Project
Ontario Community College - B2 (Demo Data)
The Ontario Community College schedule passes 5 of 13 scored DCMA criteria, earning an overall grade of F (38% compliance) with a RED status band. Criteria clearing their thresholds: C1, C4, C5, C7, C12.
The failing criteria are C2 Leads, C3 Lags, C6 High Float, C8 High Duration, C9 Valid Dates, C11 Missed Tasks, C13 CPLI, C14 BEI. Both forward-looking indices read CPLI 0.93 and BEI 0.61, and the schedule is trending toward +21 working-day overrun to 30-Sep-2026.
The schedule grades F (RED): 5 of 13 criteria pass. Failures cluster in C2, C3, C6, C8, C9, C11, C13, C14, where remediation is well defined and achievable before the next baseline re-issue.
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A2290 | Existing Structure Under Pinning | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 15-Jul-2025 | Lead (d): 2 | Has 2.0d lead from "Demolition of Existing Vestibule F100" |
| A2650 | Install Level 2 & 3 Decking | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.3 Phase 3 - Building Erection | 14-Nov-2025 | Lead (d): 5 | Has 5.0d lead from "Erect Structural Steel" |
| A3580 | Mech. & Plumbing rough-ins | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.5 Level 3 | 12-May-2026 | Lead (d): 15 | Has 15.0d lead from "Mech. & Plumbing rough-ins" |
| A3290 | Mech. & Plumbing rough-ins | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes / 1.4.5.5.3 Level 1 | 05-May-2026 | Lead (d): 5 | Has 5.0d lead from "New partition framing" |
| A3180 | Roof Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing | 03-Feb-2026 | Lead (d): 1 | Has 1.0d lead from "Install Built-up Roof" |
| A2620 | Structural Steel Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.3 Phase 3 - Building Erection | 31-Oct-2025 | Lead (d): 1 | Has 1.0d lead from "Erect Structural Steel" |
| A2580 | Underground Drainage | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 07-Nov-2025 | Lead (d): 10 | Has 10.0d lead from "Erect Structural Steel" |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A1370x | Metal Shelving | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 23-Jun-2025 | Lag (d): 60 | Lag of 60.0d from "Subcontract Award" exceeds 44 work days |
| Activity ID | Activity Name | WBS | Forecast Finish | Total Float (wd) | Issue |
|---|---|---|---|---|---|
| A3850 | Foundations | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 24-Feb-2026 | 56 | Total float of 56d exceeds 44 days |
| A3860 | Concrete Vertical Piers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 04-Mar-2026 | 56 | Total float of 56d exceeds 44 days |
| A3870 | Removal of Existing Facade for Tie In | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 06-Mar-2026 | 56 | Total float of 56d exceeds 44 days |
| A3880 | Structural Steel erection including expansion plates | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 27-Mar-2026 | 56 | Total float of 56d exceeds 44 days |
| A3890 | Envelope | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 01-May-2026 | 56 | Total float of 56d exceeds 44 days |
| A3900 | Interior M&E Rough in | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 15-May-2026 | 56 | Total float of 56d exceeds 44 days |
| A3910 | Interior Finishes | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 19-May-2026 | 56 | Total float of 56d exceeds 44 days |
| A4150 | New Exterior Paved Areas and Sidewalks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.7 Exterior Works | 01-Jun-2026 | 57 | Total float of 57d exceeds 44 days |
| A4160 | Landscape Installations | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.7 Exterior Works | 15-Jun-2026 | 57 | Total float of 57d exceeds 44 days |
| A2930 | L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 22-Apr-2026 | 53 | Total float of 53d exceeds 44 days |
| A2890 | L1 Masonry Wall Installation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 21-Apr-2026 | 95 | Total float of 95d exceeds 44 days |
| A2770 | L1 Masonry Wall installation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 14-Apr-2026 | 95 | Total float of 95d exceeds 44 days |
| A2840 | L1, L2, L3 Exterior Glazing Installation (W05) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 15-Apr-2026 | 58 | Total float of 58d exceeds 44 days |
| A2960 | L2 & L3 Cladding Installation (EW2) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 19-Jun-2026 | 53 | Total float of 53d exceeds 44 days |
| A2870 | L1, L2 & L3 Cladding Installation (EW2a) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 12-Jun-2026 | 58 | Total float of 58d exceeds 44 days |
| A3010 | L2 & L3 Exterior Glazing Installation (W08a, W08b) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 15-Apr-2026 | 53 | Total float of 53d exceeds 44 days |
| A3040 | L2 & L3 Cladding Installation (EW2) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 12-Jun-2026 | 53 | Total float of 53d exceeds 44 days |
| A3050 | Horizontal Shading Louvers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 19-Jun-2026 | 53 | Total float of 53d exceeds 44 days |
| A4540 | Interior Demoilition | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 28-Jan-2026 | 170 | Total float of 170d exceeds 44 days |
| A3940 | Existing Slab Removal and Trenching | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 09-Sep-2025 | 253 | Total float of 253d exceeds 44 days |
| A4010 | Underground Plumbing Rough-ins | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 15-Jul-2025 | 150 | Total float of 150d exceeds 44 days |
| A4760 | Trench Backfill | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 22-Jul-2025 | 150 | Total float of 150d exceeds 44 days |
| A1140 | Millwork Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 29-Jul-2025 | 228 | Total float of 228d exceeds 44 days |
| A1170 | Air Barrier System Data Sheet and Mockup | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 08-Jul-2025 | 159 | Total float of 159d exceeds 44 days |
| A1180 | Exterior Wall Cladding Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 22-Aug-2025 | 181 | Total float of 181d exceeds 44 days |
| A1200 | Hollow Metal Frames & Doors Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 29-Jul-2025 | 162 | Total float of 162d exceeds 44 days |
| A1210 | Interior Aluminum Screen | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 08-Aug-2025 | 141 | Total float of 141d exceeds 44 days |
| A1240 | Aluminum Framed Glazing System Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 06-Aug-2025 | 131 | Total float of 131d exceeds 44 days |
| A1250 | Finished Hardware Schedule | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 29-Jul-2025 | 132 | Total float of 132d exceeds 44 days |
| A1260 | Stud framing and Gypsum Board Data Sheets | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 29-Jul-2025 | 118 | Total float of 118d exceeds 44 days |
| A1270 | Tiling Data sheet and samples | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 29-Jul-2025 | 213 | Total float of 213d exceeds 44 days |
| A1300 | Flooring Data Sheets and Samples | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 29-Jul-2025 | 183 | Total float of 183d exceeds 44 days |
| A1310 | Paint Drawdowns | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 29-Jul-2025 | 212 | Total float of 212d exceeds 44 days |
| A1320 | Washroom accessories and Partitions Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 29-Jul-2025 | 228 | Total float of 228d exceeds 44 days |
| A1350 | Sprinkler & Standpipe Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 15-Jul-2025 | 192 | Total float of 192d exceeds 44 days |
| A1610 | Concrete Mix for Hardscapes | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 06-Aug-2025 | 238 | Total float of 238d exceeds 44 days |
| A1620 | Landscape Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 06-Aug-2025 | 203 | Total float of 203d exceeds 44 days |
| A1670 | Masonry and Mortar | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 25-Aug-2025 | 253 | Total float of 253d exceeds 44 days |
| A1700 | Cold-formed Metal Framing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 07-Aug-2025 | 117 | Total float of 117d exceeds 44 days |
| A1720 | Millwork | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 09-Oct-2025 | 228 | Total float of 228d exceeds 44 days |
| A1730 | Built-up Roofing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 21-Aug-2025 | 127 | Total float of 127d exceeds 44 days |
| A1740 | TPO Roofing (Bridge) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 08-Oct-2025 | 173 | Total float of 173d exceeds 44 days |
| A1750 | Air Barrier System | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 22-Jul-2025 | 159 | Total float of 159d exceeds 44 days |
| A1760 | Exterior Wall Cladding | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 18-Nov-2025 | 181 | Total float of 181d exceeds 44 days |
| A1770 | Fire-resistive Material | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 07-Aug-2025 | 161 | Total float of 161d exceeds 44 days |
| A1780 | Hollow Metal Frames | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 25-Sep-2025 | 162 | Total float of 162d exceeds 44 days |
| A1800 | Interior Aluminum Screens | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 16-Dec-2025 | 141 | Total float of 141d exceeds 44 days |
| A1810 | Flush Wood Doors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 12-Dec-2025 | 127 | Total float of 127d exceeds 44 days |
| A1820 | Coiling Doors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 14-Jan-2026 | 106 | Total float of 106d exceeds 44 days |
| A1830 | Aluminum Framed Glazing Systems | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 28-Nov-2025 | 131 | Total float of 131d exceeds 44 days |
| A1840 | Finished Hardware | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 05-Dec-2025 | 132 | Total float of 132d exceeds 44 days |
| A1850 | Stud framing & gypsum board | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 06-Aug-2025 | 118 | Total float of 118d exceeds 44 days |
| A1860 | Tiling | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 11-Sep-2025 | 213 | Total float of 213d exceeds 44 days |
| A1870 | ACT & ACB | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 17-Oct-2025 | 156 | Total float of 156d exceeds 44 days |
| A1890 | Flooring | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 24-Oct-2025 | 183 | Total float of 183d exceeds 44 days |
| A1900 | Paint Drawdowns | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 13-Aug-2025 | 212 | Total float of 212d exceeds 44 days |
| A1910 | Washroom accessories and Partitions | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 04-Sep-2025 | 228 | Total float of 228d exceeds 44 days |
| A1930 | Hydraulic Lift | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 01-Dec-2025 | 141 | Total float of 141d exceeds 44 days |
| A1940 | Sprinkler & Standpipe Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 06-Aug-2025 | 192 | Total float of 192d exceeds 44 days |
| A2200 | Concrete for Hardscape | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 13-Aug-2025 | 238 | Total float of 238d exceeds 44 days |
| A2210 | Landscape (unit pavers, furniture, etc) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 31-Oct-2025 | 203 | Total float of 203d exceeds 44 days |
| A4530 | Electrical and Mechanical Make Safe | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 14-Jan-2026 | 170 | Total float of 170d exceeds 44 days |
| A1790 | Hollow Metal Doors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 24-Oct-2025 | 162 | Total float of 162d exceeds 44 days |
| A3160 | Roof Penetration Layout | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing | 16-Dec-2025 | 46 | Total float of 46d exceeds 44 days |
| A2850 | Exterior Cladding Site Measure and Scanning | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 16-Apr-2026 | 58 | Total float of 58d exceeds 44 days |
| A2820 | Glazing Site Measure and Scanning | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 02-Feb-2026 | 68 | Total float of 68d exceeds 44 days |
| A2830 | Glazing Shop Fabrication | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 02-Mar-2026 | 68 | Total float of 68d exceeds 44 days |
| A2860 | Exterior Cladding Shop Fabrication | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 14-May-2026 | 58 | Total float of 58d exceeds 44 days |
| A2910 | Glazing Site Measure and Scanning | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 17-Feb-2026 | 53 | Total float of 53d exceeds 44 days |
| A2920 | Glazing Shop Fabrication | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 17-Mar-2026 | 53 | Total float of 53d exceeds 44 days |
| A2940 | Exterior Cladding Site Measure and Scanning | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 23-Apr-2026 | 53 | Total float of 53d exceeds 44 days |
| A2950 | Exterior Cladding Shop Fabrication | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.2 West Elevation | 22-May-2026 | 53 | Total float of 53d exceeds 44 days |
| A3000 | Glazing Shop Fabrication | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 08-Apr-2026 | 53 | Total float of 53d exceeds 44 days |
| A2990 | Glazing Site Measure and Scanning | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 10-Mar-2026 | 53 | Total float of 53d exceeds 44 days |
| A3020 | Exterior Cladding Site Measure and Scanning | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 16-Apr-2026 | 53 | Total float of 53d exceeds 44 days |
| A3030 | Exterior Cladding Shop Fabrication | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.3 South Elevation | 14-May-2026 | 53 | Total float of 53d exceeds 44 days |
| A3200 | Roof Anchor System Installation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing | 19-Jun-2026 | 58 | Total float of 58d exceeds 44 days |
| A2220 | Testing and Inspection Cash Allowance Expenditure | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 02-Jul-2025 | 89 | Total float of 89d exceeds 44 days |
| A2760 | Masonry Mock-up | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 13-Apr-2026 | 96 | Total float of 96d exceeds 44 days |
| A3680 | Misc. Metals Mock-up | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.5 Phase 5 - New Expansion Interior Finishes | 13-May-2026 | 59 | Total float of 59d exceeds 44 days |
| A2780 | Above Grade Vapour Mock-up | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 02-Feb-2026 | 129 | Total float of 129d exceeds 44 days |
| A2810 | Aluminum & Metal Panel Cladding Mock-up | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 16-Apr-2026 | 58 | Total float of 58d exceeds 44 days |
| A2720 | Tactile Attention Indicators Mock-up | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.3 Phase 3 - Building Erection | 28-Jan-2026 | 48 | Total float of 48d exceeds 44 days |
| A3180 | Roof Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.5 Roofing | 03-Feb-2026 | 123 | Total float of 123d exceeds 44 days |
| A2800 | AVB Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.1 North Elevation | 02-Feb-2026 | 87 | Total float of 87d exceeds 44 days |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.4 Phase 4 - Building Envelope / 1.4.5.4.4 East Elevation | 08-Apr-2026 | 54 | Total float of 54d exceeds 44 days |
| A1960 | 23 74 13 - Air Handling Units | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 15-May-2026 | 52 | Total float of 52d exceeds 44 days |
| A1970 | 23 21 23 - Pumps | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Jan-2026 | 70 | Total float of 70d exceeds 44 days |
| A1980 | 23 25 00 - Buffer Tanks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 24-Dec-2025 | 72 | Total float of 72d exceeds 44 days |
| A1990 | 23 21 16 - Air Separator | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | 112 | Total float of 112d exceeds 44 days |
| A2000 | 23 21 16 - Expansion Tanks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | 112 | Total float of 112d exceeds 44 days |
| A2010 | 23 57 00 - Heat Exchangers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | 112 | Total float of 112d exceeds 44 days |
| A2020 | 22 33 00 - Electric Domestic Water Heaters | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | 112 | Total float of 112d exceeds 44 days |
| A2030 | 23 81 26 - Split System | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 17-Nov-2025 | 108 | Total float of 108d exceeds 44 days |
| A2040 | 22 13 29 - Sump Pumps | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 08-Aug-2025 | 177 | Total float of 177d exceeds 44 days |
| A2060 | 23 37 13 - Diffuser and Grilles | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 10-Feb-2026 | 49 | Total float of 49d exceeds 44 days |
| A2070 | 23 00 00 - Exhaust Fans | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Dec-2025 | 154 | Total float of 154d exceeds 44 days |
| A2080 | 23 00 00 - Unit Heater | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Dec-2025 | 85 | Total float of 85d exceeds 44 days |
| A2100 | 23 00 00 - Wall Fin Heater | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Dec-2025 | 85 | Total float of 85d exceeds 44 days |
| A2120 | 20 05 10 - Electric Heat Tracing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 19-Jan-2026 | 134 | Total float of 134d exceeds 44 days |
| A2130 | 22 40 00 - Plumbing Fixtures | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 20-Jan-2026 | 64 | Total float of 64d exceeds 44 days |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Nov-2025 | 109 | Total float of 109d exceeds 44 days |
| A2190 | 28 31 00 - Fire Alarm | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 27-Oct-2025 | 123 | Total float of 123d exceeds 44 days |
| A2150 | 26 50 00 - Lighting Fixtures | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 25-Dec-2025 | 81 | Total float of 81d exceeds 44 days |
| A2180 | 26 09 23 - Lighting Control | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 23-Jan-2026 | 71 | Total float of 71d exceeds 44 days |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Apr-2026 | 70 | Total float of 70d exceeds 44 days |
| 2170 | 26 50 00 - Emergency Lighting & Exit Signs | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 05-Dec-2025 | 104 | Total float of 104d exceeds 44 days |
| A1360.2 | 23 82 19 - Fan Coil Units (R2) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 08-Sep-2025 | 48 | Total float of 48d exceeds 44 days |
| A1470.1 | 23 37 13 - Diffuser and Grilles Shop Drawings (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 18-Sep-2025 | 49 | Total float of 49d exceeds 44 days |
| A1480.1 | 23 00 00 - Exhaust Fans (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 29-Sep-2025 | 254 | Total float of 254d exceeds 44 days |
| A1530.1 | 20 05 10 - Electric Heat Tracing (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 26-Aug-2025 | 134 | Total float of 134d exceeds 44 days |
| A1540.1 | 22 40 00 - Plumbing Fixtures (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 27-Aug-2025 | 64 | Total float of 64d exceeds 44 days |
| A1590.1 | 26 09 23 - Lighting Control (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 02-Sep-2025 | 71 | Total float of 71d exceeds 44 days |
| A4370 | Underground Mechanical Installation (DCW, Sprinkler) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 23-Sep-2025 | 253 | Total float of 253d exceeds 44 days |
| A4380 | Backfilling and Concrete for SOG | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 30-Sep-2025 | 253 | Total float of 253d exceeds 44 days |
| A4510 | Metal Shelving Installation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 26-Aug-2025 | 93 | Total float of 93d exceeds 44 days |
| A4560 | Review Interferences with Steel Joist | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 08-Jul-2025 | 128 | Total float of 128d exceeds 44 days |
| A4570 | Joist Interferences Relocation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 22-Aug-2025 | 279 | Total float of 279d exceeds 44 days |
| A4600 | Stud Framing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 26-Feb-2026 | 86 | Total float of 86d exceeds 44 days |
| A4610 | MEP Rough-ins | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 05-Mar-2026 | 86 | Total float of 86d exceeds 44 days |
| A4620 | Plywood Blocking | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 10-Mar-2026 | 86 | Total float of 86d exceeds 44 days |
| A4630 | Drywall Installation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 13-Mar-2026 | 86 | Total float of 86d exceeds 44 days |
| A4640 | Taping Drywall | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 20-Mar-2026 | 86 | Total float of 86d exceeds 44 days |
| A4550 | Existing Exterior Wall Demo (New Building Must be Erected and Enclosed) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 23-Feb-2026 | 86 | Total float of 86d exceeds 44 days |
| A4660 | Setup Temporary Hoarding | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area | 25-Mar-2026 | 86 | Total float of 86d exceeds 44 days |
| A4670 | Electrical and Mechanical Make Safe | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area | 27-Mar-2026 | 86 | Total float of 86d exceeds 44 days |
| A4680 | Interior Demoilition | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area | 06-Apr-2026 | 86 | Total float of 86d exceeds 44 days |
| A4700 | Review Interferences with Steel Joist | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area | 18-Aug-2025 | 91 | Total float of 91d exceeds 44 days |
| A4730 | Steel Joist Reinforcement Installation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area | 26-Nov-2025 | 55 | Total float of 55d exceeds 44 days |
| A4770 | Concrete Slab Infill | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 06-Aug-2025 | 150 | Total float of 150d exceeds 44 days |
| A4580 | New Columns Installation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 05-Nov-2025 | 45 | Total float of 45d exceeds 44 days |
| A4720 | Existing Column Reinforcement | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area | 05-Nov-2025 | 55 | Total float of 55d exceeds 44 days |
| A4780 | New Columns Installation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 13-Aug-2025 | 150 | Total float of 150d exceeds 44 days |
| A4790 | Existing Column Reinforcement | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 20-Aug-2025 | 150 | Total float of 150d exceeds 44 days |
| A4800 | Flatness Survey @ Floor Slab | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 22-Aug-2025 | 150 | Total float of 150d exceeds 44 days |
| A4810 | Self Levelling | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) | 03-Sep-2025 | 150 | Total float of 150d exceeds 44 days |
| A2090x | Metal Shelving | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 21-Aug-2025 | 93 | Total float of 93d exceeds 44 days |
| A4650 | Painting | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo | 24-Mar-2026 | 86 | Total float of 86d exceeds 44 days |
| A4690 | Electrical Fixtures | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.3 Phase 3 - Assembly Area | 13-Apr-2026 | 86 | Total float of 86d exceeds 44 days |
| A4710 | Relocation of Interferences | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.2 Machine Shop Area | 29-Aug-2025 | 91 | Total float of 91d exceeds 44 days |
| A2550x | R6 - RFI 60 Sprinkler Diesel Pump | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 27-Aug-2025 | 48 | Total float of 48d exceeds 44 days |
| A1380x | Metal Shelving (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 23-Jul-2025 | 93 | Total float of 93d exceeds 44 days |
| A1460.1 | 23 25 00 - Water Treatment (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 05-Sep-2025 | 58 | Total float of 58d exceeds 44 days |
| A2050 | 23 25 00 - Water Treatment | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 28-Jan-2026 | 58 | Total float of 58d exceeds 44 days |
| A2420 | Form and Pour North Exit Stair | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 30-Sep-2025 | 116 | Total float of 116d exceeds 44 days |
| A2480 | Concrete for Remaining Pad Footings (Ramp) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 02-Jul-2025 | 316 | Total float of 316d exceeds 44 days |
| A5230 | Footings and Piers Along GL-B.1 (Successor to CO-005) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 21-Aug-2025 | 52 | Total float of 52d exceeds 44 days |
| A2560 | Below Grade Vapour Barrier Mock-up | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 23-Sep-2025 | 71 | Total float of 71d exceeds 44 days |
| A2570 | Footing Vapor Barrier & Insulation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 26-Sep-2025 | 68 | Total float of 68d exceeds 44 days |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A3850 | Foundations | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.6 Phase 6 - Pedestrian Bridge Construction | 24-Feb-2026 | Duration (d): 116 | Duration of 116d exceeds 44 days |
| A1710 | Misc. Metals | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 27-Jan-2026 | Duration (d): 80 | Duration of 80d exceeds 44 days |
| A1720 | Millwork | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 09-Oct-2025 | Duration (d): 51 | Duration of 51d exceeds 44 days |
| A1760 | Exterior Wall Cladding | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 18-Nov-2025 | Duration (d): 60 | Duration of 60d exceeds 44 days |
| A1800 | Interior Aluminum Screens | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 16-Dec-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A1810 | Flush Wood Doors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 12-Dec-2025 | Duration (d): 75 | Duration of 75d exceeds 44 days |
| A1820 | Coiling Doors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 14-Jan-2026 | Duration (d): 100 | Duration of 100d exceeds 44 days |
| A1830 | Aluminum Framed Glazing Systems | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 28-Nov-2025 | Duration (d): 80 | Duration of 80d exceeds 44 days |
| A1840 | Finished Hardware | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 05-Dec-2025 | Duration (d): 91 | Duration of 91d exceeds 44 days |
| A1890 | Flooring | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 24-Oct-2025 | Duration (d): 61 | Duration of 61d exceeds 44 days |
| A1920 | Fall Arrest Anchors and Horizontal Lines | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 21-Nov-2025 | Duration (d): 60 | Duration of 60d exceeds 44 days |
| A1930 | Hydraulic Lift | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 01-Dec-2025 | Duration (d): 101 | Duration of 101d exceeds 44 days |
| A2210 | Landscape (unit pavers, furniture, etc) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 31-Oct-2025 | Duration (d): 60 | Duration of 60d exceeds 44 days |
| A1790 | Hollow Metal Doors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 24-Oct-2025 | Duration (d): 61 | Duration of 61d exceeds 44 days |
| A1950 | 23 82 19 - Fan Coil Units | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 06-Mar-2026 | Duration (d): 109 | Duration of 109d exceeds 44 days |
| A1960 | 23 74 13 - Air Handling Units | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 15-May-2026 | Duration (d): 180 | Duration of 180d exceeds 44 days |
| A1970 | 23 21 23 - Pumps | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 12-Jan-2026 | Duration (d): 100 | Duration of 100d exceeds 44 days |
| A1980 | 23 25 00 - Buffer Tanks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 24-Dec-2025 | Duration (d): 120 | Duration of 120d exceeds 44 days |
| A1990 | 23 21 16 - Air Separator | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2000 | 23 21 16 - Expansion Tanks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2010 | 23 57 00 - Heat Exchangers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2020 | 22 33 00 - Electric Domestic Water Heaters | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2030 | 23 81 26 - Split System | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 17-Nov-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2060 | 23 37 13 - Diffuser and Grilles | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 10-Feb-2026 | Duration (d): 100 | Duration of 100d exceeds 44 days |
| A2070 | 23 00 00 - Exhaust Fans | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Dec-2025 | Duration (d): 72 | Duration of 72d exceeds 44 days |
| A2080 | 23 00 00 - Unit Heater | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Dec-2025 | Duration (d): 78 | Duration of 78d exceeds 44 days |
| A2090 | 23 52 16 - Heating Boilers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Feb-2026 | Duration (d): 100 | Duration of 100d exceeds 44 days |
| A2100 | 23 00 00 - Wall Fin Heater | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 18-Dec-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2110 | 23 74 13 - Air Source Heat Pump | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 05-Jun-2026 | Duration (d): 224 | Duration of 224d exceeds 44 days |
| A2120 | 20 05 10 - Electric Heat Tracing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 19-Jan-2026 | Duration (d): 100 | Duration of 100d exceeds 44 days |
| A2130 | 22 40 00 - Plumbing Fixtures | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 20-Jan-2026 | Duration (d): 100 | Duration of 100d exceeds 44 days |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Nov-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2190 | 28 31 00 - Fire Alarm | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 27-Oct-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2150 | 26 50 00 - Lighting Fixtures | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 25-Dec-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2180 | 26 09 23 - Lighting Control | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 23-Jan-2026 | Duration (d): 100 | Duration of 100d exceeds 44 days |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Apr-2026 | Duration (d): 183 | Duration of 183d exceeds 44 days |
| 2170 | 26 50 00 - Emergency Lighting & Exit Signs | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 05-Dec-2025 | Duration (d): 90 | Duration of 90d exceeds 44 days |
| A2050 | 23 25 00 - Water Treatment | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 28-Jan-2026 | Duration (d): 100 | Duration of 100d exceeds 44 days |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| 2170 | 26 50 00 - Emergency Lighting & Exit Signs | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 05-Dec-2025 | Actual start (2025-07-30) after status date (2025-07-01) | |
| A1060 | Foundation Concrete Rebar Shop Drawing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 08-Jul-2025 | Actual finish (2025-07-08) after status date (2025-07-01) | |
| A1080 | Bentonite Waterstop Data Sheet | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 02-Jul-2025 | Actual finish (2025-07-02) after status date (2025-07-01) | |
| A1090 | Masonry and Mortar Samples & Data Sheets | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 18-Aug-2025 | Actual finish (2025-08-18) after status date (2025-07-01) | |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 14-Jul-2025 | Actual finish (2025-07-14) after status date (2025-07-01) | |
| A1100.1 | Structural Steel Framing and Steel Deck Shop Drawings (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 25-Aug-2025 | Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-25) after status date (2025-07-01) | |
| A1100.2 | Structural Steel Framing and Steel Deck Shop Drawings (R2) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 04-Sep-2025 | Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A1110 | Structural Reinforcement + Decking Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 01-Aug-2025 | Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-01) after status date (2025-07-01) | |
| A1120 | Cold-formed Metal Framing Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 23-Jul-2025 | Actual finish (2025-07-23) after status date (2025-07-01) | |
| A1130 | Misc. Metals Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 02-Oct-2025 | Actual start (2025-08-26) after status date (2025-07-01) | |
| A1150 | Built-up Roofing Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 09-Jul-2025 | Actual finish (2025-07-09) after status date (2025-07-01) | |
| A1160 | TPO Roofing Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 26-Aug-2025 | Actual start (2025-07-09) after status date (2025-07-01) | Actual finish (2025-08-26) after status date (2025-07-01) | |
| A1180 | Exterior Wall Cladding Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 22-Aug-2025 | Actual start (2025-08-11) after status date (2025-07-01) | |
| A1190 | Fire-resistive Material Data Sheet | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 09-Jul-2025 | Actual finish (2025-07-09) after status date (2025-07-01) | |
| A1210 | Interior Aluminum Screen | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 08-Aug-2025 | Actual start (2025-07-25) after status date (2025-07-01) | |
| A1220 | Flush Wood Doors Sample | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 27-Aug-2025 | Actual start (2025-08-26) after status date (2025-07-01) | Actual finish (2025-08-27) after status date (2025-07-01) | |
| A1230 | Coiling Doors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 21-Aug-2025 | Actual start (2025-08-05) after status date (2025-07-01) | Actual finish (2025-08-21) after status date (2025-07-01) | |
| A12380.1 | 23 21 23 - Pumps (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 19-Aug-2025 | Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-19) after status date (2025-07-01) | |
| A1280 | ACT Data sheet and Sample | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 27-Aug-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-08-27) after status date (2025-07-01) | |
| A1280.1 | ACB Data sheet and Sample | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 04-Sep-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A1290 | Suspended Metal Soffits | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 04-Sep-2025 | Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A1330 | Fall Arrest Anchors and Horizontal Lines | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 27-Aug-2025 | Actual start (2025-08-14) after status date (2025-07-01) | |
| A1340 | Hydraulic Lift Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 09-Jul-2025 | Actual finish (2025-07-09) after status date (2025-07-01) | |
| A1360 | 23 82 19 - Fan Coil Units (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1360.1 | 23 82 19 - Fan Coil Units (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A1360.2 | 23 82 19 - Fan Coil Units (R2) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 08-Sep-2025 | Actual start (2025-08-25) after status date (2025-07-01) | |
| A1370 | 23 74 13 - Air Handling Units (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 21-Jul-2025 | Actual finish (2025-07-21) after status date (2025-07-01) | |
| A1370,1 | 23 74 13 - Air Handling Units (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 28-Aug-2025 | Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-28) after status date (2025-07-01) | |
| A1380 | 23 21 23 - Pumps (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 04-Jul-2025 | Actual finish (2025-07-04) after status date (2025-07-01) | |
| A1390 | 23 25 00 - Buffer Tanks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1400 | 23 21 16 - Air Separator | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1410 | 23 21 16 - Expansion Tanks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1420 | 23 57 00 - Heat Exchangers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1430 | 22 33 00 - Electric Domestic Water Heaters | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 03-Jul-2025 | Actual finish (2025-07-03) after status date (2025-07-01) | |
| A1460 | 23 25 00 - Water Treatment (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A1460.1 | 23 25 00 - Water Treatment (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 05-Sep-2025 | Actual start (2025-08-22) after status date (2025-07-01) | |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 14-Aug-2025 | Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-08-14) after status date (2025-07-01) | |
| A1470.1 | 23 37 13 - Diffuser and Grilles Shop Drawings (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 18-Sep-2025 | Actual start (2025-09-05) after status date (2025-07-01) | |
| A1480.1 | 23 00 00 - Exhaust Fans (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 29-Sep-2025 | Actual start (2025-09-16) after status date (2025-07-01) | |
| A1500 | 23 52 16 - Heating Boilers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 25-Sep-2025 | Actual start (2025-09-12) after status date (2025-07-01) | |
| A1510 | 23 00 00 - Wall Fin Heater | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 12-Aug-2025 | Actual start (2025-07-09) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 31-Jul-2025 | Actual start (2025-07-11) after status date (2025-07-01) | Actual finish (2025-07-31) after status date (2025-07-01) | |
| A1540.1 | 22 40 00 - Plumbing Fixtures (R1) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.38 Mechanical Equipment Shop Drawings | 27-Aug-2025 | Actual start (2025-08-14) after status date (2025-07-01) | |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 08-Jul-2025 | Actual finish (2025-07-08) after status date (2025-07-01) | |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 29-Jul-2025 | Actual finish (2025-07-29) after status date (2025-07-01) | |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 22-Jul-2025 | Actual start (2025-07-11) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) | |
| A1580 | 26 50 00 - Lighting Fixtures | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 18-Aug-2025 | Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-18) after status date (2025-07-01) | |
| A1590 | 26 09 23 - Lighting Control (R0) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 18-Aug-2025 | Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-18) after status date (2025-07-01) | |
| A1660 | Bentonite Waterstop | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 09-Jul-2025 | Actual start (2025-07-03) after status date (2025-07-01) | Actual finish (2025-07-09) after status date (2025-07-01) | |
| A1680 | Structural Steel | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 01-Oct-2025 | Actual start (2025-09-04) after status date (2025-07-01) | |
| A1980 | 23 25 00 - Buffer Tanks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 24-Dec-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A1990 | 23 21 16 - Air Separator | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A2000 | 23 21 16 - Expansion Tanks | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A2010 | 23 57 00 - Heat Exchangers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A2020 | 22 33 00 - Electric Domestic Water Heaters | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 11-Nov-2025 | Actual start (2025-07-04) after status date (2025-07-01) | |
| A2030 | 23 81 26 - Split System | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.34 Mechanical Equipment | 17-Nov-2025 | Actual start (2025-07-10) after status date (2025-07-01) | |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Nov-2025 | Actual start (2025-07-09) after status date (2025-07-01) | |
| A2150 | 26 50 00 - Lighting Fixtures | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 25-Dec-2025 | Actual start (2025-08-19) after status date (2025-07-01) | |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement / 1.3.35 Electrical Power Distribution Equipment | 14-Apr-2026 | Actual start (2025-07-23) after status date (2025-07-01) | |
| A2280 | Under Pinning Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 14-Jul-2025 | Actual finish (2025-07-14) after status date (2025-07-01) | |
| A2290 | Existing Structure Under Pinning | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 15-Jul-2025 | Actual finish (2025-07-15) after status date (2025-07-01) | |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 07-Jul-2025 | Actual finish (2025-07-07) after status date (2025-07-01) | |
| A2360 | Ductbank Shoring | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 08-Jul-2025 | Actual finish (2025-07-08) after status date (2025-07-01) | |
| A2370 | Bulk Excavation to U/S of Footings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 22-Jul-2025 | Actual start (2025-07-16) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) | |
| A2380 | Bulk Excavation to U/S North Stair Footing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 23-Jul-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) | |
| A2390 | Subgrade Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 22-Jul-2025 | Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) | |
| A2400 | Subgrade Preparation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 23-Jul-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) | |
| A2410 | Soil Bearing Capacity Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 24-Jul-2025 | Actual start (2025-07-24) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) | |
| A2410x | RFI #17 Demo Clarification | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 11-Jul-2025 | Actual finish (2025-07-11) after status date (2025-07-01) | |
| A2420 | Form and Pour North Exit Stair | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 30-Sep-2025 | Actual start (2025-08-04) after status date (2025-07-01) | |
| A2420x | PC-002 Demo Clarification Issuance | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 14-Jul-2025 | Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-14) after status date (2025-07-01) | |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 23-Jul-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) | |
| A2430x | PCO-008 (Quote) Submission | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 24-Jul-2025 | Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) | |
| A2440x | CO-005 Issuance | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 07-Aug-2025 | Actual start (2025-07-25) after status date (2025-07-01) | Actual finish (2025-08-07) after status date (2025-07-01) | |
| A2450 | Rebar for Pad Footings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 24-Jul-2025 | Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) | |
| A2450x | CD-01 Water Room Demo (Elec. FACP) Issuance | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 18-Jul-2025 | Actual start (2025-07-18) after status date (2025-07-01) | Actual finish (2025-07-18) after status date (2025-07-01) | |
| A2460 | Rebar Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 25-Jul-2025 | Actual start (2025-07-25) after status date (2025-07-01) | Actual finish (2025-07-25) after status date (2025-07-01) | |
| A2460x | CD-01 Fire Alarm Panel Relocation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 24-Jul-2025 | Actual start (2025-07-24) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) | |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 28-Jul-2025 | Actual start (2025-07-28) after status date (2025-07-01) | Actual finish (2025-07-28) after status date (2025-07-01) | |
| A2470x | Water Room Block Wall Demo | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 12-Aug-2025 | Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) | |
| A2480x | Existing Vestibule Slab Cutting | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 13-Aug-2025 | Actual start (2025-08-13) after status date (2025-07-01) | Actual finish (2025-08-13) after status date (2025-07-01) | |
| A2490 | Concrete Field Testing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 28-Jul-2025 | Actual start (2025-07-28) after status date (2025-07-01) | Actual finish (2025-07-28) after status date (2025-07-01) | |
| A2490x | Existing Vestibule Slab Removal | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.1 Change Orders / 1.4.1.1 Change Order 005 - PC 002 Demo Clarification | 14-Aug-2025 | Actual start (2025-08-14) after status date (2025-07-01) | Actual finish (2025-08-14) after status date (2025-07-01) | |
| A2500 | Install Rebar for Piers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 08-Sep-2025 | Actual start (2025-07-29) after status date (2025-07-01) | Actual finish (2025-09-08) after status date (2025-07-01) | |
| A2500x | R1 - RFI #19 & 20 – Existing DCW and Sanitary Line | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 27-Aug-2025 | Actual finish (2025-08-27) after status date (2025-07-01) | |
| A2510 | Supply of Embedment & Ankors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 22-Aug-2025 | Actual start (2025-08-22) after status date (2025-07-01) | Actual finish (2025-08-22) after status date (2025-07-01) | |
| A2520 | Form and Pour Foundation Piers | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 08-Sep-2025 | Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-09-08) after status date (2025-07-01) | |
| A2520x | R3 - RFI 45 - City of Barrie Water Department – Request to Review Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 04-Sep-2025 | Actual start (2025-07-31) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A2530 | Backfilling to U/S of Grade Beams | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 12-Sep-2025 | Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-09-12) after status date (2025-07-01) | |
| A2530x | R4 - PC-004 Grade Beam Rebar | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 10-Sep-2025 | Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-09-10) after status date (2025-07-01) | |
| A2540x | R5 - RFI #39R2 Jewelery Workshop Interior Fitout | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 04-Sep-2025 | Actual start (2025-07-17) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) | |
| A2550x | R6 - RFI 60 Sprinkler Diesel Pump | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.2 Potential Schedule Impact (RISK) | 27-Aug-2025 | Actual start (2025-08-21) after status date (2025-07-01) | |
| A2600 | Compaction Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 15-Aug-2025 | Actual start (2025-08-15) after status date (2025-07-01) | Actual finish (2025-08-15) after status date (2025-07-01) | |
| A3920 | Setup Temporary Hoarding | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 04-Jul-2025 | Actual start (2025-07-04) after status date (2025-07-01) | Actual finish (2025-07-04) after status date (2025-07-01) | |
| A3930 | Interior Demoilition | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 02-Sep-2025 | Actual start (2025-07-21) after status date (2025-07-01) | Actual finish (2025-09-02) after status date (2025-07-01) | |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 11-Jul-2025 | Actual start (2025-07-07) after status date (2025-07-01) | Actual finish (2025-07-11) after status date (2025-07-01) | |
| A4340 | Electrical and Mechanical Make Safe | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 18-Jul-2025 | Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-18) after status date (2025-07-01) | |
| A4390 | Review Interferences with Steel Joist | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 15-Aug-2025 | Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-08-15) after status date (2025-07-01) | |
| A4410 | Joist Interferences Relocation | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 22-Aug-2025 | Actual start (2025-08-16) after status date (2025-07-01) | Actual finish (2025-08-22) after status date (2025-07-01) | |
| A5070 | Removal of Existing Water and Sanitary | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 14-Jul-2025 | Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-14) after status date (2025-07-01) | |
| A5220 | Weather Impact (Rain) - August 28, 2025 | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 28-Aug-2025 | Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-08-28) after status date (2025-07-01) | |
| A5250 | Weather Impact (Rain) - September 04, 2025 | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 04-Sep-2025 | Actual start (2025-09-04) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) |
| Activity ID | Activity Name | WBS | Forecast Finish | Key Metric | Issue |
|---|---|---|---|---|---|
| A1110 | Structural Reinforcement Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 01-Aug-2025 | Working days late: 28 wd | Actual finish 28 wd later than baseline (2025-06-23) |
| A2220 | Testing and Inspection Cash Allowance Expenditure | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 02-Jul-2025 | Working days late: 3 wd | Forecast finish 3 wd later than baseline (2025-06-26) |
| A2280 | Under Pinning Inspection | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1.4.5.1 Phase 1 - Early Works | 14-Jul-2025 | Working days late: 13 wd | Actual finish 13 wd later than baseline (2025-06-24) |
| A2510 | Supply of Embedment & Ankors | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.5 Building F Expansion / 1 Phase 2 - Foundation Work | 22-Aug-2025 | Working days late: 42 wd | Actual finish 42 wd later than baseline (2025-06-24) |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 08-Jul-2025 | Working days late: 9 wd | Actual finish 9 wd later than baseline (2025-06-24) |
| A1590 | 26 09 23 - Lighting Control | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings / 1.2.39 Electrical Power Distribution Shop Drawings | 18-Aug-2025 | Working days late: 34 wd | Actual finish 34 wd later than baseline (2025-06-30) |
| A1040 | Permit (Not Required Per Ontario Community College) | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.1 Preconstruction | 16-May-2025 | Working days late: 1 wd | Actual finish 1 wd later than baseline (2025-05-15) |
| A1030 | IFC Drawings Released | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.1 Preconstruction | 15-May-2025 | Working days late: 1 wd | Actual finish 1 wd later than baseline (2025-05-14) |
| A1060 | Foundation Concrete Rebar Shop Drawing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 08-Jul-2025 | Working days late: 10 wd | Actual finish 10 wd later than baseline (2025-06-23) |
| A3920 | Setup Hoarding at Existing Areas | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 04-Jul-2025 | Working days late: 12 wd | Actual finish 12 wd later than baseline (2025-06-17) |
| A3940 | Existing Slab Removal and Trenching | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.4 Construction / 1.4.6 Existing Building F Renovations / 1.4.6.1 Woodshop Area / 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation | 09-Sep-2025 | Working days late: 54 wd | Forecast finish 54 wd later than baseline (2025-06-23) |
| A1050 | Ductbank Underpinning Drawing | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 30-Jun-2025 | Working days late: 10 wd | Actual finish 10 wd later than baseline (2025-06-16) |
| A1070 | Foundation Concrete Mix Design | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 25-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-23) |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 14-Jul-2025 | Working days late: 14 wd | Actual finish 14 wd later than baseline (2025-06-23) |
| A1120 | Cold-formed Metal Framing Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 23-Jul-2025 | Working days late: 21 wd | Actual finish 21 wd later than baseline (2025-06-23) |
| A1080 | Bentonite Waterstop Data Sheet | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 02-Jul-2025 | Working days late: 6 wd | Actual finish 6 wd later than baseline (2025-06-23) |
| A1160 | TPO Roofing Shop Drawings | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.2 Shop Drawings | 26-Aug-2025 | Working days late: 45 wd | Actual finish 45 wd later than baseline (2025-06-23) |
| A1650 | Foundation Concrete Mix Design | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 27-Jun-2025 | Working days late: 2 wd | Actual finish 2 wd later than baseline (2025-06-25) |
| A1660 | Bentonite Waterstop | Ontario Community College Building F Expansion (CURRENT - FIXED) / 1 Ontario Community College Building F Expansion / 1.3 Procurement | 09-Jul-2025 | Working days late: 6 wd | Actual finish 6 wd later than baseline (2025-06-30) |
| Metric | Baseline | Current | Variance |
|---|---|---|---|
| Total Tasks | 327 | 405 | +78 |
| Project Finish | 31-Aug-2026 | 30-Sep-2026 | +21 WD |
| Project Start | 02-Apr-2025 | 01-Jul-2025 | +61 WD |
| CPLI | — | 0.93 | below 1.0 |
| BEI | — | 0.61 | below 0.95 |