37 wd
A4540Ceiling MEP devices and tiles Level 2 Zone BInteriors / L2 Interiors - Level 231-Mar-2026-37Total float -37 wd
A4550Ceiling grid Level 2 Zone CInteriors / L2 Interiors - Level 206-Apr-2026-37Total float -37 wd
A4560Ceiling MEP devices and tiles Level 2 Zone CInteriors / L2 Interiors - Level 209-Apr-2026-37Total float -37 wd
A4570Ceiling grid Level 2 Zone DInteriors / L2 Interiors - Level 214-Apr-2026-37Total float -37 wd
A4580Ceiling MEP devices and tiles Level 2 Zone DInteriors / L2 Interiors - Level 217-Apr-2026-37Total float -37 wd
A4800Special inspection of Level 2 steel connectionsStructure14-Aug-2025-37Total float -37 wd
A4810Roof membrane flood testRoofing06-Oct-2025-2Total float -2 wd
A4830ESA rough-in inspection Level 2MEP Mechanical and Electrical Services13-Mar-2026-30Total float -30 wd
A4860Winter enclosure of open curtain wall openingsENV Building Envelope20-Oct-2025-21Total float -21 wd
A4870Second framing crew mobilized for Level 2Interiors / L2 Interiors - Level 206-Feb-2026-20Total float -20 wd
A4880Owner audio-visual rough-in (by others)BYO Work by Others26-Feb-2026-37Total float -37 wd
A4900Punch list Level 2Commissioning and Closeout20-May-2026-37Total float -37 wd
WBS shown relative to the common root: Larchmere Library and Community Hub (Demo Data). Full paths are in the tooltip and the CSV export.
C9Valid Dates Register, all flagged activities
61 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A1030Permanent Power AvailableMS Key Milestones18-Sep-2025Actual start (18-Sep-2025) after status date (05-Aug-2025) | Actual finish (18-Sep-2025) after status date (05-Aug-2025)
A1170Structural steel: fabricate and deliverPROC Submittals and Procurement20-Aug-2025Actual finish (20-Aug-2025) after status date (05-Aug-2025)
A1230Curtain wall and windows: fabricate and deliverPROC Submittals and Procurement23-Sep-2025Actual finish (23-Sep-2025) after status date (05-Aug-2025)
A1290Rooftop air handling units: fabricate and deliverPROC Submittals and Procurement27-Aug-2025Actual finish (27-Aug-2025) after status date (05-Aug-2025)
A1350Switchgear and transformers: fabricate and deliverPROC Submittals and Procurement04-Sep-2025Actual finish (04-Sep-2025) after status date (05-Aug-2025)
A1380Elevator: fabricate and deliverPROC Submittals and Procurement11-Sep-2025Actual finish (11-Sep-2025) after status date (05-Aug-2025)
A1650Backfill and compact at foundationsSite Works05-Aug-2025Actual start (08-Oct-2025) after status date (05-Aug-2025)
A1690Waterproofing and perimeter drainage Zone AFDN Foundations07-Aug-2025Actual finish (07-Aug-2025) after status date (05-Aug-2025)
A1700Underslab services Zone AFDN Foundations08-Aug-2025Actual finish (08-Aug-2025) after status date (05-Aug-2025)
A1710Slab on grade Zone AFDN Foundations15-Aug-2025Actual start (11-Aug-2025) after status date (05-Aug-2025) | Actual finish (15-Aug-2025) after status date (05-Aug-2025)
A1740Foundation walls Zone BFDN Foundations15-Aug-2025Actual finish (15-Aug-2025) after status date (05-Aug-2025)
A1750Waterproofing and perimeter drainage Zone BFDN Foundations21-Aug-2025Actual start (18-Aug-2025) after status date (05-Aug-2025) | Actual finish (21-Aug-2025) after status date (05-Aug-2025)
A1760Underslab services Zone BFDN Foundations22-Aug-2025Actual start (18-Aug-2025) after status date (05-Aug-2025) | Actual finish (22-Aug-2025) after status date (05-Aug-2025)
A1770Slab on grade Zone BFDN Foundations29-Aug-2025Actual start (25-Aug-2025) after status date (05-Aug-2025) | Actual finish (29-Aug-2025) after status date (05-Aug-2025)
A1780Footings Zone CFDN Foundations29-Aug-2025Actual start (06-Aug-2025) after status date (05-Aug-2025) | Actual finish (29-Aug-2025) after status date (05-Aug-2025)
A1790Footing inspection Zone CFDN Foundations03-Sep-2025Actual start (03-Sep-2025) after status date (05-Aug-2025) | Actual finish (03-Sep-2025) after status date (05-Aug-2025)
A1800Foundation walls Zone CFDN Foundations17-Sep-2025Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (17-Sep-2025) after status date (05-Aug-2025)
A1810Waterproofing and perimeter drainage Zone CFDN Foundations23-Sep-2025Actual start (18-Sep-2025) after status date (05-Aug-2025) | Actual finish (23-Sep-2025) after status date (05-Aug-2025)
A1820Underslab services Zone CFDN Foundations24-Sep-2025Actual start (18-Sep-2025) after status date (05-Aug-2025) | Actual finish (24-Sep-2025) after status date (05-Aug-2025)
A1830Slab on grade Zone CFDN Foundations01-Oct-2025Actual start (25-Sep-2025) after status date (05-Aug-2025) | Actual finish (01-Oct-2025) after status date (05-Aug-2025)
A1840Footings Zone DFDN Foundations11-Sep-2025Actual start (02-Sep-2025) after status date (05-Aug-2025) | Actual finish (11-Sep-2025) after status date (05-Aug-2025)
A1850Footing inspection Zone DFDN Foundations12-Sep-2025Actual start (12-Sep-2025) after status date (05-Aug-2025) | Actual finish (12-Sep-2025) after status date (05-Aug-2025)
A1860Foundation walls Zone DFDN Foundations01-Oct-2025Actual start (18-Sep-2025) after status date (05-Aug-2025) | Actual finish (01-Oct-2025) after status date (05-Aug-2025)
A1870Waterproofing and perimeter drainage Zone DFDN Foundations07-Oct-2025Actual start (02-Oct-2025) after status date (05-Aug-2025) | Actual finish (07-Oct-2025) after status date (05-Aug-2025)
A1880Underslab services Zone DFDN Foundations08-Oct-2025Actual start (02-Oct-2025) after status date (05-Aug-2025) | Actual finish (08-Oct-2025) after status date (05-Aug-2025)
A1890Slab on grade Zone DFDN Foundations05-Aug-2025Actual start (09-Oct-2025) after status date (05-Aug-2025)
A1900Erect structural steel Level 2 Zone AStructure24-Sep-2025Actual start (19-Sep-2025) after status date (05-Aug-2025) | Actual finish (24-Sep-2025) after status date (05-Aug-2025)
A1910Metal deck Level 2 Zone AStructure29-Sep-2025Actual start (25-Sep-2025) after status date (05-Aug-2025) | Actual finish (29-Sep-2025) after status date (05-Aug-2025)
A1920Concrete topping Level 2 Zone AStructure02-Oct-2025Actual start (30-Sep-2025) after status date (05-Aug-2025) | Actual finish (02-Oct-2025) after status date (05-Aug-2025)
A1930Erect structural steel Level 2 Zone BStructure10-Oct-2025Actual start (25-Sep-2025) after status date (05-Aug-2025) | Actual finish (10-Oct-2025) after status date (05-Aug-2025)
A1940Metal deck Level 2 Zone BStructure05-Aug-2025Actual start (14-Oct-2025) after status date (05-Aug-2025)
A1960Erect structural steel Level 2 Zone CStructure06-Aug-2025Actual start (14-Oct-2025) after status date (05-Aug-2025)
A2240Elevator shaft masonryStructure05-Aug-2025Actual start (25-Aug-2025) after status date (05-Aug-2025)
A2460Set boilers and pumpsMEP Mechanical and Electrical Services22-Aug-2025Actual start (18-Aug-2025) after status date (05-Aug-2025) | Actual finish (22-Aug-2025) after status date (05-Aug-2025)
A2470Mechanical room pipingMEP Mechanical and Electrical Services10-Sep-2025Actual start (25-Aug-2025) after status date (05-Aug-2025) | Actual finish (10-Sep-2025) after status date (05-Aug-2025)
A2480Ductwork mains Level 1MEP Mechanical and Electrical Services05-Aug-2025Actual start (03-Oct-2025) after status date (05-Aug-2025)
A2510Domestic water risersMEP Mechanical and Electrical Services10-Oct-2025Actual start (03-Oct-2025) after status date (05-Aug-2025) | Actual finish (10-Oct-2025) after status date (05-Aug-2025)
A2520Sprinkler mains and risersMEP Mechanical and Electrical Services05-Aug-2025Actual start (03-Oct-2025) after status date (05-Aug-2025)
A2530Set switchgear and transformersMEP Mechanical and Electrical Services11-Sep-2025Actual start (05-Sep-2025) after status date (05-Aug-2025) | Actual finish (11-Sep-2025) after status date (05-Aug-2025)
A2540Utility connection and ESA inspectionMEP Mechanical and Electrical Services18-Sep-2025Actual start (12-Sep-2025) after status date (05-Aug-2025) | Actual finish (18-Sep-2025) after status date (05-Aug-2025)
A2550Feeders and distribution panelsMEP Mechanical and Electrical Services29-Sep-2025Actual start (12-Sep-2025) after status date (05-Aug-2025) | Actual finish (29-Sep-2025) after status date (05-Aug-2025)
A2570Building automation controls rough-inMEP Mechanical and Electrical Services01-Oct-2025Actual start (11-Sep-2025) after status date (05-Aug-2025) | Actual finish (01-Oct-2025) after status date (05-Aug-2025)
A2600Layout and partition framing Level 1 Zone AInteriors / L1 Interiors - Level 125-Aug-2025Actual start (18-Aug-2025) after status date (05-Aug-2025) | Actual finish (25-Aug-2025) after status date (05-Aug-2025)
A2620Plumbing in-wall rough-in Level 1 Zone AInteriors / L1 Interiors - Level 125-Aug-2025Actual start (20-Aug-2025) after status date (05-Aug-2025) | Actual finish (25-Aug-2025) after status date (05-Aug-2025)
A2630Electrical in-wall rough-in Level 1 Zone AInteriors / L1 Interiors - Level 126-Aug-2025Actual start (20-Aug-2025) after status date (05-Aug-2025) | Actual finish (26-Aug-2025) after status date (05-Aug-2025)
A2640Sprinkler branch piping Level 1 Zone AInteriors / L1 Interiors - Level 125-Aug-2025Actual start (20-Aug-2025) after status date (05-Aug-2025) | Actual finish (25-Aug-2025) after status date (05-Aug-2025)
A2730Layout and partition framing Level 1 Zone BInteriors / L1 Interiors - Level 109-Sep-2025Actual start (02-Sep-2025) after status date (05-Aug-2025) | Actual finish (09-Sep-2025) after status date (05-Aug-2025)
A2740Mechanical in-wall rough-in Level 1 Zone BInteriors / L1 Interiors - Level 110-Sep-2025Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (10-Sep-2025) after status date (05-Aug-2025)
A2750Plumbing in-wall rough-in Level 1 Zone BInteriors / L1 Interiors - Level 109-Sep-2025Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (09-Sep-2025) after status date (05-Aug-2025)
A2760Electrical in-wall rough-in Level 1 Zone BInteriors / L1 Interiors - Level 110-Sep-2025Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (10-Sep-2025) after status date (05-Aug-2025)
A2770Sprinkler branch piping Level 1 Zone BInteriors / L1 Interiors - Level 109-Sep-2025Actual start (04-Sep-2025) after status date (05-Aug-2025) | Actual finish (09-Sep-2025) after status date (05-Aug-2025)
A2780In-wall services inspection Level 1 Zone BInteriors / L1 Interiors - Level 111-Sep-2025Actual start (11-Sep-2025) after status date (05-Aug-2025) | Actual finish (11-Sep-2025) after status date (05-Aug-2025)
A2860Layout and partition framing Level 1 Zone CInteriors / L1 Interiors - Level 109-Oct-2025Actual start (02-Oct-2025) after status date (05-Aug-2025) | Actual finish (09-Oct-2025) after status date (05-Aug-2025)
A2870Mechanical in-wall rough-in Level 1 Zone CInteriors / L1 Interiors - Level 110-Oct-2025Actual start (06-Oct-2025) after status date (05-Aug-2025) | Actual finish (10-Oct-2025) after status date (05-Aug-2025)
A2880Plumbing in-wall rough-in Level 1 Zone CInteriors / L1 Interiors - Level 109-Oct-2025Actual start (06-Oct-2025) after status date (05-Aug-2025) | Actual finish (09-Oct-2025) after status date (05-Aug-2025)
A2890Electrical in-wall rough-in Level 1 Zone CInteriors / L1 Interiors - Level 110-Oct-2025Actual start (06-Oct-2025) after status date (05-Aug-2025) | Actual finish (10-Oct-2025) after status date (05-Aug-2025)
A2900Sprinkler branch piping Level 1 Zone CInteriors / L1 Interiors - Level 109-Oct-2025Actual start (06-Oct-2025) after status date (05-Aug-2025) | Actual finish (09-Oct-2025) after status date (05-Aug-2025)
A2910In-wall services inspection Level 1 Zone CInteriors / L1 Interiors - Level 114-Oct-2025Actual start (14-Oct-2025) after status date (05-Aug-2025) | Actual finish (14-Oct-2025) after status date (05-Aug-2025)
A4300Electrical commissioningCommissioning and Closeout06-Oct-2025Actual start (30-Sep-2025) after status date (05-Aug-2025) | Actual finish (06-Oct-2025) after status date (05-Aug-2025)
A4760CD-03 Atrium framing revision: re-detail and fabricate added steelCO Change Orders18-Sep-2025Actual start (21-Aug-2025) after status date (05-Aug-2025) | Actual finish (18-Sep-2025) after status date (05-Aug-2025)
A4790Footing re-inspection Zone C after engineered fillFDN Foundations02-Sep-2025Actual start (02-Sep-2025) after status date (05-Aug-2025) | Actual finish (02-Sep-2025) after status date (05-Aug-2025)
WBS shown relative to the common root: Larchmere Library and Community Hub (Demo Data). Full paths are in the tooltip and the CSV export.
C11Missed Tasks Register, all flagged activities
6 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A1090Site survey and building layoutPreconstruction and Permits09-May-2025Working days late: 2 wdActual finish 2 wd later than baseline (07-May-2025)
A1150Structural steel shop drawings: prepare and submitPROC Submittals and Procurement16-Jun-2025Working days late: 10 wdActual finish 10 wd later than baseline (02-Jun-2025)
A1160Structural steel shop drawings: consultant reviewPROC Submittals and Procurement30-Jun-2025Working days late: 10 wdActual finish 10 wd later than baseline (16-Jun-2025)
A1220Curtain wall and windows shop drawings: consultant reviewPROC Submittals and Procurement11-Jul-2025Working days late: 18 wdActual finish 18 wd later than baseline (16-Jun-2025)
A1590Shoring along the north property lineSite Works26-Jun-2025Working days late: 21 wdActual finish 21 wd later than baseline (28-May-2025)
A1640Municipal service connection inspectionSite Works14-Jul-2025Working days late: 3 wdActual finish 3 wd later than baseline (09-Jul-2025)
WBS shown relative to the common root: Larchmere Library and Community Hub (Demo Data). Full paths are in the tooltip and the CSV export.
C12Critical Path Test Register, all flagged activities
14 activities, all listedExport CSV
Activity IDActivity NameWBSForecast FinishKey MetricIssue
A2230Steel stairs and railingsStructure07-Oct-2025Connectivity: No finish pathOrphan activity cannot reach finish
A2280Sealants and flashings, North elevationENV Building Envelope24-Sep-2025Connectivity: No finish pathOrphan activity cannot reach finish
A2320Sealants and flashings, East elevationENV Building Envelope06-Oct-2025Connectivity: No finish pathOrphan activity cannot reach finish
A2360Sealants and flashings, South elevationENV Building Envelope17-Oct-2025Connectivity: No finish pathOrphan activity cannot reach finish
A2400Sealants and flashings, West elevationENV Building Envelope29-Oct-2025Connectivity: No finish pathOrphan activity cannot reach finish
A2450Roof drains and leadersRoofing25-Sep-2025Connectivity: No finish pathOrphan activity cannot reach finish
A4230Entrance canopy steel and soffitExterior Works20-Oct-2025Connectivity: No finish pathOrphan activity cannot reach finish
A4420Owner IT and security installation (by others)BYO Work by Others17-Jun-2026Connectivity: No finish pathOrphan activity cannot reach finish
A4670Masonry veneer, North elevationENV Building Envelope17-Sep-2025Connectivity: No finish pathOrphan activity cannot reach finish
A4680Metal panel cladding, North elevationENV Building Envelope18-Sep-2025Connectivity: No finish pathOrphan activity cannot reach finish
A4690Masonry veneer, East elevationENV Building Envelope29-Sep-2025Connectivity: No finish pathOrphan activity cannot reach finish
A4700Metal panel cladding, East elevationENV Building Envelope30-Sep-2025Connectivity: No finish pathOrphan activity cannot reach finish
A4730Masonry veneer, West elevationENV Building Envelope22-Oct-2025Connectivity: No finish pathOrphan activity cannot reach finish
A4740Metal panel cladding, West elevationENV Building Envelope23-Oct-2025Connectivity: No finish pathOrphan activity cannot reach finish
WBS shown relative to the common root: Larchmere Library and Community Hub (Demo Data). Full paths are in the tooltip and the CSV export.
A-06b

Detailed Comparison

baseline → current → variance
MetricBaselineCurrentVariance
Total Tasks343379+36
Project Finish01-May-202624-Jun-2026+37 wd
Project Start05-May-202505-May-20250 wd
CPLIn/a0.83below 0.95
BEIn/a0.97at/above 0.95
A-07

Schedule Exposure

measured figures only · derivations below
Finish Drift
+37 wd
current forecast finish vs baseline finish
CPLI
0.83
critical path length index (C13)
BEI
baseline execution index (C14)
Drift Direction
Slipping
sign of the finish drift
How each figure is derived
  • Finish drift: working days from the baseline finish (01-May-2026) to the current forecast finish (24-Jun-2026), counted on the project calendar. Positive = finishing later than baseline.
  • CPLI 0.83: (contract finish − data date) ÷ (forecast finish − data date). Below 1.00 = the forecast finish falls beyond the contract finish. Here: contract finish 01-May-2026, forecast finish 24-Jun-2026, measured from the data date 05-Aug-2025.
  • BEI 0.97: baseline activities actually complete ÷ baseline activities planned complete at the data date. Below 1.00 = executing behind the baseline plan. Here: 58 complete ÷ 60 planned complete at the data date.
  • Drift direction: the sign of the finish drift. Positive drift (+37 wd), so the schedule is slipping against baseline.
  • No resource figure is reported. The schedule carries no resource assignments (C10 not scored), so no resource-based risk or resource-increase percentage can be derived from this file.
A-08

Schedule Forecast

forward-pass dates as scheduled
Forecasted Completion
schedule forward-pass finish
Baseline Completion
baseline schedule finish
Variance
+37 wd
working days, forecast vs baseline
Data Date
status date of the current update
Basis
  • These are the schedule’s own dates as read from the file: the forecast completion is the current schedule’s forward-pass finish, not a probabilistic projection. This screen models no delay probabilities and no resource requirements; a probabilistic finish-date forecast requires a schedule risk analysis (Monte Carlo), which is a separate deliverable.
A-09

Path back to green

grade re-scored per cleared criterion · 9 failing
A-09Path back to green, grade re-scored per cleared criterion
current: Grade F · 31% · RED
Criterion clearedCurrent metricGradeComplianceBand
C7 Negative Float123F38%RED
C9 Valid Dates61F38%RED
C12 Critical Path Test124 activitiesF38%RED
C11 Missed Tasks6F38%RED
C13 CPLI0.83F38%RED
C2 Leads2F38%RED
C3 Lags11.1%F38%RED
C4 Relationship Types88% FSF38%RED
C6 High Float33.7% (85)F38%RED
All 9 failing criteria clearedallA100%GREEN
How these grades are computed
  • The grade is a pure function of the pass rate: passed ÷ scored, graded A ≥90%, B ≥75%, C ≥60%, D ≥45%, else F, the same scoring the headline grade uses. Each row adds exactly one cleared criterion to the 4 currently passing of 13 scored.
  • Clearing a criterion means correcting its listed activities so the check passes (for example, clearing C9 means fixing every invalid date in its register). Other criteria are held at their computed results; knock-on effects of the corrections themselves are not modelled here.
A-10

Report Information

provenance & reproducibility
Generated
22 October 2026, 11:45 UTC
Source Schedule
Larchmere_Library_current.xer
Engine
Schedule Health Dashboard v2.0 · CPP suite at cpm-engine v2.10.13 · no CPM pass run: dates and float read from the XER as submitted
Baseline
05-May-2025
Standard
DCMA 14-Point Assessment
Data Date
05-Aug-2025
Current XER SHA-256
e5cba9fbd494323aaeed96ade700dc08e4293788284a825c081b4910595440fa
Baseline XER SHA-256 (Larchmere_Library_baseline.xer)
376945cbe81cd6c4d805b035ac746b3c6b1d8bed1055239f039f440368f6f667
Generated 22 October 2026, 11:45 UTC  ·  Source: Larchmere_Library_current.xer  ·  Grade F · 31% · RED  ·  Schedule Health Dashboard v2.0 · CPP suite at cpm-engine v2.10.13 · no CPM pass run: dates and float read from the XER as submittedDCMA 14-Point Assessment · Automated screening