Executive Summary

ℹ️
Baseline Assessment Note This report is scored out of 13/14 criteria. Excluded: C10 (Resources) — marked N/A due to project phase or data availability. An approved baseline is available.
Only 5 of 13 criteria passed Schedule quality requires immediate attention with multiple critical deficiencies identified. (Note: Scored out of 13 criteria)
Feasibility gap vs baseline/contract finish CPLI 0.933 | Contract: 2026-08-31 | Forecast: 2026-09-30 | Float: -22d (22 days late vs baseline finish)
Lead relationships found 7 negative lag relationships detected. Leads create unrealistic schedule compression and should be eliminated. → Action: Replace leads with overlapping activities or adjust activity definitions.
Excessive lag usage 10.6% of relationships contain lags (target ≤5%). Review and justify each lag or break down activities. → Action: Create intermediate milestones instead of using lags where possible.
High float activities detected 149 activities with float >44 days indicate missing relationships or incorrect sequencing. → Action: Review high float activities to ensure proper integration into schedule logic.
Long duration activities 38 activities exceed 44 working days. Break down into smaller work packages for better control. → Action: Decompose long activities into 1-week activities for improved tracking.
Missed task dates 19 activities incomplete despite passing planned dates. Update actuals and reforecast remaining work. → Action: Mark completed activities and update progress on in-progress work immediately.
38%
Health Score
RED STATUS

Key Performance Metrics

Criteria Passed
5
of 13 total criteria
C10 N/A - scored out of 13
No criteria passed yet
Criteria Failed
8
requires attention
No criteria failed yet
%
Compliance Rate
38%
overall quality score
Load schedule to see breakdown
🎓
Overall Rating
F
assessment grade
Load schedule to see grading scale

DCMA 14-Point Assessment

Comprehensive evaluation of schedule quality based on Defense Contract Management Agency (DCMA) 14-Point Assessment criteria. Each criterion measures a critical aspect of schedule health and reliability.

Health Score Breakdown 👆 Click cards for details

🔗
Logic & Flow
2/4
Fair
Complete assessment to see breakdown
👥
Resources & Progress
0/2
Poor
Complete assessment to see breakdown
⚠️
Constraints & Float
2/4
Fair
Complete assessment to see breakdown
📊
Performance
1/3
Poor
Complete assessment to see breakdown

DCMA-14 Status by Criterion

Per-criterion DCMA-14 status — one row for each of the fourteen criteria, color-coded by result. PASS means the criterion met its threshold; FAIL means it did not; N/A applies to baseline-dependent criteria like CPLI and BEI when no baseline is loaded. Reading down the chart shows exactly which criteria failed without having to count slices in a doughnut.

performanceChart
Criterion Status
1. Logic Pass
2. Leads Fail
3. Lags Fail
4. Relationship Types Pass
5. Hard Constraints Pass
6. High Float Fail
7. Negative Float Pass
8. High Duration Fail
9. Valid Dates Fail
10. Resources
11. Missed Tasks Fail
12. Critical Path Test Pass
13. CPLI Fail
14. BEI Fail

Top Schedule Problems

Activity-level problem volume across the eleven countable DCMA categories. Each bar is the number of activities (or relationships) that fail that criterion's threshold — e.g. activities missing predecessors or successors, with negative-lag leads, exceeding the 44-day duration cap, with negative float, or with invalid actual/forecast dates. Diagnostic criteria C12 (Critical Path Test), C13 (CPLI), and C14 (BEI) are scalar metrics, not counts, and appear in the Summary text below.

riskChart
Missing Logic
8
Leads
7
High Duration
38
Neg Float
0

Baseline vs Current Comparison

⚠️ Baseline Date: April 2, 2025 | ⚠️ 78 tasks added | ⚠️ 30 days late

Task Metrics

Baseline Tasks
327
BL
Pre-baseline scope snapshot
Current Tasks
405
CR
Live scope as of data date
Tasks Added
+78
327 → 405 net change
Scope Growth Rate
+23.9%
Above 10% threshold — review growth

Schedule Metrics

Baseline Start
2025-04-02
BS
Current Start
2025-07-01
CS
Baseline Finish
2026-08-31
BF
Current Finish
2026-09-30
CF

Variance Analysis

Start Delay
+90 days CD
SD
3 months delayed
👆 Click to expand detailed analysis
Project Impact:
A 3-month delayed start has significant implications for your project:

🎯 Strategic Impact:
Market Opportunity: Late market entry could mean competitors reached customers first, reducing potential market share
Stakeholder Confidence: Extended delays erode leadership trust and can impact future funding decisions
Team Momentum: Long delays disrupt team cohesion and can lead to loss of key personnel to other projects

📊 What This Means for Success:
The late start has already consumed your schedule buffer. Every additional delay now directly impacts your delivery date. You're operating with zero margin for error.

💡 Critical Actions:
• Communicate honestly with sponsors about reduced schedule flexibility
• Fast-track where feasible to recover time (parallel paths, extended hours)
• Identify scope that can be deferred to future releases
• Build recovery plan showing how you'll prevent finish date slippage
Finish Variance
+30 days CD
FV
1 month extension
👆 Click to expand detailed analysis
Business Impact:
The 30-day delay creates moderate business impact:

📊 What's at Stake:
Value Realization: 1 month delay in achieving project benefits
Commitment Credibility: Missing committed dates affects team reputation
Resource Delay: Resources tied up longer than planned, delaying other initiatives

💡 Recovery Options:
• Implement targeted fast-tracking on critical path
• Consider tactical scope reductions for non-essential features
• Increase collaboration to eliminate handoff delays
• Proactively communicate revised timeline to manage expectations
Duration Variance
-61 days
DV
-11.8% compression
👆 Click to expand detailed analysis
Execution Insights:
Duration compressed by 11.8% (61 days) - analyzing efficiency:

✓ Efficient Execution:
Slightly faster delivery suggests:
• Team worked efficiently with minimal blockers
• Good collaboration and handoff management
• Baseline included appropriate contingency that wasn't needed

This is positive performance. Ensure quality standards were maintained and capture best practices.
Net Schedule Impact
-61 days
NSI
Despite 3mo start delay
👆 Click to expand detailed analysis
Overall Project Schedule Health:
This metric tells the complete story by combining when you started with how long work took.

✓ Strong Recovery Execution:
Despite starting 90 days late, you recovered 151 days through execution, limiting net impact to -61 days.

Success Factors:
• Team successfully fast-tracked work to make up lost time
• Parallel execution and efficient sequencing compressed schedule
• Strong project leadership drove recovery actions
• Stakeholders likely recognize the recovery effort

🎯 Leadership Message:
"While we started late, the team's recovery efforts limited the finish impact. We demonstrated strong execution capability under pressure."

📊 Performance Indices

Schedule Compression Index
1.13x
SCI
-13% slower pace
👆 Click to expand detailed analysis
What this means:
The Schedule Compression Index (SCI) of 1.13x compares your baseline duration (516 days) to your current duration (455 days). This indicates you need to complete the baseline work 13% faster than originally planned.

⚠️ Risk Assessment: Aggressive schedule compression often leads to quality issues, resource burnout, and rework. Significant compression increases risk of schedule slippage.

💡 Recommendations:
• Evaluate if compression is realistic given resource constraints
• Identify opportunities for parallel execution or fast-tracking
• Consider requesting baseline re-approval if compression is unsustainable
• Monitor productivity metrics weekly to detect early warning signs
Scope-Duration Ratio
1.40
SDR
More work, less time
👆 Click to expand detailed analysis
What this means:
The Scope-Duration Ratio (SDR) of 1.40 measures task density changes. It compares current task density (0.89 tasks/day) to baseline density (0.63 tasks/day).

⚠️ Analysis: You have 40% more work per day than baseline. With 78 additional tasks in 61 fewer days, your team must complete work faster than originally planned.

💡 Implications:
• Higher risk of resource overallocation and burnout
• Potential for reduced quality if work is rushed
• May require additional resources or overtime
• Increased coordination complexity with more concurrent activities
Task Density Index
0.89
TDI
tasks/day vs 0.63 baseline
👆 Click to expand detailed analysis
What this means:
Task Density Index (TDI) measures how many activities need to be completed per calendar day. Your current density is 0.89 tasks/day compared to baseline of 0.63 tasks/day.

⚠️ Critical Alert: Task density is 41% higher than baseline. This significant increase creates serious execution challenges:

Impacts:
• Management overhead increases non-linearly with task count
• Quality control becomes more difficult
• Resource coordination complexity rises sharply
• Risk of activities being overlooked or rushed

💡 Recommendations: Consider consolidating smaller activities or extending timeline to reduce daily workload pressure.
Schedule Efficiency
88.2%
SE
Extended timeline
👆 Click to expand detailed analysis
What this means:
Schedule Efficiency (SE) of 88.2% shows how your current 455-day timeline compares to the 516-day baseline.

⚠️ Compressed Schedule: Timeline is 12% shorter than baseline (61 fewer days). Ensure this compression is achievable without sacrificing quality.

💡 Recommendation: Validate that productivity assumptions are realistic and resources are available.
Productivity Requirement
+40.5%
PR
Required vs baseline
👆 Click to expand detailed analysis
What this means:
Productivity Requirement (PR) shows how much faster your team must work compared to baseline. A value of +40.5% means your team needs to be 40.5% more productive than baseline assumptions.

🚨 Critical Alert: Requiring 40.5% productivity increase is extremely aggressive and unsustainable. This level of productivity gain:

• Rarely achievable without significant resource additions
• Often results in quality issues and rework
• Creates high risk of team burnout and turnover

💡 Urgent Recommendations:
• Add resources immediately or extend timeline
• Remove non-critical scope to reduce workload
• Implement aggressive risk mitigation strategies
• Consider baseline renegotiation with client
Resource Loading Impact
HIGH
RLI
23.9% more work
👆 Click to expand detailed analysis
What this means:
Resource Loading Impact (RLI) of HIGH reflects the 78 additional tasks (23.9% scope growth) and their effect on resource demand.

🚨 Critical Impact: Over 20% scope growth creates severe resource loading issues:

• Existing resources are likely overallocated
• New resources needed but may lack project context
• Coordination overhead increases exponentially
• Risk of resource conflicts and delays

💡 Actions Required:
• Conduct immediate resource capacity analysis
• Prioritize scope - identify must-haves vs nice-to-haves
• Plan for phased resource onboarding
• Update resource-loaded schedule to identify bottlenecks
Schedule Risk Score
8.9/10
SRS
High risk level
👆 Click to expand detailed analysis
What this means:
Your Schedule Risk Score (SRS) of 8.9/10 is calculated from compression pressure, scope growth, and resource constraints. This represents a HIGH RISK level.

🚨 High Risk Profile: Multiple risk factors are compounding:

• Schedule compression (1.13x baseline pace)
• Scope expansion (23.9% growth)
• Productivity demands (40.5% increase)

Risk Impact: This combination creates elevated risk of:
• Schedule delays beyond current forecast
• Budget overruns due to inefficiencies and rework
• Quality issues requiring corrective action

💡 Mitigation Strategies:
• Establish weekly risk review meetings
• Create contingency plans for critical path activities
• Implement early warning indicator dashboard
• Secure management support for rapid decision-making
Completion Confidence
11%
CC
Moderate confidence
👆 Click to expand detailed analysis
What this means:
Your Completion Confidence (CC) of 11% represents the probability of completing on the current finish date, based on schedule health indicators, risk factors, and historical project data.

⚠️ Moderate Confidence: Below 70% confidence indicates significant execution challenges. This confidence level suggests:

• Elevated risk of missing original completion dates
• May require scope negotiations or timeline extensions
• Need for formal recovery planning

💡 Immediate Actions:
• Develop formal recovery plan with measurable milestones
• Brief leadership on schedule challenges and needed support
• Consider requesting timeline or scope adjustments
• Implement daily standup for critical path activities

Risk Analysis

Overall Risk
8.9
High Risk
Schedule
8.0
Scope
8.5
Resource
8.5
Execution
8.3
Completion Confidence: 11%
Key Findings
  • 🔴 Primary Risk: 40.5% increase in required productivity cannot be achieved with baseline resources. Immediate resource augmentation is essential.
  • ⚠️ Secondary Risk: 23.9% scope growth indicates inadequate change control. Further additions will compound compression risks.
  • 📊 Schedule Impact: 61-day schedule compression combined with 78 added tasks creates impossible math: 23.9% more work must be completed in 11.8% less time. Late start compounds the crunch.
  • 🎯 Summary: Project carries elevated execution risk with 11% completion confidence. Without mitigation, significant delays may occur.
8.0 8.5 8.5 8.3 61-day compression. HIGH RISK: Critical schedule pressure - path forward requires executive decision +23.9% growth (+78 tasks). HIGH RISK: Change control failing - scope freeze essential 40.5% productivity gap. HIGH RISK: Baseline staffing inadequate - immediate augmentation critical 61 day compression with 90 day start delay creates execution pressure. 23.9% scope growth (78 tasks) indicates inadequate change control. 40.5% productivity increase required creates critical resource intensity. Combined schedule compression, scope expansion, and resource intensity create significant execution complexity. What this means:
Schedule Compression Risk of 8.0/10 measures the pressure from completing work faster than baseline.

🚨 Critical Risk Level: Extreme schedule compression creates severe execution risks:

Primary Concerns:
• Quality degradation - rushed work leads to defects and rework
• Resource burnout - sustained high-pressure environment unsustainable
• Safety risks - corners may be cut under time pressure
• Coordination failures - compressed schedule limits planning time

Expected Impacts: Projects with compression >30% face elevated risk of:
• Schedule overruns beyond current forecast
• Increased defect rates requiring rework
• Higher turnover of key personnel

💡 Critical Actions:
• Conduct feasibility review with technical leads
• Establish quality checkpoints that cannot be skipped
• Create stress management and morale support programs
• Request baseline revision if compression is unrealistic
What this means:
Scope Expansion Risk of 8.5/10 reflects 78 new tasks (23.9% growth) added after baseline.

🚨 Critical Scope Creep: Over 20% scope growth indicates breakdown in change control:

Typical Root Causes:
• Inadequate requirements definition in baseline
• Weak change control board or approval process
• Customer/stakeholder scope additions without timeline adjustment
• Discovery of work not captured in original planning
• "While we're at it" syndrome - bundling unplanned work

Business Impact:
• Budget overruns as unplanned work consumes resources
• Schedule delays compound as new work competes for resources
• Team confusion about true project boundaries
• Stakeholder dissatisfaction with "moving target"

💡 Immediate Actions:
• Freeze scope - implement strict change control
• Review all additions with sponsor to prioritize vs defer
• Document scope baseline and get stakeholder sign-off
• Establish formal change request process with impact analysis
What this means:
Resource Intensity Risk of 8.5/10 reflects 40.5% productivity increase required vs baseline.

🚨 Severe Resource Pressure: Requiring >30% productivity increase is typically unrealistic:

Productivity Constraints:
• Human productivity has natural limits
• Learning curve for new team members reduces effectiveness
• Coordination overhead increases non-linearly with team size
• Quality suffers when resources are overloaded
• Burnout risk increases exponentially under sustained pressure

Industry Benchmarks:
• Adding resources to late project often makes it later (Brooks' Law)
• Sustainable productivity improvements rarely exceed 15-20%
• Overtime effectiveness drops sharply after 2-3 weeks

💡 Viable Options:
• Negotiate scope reduction to match available capacity
• Request timeline extension to realistic completion date
• Add carefully selected, experienced resources early
• Implement process improvements to eliminate waste
• Automate repetitive tasks to improve efficiency
What this means:
Execution Complexity of 8.3/10 combines schedule compression, scope growth, and resource intensity into overall execution difficulty.

🚨 Extreme Complexity: Multiple high-risk factors create compounding execution challenges:

Compounding Effects:
• Schedule pressure + scope growth = quality risks
• Resource intensity + compression = burnout risks
• Scope creep + resource limits = unmet commitments
• All factors combined = project failure risk

Warning Signs to Monitor:
• Key personnel resignation or sick leave
• Increasing defect rates or rework loops
• Missed milestones becoming frequent
• Team morale deterioration and conflict
• Stakeholder complaints about lack of progress

💡 Executive Intervention Required:
• Escalate to executive sponsor immediately
• Conduct honest project health assessment
• Develop fundamental reset plan (scope, schedule, or resources must change)
• Consider project restructuring or temporary suspension to replan
• Do not continue with unrealistic plan - risks are too high
8.0 8.5 8.5 8.3 8.0 8.5 8.5 8.3 33.3 8.3

Predictive Analytics

Forecasted Completion
Nov 13, 2026
Most likely scenario
Analysis: Based on current progress, scope trends, and resource availability, project completion is forecasted. This includes buffer for identified risks and normal construction variability.
Delay Probability (45+ Days)
22%
Based on risk profile
Risk Factors: Calculated from schedule compression, scope growth, critical path pressure, and failed DCMA criteria. Higher percentage indicates greater likelihood of significant project delays without corrective action.
Additional Resources Needed
+25%
Critical trades needed for remaining work
Resource Analysis: To meet target completion date, additional resources are required to accelerate critical path activities and maintain schedule. Focus on trades with highest productivity impact.
Critical Path Pressure
High
High pressure on critical path activities
Pressure Index: Measures how much schedule compression has occurred on critical path. Higher pressure indicates less float available and greater vulnerability to delays. Monitor closely for activities with negative float.
Scenario Analysis
✓ Best Case
With immediate resource augmentation (+25%) and scope freeze, completion possible within 21 days of current forecast. Requires executive sponsorship and rapid mobilization.
◆ Most Likely
With standard mitigation (enhanced monitoring, selective resource adds), expect completion within 33 days of baseline. Requires sustained focus and active risk management.
✗ Worst Case
Without mitigation, continued scope creep and resource constraints could extend completion by 45-60 days beyond current forecast. Risk of cascading delays increases.
Detailed Comparison
MetricBaselineCurrentVariance
Total Tasks 327 405 +78 tasks
Start Date Apr 2, 2025 Jul 1, 2025 +90 days delayed
Finish Date Aug 31, 2026 Sep 30, 2026 +30 days
Total Duration 516 days 455 days -61 days
Task Density 0.63 tasks/day 0.89 tasks/day +41%
Scope Growth Baseline +23.9% 78 tasks added
Productivity Requirement 100% 140.5% +40.5%
Summary
Project is feasible but carries elevated execution risk. Success requires immediate resource augmentation, strict scope control, and enhanced monitoring. The 23.9% scope increase with 61 day compression creates a 40.5% productivity requirement increase. Without mitigation, 22% probability of 45+ day delay exists. Executive attention and active risk management are essential.

Strategic Recommendations

Immediate Action Required
Critical Priority
30-day delay + 40.5% productivity demand = high-probability failure scenario requiring executive intervention.
Required Actions (Next 48 Hours)
1
Emergency Sponsor Meeting
Present options: Add 3 FTEs, reduce scope by 12%, or accept 5-week extension
2
Stop Non-Critical Work
Focus 100% of resources on critical path activities only
3
Daily Leadership Standups
15-minute executive check-ins to remove blockers instantly
4
Freeze All Changes
Zero-tolerance scope freeze until recovery plan implemented
⚠️
Without Action: Current trajectory suggests 39-day actual delay with very low completion confidence.
High Priority Actions
Risk Mitigation
Risk score 8.9/10 indicates elevated failure probability. Multiple risk factors compounding.
Risk Response Actions (Next 2 Weeks)
1
Weekly Risk Reviews
1-hour session with full project team to surface emerging issues
2
Contingency Planning
Develop "Plan B" for top 5 risks (what if critical path delays 2 weeks?)
3
Early Warning Dashboard
Track leading indicators (productivity, quality, morale) not just lag indicators
4
Escalation Protocol
Clear triggers for when issues get escalated to sponsor
💡
Prevention ROI: 5 hours/week on risk management now prevents 50+ hours of crisis management later.
Recommended Actions
Enhanced Monitoring
Optimization Opportunities
Process Improvement
Small process improvements can yield significant schedule compression.
Quick Wins
1
Eliminate Handoff Delays
Co-locate teams or use collaboration tools to cut approval cycles by 30%
2
Decision Speed
Empower project team to make minor decisions without escalation
3
Meeting Efficiency
Cut recurring meetings by 25%, make remainder action-focused only
4
Automation
Automate status reporting, document generation, data entry (saves 5-10 hrs/week)
5
Prefabrication
Move work off critical path into controlled environments where possible
🔄
Continuous Improvement: Hold monthly retrospectives to identify process bottlenecks. Team knows the issues - provide forum to surface improvements.

DCMA 14-Point Assessment

Comprehensive evaluation of schedule quality based on Defense Contract Management Agency (DCMA) 14-Point Assessment criteria. Each criterion measures a critical aspect of schedule health and reliability.

C1

Logic

287 checked
0 failed
100%
PASS
All activities (excluding the first and last milestone) shall have at least one predecessor and one successor.
Manual Override:
📋 Assessment
PASS - All activities have at least one predecessor and one successor, establishing a complete logic network.
🔧 Corrective Action Plan
C2

Leads

653 checked
7 failed
99%
FAIL
Leads (negative lags) shall not be used in schedule logic.
Manual Override:
📋 Assessment
FAILED - 7 leads detected. Leads allow successors to start before predecessors finish, which creates artificial compression and masks poor logic. All leads should be eliminated and replaced with proper finish-to-start relationships.
⚠️ Failed Activities (7 activities)
ACTIVITY ID ACTIVITY NAME WBS START DATE FINISH DATE KEY METRIC ISSUE RECOMMENDED FIX
A3580 Mech. & Plumbing rough-ins 1.4.5.5.5 Level 3 2026-04-29 08:00 2026-05-12 17:00 Lead (d): 15.0 Has 15.0d lead from "Mech. & Plumbing rough-ins" A3580 "Mech. & Plumbing rough-ins" - Lead detected (negative lag). Restructure with explicit overlap activities or change the relationship type. (Has 15.0d lead from "Mech. & Plumbing rough-ins")
A2580 Underground Drainage 1 Phase 2 - Foundation Work 2025-10-20 08:00 2025-11-07 17:00 Lead (d): 10.0 Has 10.0d lead from "Erect Structural Steel" A2580 "Underground Drainage" - Lead detected (negative lag). Restructure with explicit overlap activities or change the relationship type. (Has 10.0d lead from "Erect Structural Steel")
A2650 Install Level 2 & 3 Decking 1.4.5.3 Phase 3 - Building Erection 2025-11-03 08:00 2025-11-14 17:00 Lead (d): 5.0 Has 5.0d lead from "Erect Structural Steel" A2650 "Install Level 2 & 3 Decking" - Lead detected (negative lag). Restructure with explicit overlap activities or change the relationship type. (Has 5.0d lead from "Erect Structural Steel")
A3290 Mech. & Plumbing rough-ins 1.4.5.5.3 Level 1 2026-04-22 08:00 2026-05-05 17:00 Lead (d): 5.0 Has 5.0d lead from "New partition framing" A3290 "Mech. & Plumbing rough-ins" - Lead detected (negative lag). Restructure with explicit overlap activities or change the relationship type. (Has 5.0d lead from "New partition framing")
A2290 Existing Structure Under Pinning 1.4.5.1 Phase 1 - Early Works 2025-06-24 08:00 2025-07-15 17:00 Lead (d): 2.0 Has 2.0d lead from "Demolition of Existing Vestibule F100" A2290 "Existing Structure Under Pinning" - Lead detected (negative lag). Restructure with explicit overlap activities or change the relationship type. (Has 2.0d lead from "Demolition of Existing Vestibule F100")
A2620 Structural Steel Inspection 1.4.5.3 Phase 3 - Building Erection 2025-10-31 08:00 2025-10-31 17:00 Lead (d): 1.0 Has 1.0d lead from "Erect Structural Steel" A2620 "Structural Steel Inspection" - Lead detected (negative lag). Restructure with explicit overlap activities or change the relationship type. (Has 1.0d lead from "Erect Structural Steel")
A3180 Roof Inspection 1.4.5.4.5 Roofing 2026-02-03 08:00 2026-02-03 17:00 Lead (d): 1.0 Has 1.0d lead from "Install Built-up Roof" A3180 "Roof Inspection" - Lead detected (negative lag). Restructure with explicit overlap activities or change the relationship type. (Has 1.0d lead from "Install Built-up Roof")
🔧 Corrective Action Plan
Negative-lag (lead) relationships
  1. 1Filter the relationship view for Lag < 0 (in P6: Activities > Relationships > group/sort by Lag).
  2. 2Print the list and walk the trades. Each lead means somebody is starting before the predecessor finishes — verify that's actually possible on site.
  3. 3If the work truly overlaps, replace the lead with a Start-to-Start + positive lag. If it doesn't, the predecessor needs to be split.
  4. 4Document any lead you keep with a one-line note in the activity Notebook field. DCMA reviewers will ask.
Heads up
A lead in the schedule is almost always the scheduler papering over a logic problem. If you can't write a one-sentence justification a superintendent would sign, get rid of it.
C3

Lags

653 checked
1 failed
100%
FAIL
⚠️
Intelligent Override Applied
The lag percentage of 10.6% exceeds the acceptable threshold of ≤5%, which indicates a FAIL. Manual pass selection has been overridden.
Lags shall not be excessive (generally should not exceed 5% of relationships, and no individual lag should exceed 44 working days).
Manual Override:
%
📋 Assessment
FAILED - 10.6% of relationships contain lags (threshold: 5%). Excessive lag usage indicates waiting periods aren't modeled as actual activities, reducing schedule transparency.
⚠️ Failed Activities (1 activity)
ACTIVITY ID ACTIVITY NAME WBS START DATE FINISH DATE KEY METRIC ISSUE RECOMMENDED FIX
A1370x Metal Shelving 1.2 Shop Drawings 2025-06-23 08:00 2025-06-23 08:00 Lag (d): 60.0 Lag of 60.0d from "Subcontract Award" exceeds 44 work days A1370x "Metal Shelving" - Excessive lag detected. Justify lag or convert to separate activity.
🔧 Corrective Action Plan
Excessive lags on relationships
  1. 1Filter relationships for Lag > 0 working days. Bucket them by intent: cure time, procurement, owner approvals, design review, transport.
  2. 2Anything > 10 days becomes a discrete activity. 'Concrete Cure - 14d', 'Long-Lead Switchgear Fab', 'Owner Submittal Review' — make the wait visible.
  3. 3Real technical waits stay as lags but only if they're under ~5 days (mortar set, paint dry, cooldown).
  4. 4Add the new activities into the WBS where the work happens, not in a 'Lags' bucket — the trade superintendent needs to see them in context.
Heads up
Procurement lags hide schedule risk. The day the supplier slips, you have no activity to status — your forecast still calculates clean and the project drifts silently.
C4

Relationship Types

PASS
Finish-to-Start (FS) relationships shall be predominantly used.
Manual Override:
%
%
%
%
📋 Assessment
PASS - 94% Finish-to-Start (threshold: 90%). Also includes 4.6% SS, 1.4% FF, 0.0% SF. Straightforward logic.
🔧 Corrective Action Plan
C5

Hard Constraints

287 checked
0 failed
100%
PASS
Hard constraints (Must Start/Finish On) shall be eliminated. DCMA targets zero hard constraints; industry practice allows <5% with documented justification for contractual milestones only.
Manual Override:
📋 Assessment
PASS - Minimal hard constraints. Schedule maintains flexibility and can calculate properly.
🔧 Corrective Action Plan
C6

High Float

287 checked
149 failed
48%
FAIL
High float (typically >44 working days) shall be minimized.
Manual Override:
📋 Assessment
FAILED - 149 activities with high float (>44 days). High-float activities indicate missing logic connections or activities not properly integrated into the project network.
⚠️ Failed Activities (149 activities)
ACTIVITY ID ACTIVITY NAME WBS START DATE FINISH DATE KEY METRIC ISSUE RECOMMENDED FIX
A2480 Concrete for Remaining Pad Footings (Ramp) 1 Phase 2 - Foundation Work 2025-07-02 08:00 2025-07-02 17:00 Total Float (d): 316.0 Total float of 316d exceeds 44 days A2480 "Concrete for Remaining Pad Footings (Ramp)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 316d exceeds 44 days)
A4570 Joist Interferences Relocation 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2025-08-18 08:00 2025-08-22 17:00 Total Float (d): 279.0 Total float of 279d exceeds 44 days A4570 "Joist Interferences Relocation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 279d exceeds 44 days)
A1480.1 23 00 00 - Exhaust Fans (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-09-16 08:00 2025-09-29 17:00 Total Float (d): 254.0 Total float of 254d exceeds 44 days A1480.1 "23 00 00 - Exhaust Fans (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 254d exceeds 44 days)
A1670 Masonry and Mortar 1.3 Procurement 2025-08-19 08:00 2025-08-25 17:00 Total Float (d): 253.0 Total float of 253d exceeds 44 days A1670 "Masonry and Mortar" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 253d exceeds 44 days)
A3940 Existing Slab Removal and Trenching 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-09-03 08:00 2025-09-09 17:00 Total Float (d): 253.0 Total float of 253d exceeds 44 days A3940 "Existing Slab Removal and Trenching" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 253d exceeds 44 days)
A4370 Underground Mechanical Installation (DCW, Sprinkler) 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-09-10 08:00 2025-09-23 17:00 Total Float (d): 253.0 Total float of 253d exceeds 44 days A4370 "Underground Mechanical Installation (DCW, Sprinkler)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 253d exceeds 44 days)
A4380 Backfilling and Concrete for SOG 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-09-24 08:00 2025-09-30 17:00 Total Float (d): 253.0 Total float of 253d exceeds 44 days A4380 "Backfilling and Concrete for SOG" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 253d exceeds 44 days)
A1610 Concrete Mix for Hardscapes 1.2 Shop Drawings 2025-07-23 08:00 2025-08-06 17:00 Total Float (d): 238.0 Total float of 238d exceeds 44 days A1610 "Concrete Mix for Hardscapes" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 238d exceeds 44 days)
A2200 Concrete for Hardscape 1.3 Procurement 2025-08-07 08:00 2025-08-13 17:00 Total Float (d): 238.0 Total float of 238d exceeds 44 days A2200 "Concrete for Hardscape" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 238d exceeds 44 days)
A1140 Millwork Shop Drawings 1.2 Shop Drawings 2025-07-16 08:00 2025-07-29 17:00 Total Float (d): 228.0 Total float of 228d exceeds 44 days A1140 "Millwork Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 228d exceeds 44 days)
A1320 Washroom accessories and Partitions Shop Drawings 1.2 Shop Drawings 2025-07-16 08:00 2025-07-29 17:00 Total Float (d): 228.0 Total float of 228d exceeds 44 days A1320 "Washroom accessories and Partitions Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 228d exceeds 44 days)
A1720 Millwork 1.3 Procurement 2025-07-30 08:00 2025-10-09 17:00 Total Float (d): 228.0 Total float of 228d exceeds 44 days A1720 "Millwork " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 228d exceeds 44 days)
A1910 Washroom accessories and Partitions 1.3 Procurement 2025-07-30 08:00 2025-09-04 17:00 Total Float (d): 228.0 Total float of 228d exceeds 44 days A1910 "Washroom accessories and Partitions " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 228d exceeds 44 days)
A1270 Tiling Data sheet and samples 1.2 Shop Drawings 2025-07-16 08:00 2025-07-29 17:00 Total Float (d): 213.0 Total float of 213d exceeds 44 days A1270 "Tiling Data sheet and samples" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 213d exceeds 44 days)
A1860 Tiling 1.3 Procurement 2025-07-30 08:00 2025-09-11 17:00 Total Float (d): 213.0 Total float of 213d exceeds 44 days A1860 "Tiling " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 213d exceeds 44 days)
A1310 Paint Drawdowns 1.2 Shop Drawings 2025-07-16 08:00 2025-07-29 17:00 Total Float (d): 212.0 Total float of 212d exceeds 44 days A1310 "Paint Drawdowns" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 212d exceeds 44 days)
A1900 Paint Drawdowns 1.3 Procurement 2025-07-30 08:00 2025-08-13 17:00 Total Float (d): 212.0 Total float of 212d exceeds 44 days A1900 "Paint Drawdowns" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 212d exceeds 44 days)
A1620 Landscape Shop Drawings 1.2 Shop Drawings 2025-07-23 08:00 2025-08-06 17:00 Total Float (d): 203.0 Total float of 203d exceeds 44 days A1620 "Landscape Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 203d exceeds 44 days)
A2210 Landscape (unit pavers, furniture, etc) 1.3 Procurement 2025-08-07 08:00 2025-10-31 17:00 Total Float (d): 203.0 Total float of 203d exceeds 44 days A2210 "Landscape (unit pavers, furniture, etc)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 203d exceeds 44 days)
A1350 Sprinkler & Standpipe Shop Drawings 1.2 Shop Drawings 2025-07-02 08:00 2025-07-15 17:00 Total Float (d): 192.0 Total float of 192d exceeds 44 days A1350 "Sprinkler & Standpipe Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 192d exceeds 44 days)
A1940 Sprinkler & Standpipe Shop Drawings 1.3 Procurement 2025-07-16 08:00 2025-08-06 17:00 Total Float (d): 192.0 Total float of 192d exceeds 44 days A1940 "Sprinkler & Standpipe Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 192d exceeds 44 days)
A1300 Flooring Data Sheets and Samples 1.2 Shop Drawings 2025-07-16 08:00 2025-07-29 17:00 Total Float (d): 183.0 Total float of 183d exceeds 44 days A1300 "Flooring Data Sheets and Samples" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 183d exceeds 44 days)
A1890 Flooring 1.3 Procurement 2025-07-30 08:00 2025-10-24 17:00 Total Float (d): 183.0 Total float of 183d exceeds 44 days A1890 "Flooring " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 183d exceeds 44 days)
A1180 Exterior Wall Cladding Shop Drawings 1.2 Shop Drawings 2025-08-11 08:00 2025-08-22 17:00 Total Float (d): 181.0 Total float of 181d exceeds 44 days A1180 "Exterior Wall Cladding Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 181d exceeds 44 days)
A1760 Exterior Wall Cladding 1.3 Procurement 2025-08-25 08:00 2025-11-18 17:00 Total Float (d): 181.0 Total float of 181d exceeds 44 days A1760 "Exterior Wall Cladding" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 181d exceeds 44 days)
A2040 22 13 29 - Sump Pumps 1.3.34 Mechanical Equipment 2025-06-19 08:00 2025-08-08 17:00 Total Float (d): 177.0 Total float of 177d exceeds 44 days A2040 "22 13 29 - Sump Pumps" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 177d exceeds 44 days)
A1740 TPO Roofing (Bridge) 1.3 Procurement 2025-08-27 08:00 2025-10-08 17:00 Total Float (d): 173.0 Total float of 173d exceeds 44 days A1740 "TPO Roofing (Bridge)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 173d exceeds 44 days)
A4530 Electrical and Mechanical Make Safe 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-01-12 08:00 2026-01-14 17:00 Total Float (d): 170.0 Total float of 170d exceeds 44 days A4530 "Electrical and Mechanical Make Safe" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 170d exceeds 44 days)
A4540 Interior Demoilition 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-01-15 08:00 2026-01-28 17:00 Total Float (d): 170.0 Total float of 170d exceeds 44 days A4540 "Interior Demoilition " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 170d exceeds 44 days)
A1200 Hollow Metal Frames & Doors Shop Drawings 1.2 Shop Drawings 2025-07-16 08:00 2025-07-29 17:00 Total Float (d): 162.0 Total float of 162d exceeds 44 days A1200 "Hollow Metal Frames & Doors Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 162d exceeds 44 days)
A1780 Hollow Metal Frames 1.3 Procurement 2025-07-30 08:00 2025-09-25 17:00 Total Float (d): 162.0 Total float of 162d exceeds 44 days A1780 "Hollow Metal Frames" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 162d exceeds 44 days)
A1790 Hollow Metal Doors 1.3 Procurement 2025-07-30 08:00 2025-10-24 17:00 Total Float (d): 162.0 Total float of 162d exceeds 44 days A1790 "Hollow Metal Doors" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 162d exceeds 44 days)
A1770 Fire-resistive Material 1.3 Procurement 2025-07-10 08:00 2025-08-07 17:00 Total Float (d): 161.0 Total float of 161d exceeds 44 days A1770 "Fire-resistive Material " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 161d exceeds 44 days)
A1170 Air Barrier System Data Sheet and Mockup 1.2 Shop Drawings 2025-07-02 08:00 2025-07-08 17:00 Total Float (d): 159.0 Total float of 159d exceeds 44 days A1170 "Air Barrier System Data Sheet and Mockup" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 159d exceeds 44 days)
A1750 Air Barrier System 1.3 Procurement 2025-07-09 08:00 2025-07-22 17:00 Total Float (d): 159.0 Total float of 159d exceeds 44 days A1750 "Air Barrier System" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 159d exceeds 44 days)
A1870 ACT & ACB 1.3 Procurement 2025-09-05 08:00 2025-10-17 17:00 Total Float (d): 156.0 Total float of 156d exceeds 44 days A1870 "ACT & ACB " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 156d exceeds 44 days)
A2070 23 00 00 - Exhaust Fans 1.3.34 Mechanical Equipment 2025-09-09 08:00 2025-12-18 17:00 Total Float (d): 154.0 Total float of 154d exceeds 44 days A2070 "23 00 00 - Exhaust Fans" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 154d exceeds 44 days)
A4010 Underground Plumbing Rough-ins 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) 2025-07-02 08:00 2025-07-15 17:00 Total Float (d): 150.0 Total float of 150d exceeds 44 days A4010 "Underground Plumbing Rough-ins" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days)
A4760 Trench Backfill 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) 2025-07-16 08:00 2025-07-22 17:00 Total Float (d): 150.0 Total float of 150d exceeds 44 days A4760 "Trench Backfill" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days)
A4770 Concrete Slab Infill 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) 2025-07-23 08:00 2025-08-06 17:00 Total Float (d): 150.0 Total float of 150d exceeds 44 days A4770 "Concrete Slab Infill" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days)
A4780 New Columns Installation 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) 2025-08-07 08:00 2025-08-13 17:00 Total Float (d): 150.0 Total float of 150d exceeds 44 days A4780 "New Columns Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days)
A4790 Existing Column Reinforcement 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) 2025-08-14 08:00 2025-08-20 17:00 Total Float (d): 150.0 Total float of 150d exceeds 44 days A4790 "Existing Column Reinforcement" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days)
A4800 Flatness Survey @ Floor Slab 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) 2025-08-21 08:00 2025-08-22 17:00 Total Float (d): 150.0 Total float of 150d exceeds 44 days A4800 "Flatness Survey @ Floor Slab" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days)
A4810 Self Levelling 1.4.6.3 Existing Space for Future Classroom (GL 3-4 & J.1-B.1) 2025-08-25 08:00 2025-09-03 17:00 Total Float (d): 150.0 Total float of 150d exceeds 44 days A4810 "Self Levelling" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 150d exceeds 44 days)
A1210 Interior Aluminum Screen 1.2 Shop Drawings 2025-07-25 08:00 2025-08-08 17:00 Total Float (d): 141.0 Total float of 141d exceeds 44 days A1210 "Interior Aluminum Screen" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 141d exceeds 44 days)
A1800 Interior Aluminum Screens 1.3 Procurement 2025-08-11 08:00 2025-12-16 17:00 Total Float (d): 141.0 Total float of 141d exceeds 44 days A1800 "Interior Aluminum Screens" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 141d exceeds 44 days)
A1930 Hydraulic Lift 1.3 Procurement 2025-07-10 08:00 2025-12-01 17:00 Total Float (d): 141.0 Total float of 141d exceeds 44 days A1930 "Hydraulic Lift " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 141d exceeds 44 days)
A1530.1 20 05 10 - Electric Heat Tracing (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-08-13 08:00 2025-08-26 17:00 Total Float (d): 134.0 Total float of 134d exceeds 44 days A1530.1 "20 05 10 - Electric Heat Tracing (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 134d exceeds 44 days)
A2120 20 05 10 - Electric Heat Tracing 1.3.34 Mechanical Equipment 2025-08-27 08:00 2026-01-19 17:00 Total Float (d): 134.0 Total float of 134d exceeds 44 days A2120 "20 05 10 - Electric Heat Tracing" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 134d exceeds 44 days)
A1250 Finished Hardware Schedule 1.2 Shop Drawings 2025-07-16 08:00 2025-07-29 17:00 Total Float (d): 132.0 Total float of 132d exceeds 44 days A1250 "Finished Hardware Schedule" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 132d exceeds 44 days)
A1840 Finished Hardware 1.3 Procurement 2025-07-30 08:00 2025-12-05 17:00 Total Float (d): 132.0 Total float of 132d exceeds 44 days A1840 "Finished Hardware " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 132d exceeds 44 days)
A1240 Aluminum Framed Glazing System Shop Drawings 1.2 Shop Drawings 2025-07-23 08:00 2025-08-06 17:00 Total Float (d): 131.0 Total float of 131d exceeds 44 days A1240 "Aluminum Framed Glazing System Shop Drawings" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 131d exceeds 44 days)
A1830 Aluminum Framed Glazing Systems 1.3 Procurement 2025-08-07 08:00 2025-11-28 17:00 Total Float (d): 131.0 Total float of 131d exceeds 44 days A1830 "Aluminum Framed Glazing Systems" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 131d exceeds 44 days)
A2780 Above Grade Vapour Mock-up 1.4.5.4.1 North Elevation 2026-02-02 08:00 2026-02-02 17:00 Total Float (d): 129.0 Total float of 129d exceeds 44 days A2780 "Above Grade Vapour Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 129d exceeds 44 days)
A4560 Review Interferences with Steel Joist 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2025-07-02 08:00 2025-07-08 17:00 Total Float (d): 128.0 Total float of 128d exceeds 44 days A4560 "Review Interferences with Steel Joist" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 128d exceeds 44 days)
A1730 Built-up Roofing 1.3 Procurement 2025-07-10 08:00 2025-08-21 17:00 Total Float (d): 127.0 Total float of 127d exceeds 44 days A1730 "Built-up Roofing " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 127d exceeds 44 days)
A1810 Flush Wood Doors 1.3 Procurement 2025-08-28 08:00 2025-12-12 17:00 Total Float (d): 127.0 Total float of 127d exceeds 44 days A1810 "Flush Wood Doors " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 127d exceeds 44 days)
A2190 28 31 00 - Fire Alarm 1.3.35 Electrical Power Distribution Equipment 2025-06-18 08:00 2025-10-27 17:00 Total Float (d): 123.0 Total float of 123d exceeds 44 days A2190 "28 31 00 - Fire Alarm" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 123d exceeds 44 days)
A3180 Roof Inspection 1.4.5.4.5 Roofing 2026-02-03 08:00 2026-02-03 17:00 Total Float (d): 123.0 Total float of 123d exceeds 44 days A3180 "Roof Inspection" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 123d exceeds 44 days)
A1260 Stud framing and Gypsum Board Data Sheets 1.2 Shop Drawings 2025-07-16 08:00 2025-07-29 17:00 Total Float (d): 118.0 Total float of 118d exceeds 44 days A1260 "Stud framing and Gypsum Board Data Sheets" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 118d exceeds 44 days)
A1850 Stud framing & gypsum board 1.3 Procurement 2025-07-30 08:00 2025-08-06 17:00 Total Float (d): 118.0 Total float of 118d exceeds 44 days A1850 "Stud framing & gypsum board" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 118d exceeds 44 days)
A1700 Cold-formed Metal Framing 1.3 Procurement 2025-07-24 08:00 2025-08-07 17:00 Total Float (d): 117.0 Total float of 117d exceeds 44 days A1700 "Cold-formed Metal Framing " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 117d exceeds 44 days)
A2420 Form and Pour North Exit Stair 1 Phase 2 - Foundation Work 2025-08-04 08:00 2025-09-30 17:00 Total Float (d): 116.0 Total float of 116d exceeds 44 days A2420 "Form and Pour North Exit Stair" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 116d exceeds 44 days)
A1990 23 21 16 - Air Separator 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Total Float (d): 112.0 Total float of 112d exceeds 44 days A1990 "23 21 16 - Air Separator" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 112d exceeds 44 days)
A2000 23 21 16 - Expansion Tanks 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Total Float (d): 112.0 Total float of 112d exceeds 44 days A2000 "23 21 16 - Expansion Tanks" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 112d exceeds 44 days)
A2010 23 57 00 - Heat Exchangers 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Total Float (d): 112.0 Total float of 112d exceeds 44 days A2010 "23 57 00 - Heat Exchangers" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 112d exceeds 44 days)
A2020 22 33 00 - Electric Domestic Water Heaters 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Total Float (d): 112.0 Total float of 112d exceeds 44 days A2020 "22 33 00 - Electric Domestic Water Heaters" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 112d exceeds 44 days)
A2140 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes 1.3.35 Electrical Power Distribution Equipment 2025-07-09 08:00 2025-11-14 17:00 Total Float (d): 109.0 Total float of 109d exceeds 44 days A2140 "26 27 26 - Wiring Devices, Service Poles, & Floor Boxes" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 109d exceeds 44 days)
A2030 23 81 26 - Split System 1.3.34 Mechanical Equipment 2025-07-10 08:00 2025-11-17 17:00 Total Float (d): 108.0 Total float of 108d exceeds 44 days A2030 "23 81 26 - Split System" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 108d exceeds 44 days)
A1820 Coiling Doors 1.3 Procurement 2025-08-22 08:00 2026-01-14 17:00 Total Float (d): 106.0 Total float of 106d exceeds 44 days A1820 "Coiling Doors" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 106d exceeds 44 days)
2170 26 50 00 - Emergency Lighting & Exit Signs 1.3.35 Electrical Power Distribution Equipment 2025-07-30 08:00 2025-12-05 17:00 Total Float (d): 104.0 Total float of 104d exceeds 44 days 2170 "26 50 00 - Emergency Lighting & Exit Signs" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 104d exceeds 44 days)
A2760 Masonry Mock-up 1.4.5.4.1 North Elevation 2026-04-13 08:00 2026-04-13 17:00 Total Float (d): 96.0 Total float of 96d exceeds 44 days A2760 "Masonry Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 96d exceeds 44 days)
A2770 L1 Masonry Wall installation 1.4.5.4.1 North Elevation 2026-04-13 08:00 2026-04-14 17:00 Total Float (d): 95.0 Total float of 95d exceeds 44 days A2770 "L1 Masonry Wall installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 95d exceeds 44 days)
A2890 L1 Masonry Wall Installation 1.4.5.4.2 West Elevation 2026-04-15 08:00 2026-04-21 17:00 Total Float (d): 95.0 Total float of 95d exceeds 44 days A2890 "L1 Masonry Wall Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 95d exceeds 44 days)
A1380x Metal Shelving (R1) 1.2 Shop Drawings 2025-07-10 08:00 2025-07-23 17:00 Total Float (d): 93.0 Total float of 93d exceeds 44 days A1380x "Metal Shelving (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 93d exceeds 44 days)
A2090x Metal Shelving 1.3 Procurement 2025-07-24 08:00 2025-08-21 17:00 Total Float (d): 93.0 Total float of 93d exceeds 44 days A2090x "Metal Shelving" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 93d exceeds 44 days)
A4510 Metal Shelving Installation 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-08-22 08:00 2025-08-26 17:00 Total Float (d): 93.0 Total float of 93d exceeds 44 days A4510 "Metal Shelving Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 93d exceeds 44 days)
A4700 Review Interferences with Steel Joist 1.4.6.2 Machine Shop Area 2025-08-18 08:00 2025-08-18 08:00 Total Float (d): 91.0 Total float of 91d exceeds 44 days A4700 "Review Interferences with Steel Joist" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 91d exceeds 44 days)
A4710 Relocation of Interferences 1.4.6.2 Machine Shop Area 2025-08-18 08:00 2025-08-29 17:00 Total Float (d): 91.0 Total float of 91d exceeds 44 days A4710 "Relocation of Interferences" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 91d exceeds 44 days)
A2220 Testing and Inspection Cash Allowance Expenditure 1.3 Procurement 2025-07-02 08:00 2025-07-02 08:00 Total Float (d): 89.0 Total float of 89d exceeds 44 days A2220 "Testing and Inspection Cash Allowance Expenditure" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 89d exceeds 44 days)
A2800 AVB Inspection 1.4.5.4.1 North Elevation 2026-02-02 08:00 2026-02-02 17:00 Total Float (d): 87.0 Total float of 87d exceeds 44 days A2800 "AVB Inspection" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 87d exceeds 44 days)
A4550 Existing Exterior Wall Demo (New Building Must be Erected and Enclosed) 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-02-17 08:00 2026-02-23 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4550 "Existing Exterior Wall Demo (New Building Must be Erected and Enclosed)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4600 Stud Framing 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-02-24 08:00 2026-02-26 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4600 "Stud Framing" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4610 MEP Rough-ins 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-02-27 08:00 2026-03-05 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4610 "MEP Rough-ins" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4620 Plywood Blocking 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-03-06 08:00 2026-03-10 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4620 "Plywood Blocking" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4630 Drywall Installation 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-03-11 08:00 2026-03-13 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4630 "Drywall Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4640 Taping Drywall 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-03-16 08:00 2026-03-20 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4640 "Taping Drywall" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4650 Painting 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2026-03-23 08:00 2026-03-24 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4650 "Painting" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4660 Setup Temporary Hoarding 1.4.6.1.3 Phase 3 - Assembly Area 2026-03-25 08:00 2026-03-25 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4660 "Setup Temporary Hoarding" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4670 Electrical and Mechanical Make Safe 1.4.6.1.3 Phase 3 - Assembly Area 2026-03-26 08:00 2026-03-27 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4670 "Electrical and Mechanical Make Safe" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4680 Interior Demoilition 1.4.6.1.3 Phase 3 - Assembly Area 2026-03-30 08:00 2026-04-06 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4680 "Interior Demoilition " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A4690 Electrical Fixtures 1.4.6.1.3 Phase 3 - Assembly Area 2026-04-07 08:00 2026-04-13 17:00 Total Float (d): 86.0 Total float of 86d exceeds 44 days A4690 "Electrical Fixtures" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 86d exceeds 44 days)
A2080 23 00 00 - Unit Heater 1.3.34 Mechanical Equipment 2025-08-29 08:00 2025-12-18 17:00 Total Float (d): 85.0 Total float of 85d exceeds 44 days A2080 "23 00 00 - Unit Heater" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 85d exceeds 44 days)
A2100 23 00 00 - Wall Fin Heater 1.3.34 Mechanical Equipment 2025-08-13 08:00 2025-12-18 17:00 Total Float (d): 85.0 Total float of 85d exceeds 44 days A2100 "23 00 00 - Wall Fin Heater" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 85d exceeds 44 days)
A2150 26 50 00 - Lighting Fixtures 1.3.35 Electrical Power Distribution Equipment 2025-08-19 08:00 2025-12-25 17:00 Total Float (d): 81.0 Total float of 81d exceeds 44 days A2150 "26 50 00 - Lighting Fixtures" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 81d exceeds 44 days)
A1980 23 25 00 - Buffer Tanks 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-12-24 17:00 Total Float (d): 72.0 Total float of 72d exceeds 44 days A1980 "23 25 00 - Buffer Tanks" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 72d exceeds 44 days)
A1590.1 26 09 23 - Lighting Control (R1) 1.2.39 Electrical Power Distribution Shop Drawings 2025-08-19 08:00 2025-09-02 17:00 Total Float (d): 71.0 Total float of 71d exceeds 44 days A1590.1 "26 09 23 - Lighting Control (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 71d exceeds 44 days)
A2180 26 09 23 - Lighting Control 1.3.35 Electrical Power Distribution Equipment 2025-09-03 08:00 2026-01-23 17:00 Total Float (d): 71.0 Total float of 71d exceeds 44 days A2180 "26 09 23 - Lighting Control" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 71d exceeds 44 days)
A2560 Below Grade Vapour Barrier Mock-up 1 Phase 2 - Foundation Work 2025-09-23 08:00 2025-09-23 17:00 Total Float (d): 71.0 Total float of 71d exceeds 44 days A2560 "Below Grade Vapour Barrier Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 71d exceeds 44 days)
A1970 23 21 23 - Pumps 1.3.34 Mechanical Equipment 2025-08-20 08:00 2026-01-12 17:00 Total Float (d): 70.0 Total float of 70d exceeds 44 days A1970 "23 21 23 - Pumps" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 70d exceeds 44 days)
A2160 27 10 00 - Structural Cabling System (Fiber Optic Cable) 1.3.35 Electrical Power Distribution Equipment 2025-07-23 08:00 2026-04-14 17:00 Total Float (d): 70.0 Total float of 70d exceeds 44 days A2160 "27 10 00 - Structural Cabling System (Fiber Optic Cable)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 70d exceeds 44 days)
A2570 Footing Vapor Barrier & Insulation 1 Phase 2 - Foundation Work 2025-09-23 08:00 2025-09-26 17:00 Total Float (d): 68.0 Total float of 68d exceeds 44 days A2570 "Footing Vapor Barrier & Insulation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 68d exceeds 44 days)
A2820 Glazing Site Measure and Scanning 1.4.5.4.1 North Elevation 2026-02-02 08:00 2026-02-02 17:00 Total Float (d): 68.0 Total float of 68d exceeds 44 days A2820 "Glazing Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 68d exceeds 44 days)
A2830 Glazing Shop Fabrication 1.4.5.4.1 North Elevation 2026-02-03 08:00 2026-03-02 17:00 Total Float (d): 68.0 Total float of 68d exceeds 44 days A2830 "Glazing Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 68d exceeds 44 days)
A1540.1 22 40 00 - Plumbing Fixtures (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-08-14 08:00 2025-08-27 17:00 Total Float (d): 64.0 Total float of 64d exceeds 44 days A1540.1 "22 40 00 - Plumbing Fixtures (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 64d exceeds 44 days)
A2130 22 40 00 - Plumbing Fixtures 1.3.34 Mechanical Equipment 2025-08-28 08:00 2026-01-20 17:00 Total Float (d): 64.0 Total float of 64d exceeds 44 days A2130 "22 40 00 - Plumbing Fixtures" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 64d exceeds 44 days)
A3680 Misc. Metals Mock-up 1.4.5.5 Phase 5 - New Expansion Interior Finishes 2026-05-13 08:00 2026-05-13 17:00 Total Float (d): 59.0 Total float of 59d exceeds 44 days A3680 "Misc. Metals Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 59d exceeds 44 days)
A1460.1 23 25 00 - Water Treatment (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-08-22 08:00 2025-09-05 17:00 Total Float (d): 58.0 Total float of 58d exceeds 44 days A1460.1 "23 25 00 - Water Treatment (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days)
A2050 23 25 00 - Water Treatment 1.3.34 Mechanical Equipment 2025-09-08 08:00 2026-01-28 17:00 Total Float (d): 58.0 Total float of 58d exceeds 44 days A2050 "23 25 00 - Water Treatment" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days)
A2810 Aluminum & Metal Panel Cladding Mock-up 1.4.5.4.1 North Elevation 2026-04-16 08:00 2026-04-16 17:00 Total Float (d): 58.0 Total float of 58d exceeds 44 days A2810 "Aluminum & Metal Panel Cladding Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days)
A2840 L1, L2, L3 Exterior Glazing Installation (W05) 1.4.5.4.1 North Elevation 2026-03-18 08:00 2026-04-15 17:00 Total Float (d): 58.0 Total float of 58d exceeds 44 days A2840 "L1, L2, L3 Exterior Glazing Installation (W05)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days)
A2850 Exterior Cladding Site Measure and Scanning 1.4.5.4.1 North Elevation 2026-04-16 08:00 2026-04-16 17:00 Total Float (d): 58.0 Total float of 58d exceeds 44 days A2850 "Exterior Cladding Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days)
A2860 Exterior Cladding Shop Fabrication 1.4.5.4.1 North Elevation 2026-04-17 08:00 2026-05-14 17:00 Total Float (d): 58.0 Total float of 58d exceeds 44 days A2860 "Exterior Cladding Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days)
A2870 L1, L2 & L3 Cladding Installation (EW2a) 1.4.5.4.1 North Elevation 2026-05-15 08:00 2026-06-12 17:00 Total Float (d): 58.0 Total float of 58d exceeds 44 days A2870 "L1, L2 & L3 Cladding Installation (EW2a)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days)
A3200 Roof Anchor System Installation 1.4.5.4.5 Roofing 2026-06-15 08:00 2026-06-19 17:00 Total Float (d): 58.0 Total float of 58d exceeds 44 days A3200 "Roof Anchor System Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 58d exceeds 44 days)
A4150 New Exterior Paved Areas and Sidewalks 1.4.7 Exterior Works 2026-05-04 08:00 2026-06-01 17:00 Total Float (d): 57.0 Total float of 57d exceeds 44 days A4150 "New Exterior Paved Areas and Sidewalks " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 57d exceeds 44 days)
A4160 Landscape Installations 1.4.7 Exterior Works 2026-06-02 08:00 2026-06-15 17:00 Total Float (d): 57.0 Total float of 57d exceeds 44 days A4160 "Landscape Installations" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 57d exceeds 44 days)
A3850 Foundations 1.4.5.6 Phase 6 - Pedestrian Bridge Construction 2025-09-10 08:00 2026-02-24 17:00 Total Float (d): 56.0 Total float of 56d exceeds 44 days A3850 "Foundations" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days)
A3860 Concrete Vertical Piers 1.4.5.6 Phase 6 - Pedestrian Bridge Construction 2026-02-25 08:00 2026-03-04 17:00 Total Float (d): 56.0 Total float of 56d exceeds 44 days A3860 "Concrete Vertical Piers" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days)
A3870 Removal of Existing Facade for Tie In 1.4.5.6 Phase 6 - Pedestrian Bridge Construction 2026-03-05 08:00 2026-03-06 17:00 Total Float (d): 56.0 Total float of 56d exceeds 44 days A3870 "Removal of Existing Facade for Tie In" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days)
A3880 Structural Steel erection including expansion plates 1.4.5.6 Phase 6 - Pedestrian Bridge Construction 2026-03-09 08:00 2026-03-27 17:00 Total Float (d): 56.0 Total float of 56d exceeds 44 days A3880 "Structural Steel erection including expansion plates " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days)
A3890 Envelope 1.4.5.6 Phase 6 - Pedestrian Bridge Construction 2026-03-30 08:00 2026-05-01 17:00 Total Float (d): 56.0 Total float of 56d exceeds 44 days A3890 "Envelope " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days)
A3900 Interior M&E Rough in 1.4.5.6 Phase 6 - Pedestrian Bridge Construction 2026-05-04 08:00 2026-05-15 17:00 Total Float (d): 56.0 Total float of 56d exceeds 44 days A3900 "Interior M&E Rough in " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days)
A3910 Interior Finishes 1.4.5.6 Phase 6 - Pedestrian Bridge Construction 2026-05-19 08:00 2026-05-19 17:00 Total Float (d): 56.0 Total float of 56d exceeds 44 days A3910 "Interior Finishes" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 56d exceeds 44 days)
A4720 Existing Column Reinforcement 1.4.6.2 Machine Shop Area 2025-10-23 08:00 2025-11-05 17:00 Total Float (d): 55.0 Total float of 55d exceeds 44 days A4720 "Existing Column Reinforcement" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 55d exceeds 44 days)
A4730 Steel Joist Reinforcement Installation 1.4.6.2 Machine Shop Area 2025-11-06 08:00 2025-11-26 17:00 Total Float (d): 55.0 Total float of 55d exceeds 44 days A4730 "Steel Joist Reinforcement Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 55d exceeds 44 days)
A3080 L1, L2 & L3 Air Vapor Barrier Inspection 1.4.5.4.4 East Elevation 2026-04-08 08:00 2026-04-08 08:00 Total Float (d): 54.0 Total float of 54d exceeds 44 days A3080 "L1, L2 & L3 Air Vapor Barrier Inspection" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 54d exceeds 44 days)
A2910 Glazing Site Measure and Scanning 1.4.5.4.2 West Elevation 2026-02-17 08:00 2026-02-17 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A2910 "Glazing Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A2920 Glazing Shop Fabrication 1.4.5.4.2 West Elevation 2026-02-18 08:00 2026-03-17 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A2920 "Glazing Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A2930 L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) 1.4.5.4.2 West Elevation 2026-03-18 08:00 2026-04-22 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A2930 "L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A2940 Exterior Cladding Site Measure and Scanning 1.4.5.4.2 West Elevation 2026-04-23 08:00 2026-04-23 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A2940 "Exterior Cladding Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A2950 Exterior Cladding Shop Fabrication 1.4.5.4.2 West Elevation 2026-04-24 08:00 2026-05-22 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A2950 "Exterior Cladding Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A2960 L2 & L3 Cladding Installation (EW2) 1.4.5.4.2 West Elevation 2026-05-25 08:00 2026-06-19 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A2960 "L2 & L3 Cladding Installation (EW2)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A2990 Glazing Site Measure and Scanning 1.4.5.4.3 South Elevation 2026-03-10 08:00 2026-03-10 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A2990 "Glazing Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A3000 Glazing Shop Fabrication 1.4.5.4.3 South Elevation 2026-03-11 08:00 2026-04-08 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A3000 "Glazing Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A3010 L2 & L3 Exterior Glazing Installation (W08a, W08b) 1.4.5.4.3 South Elevation 2026-04-09 08:00 2026-04-15 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A3010 "L2 & L3 Exterior Glazing Installation (W08a, W08b)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A3020 Exterior Cladding Site Measure and Scanning 1.4.5.4.3 South Elevation 2026-04-16 08:00 2026-04-16 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A3020 "Exterior Cladding Site Measure and Scanning" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A3030 Exterior Cladding Shop Fabrication 1.4.5.4.3 South Elevation 2026-04-17 08:00 2026-05-14 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A3030 "Exterior Cladding Shop Fabrication" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A3040 L2 & L3 Cladding Installation (EW2) 1.4.5.4.3 South Elevation 2026-05-15 08:00 2026-06-12 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A3040 "L2 & L3 Cladding Installation (EW2)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A3050 Horizontal Shading Louvers 1.4.5.4.3 South Elevation 2026-06-15 08:00 2026-06-19 17:00 Total Float (d): 53.0 Total float of 53d exceeds 44 days A3050 "Horizontal Shading Louvers" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 53d exceeds 44 days)
A1960 23 74 13 - Air Handling Units 1.3.34 Mechanical Equipment 2025-08-29 08:00 2026-05-15 17:00 Total Float (d): 52.0 Total float of 52d exceeds 44 days A1960 "23 74 13 - Air Handling Units" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 52d exceeds 44 days)
A5230 Footings and Piers Along GL-B.1 (Successor to CO-005) 1 Phase 2 - Foundation Work 2025-08-15 08:00 2025-08-21 17:00 Total Float (d): 52.0 Total float of 52d exceeds 44 days A5230 "Footings and Piers Along GL-B.1 (Successor to CO-005)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 52d exceeds 44 days)
A1470.1 23 37 13 - Diffuser and Grilles Shop Drawings (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-09-05 08:00 2025-09-18 17:00 Total Float (d): 49.0 Total float of 49d exceeds 44 days A1470.1 "23 37 13 - Diffuser and Grilles Shop Drawings (R1)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 49d exceeds 44 days)
A2060 23 37 13 - Diffuser and Grilles 1.3.34 Mechanical Equipment 2025-09-19 08:00 2026-02-10 17:00 Total Float (d): 49.0 Total float of 49d exceeds 44 days A2060 "23 37 13 - Diffuser and Grilles" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 49d exceeds 44 days)
A1360.2 23 82 19 - Fan Coil Units (R2) 1.2.38 Mechanical Equipment Shop Drawings 2025-08-25 08:00 2025-09-08 17:00 Total Float (d): 48.0 Total float of 48d exceeds 44 days A1360.2 "23 82 19 - Fan Coil Units (R2)" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 48d exceeds 44 days)
A2550x R6 - RFI 60 Sprinkler Diesel Pump 1.4.2 Potential Schedule Impact (RISK) 2025-08-21 08:00 2025-08-27 17:00 Total Float (d): 48.0 Total float of 48d exceeds 44 days A2550x "R6 - RFI 60 Sprinkler Diesel Pump " - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 48d exceeds 44 days)
A2720 Tactile Attention Indicators Mock-up 1.4.5.3 Phase 3 - Building Erection 2026-01-28 08:00 2026-01-28 17:00 Total Float (d): 48.0 Total float of 48d exceeds 44 days A2720 "Tactile Attention Indicators Mock-up" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 48d exceeds 44 days)
A3160 Roof Penetration Layout 1.4.5.4.5 Roofing 2025-12-15 08:00 2025-12-16 17:00 Total Float (d): 46.0 Total float of 46d exceeds 44 days A3160 "Roof Penetration Layout" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 46d exceeds 44 days)
A4580 New Columns Installation 1.4.6.1.2 Phase 2 - Existing Spray Booth Demo, Storage and Corridor & New Vestibule Demo 2025-10-23 08:00 2025-11-05 17:00 Total Float (d): 45.0 Total float of 45d exceeds 44 days A4580 "New Columns Installation" - Total float exceeds the high-float threshold (>44 working days). Likely missing or incorrect successor logic. (Total float of 45d exceeds 44 days)
🔧 Corrective Action Plan
Activities with > 44 days of total float
  1. 1Sort the activity list by Total Float descending. Anything over 44 working days needs scrutiny.
  2. 2First check: does the activity have a successor at all? Open-ended activities float to infinity. Add the missing successor.
  3. 3Second check: is it on the wrong calendar? A 5-day activity on a 7-day calendar will read very differently from one on a Mon-Fri calendar.
  4. 4Third check: is the scope actually optional? If yes, mark it LOE or move it to a separate WBS so it stops contaminating the critical-path calc.
Heads up
High-float work is where most contractors hide bad logic. The reviewer's eye goes to the critical path; everything else gets a free pass. That's where the schedule rot starts.
C7

Negative Float

287 checked
0 failed
100%
PASS
Negative total float indicates activities calculated as finishing later than the schedule's driving completion date/constraint. This check flags any eligible activities with negative total float. Note: if the contractual finish is not modeled to drive float, negative float may be zero even when the forecast finish is later than the baseline/contract finish.
Manual Override:
📋 Assessment
PASS - Zero negative float. Schedule is not over-constrained and can calculate properly.
🔧 Corrective Action Plan
C8

High Duration

287 checked
38 failed
87%
FAIL
Activity durations shall be reasonable (≤44 working days).
Manual Override:
📋 Assessment
FAILED - 38 activities exceed 44 working days. Long-duration activities reduce schedule control and make progress measurement difficult. Break into smaller tasks.
⚠️ Failed Activities (38 activities)
ACTIVITY ID ACTIVITY NAME WBS START DATE FINISH DATE KEY METRIC ISSUE RECOMMENDED FIX
A2110 23 74 13 - Air Source Heat Pump 1.3.34 Mechanical Equipment 2025-07-18 08:00 2026-06-05 17:00 Duration (d): 224.0 Duration of 224d exceeds 44 days A2110 "23 74 13 - Air Source Heat Pump" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 224d exceeds 44 days)
A2160 27 10 00 - Structural Cabling System (Fiber Optic Cable) 1.3.35 Electrical Power Distribution Equipment 2025-07-23 08:00 2026-04-14 17:00 Duration (d): 183.0 Duration of 183d exceeds 44 days A2160 "27 10 00 - Structural Cabling System (Fiber Optic Cable)" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 183d exceeds 44 days)
A1960 23 74 13 - Air Handling Units 1.3.34 Mechanical Equipment 2025-08-29 08:00 2026-05-15 17:00 Duration (d): 180.0 Duration of 180d exceeds 44 days A1960 "23 74 13 - Air Handling Units" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 180d exceeds 44 days)
A1980 23 25 00 - Buffer Tanks 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-12-24 17:00 Duration (d): 120.0 Duration of 120d exceeds 44 days A1980 "23 25 00 - Buffer Tanks" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 120d exceeds 44 days)
A3850 Foundations 1.4.5.6 Phase 6 - Pedestrian Bridge Construction 2025-09-10 08:00 2026-02-24 17:00 Duration (d): 116.0 Duration of 116d exceeds 44 days A3850 "Foundations" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 116d exceeds 44 days)
A1950 23 82 19 - Fan Coil Units 1.3.34 Mechanical Equipment 2025-09-30 08:00 2026-03-06 17:00 Duration (d): 109.0 Duration of 109d exceeds 44 days A1950 "23 82 19 - Fan Coil Units" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 109d exceeds 44 days)
A1930 Hydraulic Lift 1.3 Procurement 2025-07-10 08:00 2025-12-01 17:00 Duration (d): 101.0 Duration of 101d exceeds 44 days A1930 "Hydraulic Lift " - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 101d exceeds 44 days)
A1820 Coiling Doors 1.3 Procurement 2025-08-22 08:00 2026-01-14 17:00 Duration (d): 100.0 Duration of 100d exceeds 44 days A1820 "Coiling Doors" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 100d exceeds 44 days)
A1970 23 21 23 - Pumps 1.3.34 Mechanical Equipment 2025-08-20 08:00 2026-01-12 17:00 Duration (d): 100.0 Duration of 100d exceeds 44 days A1970 "23 21 23 - Pumps" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 100d exceeds 44 days)
A2050 23 25 00 - Water Treatment 1.3.34 Mechanical Equipment 2025-09-08 08:00 2026-01-28 17:00 Duration (d): 100.0 Duration of 100d exceeds 44 days A2050 "23 25 00 - Water Treatment" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 100d exceeds 44 days)
A2060 23 37 13 - Diffuser and Grilles 1.3.34 Mechanical Equipment 2025-09-19 08:00 2026-02-10 17:00 Duration (d): 100.0 Duration of 100d exceeds 44 days A2060 "23 37 13 - Diffuser and Grilles" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 100d exceeds 44 days)
A2090 23 52 16 - Heating Boilers 1.3.34 Mechanical Equipment 2025-09-26 08:00 2026-02-18 17:00 Duration (d): 100.0 Duration of 100d exceeds 44 days A2090 "23 52 16 - Heating Boilers" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 100d exceeds 44 days)
A2120 20 05 10 - Electric Heat Tracing 1.3.34 Mechanical Equipment 2025-08-27 08:00 2026-01-19 17:00 Duration (d): 100.0 Duration of 100d exceeds 44 days A2120 "20 05 10 - Electric Heat Tracing" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 100d exceeds 44 days)
A2130 22 40 00 - Plumbing Fixtures 1.3.34 Mechanical Equipment 2025-08-28 08:00 2026-01-20 17:00 Duration (d): 100.0 Duration of 100d exceeds 44 days A2130 "22 40 00 - Plumbing Fixtures" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 100d exceeds 44 days)
A2180 26 09 23 - Lighting Control 1.3.35 Electrical Power Distribution Equipment 2025-09-03 08:00 2026-01-23 17:00 Duration (d): 100.0 Duration of 100d exceeds 44 days A2180 "26 09 23 - Lighting Control" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 100d exceeds 44 days)
A1840 Finished Hardware 1.3 Procurement 2025-07-30 08:00 2025-12-05 17:00 Duration (d): 91.0 Duration of 91d exceeds 44 days A1840 "Finished Hardware " - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 91d exceeds 44 days)
2170 26 50 00 - Emergency Lighting & Exit Signs 1.3.35 Electrical Power Distribution Equipment 2025-07-30 08:00 2025-12-05 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days 2170 "26 50 00 - Emergency Lighting & Exit Signs" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A1800 Interior Aluminum Screens 1.3 Procurement 2025-08-11 08:00 2025-12-16 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A1800 "Interior Aluminum Screens" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A1990 23 21 16 - Air Separator 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A1990 "23 21 16 - Air Separator" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A2000 23 21 16 - Expansion Tanks 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A2000 "23 21 16 - Expansion Tanks" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A2010 23 57 00 - Heat Exchangers 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A2010 "23 57 00 - Heat Exchangers" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A2020 22 33 00 - Electric Domestic Water Heaters 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A2020 "22 33 00 - Electric Domestic Water Heaters" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A2030 23 81 26 - Split System 1.3.34 Mechanical Equipment 2025-07-10 08:00 2025-11-17 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A2030 "23 81 26 - Split System" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A2100 23 00 00 - Wall Fin Heater 1.3.34 Mechanical Equipment 2025-08-13 08:00 2025-12-18 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A2100 "23 00 00 - Wall Fin Heater" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A2140 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes 1.3.35 Electrical Power Distribution Equipment 2025-07-09 08:00 2025-11-14 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A2140 "26 27 26 - Wiring Devices, Service Poles, & Floor Boxes" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A2150 26 50 00 - Lighting Fixtures 1.3.35 Electrical Power Distribution Equipment 2025-08-19 08:00 2025-12-25 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A2150 "26 50 00 - Lighting Fixtures" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A2190 28 31 00 - Fire Alarm 1.3.35 Electrical Power Distribution Equipment 2025-06-18 08:00 2025-10-27 17:00 Duration (d): 90.0 Duration of 90d exceeds 44 days A2190 "28 31 00 - Fire Alarm" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 90d exceeds 44 days)
A1710 Misc. Metals 1.3 Procurement 2025-10-03 08:00 2026-01-27 17:00 Duration (d): 80.0 Duration of 80d exceeds 44 days A1710 "Misc. Metals " - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 80d exceeds 44 days)
A1830 Aluminum Framed Glazing Systems 1.3 Procurement 2025-08-07 08:00 2025-11-28 17:00 Duration (d): 80.0 Duration of 80d exceeds 44 days A1830 "Aluminum Framed Glazing Systems" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 80d exceeds 44 days)
A2080 23 00 00 - Unit Heater 1.3.34 Mechanical Equipment 2025-08-29 08:00 2025-12-18 17:00 Duration (d): 78.0 Duration of 78d exceeds 44 days A2080 "23 00 00 - Unit Heater" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 78d exceeds 44 days)
A1810 Flush Wood Doors 1.3 Procurement 2025-08-28 08:00 2025-12-12 17:00 Duration (d): 75.0 Duration of 75d exceeds 44 days A1810 "Flush Wood Doors " - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 75d exceeds 44 days)
A2070 23 00 00 - Exhaust Fans 1.3.34 Mechanical Equipment 2025-09-09 08:00 2025-12-18 17:00 Duration (d): 72.0 Duration of 72d exceeds 44 days A2070 "23 00 00 - Exhaust Fans" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 72d exceeds 44 days)
A1790 Hollow Metal Doors 1.3 Procurement 2025-07-30 08:00 2025-10-24 17:00 Duration (d): 61.0 Duration of 61d exceeds 44 days A1790 "Hollow Metal Doors" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 61d exceeds 44 days)
A1890 Flooring 1.3 Procurement 2025-07-30 08:00 2025-10-24 17:00 Duration (d): 61.0 Duration of 61d exceeds 44 days A1890 "Flooring " - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 61d exceeds 44 days)
A1760 Exterior Wall Cladding 1.3 Procurement 2025-08-25 08:00 2025-11-18 17:00 Duration (d): 60.0 Duration of 60d exceeds 44 days A1760 "Exterior Wall Cladding" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 60d exceeds 44 days)
A1920 Fall Arrest Anchors and Horizontal Lines 1.3 Procurement 2025-08-28 08:00 2025-11-21 17:00 Duration (d): 60.0 Duration of 60d exceeds 44 days A1920 "Fall Arrest Anchors and Horizontal Lines" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 60d exceeds 44 days)
A2210 Landscape (unit pavers, furniture, etc) 1.3 Procurement 2025-08-07 08:00 2025-10-31 17:00 Duration (d): 60.0 Duration of 60d exceeds 44 days A2210 "Landscape (unit pavers, furniture, etc)" - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 60d exceeds 44 days)
A1720 Millwork 1.3 Procurement 2025-07-30 08:00 2025-10-09 17:00 Duration (d): 51.0 Duration of 51d exceeds 44 days A1720 "Millwork " - Remaining duration exceeds 44 working days. Break into smaller, monitorable pieces. (Duration of 51d exceeds 44 days)
🔧 Corrective Action Plan
Activities longer than 44 working days
  1. 1Sort by Original Duration descending. Anything over 44 working days gets a hard look.
  2. 2LOE activities (project management, supervision, dewatering) can stay long with a Notebook entry explaining why.
  3. 3Real work activities get split. Find a natural breakpoint — a deck pour, a floor finish, a system test — and split there.
  4. 4Add interim milestones at the breakpoints so progress reporting actually means something. A 90-day activity at 45% complete tells you nothing; two 45-day activities, one done and one 0%, tells you everything.
Heads up
A long activity with high % complete is a black box. You can't tell if the back half is on track until it's too late. The DCMA-14 industry-standard guideline recommends activity duration ≤44 days for tracking granularity; your contract may permit longer durations on intentionally aggregated work.
C9

Valid Dates

395 checked
103 failed
74%
FAIL
All activity dates shall be valid and logically sequenced.
Manual Override:
📋 Assessment
FAILED - 103 activities have dates inconsistent with the Status (Data) Date (forecast dates in the past and/or actual dates after the status date). Update progress and reschedule to remove dates that fall outside the status window.
⚠️ Failed Activities (103 activities)
ACTIVITY ID ACTIVITY NAME WBS START DATE FINISH DATE KEY METRIC ISSUE RECOMMENDED FIX
2170 26 50 00 - Emergency Lighting & Exit Signs 1.3.35 Electrical Power Distribution Equipment 2025-07-30 08:00 2025-12-05 17:00 Actual start (2025-07-30) after status date (2025-07-01) 2170 "26 50 00 - Emergency Lighting & Exit Signs" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1060 Foundation Concrete Rebar Shop Drawing 1.2 Shop Drawings 2025-05-29 08:00 2025-07-08 17:00 Actual finish (2025-07-08) after status date (2025-07-01) A1060 "Foundation Concrete Rebar Shop Drawing" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1080 Bentonite Waterstop Data Sheet 1.2 Shop Drawings 2025-06-09 08:00 2025-07-02 17:00 Actual finish (2025-07-02) after status date (2025-07-01) A1080 "Bentonite Waterstop Data Sheet" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1090 Masonry and Mortar Samples & Data Sheets 1.2 Shop Drawings 2025-06-10 08:00 2025-08-18 17:00 Actual finish (2025-08-18) after status date (2025-07-01) A1090 "Masonry and Mortar Samples & Data Sheets" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1100 Structural Steel Framing and Steel Deck Shop Drawings (R0) 1.2 Shop Drawings 2025-06-20 08:00 2025-07-14 17:00 Actual finish (2025-07-14) after status date (2025-07-01) A1100 "Structural Steel Framing and Steel Deck Shop Drawings (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1100.1 Structural Steel Framing and Steel Deck Shop Drawings (R1) 1.2 Shop Drawings 2025-08-08 08:00 2025-08-25 17:00 Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-25) after status date (2025-07-01) A1100.1 "Structural Steel Framing and Steel Deck Shop Drawings (R1)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1100.2 Structural Steel Framing and Steel Deck Shop Drawings (R2) 1.2 Shop Drawings 2025-08-28 08:00 2025-09-04 17:00 Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) A1100.2 "Structural Steel Framing and Steel Deck Shop Drawings (R2)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1110 Structural Reinforcement + Decking Shop Drawings 1.2 Shop Drawings 2025-08-01 08:00 2025-08-01 08:00 Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-01) after status date (2025-07-01) A1110 "Structural Reinforcement + Decking Shop Drawings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1120 Cold-formed Metal Framing Shop Drawings 1.2 Shop Drawings 2025-06-26 08:00 2025-07-23 17:00 Actual finish (2025-07-23) after status date (2025-07-01) A1120 "Cold-formed Metal Framing Shop Drawings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1130 Misc. Metals Shop Drawings 1.2 Shop Drawings 2025-08-26 08:00 2025-10-02 17:00 Actual start (2025-08-26) after status date (2025-07-01) A1130 "Misc. Metals Shop Drawings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1150 Built-up Roofing Shop Drawings 1.2 Shop Drawings 2025-06-19 08:00 2025-07-09 17:00 Actual finish (2025-07-09) after status date (2025-07-01) A1150 "Built-up Roofing Shop Drawings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1160 TPO Roofing Shop Drawings 1.2 Shop Drawings 2025-07-09 08:00 2025-08-26 17:00 Actual start (2025-07-09) after status date (2025-07-01) | Actual finish (2025-08-26) after status date (2025-07-01) A1160 "TPO Roofing Shop Drawings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1180 Exterior Wall Cladding Shop Drawings 1.2 Shop Drawings 2025-08-11 08:00 2025-08-22 17:00 Actual start (2025-08-11) after status date (2025-07-01) A1180 "Exterior Wall Cladding Shop Drawings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1190 Fire-resistive Material Data Sheet 1.2 Shop Drawings 2025-06-27 08:00 2025-07-09 17:00 Actual finish (2025-07-09) after status date (2025-07-01) A1190 "Fire-resistive Material Data Sheet" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1210 Interior Aluminum Screen 1.2 Shop Drawings 2025-07-25 08:00 2025-08-08 17:00 Actual start (2025-07-25) after status date (2025-07-01) A1210 "Interior Aluminum Screen" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1220 Flush Wood Doors Sample 1.2 Shop Drawings 2025-08-26 08:00 2025-08-27 17:00 Actual start (2025-08-26) after status date (2025-07-01) | Actual finish (2025-08-27) after status date (2025-07-01) A1220 "Flush Wood Doors Sample" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1230 Coiling Doors 1.2 Shop Drawings 2025-08-05 08:00 2025-08-21 17:00 Actual start (2025-08-05) after status date (2025-07-01) | Actual finish (2025-08-21) after status date (2025-07-01) A1230 "Coiling Doors" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A12380.1 23 21 23 - Pumps (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-07-22 08:00 2025-08-19 17:00 Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-19) after status date (2025-07-01) A12380.1 "23 21 23 - Pumps (R1)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1280 ACT Data sheet and Sample 1.2 Shop Drawings 2025-07-23 08:00 2025-08-27 17:00 Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-08-27) after status date (2025-07-01) A1280 "ACT Data sheet and Sample" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1280.1 ACB Data sheet and Sample 1.2 Shop Drawings 2025-07-23 08:00 2025-09-04 17:00 Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) A1280.1 "ACB Data sheet and Sample" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1290 Suspended Metal Soffits 1.2 Shop Drawings 2025-08-28 08:00 2025-09-04 17:00 Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) A1290 "Suspended Metal Soffits" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1330 Fall Arrest Anchors and Horizontal Lines 1.2 Shop Drawings 2025-08-14 08:00 2025-08-27 17:00 Actual start (2025-08-14) after status date (2025-07-01) A1330 "Fall Arrest Anchors and Horizontal Lines" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1340 Hydraulic Lift Shop Drawings 1.2 Shop Drawings 2025-06-26 08:00 2025-07-09 17:00 Actual finish (2025-07-09) after status date (2025-07-01) A1340 "Hydraulic Lift Shop Drawings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1360 23 82 19 - Fan Coil Units (R0) 1.2.38 Mechanical Equipment Shop Drawings 2025-06-19 08:00 2025-07-03 17:00 Actual finish (2025-07-03) after status date (2025-07-01) A1360 "23 82 19 - Fan Coil Units (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1360.1 23 82 19 - Fan Coil Units (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-07-22 08:00 2025-08-12 17:00 Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) A1360.1 "23 82 19 - Fan Coil Units (R1)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1360.2 23 82 19 - Fan Coil Units (R2) 1.2.38 Mechanical Equipment Shop Drawings 2025-08-25 08:00 2025-09-08 17:00 Actual start (2025-08-25) after status date (2025-07-01) A1360.2 "23 82 19 - Fan Coil Units (R2)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1370 23 74 13 - Air Handling Units (R0) 1.2.38 Mechanical Equipment Shop Drawings 2025-06-26 08:00 2025-07-21 17:00 Actual finish (2025-07-21) after status date (2025-07-01) A1370 "23 74 13 - Air Handling Units (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1370,1 23 74 13 - Air Handling Units (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-08-08 08:00 2025-08-28 17:00 Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-28) after status date (2025-07-01) A1370,1 "23 74 13 - Air Handling Units (R1)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1380 23 21 23 - Pumps (R0) 1.2.38 Mechanical Equipment Shop Drawings 2025-06-24 08:00 2025-07-04 17:00 Actual finish (2025-07-04) after status date (2025-07-01) A1380 "23 21 23 - Pumps (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1390 23 25 00 - Buffer Tanks 1.2.38 Mechanical Equipment Shop Drawings 2025-06-24 08:00 2025-07-03 17:00 Actual finish (2025-07-03) after status date (2025-07-01) A1390 "23 25 00 - Buffer Tanks" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1400 23 21 16 - Air Separator 1.2.38 Mechanical Equipment Shop Drawings 2025-06-24 08:00 2025-07-03 17:00 Actual finish (2025-07-03) after status date (2025-07-01) A1400 "23 21 16 - Air Separator" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1410 23 21 16 - Expansion Tanks 1.2.38 Mechanical Equipment Shop Drawings 2025-06-24 08:00 2025-07-03 17:00 Actual finish (2025-07-03) after status date (2025-07-01) A1410 "23 21 16 - Expansion Tanks" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1420 23 57 00 - Heat Exchangers 1.2.38 Mechanical Equipment Shop Drawings 2025-06-23 08:00 2025-07-03 17:00 Actual finish (2025-07-03) after status date (2025-07-01) A1420 "23 57 00 - Heat Exchangers" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1430 22 33 00 - Electric Domestic Water Heaters 1.2.38 Mechanical Equipment Shop Drawings 2025-06-19 08:00 2025-07-03 17:00 Actual finish (2025-07-03) after status date (2025-07-01) A1430 "22 33 00 - Electric Domestic Water Heaters" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1460 23 25 00 - Water Treatment (R0) 1.2.38 Mechanical Equipment Shop Drawings 2025-06-26 08:00 2025-08-12 17:00 Actual finish (2025-08-12) after status date (2025-07-01) A1460 "23 25 00 - Water Treatment (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1460.1 23 25 00 - Water Treatment (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-08-22 08:00 2025-09-05 17:00 Actual start (2025-08-22) after status date (2025-07-01) A1460.1 "23 25 00 - Water Treatment (R1)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1470 23 37 13 - Diffuser and Grilles Shop Drawings (R0) 1.2.38 Mechanical Equipment Shop Drawings 2025-07-15 08:00 2025-08-14 17:00 Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-08-14) after status date (2025-07-01) A1470 "23 37 13 - Diffuser and Grilles Shop Drawings (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1470.1 23 37 13 - Diffuser and Grilles Shop Drawings (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-09-05 08:00 2025-09-18 17:00 Actual start (2025-09-05) after status date (2025-07-01) A1470.1 "23 37 13 - Diffuser and Grilles Shop Drawings (R1)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1480.1 23 00 00 - Exhaust Fans (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-09-16 08:00 2025-09-29 17:00 Actual start (2025-09-16) after status date (2025-07-01) A1480.1 "23 00 00 - Exhaust Fans (R1)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1500 23 52 16 - Heating Boilers 1.2.38 Mechanical Equipment Shop Drawings 2025-09-12 08:00 2025-09-25 17:00 Actual start (2025-09-12) after status date (2025-07-01) A1500 "23 52 16 - Heating Boilers" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1510 23 00 00 - Wall Fin Heater 1.2.38 Mechanical Equipment Shop Drawings 2025-07-22 08:00 2025-08-12 17:00 Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) A1510 "23 00 00 - Wall Fin Heater" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1530 20 05 10 - Electric Heat Tracing (R0) 1.2.38 Mechanical Equipment Shop Drawings 2025-07-09 08:00 2025-08-12 17:00 Actual start (2025-07-09) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) A1530 "20 05 10 - Electric Heat Tracing (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1540 22 40 00 - Plumbing Fixtures (R0) 1.2.38 Mechanical Equipment Shop Drawings 2025-07-11 08:00 2025-07-31 17:00 Actual start (2025-07-11) after status date (2025-07-01) | Actual finish (2025-07-31) after status date (2025-07-01) A1540 "22 40 00 - Plumbing Fixtures (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1540.1 22 40 00 - Plumbing Fixtures (R1) 1.2.38 Mechanical Equipment Shop Drawings 2025-08-14 08:00 2025-08-27 17:00 Actual start (2025-08-14) after status date (2025-07-01) A1540.1 "22 40 00 - Plumbing Fixtures (R1)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1550 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes 1.2.39 Electrical Power Distribution Shop Drawings 2025-06-11 08:00 2025-07-08 17:00 Actual finish (2025-07-08) after status date (2025-07-01) A1550 "26 27 26 - Wiring Devices, Service Poles, & Floor Boxes" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1560 26 50 00 - Emergency Lighting & Exit Signs 1.2.39 Electrical Power Distribution Shop Drawings 2025-06-27 08:00 2025-07-29 17:00 Actual finish (2025-07-29) after status date (2025-07-01) A1560 "26 50 00 - Emergency Lighting & Exit Signs" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1570 27 10 00 - Structural Cabling System (Fiber Optic Cable) 1.2.39 Electrical Power Distribution Shop Drawings 2025-07-11 08:00 2025-07-22 17:00 Actual start (2025-07-11) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) A1570 "27 10 00 - Structural Cabling System (Fiber Optic Cable)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1580 26 50 00 - Lighting Fixtures 1.2.39 Electrical Power Distribution Shop Drawings 2025-08-01 08:00 2025-08-18 17:00 Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-18) after status date (2025-07-01) A1580 "26 50 00 - Lighting Fixtures" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1590 26 09 23 - Lighting Control (R0) 1.2.39 Electrical Power Distribution Shop Drawings 2025-08-01 08:00 2025-08-18 17:00 Actual start (2025-08-01) after status date (2025-07-01) | Actual finish (2025-08-18) after status date (2025-07-01) A1590 "26 09 23 - Lighting Control (R0)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1660 Bentonite Waterstop 1.3 Procurement 2025-07-03 08:00 2025-07-09 17:00 Actual start (2025-07-03) after status date (2025-07-01) | Actual finish (2025-07-09) after status date (2025-07-01) A1660 "Bentonite Waterstop " - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1680 Structural Steel 1.3 Procurement 2025-09-04 08:00 2025-10-02 17:00 Actual start (2025-09-04) after status date (2025-07-01) A1680 "Structural Steel " - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1980 23 25 00 - Buffer Tanks 1.3.34 Mechanical Equipment 2025-07-04 08:00 2026-01-08 17:00 Actual start (2025-07-04) after status date (2025-07-01) A1980 "23 25 00 - Buffer Tanks" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A1990 23 21 16 - Air Separator 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Actual start (2025-07-04) after status date (2025-07-01) A1990 "23 21 16 - Air Separator" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2000 23 21 16 - Expansion Tanks 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Actual start (2025-07-04) after status date (2025-07-01) A2000 "23 21 16 - Expansion Tanks" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2010 23 57 00 - Heat Exchangers 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Actual start (2025-07-04) after status date (2025-07-01) A2010 "23 57 00 - Heat Exchangers" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2020 22 33 00 - Electric Domestic Water Heaters 1.3.34 Mechanical Equipment 2025-07-04 08:00 2025-11-11 17:00 Actual start (2025-07-04) after status date (2025-07-01) A2020 "22 33 00 - Electric Domestic Water Heaters" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2030 23 81 26 - Split System 1.3.34 Mechanical Equipment 2025-07-10 08:00 2025-11-17 17:00 Actual start (2025-07-10) after status date (2025-07-01) A2030 "23 81 26 - Split System" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2140 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes 1.3.35 Electrical Power Distribution Equipment 2025-07-09 08:00 2025-11-14 17:00 Actual start (2025-07-09) after status date (2025-07-01) A2140 "26 27 26 - Wiring Devices, Service Poles, & Floor Boxes" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2150 26 50 00 - Lighting Fixtures 1.3.35 Electrical Power Distribution Equipment 2025-08-19 08:00 2026-01-09 17:00 Actual start (2025-08-19) after status date (2025-07-01) A2150 "26 50 00 - Lighting Fixtures" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2160 27 10 00 - Structural Cabling System (Fiber Optic Cable) 1.3.35 Electrical Power Distribution Equipment 2025-07-23 08:00 2026-04-28 17:00 Actual start (2025-07-23) after status date (2025-07-01) A2160 "27 10 00 - Structural Cabling System (Fiber Optic Cable)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2280 Under Pinning Inspection 1.4.5.1 Phase 1 - Early Works 2025-06-23 08:00 2025-07-14 17:00 Actual finish (2025-07-14) after status date (2025-07-01) A2280 "Under Pinning Inspection" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2290 Existing Structure Under Pinning 1.4.5.1 Phase 1 - Early Works 2025-06-24 08:00 2025-07-15 17:00 Actual finish (2025-07-15) after status date (2025-07-01) A2290 "Existing Structure Under Pinning" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2350 Daylighting of Existing Hydro Ductbank & Services 1.4.5.1 Phase 1 - Early Works 2025-06-23 08:00 2025-07-07 17:00 Actual finish (2025-07-07) after status date (2025-07-01) A2350 "Daylighting of Existing Hydro Ductbank & Services" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2360 Ductbank Shoring 1.4.5.1 Phase 1 - Early Works 2025-06-23 08:00 2025-07-08 17:00 Actual finish (2025-07-08) after status date (2025-07-01) A2360 "Ductbank Shoring " - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2370 Bulk Excavation to U/S of Footings 1 Phase 2 - Foundation Work 2025-07-16 08:00 2025-07-22 17:00 Actual start (2025-07-16) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) A2370 "Bulk Excavation to U/S of Footings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2380 Bulk Excavation to U/S North Stair Footing 1 Phase 2 - Foundation Work 2025-07-23 08:00 2025-07-23 17:00 Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) A2380 "Bulk Excavation to U/S North Stair Footing" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2390 Subgrade Inspection 1 Phase 2 - Foundation Work 2025-07-22 08:00 2025-07-22 17:00 Actual start (2025-07-22) after status date (2025-07-01) | Actual finish (2025-07-22) after status date (2025-07-01) A2390 "Subgrade Inspection" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2400 Subgrade Preparation 1 Phase 2 - Foundation Work 2025-07-23 08:00 2025-07-23 17:00 Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) A2400 "Subgrade Preparation" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2410 Soil Bearing Capacity Inspection 1 Phase 2 - Foundation Work 2025-07-24 08:00 2025-07-24 17:00 Actual start (2025-07-24) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) A2410 "Soil Bearing Capacity Inspection" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2410x RFI #17 Demo Clarification 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-06-11 08:00 2025-07-11 17:00 Actual finish (2025-07-11) after status date (2025-07-01) A2410x "RFI #17 Demo Clarification" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2420 Form and Pour North Exit Stair 1 Phase 2 - Foundation Work 2025-08-04 08:00 2025-09-30 17:00 Actual start (2025-08-04) after status date (2025-07-01) A2420 "Form and Pour North Exit Stair" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2420x PC-002 Demo Clarification Issuance 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-07-14 08:00 2025-07-14 17:00 Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-14) after status date (2025-07-01) A2420x "PC-002 Demo Clarification Issuance" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2430 Formwork for Pad Footing (GL:AG-AC & X1-A5) 1 Phase 2 - Foundation Work 2025-07-23 08:00 2025-07-23 17:00 Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-23) after status date (2025-07-01) A2430 "Formwork for Pad Footing (GL:AG-AC & X1-A5)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2430x PCO-008 (Quote) Submission 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-07-15 08:00 2025-07-24 17:00 Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) A2430x "PCO-008 (Quote) Submission" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2440x CO-005 Issuance 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-07-25 08:00 2025-08-07 17:00 Actual start (2025-07-25) after status date (2025-07-01) | Actual finish (2025-08-07) after status date (2025-07-01) A2440x "CO-005 Issuance " - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2450 Rebar for Pad Footings 1 Phase 2 - Foundation Work 2025-07-23 08:00 2025-07-24 17:00 Actual start (2025-07-23) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) A2450 "Rebar for Pad Footings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2450x CD-01 Water Room Demo (Elec. FACP) Issuance 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-07-18 08:00 2025-07-18 17:00 Actual start (2025-07-18) after status date (2025-07-01) | Actual finish (2025-07-18) after status date (2025-07-01) A2450x "CD-01 Water Room Demo (Elec. FACP) Issuance" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2460 Rebar Inspection 1 Phase 2 - Foundation Work 2025-07-25 08:00 2025-07-25 17:00 Actual start (2025-07-25) after status date (2025-07-01) | Actual finish (2025-07-25) after status date (2025-07-01) A2460 "Rebar Inspection" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2460x CD-01 Fire Alarm Panel Relocation 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-07-24 08:00 2025-07-24 17:00 Actual start (2025-07-24) after status date (2025-07-01) | Actual finish (2025-07-24) after status date (2025-07-01) A2460x "CD-01 Fire Alarm Panel Relocation" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2470 Concrete for Pad Footings (GL:AG-AC & X1-A5) 1 Phase 2 - Foundation Work 2025-07-28 08:00 2025-07-28 17:00 Actual start (2025-07-28) after status date (2025-07-01) | Actual finish (2025-07-28) after status date (2025-07-01) A2470 "Concrete for Pad Footings (GL:AG-AC & X1-A5)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2470x Water Room Block Wall Demo 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-08-08 08:00 2025-08-12 17:00 Actual start (2025-08-08) after status date (2025-07-01) | Actual finish (2025-08-12) after status date (2025-07-01) A2470x "Water Room Block Wall Demo" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2480x Existing Vestibule Slab Cutting 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-08-13 08:00 2025-08-13 17:00 Actual start (2025-08-13) after status date (2025-07-01) | Actual finish (2025-08-13) after status date (2025-07-01) A2480x "Existing Vestibule Slab Cutting" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2490 Concrete Field Testing 1 Phase 2 - Foundation Work 2025-07-28 08:00 2025-07-28 17:00 Actual start (2025-07-28) after status date (2025-07-01) | Actual finish (2025-07-28) after status date (2025-07-01) A2490 "Concrete Field Testing" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2490x Existing Vestibule Slab Removal 1.4.1.1 Change Order 005 - PC 002 Demo Clarification 2025-08-14 08:00 2025-08-14 17:00 Actual start (2025-08-14) after status date (2025-07-01) | Actual finish (2025-08-14) after status date (2025-07-01) A2490x "Existing Vestibule Slab Removal" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2500 Install Rebar for Piers 1 Phase 2 - Foundation Work 2025-07-29 08:00 2025-09-08 17:00 Actual start (2025-07-29) after status date (2025-07-01) | Actual finish (2025-09-08) after status date (2025-07-01) A2500 "Install Rebar for Piers" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2500x R1 - RFI #19 & 20 – Existing DCW and Sanitary Line 1.4.2 Potential Schedule Impact (RISK) 2025-06-17 08:00 2025-08-27 17:00 Actual finish (2025-08-27) after status date (2025-07-01) A2500x "R1 - RFI #19 & 20 – Existing DCW and Sanitary Line" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2510 Supply of Embedment & Ankors 1 Phase 2 - Foundation Work 2025-08-22 08:00 2025-08-22 17:00 Actual start (2025-08-22) after status date (2025-07-01) | Actual finish (2025-08-22) after status date (2025-07-01) A2510 "Supply of Embedment & Ankors" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2520 Form and Pour Foundation Piers 1 Phase 2 - Foundation Work 2025-08-11 13:00 2025-09-08 17:00 Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-09-08) after status date (2025-07-01) A2520 "Form and Pour Foundation Piers" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2520x R3 - RFI 45 - City of Barrie Water Department – Request to Review Drawings 1.4.2 Potential Schedule Impact (RISK) 2025-07-31 08:00 2025-09-04 17:00 Actual start (2025-07-31) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) A2520x "R3 - RFI 45 - City of Barrie Water Department – Request to Review Drawings" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2530 Backfilling to U/S of Grade Beams 1 Phase 2 - Foundation Work 2025-08-11 08:00 2025-09-12 12:00 Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-09-12) after status date (2025-07-01) A2530 "Backfilling to U/S of Grade Beams" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2530x R4 - PC-004 Grade Beam Rebar 1.4.2 Potential Schedule Impact (RISK) 2025-07-15 08:00 2025-09-10 17:00 Actual start (2025-07-15) after status date (2025-07-01) | Actual finish (2025-09-10) after status date (2025-07-01) A2530x "R4 - PC-004 Grade Beam Rebar" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2540x R5 - RFI #39R2 Jewelery Workshop Interior Fitout 1.4.2 Potential Schedule Impact (RISK) 2025-07-17 08:00 2025-09-04 17:00 Actual start (2025-07-17) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) A2540x "R5 - RFI #39R2 Jewelery Workshop Interior Fitout" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2550x R6 - RFI 60 Sprinkler Diesel Pump 1.4.2 Potential Schedule Impact (RISK) 2025-08-21 08:00 2025-08-27 17:00 Actual start (2025-08-21) after status date (2025-07-01) A2550x "R6 - RFI 60 Sprinkler Diesel Pump " - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A2600 Compaction Inspection 1 Phase 2 - Foundation Work 2025-08-15 08:00 2025-08-15 17:00 Actual start (2025-08-15) after status date (2025-07-01) | Actual finish (2025-08-15) after status date (2025-07-01) A2600 "Compaction Inspection" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A3920 Setup Temporary Hoarding 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-07-04 08:00 2025-07-04 17:00 Actual start (2025-07-04) after status date (2025-07-01) | Actual finish (2025-07-04) after status date (2025-07-01) A3920 "Setup Temporary Hoarding" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A3930 Interior Demoilition 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-07-21 08:00 2025-09-02 17:00 Actual start (2025-07-21) after status date (2025-07-01) | Actual finish (2025-09-02) after status date (2025-07-01) A3930 "Interior Demoilition" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A3960 Vinyl Flooring Abatement (Cash Allowance) 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-07-07 08:00 2025-07-11 17:00 Actual start (2025-07-07) after status date (2025-07-01) | Actual finish (2025-07-11) after status date (2025-07-01) A3960 "Vinyl Flooring Abatement (Cash Allowance)" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A4340 Electrical and Mechanical Make Safe 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-07-14 08:00 2025-07-18 17:00 Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-18) after status date (2025-07-01) A4340 "Electrical and Mechanical Make Safe" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A4390 Review Interferences with Steel Joist 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-08-11 08:00 2025-08-15 17:00 Actual start (2025-08-11) after status date (2025-07-01) | Actual finish (2025-08-15) after status date (2025-07-01) A4390 "Review Interferences with Steel Joist" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A4410 Joist Interferences Relocation 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-08-16 08:00 2025-08-22 17:00 Actual start (2025-08-16) after status date (2025-07-01) | Actual finish (2025-08-22) after status date (2025-07-01) A4410 "Joist Interferences Relocation" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A5070 Removal of Existing Water and Sanitary 1 Phase 2 - Foundation Work 2025-07-14 08:00 2025-07-14 17:00 Actual start (2025-07-14) after status date (2025-07-01) | Actual finish (2025-07-14) after status date (2025-07-01) A5070 "Removal of Existing Water and Sanitary" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A5220 Weather Impact (Rain) - August 28, 2025 1 Phase 2 - Foundation Work 2025-08-28 08:00 2025-08-28 17:00 Actual start (2025-08-28) after status date (2025-07-01) | Actual finish (2025-08-28) after status date (2025-07-01) A5220 "Weather Impact (Rain) - August 28, 2025" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
A5250 Weather Impact (Rain) - September 04, 2025 1 Phase 2 - Foundation Work 2025-09-04 08:00 2025-09-04 17:00 Actual start (2025-09-04) after status date (2025-07-01) | Actual finish (2025-09-04) after status date (2025-07-01) A5250 "Weather Impact (Rain) - September 04, 2025" - Actual dates are after the project status date. Either advance the Data Date and reschedule, or correct the actual dates/status coding.
🔧 Corrective Action Plan
Activities with invalid actual or forecast dates
  1. 1Run Tools > Schedule with the Date Check option on. Look for Actual Start or Actual Finish AFTER the data date — that's a data-entry error 100% of the time.
  2. 2In-progress activities with remaining duration = 0 but % complete < 100: either status it complete or restore the remaining duration.
  3. 3Verify the data date is right (Project > Properties). Then F9 with 'Recalculate retained logic'.
  4. 4Check the trades who entered actuals — usually one person mass-entered the wrong week.
Heads up
Bad actuals corrupt every forecast downstream. CPLI, BEI, finish variance — none of them mean anything until the dates are clean.
C10

Resources

282 checked
0 failed
100%
N/A
Resources shall be assigned to activities to enable workload analysis and schedule realism validation.
Manual Override:
%
📋 Assessment
NOT SCORED (N/A) — TASKRSRC section not found in XER export. (282 eligible activities ≥1d)
🔧 Corrective Action Plan
C11

Missed Tasks

38 checked
19 failed
50%
FAIL
Tasks that should have started or completed shall be managed.
Manual Override:
📋 Assessment
FAILED - 19 missed tasks (activities that should have started/completed by data date but remain unupdated). Schedule not being properly maintained.
⚠️ Failed Activities (19 activities)
ACTIVITY ID ACTIVITY NAME WBS START DATE FINISH DATE KEY METRIC ISSUE RECOMMENDED FIX
A3940 Existing Slab Removal and Trenching 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-09-03 08:00 2025-09-09 17:00 Days late: 78d Forecast finish 78d later than baseline (2025-06-23) A3940 "Existing Slab Removal and Trenching" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Forecast finish 78d later than baseline (2025-06-23))
A1160 TPO Roofing Shop Drawings 1.2 Shop Drawings 2025-07-09 08:00 2025-08-26 17:00 Days late: 64d Actual finish 64d later than baseline (2025-06-23) A1160 "TPO Roofing Shop Drawings" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 64d later than baseline (2025-06-23))
A2510 Supply of Embedment & Ankors 1 Phase 2 - Foundation Work 2025-08-22 08:00 2025-08-22 17:00 Days late: 59d Actual finish 59d later than baseline (2025-06-24) A2510 "Supply of Embedment & Ankors" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 59d later than baseline (2025-06-24))
A1590 26 09 23 - Lighting Control 1.2.39 Electrical Power Distribution Shop Drawings 2025-08-01 08:00 2025-08-18 17:00 Days late: 49d Actual finish 49d later than baseline (2025-06-30) A1590 "26 09 23 - Lighting Control" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 49d later than baseline (2025-06-30))
A1110 Structural Reinforcement Shop Drawings 1.2 Shop Drawings 2025-08-01 08:00 2025-08-01 08:00 Days late: 39d Actual finish 39d later than baseline (2025-06-23) A1110 "Structural Reinforcement Shop Drawings" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 39d later than baseline (2025-06-23))
A1120 Cold-formed Metal Framing Shop Drawings 1.2 Shop Drawings 2025-06-26 08:00 2025-07-23 17:00 Days late: 30d Actual finish 30d later than baseline (2025-06-23) A1120 "Cold-formed Metal Framing Shop Drawings" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 30d later than baseline (2025-06-23))
A1100 Structural Steel Framing and Steel Deck Shop Drawings 1.2 Shop Drawings 2025-06-20 08:00 2025-07-14 17:00 Days late: 21d Actual finish 21d later than baseline (2025-06-23) A1100 "Structural Steel Framing and Steel Deck Shop Drawings" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 21d later than baseline (2025-06-23))
A2280 Under Pinning Inspection 1.4.5.1 Phase 1 - Early Works 2025-06-23 08:00 2025-07-14 17:00 Days late: 20d Actual finish 20d later than baseline (2025-06-24) A2280 "Under Pinning Inspection" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 20d later than baseline (2025-06-24))
A3920 Setup Hoarding at Existing Areas 1.4.6.1.1 Phase 1 - Storage Relocation & Washrooms/Offices & CNC Relocation 2025-07-04 08:00 2025-07-04 17:00 Days late: 17d Actual finish 17d later than baseline (2025-06-17) A3920 "Setup Hoarding at Existing Areas" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 17d later than baseline (2025-06-17))
A1060 Foundation Concrete Rebar Shop Drawing 1.2 Shop Drawings 2025-05-29 08:00 2025-07-08 17:00 Days late: 15d Actual finish 15d later than baseline (2025-06-23) A1060 "Foundation Concrete Rebar Shop Drawing" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 15d later than baseline (2025-06-23))
A1050 Ductbank Underpinning Drawing 1.2 Shop Drawings 2025-06-16 08:00 2025-06-30 17:00 Days late: 14d Actual finish 14d later than baseline (2025-06-16) A1050 "Ductbank Underpinning Drawing" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 14d later than baseline (2025-06-16))
A1550 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes 1.2.39 Electrical Power Distribution Shop Drawings 2025-06-11 08:00 2025-07-08 17:00 Days late: 14d Actual finish 14d later than baseline (2025-06-24) A1550 "26 27 26 - Wiring Devices, Service Poles, & Floor Boxes" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 14d later than baseline (2025-06-24))
A1080 Bentonite Waterstop Data Sheet 1.2 Shop Drawings 2025-06-09 08:00 2025-07-02 17:00 Days late: 9d Actual finish 9d later than baseline (2025-06-23) A1080 "Bentonite Waterstop Data Sheet" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 9d later than baseline (2025-06-23))
A1660 Bentonite Waterstop 1.3 Procurement 2025-07-03 08:00 2025-07-09 17:00 Days late: 9d Actual finish 9d later than baseline (2025-06-30) A1660 "Bentonite Waterstop " - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 9d later than baseline (2025-06-30))
A2220 Testing and Inspection Cash Allowance Expenditure 1.3 Procurement 2025-07-02 08:00 2025-07-02 08:00 Days late: 6d Forecast finish 6d later than baseline (2025-06-26) A2220 "Testing and Inspection Cash Allowance Expenditure" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Forecast finish 6d later than baseline (2025-06-26))
A1070 Foundation Concrete Mix Design 1.2 Shop Drawings 2025-06-13 08:00 2025-06-25 17:00 Days late: 2d Actual finish 2d later than baseline (2025-06-23) A1070 "Foundation Concrete Mix Design" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 2d later than baseline (2025-06-23))
A1650 Foundation Concrete Mix Design 1.3 Procurement 2025-06-26 08:00 2025-06-27 17:00 Days late: 2d Actual finish 2d later than baseline (2025-06-25) A1650 "Foundation Concrete Mix Design" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 2d later than baseline (2025-06-25))
A1030 IFC Drawings Released 1.1 Preconstruction 2025-05-15 08:00 2025-05-15 17:00 Days late: 1d Actual finish 1d later than baseline (2025-05-14) A1030 "IFC Drawings Released" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 1d later than baseline (2025-05-14))
A1040 Permit (Not Required Per SAMPLE PROJECT) 1.1 Preconstruction 2025-05-16 08:00 2025-05-16 17:00 Days late: 1d Actual finish 1d later than baseline (2025-05-15) A1040 "Permit (Not Required Per SAMPLE PROJECT)" - Activity end date is past the data date but is not statused complete. Log actual finish or revise remaining duration. (Actual finish 1d later than baseline (2025-05-15))
🔧 Corrective Action Plan
Activities behind plan as of the data date
  1. 1Filter for Activity Status = Not Started where Early Start < Data Date — these should have started but didn't.
  2. 2Filter for Activity Status = In Progress where Early Finish < Data Date — these should be done but aren't.
  3. 3Status each one: actual start/finish if the work is done, updated remaining duration if it's still going, delay reason in the Notebook if it slipped.
  4. 4Talk to the project manager about each missed item. If the cause is owner-driven (RFI, change, access), flag it for a potential claim before the trail goes cold.
Heads up
A missed task isn't a schedule problem — it's an execution signal. The schedule's job is to make it visible. If you 'fix' it by sliding the dates without statusing what actually happened, you've buried the evidence.
C12

Critical Path Test

PASS
Network integrity and critical path coherence: no logic cycles; finish must be reachable from start; and critical (TF≤0) activities should form a coherent chain. SCREENING TOOL ONLY: This dashboard performs network-integrity checks (no cycles + connected critical chain ≥90%). It does NOT replicate the formal DCMA C12 perturbation test, which requires perturbing each critical activity by +1 day and verifying project finish moves by exactly +1 day (a CPM recalculation not implemented in this self-contained dashboard). Use this as a health-screening signal; do NOT cite it as a formal DCMA C12 PASS in contract claims or forensic submissions — run the cpp-forensic-mcp `critical_path_validator` or an external CPM tool for the formal test.
Manual Override:
📋 Assessment
PASS - Continuous critical path of 35 working days from start to finish. CPM calculation is functioning correctly.
🔧 Corrective Action Plan
C13

CPLI

FAIL
CPLI (Critical Path Length Index) indicates feasibility against the baseline/contract finish. In this dashboard: CPLI = (Baseline/Contract Finish − Data Date) ÷ (Forecast Finish − Data Date). Pass threshold: CPLI ≥ 1.0. Requires a baseline schedule.
Manual Override:
📋 Assessment
FAILED - CPLI: 0.933 (threshold: ≥1.0). Critical path has compressed significantly vs. baseline, indicating potential unrealistic acceleration or missing logic.
🔧 Corrective Action Plan
CPLI below 1.00 — schedule has no margin
  1. 1Recalculate: CPLI = (Critical Path Length + Total Float) ÷ Critical Path Length. Below 1.00 means the path can't recover its own slip.
  2. 2Identify the constraint or milestone driving criticality. If it's a contract milestone, you have an EOT conversation coming.
  3. 3Compression options before you ask for an extension: re-sequence near-critical work to feed criticality, fast-track overlap, then crash with crews/overtime as the last resort.
  4. 4If you're crashing, model it on a copy of the schedule first — added crews often create resource conflicts that make the path worse, not better.
Heads up
CPLI = 1.00 doesn't mean you're fine — it means you have zero room. One bad weather week, one late submittal, and you're sub-1.00. Treat 1.05 as your real floor.
C14

BEI

FAIL
BEI (Baseline Execution Index) = (baseline tasks actually complete by data date) / (baseline tasks scheduled to be complete by data date). Uses Start/Finish dates from current schedule. Pass threshold: BEI ≥ 0.95 (i.e. at least 95% of baseline-due tasks have actually completed). Requires baseline.
Manual Override:
📋 Assessment
FAILED - BEI: 0.615 (threshold: ≥0.95). 24 of 39 baseline tasks complete. Progress lagging 39% behind schedule.
🔧 Corrective Action Plan
BEI below 0.95 — falling behind baseline pace
  1. 1Recalculate: BEI = (Activities Actually Finished by Data Date) ÷ (Activities Baselined to Finish by Data Date). Below 0.95 = trending late.
  2. 2List every baselined activity that should be done but isn't. Sort by Total Float — anything near-critical is the priority.
  3. 3For each one, decide: status it complete (with the real actual finish), update remaining duration, or escalate the cause to the PM. No fourth option.
  4. 4Track BEI weekly. The trend matters more than the snapshot — a flat 0.92 is recoverable; a slope from 0.98 to 0.85 over four updates is the real problem.
Heads up
BEI is the easiest DCMA metric to game by re-baselining. Don't. If you re-baseline to fix BEI, you've also reset every variance metric — and an experienced reviewer will catch the gap between the original baseline date and the new one.

Executive Schedule Intelligence

Schedule Grade
F
Critical · 5/13 Pass
This schedule is critically deficient with only 5 of 13 criteria passing. The schedule cannot be relied upon for project planning or performance measurement. Fundamental reconstruction is required including logic development, constraint removal, and duration rationalization. Recommend engaging scheduling expertise to rebuild the integrated master schedule.
1. Logic Integrity: 2 logic-related criteria failed. Activities without predecessors/successors, negative lags, or excessive lags create an unreliable schedule network that cannot accurately predict project completion.
2. Duration Risk: 38 activities exceed 44 working days. Long-duration activities hide progress problems and reduce schedule agility. These should be decomposed into measurable milestones.
3. Resource Gaps: Activities lack resource or cost loading, making it impossible to identify overallocations or validate budget alignment. Resource-load critical path activities at minimum.
4. Critical Path Instability: CPLI below threshold indicates the critical path length does not align with actual schedule duration, suggesting hidden constraints or logic gaps affecting the driving path.
1.Review and correct relationship lags. Eliminate negative lags (leads) entirely and justify any positive lags greater than 5 days with documented rationale.
2.Decompose activities exceeding 44 days into smaller work packages with interim milestones to enable objective progress measurement.
405 activities, 655 relationships. 5 of 13 DCMA criteria passing (38%) — grade F (Critical). Failing: C2 Leads, C3 Lags, C6 High Float, C8 High Duration, C9 Invalid Dates, C11 Missed Tasks, C13 CPLI, C14 BEI. Top problem volumes: 149 high-float activities; 103 activities with invalid dates; 38 high-duration activities. Forecast finish is 30 calendar days late vs baseline (2026-08-31 → 2026-09-30). Schedule is not suitable for project management without reconstruction. Engage an experienced IMS specialist to rebuild logic, remove non-contractual constraints, and re-baseline. Current state is unacceptable risk for cost/schedule commitments.

Overall Quality Rating

Green Status
12-13 criteria passed · Excellent
Yellow Status
9-11 criteria passed · Acceptable
Red Status
≤8 criteria passed · Critical
Recommended Corrective Actions
Next Scheduled Review
Report Information
Generated: May 3, 2026 10:24 AM Source: Current Schedule (Data Date: 2025-07-01 17:00 | Day: 2025-07-01 | Cal: Mon-Tue-Wed-Thu-Fri [clndr_data]) Schedule Run: 2025-10-17 10:50 | Day: 2025-10-17 | Δ108d Baseline: Baseline Schedule (Data Date: 2025-04-01 17:00 | Day: 2025-04-01) Baseline Run: 2025-10-16 14:47 | Day: 2025-10-16 | Δ198d