| A2480 |
Concrete for Remaining Pad Footings (Ramp) |
1 Phase 2 - Foundation Work |
2025-07-02 08:00 |
2025-07-02 17:00 |
Total Float (d): 316.0 |
Total float of 316d exceeds 44 days |
A2480 "Concrete for Remaining Pad Footings (Ramp)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 316d exceeds 44 days) |
| A4570 |
Joist Interferences Relocation |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2025-08-18 08:00 |
2025-08-22 17:00 |
Total Float (d): 279.0 |
Total float of 279d exceeds 44 days |
A4570 "Joist Interferences Relocation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 279d exceeds 44 days) |
| A1480.1 |
23 00 00 - Exhaust Fans (R1) |
1.2.38 Mechanical Equipment Shop Drawings |
2025-09-16 08:00 |
2025-09-29 17:00 |
Total Float (d): 254.0 |
Total float of 254d exceeds 44 days |
A1480.1 "23 00 00 - Exhaust Fans (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 254d exceeds 44 days) |
| A1670 |
Masonry and Mortar |
1.3 Procurement |
2025-08-19 08:00 |
2025-08-25 17:00 |
Total Float (d): 253.0 |
Total float of 253d exceeds 44 days |
A1670 "Masonry and Mortar" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 253d exceeds 44 days) |
| A3940 |
Existing Slab Removal and Trenching |
1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation |
2025-09-03 08:00 |
2025-09-09 17:00 |
Total Float (d): 253.0 |
Total float of 253d exceeds 44 days |
A3940 "Existing Slab Removal and Trenching" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 253d exceeds 44 days) |
| A4370 |
Underground Mechanical Installation (DCW, Sprinkler) |
1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation |
2025-09-10 08:00 |
2025-09-23 17:00 |
Total Float (d): 253.0 |
Total float of 253d exceeds 44 days |
A4370 "Underground Mechanical Installation (DCW, Sprinkler)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 253d exceeds 44 days) |
| A4380 |
Backfilling and Concrete for SOG |
1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation |
2025-09-24 08:00 |
2025-09-30 17:00 |
Total Float (d): 253.0 |
Total float of 253d exceeds 44 days |
A4380 "Backfilling and Concrete for SOG" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 253d exceeds 44 days) |
| A1610 |
Concrete Mix for Hardscapes |
1.2 Shop Drawings |
2025-07-23 08:00 |
2025-08-06 17:00 |
Total Float (d): 238.0 |
Total float of 238d exceeds 44 days |
A1610 "Concrete Mix for Hardscapes" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 238d exceeds 44 days) |
| A2200 |
Concrete for Hardscape |
1.3 Procurement |
2025-08-07 08:00 |
2025-08-13 17:00 |
Total Float (d): 238.0 |
Total float of 238d exceeds 44 days |
A2200 "Concrete for Hardscape" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 238d exceeds 44 days) |
| A1140 |
Millwork Shop Drawings |
1.2 Shop Drawings |
2025-07-16 08:00 |
2025-07-29 17:00 |
Total Float (d): 228.0 |
Total float of 228d exceeds 44 days |
A1140 "Millwork Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 228d exceeds 44 days) |
| A1320 |
Washroom accessories and Partitions Shop Drawings |
1.2 Shop Drawings |
2025-07-16 08:00 |
2025-07-29 17:00 |
Total Float (d): 228.0 |
Total float of 228d exceeds 44 days |
A1320 "Washroom accessories and Partitions Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 228d exceeds 44 days) |
| A1720 |
Millwork |
1.3 Procurement |
2025-07-30 08:00 |
2025-10-09 17:00 |
Total Float (d): 228.0 |
Total float of 228d exceeds 44 days |
A1720 "Millwork " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 228d exceeds 44 days) |
| A1910 |
Washroom accessories and Partitions |
1.3 Procurement |
2025-07-30 08:00 |
2025-09-04 17:00 |
Total Float (d): 228.0 |
Total float of 228d exceeds 44 days |
A1910 "Washroom accessories and Partitions " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 228d exceeds 44 days) |
| A1270 |
Tiling Data sheet and samples |
1.2 Shop Drawings |
2025-07-16 08:00 |
2025-07-29 17:00 |
Total Float (d): 213.0 |
Total float of 213d exceeds 44 days |
A1270 "Tiling Data sheet and samples" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 213d exceeds 44 days) |
| A1860 |
Tiling |
1.3 Procurement |
2025-07-30 08:00 |
2025-09-11 17:00 |
Total Float (d): 213.0 |
Total float of 213d exceeds 44 days |
A1860 "Tiling " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 213d exceeds 44 days) |
| A1310 |
Paint Drawdowns |
1.2 Shop Drawings |
2025-07-16 08:00 |
2025-07-29 17:00 |
Total Float (d): 212.0 |
Total float of 212d exceeds 44 days |
A1310 "Paint Drawdowns" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 212d exceeds 44 days) |
| A1900 |
Paint Drawdowns |
1.3 Procurement |
2025-07-30 08:00 |
2025-08-13 17:00 |
Total Float (d): 212.0 |
Total float of 212d exceeds 44 days |
A1900 "Paint Drawdowns" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 212d exceeds 44 days) |
| A1620 |
Landscape Shop Drawings |
1.2 Shop Drawings |
2025-07-23 08:00 |
2025-08-06 17:00 |
Total Float (d): 203.0 |
Total float of 203d exceeds 44 days |
A1620 "Landscape Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 203d exceeds 44 days) |
| A2210 |
Landscape (unit pavers, furniture, etc) |
1.3 Procurement |
2025-08-07 08:00 |
2025-10-31 17:00 |
Total Float (d): 203.0 |
Total float of 203d exceeds 44 days |
A2210 "Landscape (unit pavers, furniture, etc)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 203d exceeds 44 days) |
| A1350 |
Sprinkler & Standpipe Shop Drawings |
1.2 Shop Drawings |
2025-07-02 08:00 |
2025-07-15 17:00 |
Total Float (d): 192.0 |
Total float of 192d exceeds 44 days |
A1350 "Sprinkler & Standpipe Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 192d exceeds 44 days) |
| A1940 |
Sprinkler & Standpipe Shop Drawings |
1.3 Procurement |
2025-07-16 08:00 |
2025-08-06 17:00 |
Total Float (d): 192.0 |
Total float of 192d exceeds 44 days |
A1940 "Sprinkler & Standpipe Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 192d exceeds 44 days) |
| A1300 |
Flooring Data Sheets and Samples |
1.2 Shop Drawings |
2025-07-16 08:00 |
2025-07-29 17:00 |
Total Float (d): 183.0 |
Total float of 183d exceeds 44 days |
A1300 "Flooring Data Sheets and Samples" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 183d exceeds 44 days) |
| A1890 |
Flooring |
1.3 Procurement |
2025-07-30 08:00 |
2025-10-24 17:00 |
Total Float (d): 183.0 |
Total float of 183d exceeds 44 days |
A1890 "Flooring " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 183d exceeds 44 days) |
| A1180 |
Exterior Wall Cladding Shop Drawings |
1.2 Shop Drawings |
2025-08-11 08:00 |
2025-08-22 17:00 |
Total Float (d): 181.0 |
Total float of 181d exceeds 44 days |
A1180 "Exterior Wall Cladding Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 181d exceeds 44 days) |
| A1760 |
Exterior Wall Cladding |
1.3 Procurement |
2025-08-25 08:00 |
2025-11-18 17:00 |
Total Float (d): 181.0 |
Total float of 181d exceeds 44 days |
A1760 "Exterior Wall Cladding" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 181d exceeds 44 days) |
| A2040 |
22 13 29 - Sump Pumps |
1.3.34 Mechanical Equipment |
2025-06-19 08:00 |
2025-08-08 17:00 |
Total Float (d): 177.0 |
Total float of 177d exceeds 44 days |
A2040 "22 13 29 - Sump Pumps" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 177d exceeds 44 days) |
| A1740 |
TPO Roofing (Bridge) |
1.3 Procurement |
2025-08-27 08:00 |
2025-10-08 17:00 |
Total Float (d): 173.0 |
Total float of 173d exceeds 44 days |
A1740 "TPO Roofing (Bridge)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 173d exceeds 44 days) |
| A4530 |
Electrical and Mechanical Make Safe |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-01-12 08:00 |
2026-01-14 17:00 |
Total Float (d): 170.0 |
Total float of 170d exceeds 44 days |
A4530 "Electrical and Mechanical Make Safe" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 170d exceeds 44 days) |
| A4540 |
Interior Demoilition |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-01-15 08:00 |
2026-01-28 17:00 |
Total Float (d): 170.0 |
Total float of 170d exceeds 44 days |
A4540 "Interior Demoilition " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 170d exceeds 44 days) |
| A1200 |
Hollow Metal Frames & Doors Shop Drawings |
1.2 Shop Drawings |
2025-07-16 08:00 |
2025-07-29 17:00 |
Total Float (d): 162.0 |
Total float of 162d exceeds 44 days |
A1200 "Hollow Metal Frames & Doors Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 162d exceeds 44 days) |
| A1780 |
Hollow Metal Frames |
1.3 Procurement |
2025-07-30 08:00 |
2025-09-25 17:00 |
Total Float (d): 162.0 |
Total float of 162d exceeds 44 days |
A1780 "Hollow Metal Frames" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 162d exceeds 44 days) |
| A1790 |
Hollow Metal Doors |
1.3 Procurement |
2025-07-30 08:00 |
2025-10-24 17:00 |
Total Float (d): 162.0 |
Total float of 162d exceeds 44 days |
A1790 "Hollow Metal Doors" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 162d exceeds 44 days) |
| A1770 |
Fire-resistive Material |
1.3 Procurement |
2025-07-10 08:00 |
2025-08-07 17:00 |
Total Float (d): 161.0 |
Total float of 161d exceeds 44 days |
A1770 "Fire-resistive Material " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 161d exceeds 44 days) |
| A1170 |
Air Barrier System Data Sheet and Mockup |
1.2 Shop Drawings |
2025-07-02 08:00 |
2025-07-08 17:00 |
Total Float (d): 159.0 |
Total float of 159d exceeds 44 days |
A1170 "Air Barrier System Data Sheet and Mockup" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 159d exceeds 44 days) |
| A1750 |
Air Barrier System |
1.3 Procurement |
2025-07-09 08:00 |
2025-07-22 17:00 |
Total Float (d): 159.0 |
Total float of 159d exceeds 44 days |
A1750 "Air Barrier System" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 159d exceeds 44 days) |
| A1870 |
ACT & ACB |
1.3 Procurement |
2025-09-05 08:00 |
2025-10-17 17:00 |
Total Float (d): 156.0 |
Total float of 156d exceeds 44 days |
A1870 "ACT & ACB " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 156d exceeds 44 days) |
| A2070 |
23 00 00 - Exhaust Fans |
1.3.34 Mechanical Equipment |
2025-09-09 08:00 |
2025-12-18 17:00 |
Total Float (d): 154.0 |
Total float of 154d exceeds 44 days |
A2070 "23 00 00 - Exhaust Fans" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 154d exceeds 44 days) |
| A4010 |
Underground Plumbing Rough-ins |
1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) |
2025-07-02 08:00 |
2025-07-15 17:00 |
Total Float (d): 150.0 |
Total float of 150d exceeds 44 days |
A4010 "Underground Plumbing Rough-ins" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days) |
| A4760 |
Trench Backfill |
1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) |
2025-07-16 08:00 |
2025-07-22 17:00 |
Total Float (d): 150.0 |
Total float of 150d exceeds 44 days |
A4760 "Trench Backfill" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days) |
| A4770 |
Concrete Slab Infill |
1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) |
2025-07-23 08:00 |
2025-08-06 17:00 |
Total Float (d): 150.0 |
Total float of 150d exceeds 44 days |
A4770 "Concrete Slab Infill" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days) |
| A4780 |
New Columns Installation |
1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) |
2025-08-07 08:00 |
2025-08-13 17:00 |
Total Float (d): 150.0 |
Total float of 150d exceeds 44 days |
A4780 "New Columns Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days) |
| A4790 |
Existing Column Reinforcement |
1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) |
2025-08-14 08:00 |
2025-08-20 17:00 |
Total Float (d): 150.0 |
Total float of 150d exceeds 44 days |
A4790 "Existing Column Reinforcement" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days) |
| A4800 |
Flatness Survey @ Floor Slab |
1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) |
2025-08-21 08:00 |
2025-08-22 17:00 |
Total Float (d): 150.0 |
Total float of 150d exceeds 44 days |
A4800 "Flatness Survey @ Floor Slab" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days) |
| A4810 |
Self Levelling |
1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) |
2025-08-25 08:00 |
2025-09-03 17:00 |
Total Float (d): 150.0 |
Total float of 150d exceeds 44 days |
A4810 "Self Levelling" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days) |
| A1210 |
Interior Aluminum Screen |
1.2 Shop Drawings |
2025-07-25 08:00 |
2025-08-08 17:00 |
Total Float (d): 141.0 |
Total float of 141d exceeds 44 days |
A1210 "Interior Aluminum Screen" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 141d exceeds 44 days) |
| A1800 |
Interior Aluminum Screens |
1.3 Procurement |
2025-08-11 08:00 |
2025-12-16 17:00 |
Total Float (d): 141.0 |
Total float of 141d exceeds 44 days |
A1800 "Interior Aluminum Screens" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 141d exceeds 44 days) |
| A1930 |
Hydraulic Lift |
1.3 Procurement |
2025-07-10 08:00 |
2025-12-01 17:00 |
Total Float (d): 141.0 |
Total float of 141d exceeds 44 days |
A1930 "Hydraulic Lift " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 141d exceeds 44 days) |
| A1530.1 |
20 05 10 - Electric Heat Tracing (R1) |
1.2.38 Mechanical Equipment Shop Drawings |
2025-08-13 08:00 |
2025-08-26 17:00 |
Total Float (d): 134.0 |
Total float of 134d exceeds 44 days |
A1530.1 "20 05 10 - Electric Heat Tracing (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 134d exceeds 44 days) |
| A2120 |
20 05 10 - Electric Heat Tracing |
1.3.34 Mechanical Equipment |
2025-08-27 08:00 |
2026-01-19 17:00 |
Total Float (d): 134.0 |
Total float of 134d exceeds 44 days |
A2120 "20 05 10 - Electric Heat Tracing" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 134d exceeds 44 days) |
| A1250 |
Finished Hardware Schedule |
1.2 Shop Drawings |
2025-07-16 08:00 |
2025-07-29 17:00 |
Total Float (d): 132.0 |
Total float of 132d exceeds 44 days |
A1250 "Finished Hardware Schedule" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 132d exceeds 44 days) |
| A1840 |
Finished Hardware |
1.3 Procurement |
2025-07-30 08:00 |
2025-12-05 17:00 |
Total Float (d): 132.0 |
Total float of 132d exceeds 44 days |
A1840 "Finished Hardware " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 132d exceeds 44 days) |
| A1240 |
Aluminum Framed Glazing System Shop Drawings |
1.2 Shop Drawings |
2025-07-23 08:00 |
2025-08-06 17:00 |
Total Float (d): 131.0 |
Total float of 131d exceeds 44 days |
A1240 "Aluminum Framed Glazing System Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 131d exceeds 44 days) |
| A1830 |
Aluminum Framed Glazing Systems |
1.3 Procurement |
2025-08-07 08:00 |
2025-11-28 17:00 |
Total Float (d): 131.0 |
Total float of 131d exceeds 44 days |
A1830 "Aluminum Framed Glazing Systems" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 131d exceeds 44 days) |
| A2780 |
Above Grade Vapour Mock-up |
1.4.5.4.1 North Elevation |
2026-02-02 08:00 |
2026-02-02 17:00 |
Total Float (d): 129.0 |
Total float of 129d exceeds 44 days |
A2780 "Above Grade Vapour Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 129d exceeds 44 days) |
| A4560 |
Review Interferences with Steel Joist |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2025-07-02 08:00 |
2025-07-08 17:00 |
Total Float (d): 128.0 |
Total float of 128d exceeds 44 days |
A4560 "Review Interferences with Steel Joist" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 128d exceeds 44 days) |
| A1730 |
Built-up Roofing |
1.3 Procurement |
2025-07-10 08:00 |
2025-08-21 17:00 |
Total Float (d): 127.0 |
Total float of 127d exceeds 44 days |
A1730 "Built-up Roofing " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 127d exceeds 44 days) |
| A1810 |
Flush Wood Doors |
1.3 Procurement |
2025-08-28 08:00 |
2025-12-12 17:00 |
Total Float (d): 127.0 |
Total float of 127d exceeds 44 days |
A1810 "Flush Wood Doors " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 127d exceeds 44 days) |
| A2190 |
28 31 00 - Fire Alarm |
1.3.35 Electrical Power Distribution Equipment |
2025-06-18 08:00 |
2025-10-27 17:00 |
Total Float (d): 123.0 |
Total float of 123d exceeds 44 days |
A2190 "28 31 00 - Fire Alarm" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 123d exceeds 44 days) |
| A3180 |
Roof Inspection |
1.4.5.4.5 Roofing |
2026-02-03 08:00 |
2026-02-03 17:00 |
Total Float (d): 123.0 |
Total float of 123d exceeds 44 days |
A3180 "Roof Inspection" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 123d exceeds 44 days) |
| A1260 |
Stud framing and Gypsum Board Data Sheets |
1.2 Shop Drawings |
2025-07-16 08:00 |
2025-07-29 17:00 |
Total Float (d): 118.0 |
Total float of 118d exceeds 44 days |
A1260 "Stud framing and Gypsum Board Data Sheets" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 118d exceeds 44 days) |
| A1850 |
Stud framing & gypsum board |
1.3 Procurement |
2025-07-30 08:00 |
2025-08-06 17:00 |
Total Float (d): 118.0 |
Total float of 118d exceeds 44 days |
A1850 "Stud framing & gypsum board" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 118d exceeds 44 days) |
| A1700 |
Cold-formed Metal Framing |
1.3 Procurement |
2025-07-24 08:00 |
2025-08-07 17:00 |
Total Float (d): 117.0 |
Total float of 117d exceeds 44 days |
A1700 "Cold-formed Metal Framing " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 117d exceeds 44 days) |
| A2420 |
Form and Pour North Exit Stair |
1 Phase 2 - Foundation Work |
2025-08-04 08:00 |
2025-09-30 17:00 |
Total Float (d): 116.0 |
Total float of 116d exceeds 44 days |
A2420 "Form and Pour North Exit Stair" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 116d exceeds 44 days) |
| A1990 |
23 21 16 - Air Separator |
1.3.34 Mechanical Equipment |
2025-07-04 08:00 |
2025-11-11 17:00 |
Total Float (d): 112.0 |
Total float of 112d exceeds 44 days |
A1990 "23 21 16 - Air Separator" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 112d exceeds 44 days) |
| A2000 |
23 21 16 - Expansion Tanks |
1.3.34 Mechanical Equipment |
2025-07-04 08:00 |
2025-11-11 17:00 |
Total Float (d): 112.0 |
Total float of 112d exceeds 44 days |
A2000 "23 21 16 - Expansion Tanks" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 112d exceeds 44 days) |
| A2010 |
23 57 00 - Heat Exchangers |
1.3.34 Mechanical Equipment |
2025-07-04 08:00 |
2025-11-11 17:00 |
Total Float (d): 112.0 |
Total float of 112d exceeds 44 days |
A2010 "23 57 00 - Heat Exchangers" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 112d exceeds 44 days) |
| A2020 |
22 33 00 - Electric Domestic Water Heaters |
1.3.34 Mechanical Equipment |
2025-07-04 08:00 |
2025-11-11 17:00 |
Total Float (d): 112.0 |
Total float of 112d exceeds 44 days |
A2020 "22 33 00 - Electric Domestic Water Heaters" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 112d exceeds 44 days) |
| A2140 |
26 27 26 - Wiring Devices, Service Poles, & Floor Boxes |
1.3.35 Electrical Power Distribution Equipment |
2025-07-09 08:00 |
2025-11-14 17:00 |
Total Float (d): 109.0 |
Total float of 109d exceeds 44 days |
A2140 "26 27 26 - Wiring Devices, Service Poles, & Floor Boxes" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 109d exceeds 44 days) |
| A2030 |
23 81 26 - Split System |
1.3.34 Mechanical Equipment |
2025-07-10 08:00 |
2025-11-17 17:00 |
Total Float (d): 108.0 |
Total float of 108d exceeds 44 days |
A2030 "23 81 26 - Split System" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 108d exceeds 44 days) |
| A1820 |
Coiling Doors |
1.3 Procurement |
2025-08-22 08:00 |
2026-01-14 17:00 |
Total Float (d): 106.0 |
Total float of 106d exceeds 44 days |
A1820 "Coiling Doors" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 106d exceeds 44 days) |
| 2170 |
26 50 00 - Emergency Lighting & Exit Signs |
1.3.35 Electrical Power Distribution Equipment |
2025-07-30 08:00 |
2025-12-05 17:00 |
Total Float (d): 104.0 |
Total float of 104d exceeds 44 days |
2170 "26 50 00 - Emergency Lighting & Exit Signs" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 104d exceeds 44 days) |
| A2760 |
Masonry Mock-up |
1.4.5.4.1 North Elevation |
2026-04-13 08:00 |
2026-04-13 17:00 |
Total Float (d): 96.0 |
Total float of 96d exceeds 44 days |
A2760 "Masonry Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 96d exceeds 44 days) |
| A2770 |
L1 Masonry Wall installation |
1.4.5.4.1 North Elevation |
2026-04-13 08:00 |
2026-04-14 17:00 |
Total Float (d): 95.0 |
Total float of 95d exceeds 44 days |
A2770 "L1 Masonry Wall installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 95d exceeds 44 days) |
| A2890 |
L1 Masonry Wall Installation |
1.4.5.4.2 West Elevation |
2026-04-15 08:00 |
2026-04-21 17:00 |
Total Float (d): 95.0 |
Total float of 95d exceeds 44 days |
A2890 "L1 Masonry Wall Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 95d exceeds 44 days) |
| A1380x |
Metal Shelving (R1) |
1.2 Shop Drawings |
2025-07-10 08:00 |
2025-07-23 17:00 |
Total Float (d): 93.0 |
Total float of 93d exceeds 44 days |
A1380x "Metal Shelving (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 93d exceeds 44 days) |
| A2090x |
Metal Shelving |
1.3 Procurement |
2025-07-24 08:00 |
2025-08-21 17:00 |
Total Float (d): 93.0 |
Total float of 93d exceeds 44 days |
A2090x "Metal Shelving" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 93d exceeds 44 days) |
| A4510 |
Metal Shelving Installation |
1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation |
2025-08-22 08:00 |
2025-08-26 17:00 |
Total Float (d): 93.0 |
Total float of 93d exceeds 44 days |
A4510 "Metal Shelving Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 93d exceeds 44 days) |
| A4700 |
Review Interferences with Steel Joist |
1.4.6.2 Machine Shop Area |
2025-08-18 08:00 |
2025-08-18 08:00 |
Total Float (d): 91.0 |
Total float of 91d exceeds 44 days |
A4700 "Review Interferences with Steel Joist" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 91d exceeds 44 days) |
| A4710 |
Relocation of Interferences |
1.4.6.2 Machine Shop Area |
2025-08-18 08:00 |
2025-08-29 17:00 |
Total Float (d): 91.0 |
Total float of 91d exceeds 44 days |
A4710 "Relocation of Interferences" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 91d exceeds 44 days) |
| A2220 |
Testing and Inspection Cash Allowance Expenditure |
1.3 Procurement |
2025-07-02 08:00 |
2025-07-02 08:00 |
Total Float (d): 89.0 |
Total float of 89d exceeds 44 days |
A2220 "Testing and Inspection Cash Allowance Expenditure" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 89d exceeds 44 days) |
| A2800 |
AVB Inspection |
1.4.5.4.1 North Elevation |
2026-02-02 08:00 |
2026-02-02 17:00 |
Total Float (d): 87.0 |
Total float of 87d exceeds 44 days |
A2800 "AVB Inspection" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 87d exceeds 44 days) |
| A4550 |
Existing Exterior Wall Demo (New Building Must be Erected and Enclosed) |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-02-17 08:00 |
2026-02-23 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4550 "Existing Exterior Wall Demo (New Building Must be Erected and Enclosed)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4600 |
Stud Framing |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-02-24 08:00 |
2026-02-26 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4600 "Stud Framing" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4610 |
MEP Rough-ins |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-02-27 08:00 |
2026-03-05 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4610 "MEP Rough-ins" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4620 |
Plywood Blocking |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-03-06 08:00 |
2026-03-10 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4620 "Plywood Blocking" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4630 |
Drywall Installation |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-03-11 08:00 |
2026-03-13 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4630 "Drywall Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4640 |
Taping Drywall |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-03-16 08:00 |
2026-03-20 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4640 "Taping Drywall" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4650 |
Painting |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2026-03-23 08:00 |
2026-03-24 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4650 "Painting" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4660 |
Setup Temporary Hoarding |
1.4.6.1.3 Phase 3 - Assembly Area |
2026-03-25 08:00 |
2026-03-25 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4660 "Setup Temporary Hoarding" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4670 |
Electrical and Mechanical Make Safe |
1.4.6.1.3 Phase 3 - Assembly Area |
2026-03-26 08:00 |
2026-03-27 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4670 "Electrical and Mechanical Make Safe" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4680 |
Interior Demoilition |
1.4.6.1.3 Phase 3 - Assembly Area |
2026-03-30 08:00 |
2026-04-06 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4680 "Interior Demoilition " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A4690 |
Electrical Fixtures |
1.4.6.1.3 Phase 3 - Assembly Area |
2026-04-07 08:00 |
2026-04-13 17:00 |
Total Float (d): 86.0 |
Total float of 86d exceeds 44 days |
A4690 "Electrical Fixtures" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days) |
| A2080 |
23 00 00 - Unit Heater |
1.3.34 Mechanical Equipment |
2025-08-29 08:00 |
2025-12-18 17:00 |
Total Float (d): 85.0 |
Total float of 85d exceeds 44 days |
A2080 "23 00 00 - Unit Heater" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 85d exceeds 44 days) |
| A2100 |
23 00 00 - Wall Fin Heater |
1.3.34 Mechanical Equipment |
2025-08-13 08:00 |
2025-12-18 17:00 |
Total Float (d): 85.0 |
Total float of 85d exceeds 44 days |
A2100 "23 00 00 - Wall Fin Heater" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 85d exceeds 44 days) |
| A2150 |
26 50 00 - Lighting Fixtures |
1.3.35 Electrical Power Distribution Equipment |
2025-08-19 08:00 |
2025-12-25 17:00 |
Total Float (d): 81.0 |
Total float of 81d exceeds 44 days |
A2150 "26 50 00 - Lighting Fixtures" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 81d exceeds 44 days) |
| A1980 |
23 25 00 - Buffer Tanks |
1.3.34 Mechanical Equipment |
2025-07-04 08:00 |
2025-12-24 17:00 |
Total Float (d): 72.0 |
Total float of 72d exceeds 44 days |
A1980 "23 25 00 - Buffer Tanks" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 72d exceeds 44 days) |
| A1590.1 |
26 09 23 - Lighting Control (R1) |
1.2.39 Electrical Power Distribution Shop Drawings |
2025-08-19 08:00 |
2025-09-02 17:00 |
Total Float (d): 71.0 |
Total float of 71d exceeds 44 days |
A1590.1 "26 09 23 - Lighting Control (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 71d exceeds 44 days) |
| A2180 |
26 09 23 - Lighting Control |
1.3.35 Electrical Power Distribution Equipment |
2025-09-03 08:00 |
2026-01-23 17:00 |
Total Float (d): 71.0 |
Total float of 71d exceeds 44 days |
A2180 "26 09 23 - Lighting Control" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 71d exceeds 44 days) |
| A2560 |
Below Grade Vapour Barrier Mock-up |
1 Phase 2 - Foundation Work |
2025-09-23 08:00 |
2025-09-23 17:00 |
Total Float (d): 71.0 |
Total float of 71d exceeds 44 days |
A2560 "Below Grade Vapour Barrier Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 71d exceeds 44 days) |
| A1970 |
23 21 23 - Pumps |
1.3.34 Mechanical Equipment |
2025-08-20 08:00 |
2026-01-12 17:00 |
Total Float (d): 70.0 |
Total float of 70d exceeds 44 days |
A1970 "23 21 23 - Pumps" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 70d exceeds 44 days) |
| A2160 |
27 10 00 - Structural Cabling System (Fiber Optic Cable) |
1.3.35 Electrical Power Distribution Equipment |
2025-07-23 08:00 |
2026-04-14 17:00 |
Total Float (d): 70.0 |
Total float of 70d exceeds 44 days |
A2160 "27 10 00 - Structural Cabling System (Fiber Optic Cable)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 70d exceeds 44 days) |
| A2570 |
Footing Vapor Barrier & Insulation |
1 Phase 2 - Foundation Work |
2025-09-23 08:00 |
2025-09-26 17:00 |
Total Float (d): 68.0 |
Total float of 68d exceeds 44 days |
A2570 "Footing Vapor Barrier & Insulation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 68d exceeds 44 days) |
| A2820 |
Glazing Site Measure and Scanning |
1.4.5.4.1 North Elevation |
2026-02-02 08:00 |
2026-02-02 17:00 |
Total Float (d): 68.0 |
Total float of 68d exceeds 44 days |
A2820 "Glazing Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 68d exceeds 44 days) |
| A2830 |
Glazing Shop Fabrication |
1.4.5.4.1 North Elevation |
2026-02-03 08:00 |
2026-03-02 17:00 |
Total Float (d): 68.0 |
Total float of 68d exceeds 44 days |
A2830 "Glazing Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 68d exceeds 44 days) |
| A1540.1 |
22 40 00 - Plumbing Fixtures (R1) |
1.2.38 Mechanical Equipment Shop Drawings |
2025-08-14 08:00 |
2025-08-27 17:00 |
Total Float (d): 64.0 |
Total float of 64d exceeds 44 days |
A1540.1 "22 40 00 - Plumbing Fixtures (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 64d exceeds 44 days) |
| A2130 |
22 40 00 - Plumbing Fixtures |
1.3.34 Mechanical Equipment |
2025-08-28 08:00 |
2026-01-20 17:00 |
Total Float (d): 64.0 |
Total float of 64d exceeds 44 days |
A2130 "22 40 00 - Plumbing Fixtures" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 64d exceeds 44 days) |
| A3680 |
Misc. Metals Mock-up |
1.4.5.5 Phase 5 - New Expansion Interior Finishes |
2026-05-13 08:00 |
2026-05-13 17:00 |
Total Float (d): 59.0 |
Total float of 59d exceeds 44 days |
A3680 "Misc. Metals Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 59d exceeds 44 days) |
| A1460.1 |
23 25 00 - Water Treatment (R1) |
1.2.38 Mechanical Equipment Shop Drawings |
2025-08-22 08:00 |
2025-09-05 17:00 |
Total Float (d): 58.0 |
Total float of 58d exceeds 44 days |
A1460.1 "23 25 00 - Water Treatment (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days) |
| A2050 |
23 25 00 - Water Treatment |
1.3.34 Mechanical Equipment |
2025-09-08 08:00 |
2026-01-28 17:00 |
Total Float (d): 58.0 |
Total float of 58d exceeds 44 days |
A2050 "23 25 00 - Water Treatment" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days) |
| A2810 |
Aluminum & Metal Panel Cladding Mock-up |
1.4.5.4.1 North Elevation |
2026-04-16 08:00 |
2026-04-16 17:00 |
Total Float (d): 58.0 |
Total float of 58d exceeds 44 days |
A2810 "Aluminum & Metal Panel Cladding Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days) |
| A2840 |
L1, L2, L3 Exterior Glazing Installation (W05) |
1.4.5.4.1 North Elevation |
2026-03-18 08:00 |
2026-04-15 17:00 |
Total Float (d): 58.0 |
Total float of 58d exceeds 44 days |
A2840 "L1, L2, L3 Exterior Glazing Installation (W05)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days) |
| A2850 |
Exterior Cladding Site Measure and Scanning |
1.4.5.4.1 North Elevation |
2026-04-16 08:00 |
2026-04-16 17:00 |
Total Float (d): 58.0 |
Total float of 58d exceeds 44 days |
A2850 "Exterior Cladding Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days) |
| A2860 |
Exterior Cladding Shop Fabrication |
1.4.5.4.1 North Elevation |
2026-04-17 08:00 |
2026-05-14 17:00 |
Total Float (d): 58.0 |
Total float of 58d exceeds 44 days |
A2860 "Exterior Cladding Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days) |
| A2870 |
L1, L2 & L3 Cladding Installation (EW2a) |
1.4.5.4.1 North Elevation |
2026-05-15 08:00 |
2026-06-12 17:00 |
Total Float (d): 58.0 |
Total float of 58d exceeds 44 days |
A2870 "L1, L2 & L3 Cladding Installation (EW2a)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days) |
| A3200 |
Roof Anchor System Installation |
1.4.5.4.5 Roofing |
2026-06-15 08:00 |
2026-06-19 17:00 |
Total Float (d): 58.0 |
Total float of 58d exceeds 44 days |
A3200 "Roof Anchor System Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days) |
| A4150 |
New Exterior Paved Areas and Sidewalks |
1.4.7 Exterior Works |
2026-05-04 08:00 |
2026-06-01 17:00 |
Total Float (d): 57.0 |
Total float of 57d exceeds 44 days |
A4150 "New Exterior Paved Areas and Sidewalks " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 57d exceeds 44 days) |
| A4160 |
Landscape Installations |
1.4.7 Exterior Works |
2026-06-02 08:00 |
2026-06-15 17:00 |
Total Float (d): 57.0 |
Total float of 57d exceeds 44 days |
A4160 "Landscape Installations" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 57d exceeds 44 days) |
| A3850 |
Foundations |
1.4.5.6 Phase 6 - Pedestrian Bridge Construction |
2025-09-10 08:00 |
2026-02-24 17:00 |
Total Float (d): 56.0 |
Total float of 56d exceeds 44 days |
A3850 "Foundations" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days) |
| A3860 |
Concrete Vertical Piers |
1.4.5.6 Phase 6 - Pedestrian Bridge Construction |
2026-02-25 08:00 |
2026-03-04 17:00 |
Total Float (d): 56.0 |
Total float of 56d exceeds 44 days |
A3860 "Concrete Vertical Piers" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days) |
| A3870 |
Removal of Existing Facade for Tie In |
1.4.5.6 Phase 6 - Pedestrian Bridge Construction |
2026-03-05 08:00 |
2026-03-06 17:00 |
Total Float (d): 56.0 |
Total float of 56d exceeds 44 days |
A3870 "Removal of Existing Facade for Tie In" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days) |
| A3880 |
Structural Steel erection including expansion plates |
1.4.5.6 Phase 6 - Pedestrian Bridge Construction |
2026-03-09 08:00 |
2026-03-27 17:00 |
Total Float (d): 56.0 |
Total float of 56d exceeds 44 days |
A3880 "Structural Steel erection including expansion plates " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days) |
| A3890 |
Envelope |
1.4.5.6 Phase 6 - Pedestrian Bridge Construction |
2026-03-30 08:00 |
2026-05-01 17:00 |
Total Float (d): 56.0 |
Total float of 56d exceeds 44 days |
A3890 "Envelope " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days) |
| A3900 |
Interior M&E Rough in |
1.4.5.6 Phase 6 - Pedestrian Bridge Construction |
2026-05-04 08:00 |
2026-05-15 17:00 |
Total Float (d): 56.0 |
Total float of 56d exceeds 44 days |
A3900 "Interior M&E Rough in " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days) |
| A3910 |
Interior Finishes |
1.4.5.6 Phase 6 - Pedestrian Bridge Construction |
2026-05-19 08:00 |
2026-05-19 17:00 |
Total Float (d): 56.0 |
Total float of 56d exceeds 44 days |
A3910 "Interior Finishes" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days) |
| A4720 |
Existing Column Reinforcement |
1.4.6.2 Machine Shop Area |
2025-10-23 08:00 |
2025-11-05 17:00 |
Total Float (d): 55.0 |
Total float of 55d exceeds 44 days |
A4720 "Existing Column Reinforcement" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 55d exceeds 44 days) |
| A4730 |
Steel Joist Reinforcement Installation |
1.4.6.2 Machine Shop Area |
2025-11-06 08:00 |
2025-11-26 17:00 |
Total Float (d): 55.0 |
Total float of 55d exceeds 44 days |
A4730 "Steel Joist Reinforcement Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 55d exceeds 44 days) |
| A3080 |
L1, L2 & L3 Air Vapor Barrier Inspection |
1.4.5.4.4 East Elevation |
2026-04-08 08:00 |
2026-04-08 08:00 |
Total Float (d): 54.0 |
Total float of 54d exceeds 44 days |
A3080 "L1, L2 & L3 Air Vapor Barrier Inspection" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 54d exceeds 44 days) |
| A2910 |
Glazing Site Measure and Scanning |
1.4.5.4.2 West Elevation |
2026-02-17 08:00 |
2026-02-17 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A2910 "Glazing Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A2920 |
Glazing Shop Fabrication |
1.4.5.4.2 West Elevation |
2026-02-18 08:00 |
2026-03-17 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A2920 "Glazing Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A2930 |
L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) |
1.4.5.4.2 West Elevation |
2026-03-18 08:00 |
2026-04-22 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A2930 "L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A2940 |
Exterior Cladding Site Measure and Scanning |
1.4.5.4.2 West Elevation |
2026-04-23 08:00 |
2026-04-23 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A2940 "Exterior Cladding Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A2950 |
Exterior Cladding Shop Fabrication |
1.4.5.4.2 West Elevation |
2026-04-24 08:00 |
2026-05-22 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A2950 "Exterior Cladding Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A2960 |
L2 & L3 Cladding Installation (EW2) |
1.4.5.4.2 West Elevation |
2026-05-25 08:00 |
2026-06-19 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A2960 "L2 & L3 Cladding Installation (EW2)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A2990 |
Glazing Site Measure and Scanning |
1.4.5.4.3 South Elevation |
2026-03-10 08:00 |
2026-03-10 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A2990 "Glazing Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A3000 |
Glazing Shop Fabrication |
1.4.5.4.3 South Elevation |
2026-03-11 08:00 |
2026-04-08 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A3000 "Glazing Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A3010 |
L2 & L3 Exterior Glazing Installation (W08a, W08b) |
1.4.5.4.3 South Elevation |
2026-04-09 08:00 |
2026-04-15 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A3010 "L2 & L3 Exterior Glazing Installation (W08a, W08b)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A3020 |
Exterior Cladding Site Measure and Scanning |
1.4.5.4.3 South Elevation |
2026-04-16 08:00 |
2026-04-16 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A3020 "Exterior Cladding Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A3030 |
Exterior Cladding Shop Fabrication |
1.4.5.4.3 South Elevation |
2026-04-17 08:00 |
2026-05-14 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A3030 "Exterior Cladding Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A3040 |
L2 & L3 Cladding Installation (EW2) |
1.4.5.4.3 South Elevation |
2026-05-15 08:00 |
2026-06-12 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A3040 "L2 & L3 Cladding Installation (EW2)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A3050 |
Horizontal Shading Louvers |
1.4.5.4.3 South Elevation |
2026-06-15 08:00 |
2026-06-19 17:00 |
Total Float (d): 53.0 |
Total float of 53d exceeds 44 days |
A3050 "Horizontal Shading Louvers" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days) |
| A1960 |
23 74 13 - Air Handling Units |
1.3.34 Mechanical Equipment |
2025-08-29 08:00 |
2026-05-15 17:00 |
Total Float (d): 52.0 |
Total float of 52d exceeds 44 days |
A1960 "23 74 13 - Air Handling Units" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 52d exceeds 44 days) |
| A5230 |
Footings and Piers Along GL-B.1 (Successor to CO-005) |
1 Phase 2 - Foundation Work |
2025-08-15 08:00 |
2025-08-21 17:00 |
Total Float (d): 52.0 |
Total float of 52d exceeds 44 days |
A5230 "Footings and Piers Along GL-B.1 (Successor to CO-005)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 52d exceeds 44 days) |
| A1470.1 |
23 37 13 - Diffuser and Grilles Shop Drawings (R1) |
1.2.38 Mechanical Equipment Shop Drawings |
2025-09-05 08:00 |
2025-09-18 17:00 |
Total Float (d): 49.0 |
Total float of 49d exceeds 44 days |
A1470.1 "23 37 13 - Diffuser and Grilles Shop Drawings (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 49d exceeds 44 days) |
| A2060 |
23 37 13 - Diffuser and Grilles |
1.3.34 Mechanical Equipment |
2025-09-19 08:00 |
2026-02-10 17:00 |
Total Float (d): 49.0 |
Total float of 49d exceeds 44 days |
A2060 "23 37 13 - Diffuser and Grilles" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 49d exceeds 44 days) |
| A1360.2 |
23 82 19 - Fan Coil Units (R2) |
1.2.38 Mechanical Equipment Shop Drawings |
2025-08-25 08:00 |
2025-09-08 17:00 |
Total Float (d): 48.0 |
Total float of 48d exceeds 44 days |
A1360.2 "23 82 19 - Fan Coil Units (R2)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 48d exceeds 44 days) |
| A2550x |
R6 - RFI 60 Sprinkler Diesel Pump |
1.4.2 Potential Schedule Impact (RISK) |
2025-08-21 08:00 |
2025-08-27 17:00 |
Total Float (d): 48.0 |
Total float of 48d exceeds 44 days |
A2550x "R6 - RFI 60 Sprinkler Diesel Pump " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 48d exceeds 44 days) |
| A2720 |
Tactile Attention Indicators Mock-up |
1.4.5.3 Phase 3 - Building Erection |
2026-01-28 08:00 |
2026-01-28 17:00 |
Total Float (d): 48.0 |
Total float of 48d exceeds 44 days |
A2720 "Tactile Attention Indicators Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 48d exceeds 44 days) |
| A3160 |
Roof Penetration Layout |
1.4.5.4.5 Roofing |
2025-12-15 08:00 |
2025-12-16 17:00 |
Total Float (d): 46.0 |
Total float of 46d exceeds 44 days |
A3160 "Roof Penetration Layout" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 46d exceeds 44 days) |
| A4580 |
New Columns Installation |
1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo |
2025-10-23 08:00 |
2025-11-05 17:00 |
Total Float (d): 45.0 |
Total float of 45d exceeds 44 days |
A4580 "New Columns Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 45d exceeds 44 days) |