Skip to main content
Sample deliverable: demonstration data. This is actual rendered output from the CPP forensic toolkit, run on a fictional project. The methodology, detectors and calculations are the production ones; the activity codes, RFI numbers, change orders and party assignments are illustrative and were chosen to exercise the full range of forensic detectors. Nothing here is a real project, a real party, or a real claim. See all sample deliverables · criticalpathpartners.ca
Skip to main content
CPP
Critical Path PartnersForensic schedule analysis
DWG · CPP-SRA / SHEET A-00
Monte Carlo Schedule Risk Analysis
Schedule Risk Analysis

Ontario Community College - B2 (Demo Data) Monte Carlo simulation results · Basis: working days

Project
Ontario Community College - B2 (Demo Data)
Data date
01-Jul-2025
Generated
09-Sep-2026
Iterations
5,000
P80 Completion
04-Nov-2026
P50 28-Oct-2026 · P90 09-Nov-2026
Distribution
Triangular
Det. Finish
30-Sep-2026
Anchor disclosure. The risk network’s own finish lies 12 working days after the schedule’s stored forecast (2026-09-30). Every date on this page is anchored to the stored forecast and the distribution shifted by that amount; the residual means the simulation network (logic, durations and constraint floors only, with no resource levelling or progress override modelling) does not fully reproduce the scheduled record, and the spread and sensitivity rankings should be read with that limitation in view.
ES-01

Executive Summary

computed from this run · not boilerplate
Executive Summary

This Monte Carlo run simulated the schedule 5,000 times. The deterministic CPM finish of 2026-09-30 was achieved or beaten in 0% of iterations, which places it near the P0 point of the simulated range. The even-odds (P50) finish is 2026-10-28, 19 working days later than the deterministic date. CPP recommends committing to the P80 date of 2026-11-04, which carries 24 working days of schedule contingency over the deterministic finish; that date holds in 80% of simulated outcomes.

The strongest single driver of finish-date uncertainty is A2550x (R6 - RFI 60 Sprinkler Diesel Pump), with correlation +0.60. The P10 to P90 spread of 15 working days is the expected uncertainty of the plan, not a per-percentile alarm.

P(Det. Finish)
0%
P50 vs Det.
+19 wd
P80 Commitment
2026-11-04
Top Driver
A2550x
P(Deterministic Finish)
0%
LOW
share of iterations at or before the deterministic date
A-01

Headline Risk Metrics

Monte Carlo · 5,000 iterations
Iterations
5,000
simulation trials
Distribution
Triangular
opt 90% / ml 100% / pes 130%
P50 Finish
2026-10-28
day offset 336
P80 Finish
2026-11-04
day offset 341
P90 Finish
2026-11-09
day offset 344
Deterministic Finish
2026-09-30
single-point CPM
Three-point Inputs
90/100/130%
opt / ml / pes
Random Seed
42
reproducible run
Basis of measurementHow to read the numbers in this report
Day unit
Working days
Every day count in this deliverable is in working days. No calendar-day figure is displayed. Where a contract clause is quoted verbatim in calendar days, the computed equivalent is given in working days alongside.
Calendar
The activity's own P6 calendar
Deltas are counted on the activity's own P6 calendar via work_day_delta. Where no project calendar is available the documented fallback is Monday to Friday with no holidays, and that fallback is disclosed on the affected figure.
Date fields read
P6 Start and Finish columns only
Float basis
total float from the deterministic CPM pass; percentile dates come from the Monte Carlo completion-day vector, not from float
A positive figure means the percentile completion is later than the deterministic finish, which is the adverse direction in this report
Convention: risk-overrun: positive = the percentile completion is later than the deterministic finish
Variance
How it is computed
A positive value means
Percentile overrun
percentile completion day - deterministic completion day
later than the deterministic finish
One uniform subtraction order is used, percentile completion day minus deterministic completion day, so a negative figure means the percentile lands earlier than the deterministic finish. This is the reverse of the contractor-loss convention used in the contract-versus-baseline deliverables; the two must not be read against each other without converting the sign.
A-02

QRAMM-Aligned Maturity Reading

five levels · informed by AACE RP 122R-22
Maturity Reading

Calibrated three-point inputs (optimistic / most-likely / pessimistic) with documented distribution choice, sufficient iteration count, and per-activity sensitivity (Pearson correlation tornado) showing which activities drive the completion-day variance. The analysis stands on its own but is still a one-off, with nothing to compare it against.

AACE 122R-22 names five levels of maturity: Level 1 Reactive, Level 2 Ad-hoc, Level 3 Centralized, Level 4 Dynamic, Level 5 Adaptive.

Reference: AACE International RP 122R-22, "Quantitative Risk Analysis Maturity Model" (QRAMM), rev. October 13 2022 (editorial revision April 22 2024); TCM Framework 7.6 Risk Management, 3.3 Investment Decision Making.

Level
2 / 5
Iterations
5,000
Drivers Ranked
282
Scenarios
1
Maturity Level
2/5
LEVEL 2 · AD-HOC
scenario comparison absent
Evidence In This Run
  • Iteration count: 5,000
  • Baseline P50 / P80 produced: 2026-10-28 / 2026-11-04
  • Three-point inputs: opt 90% / ml 100% / pes 130%
  • Distribution: Triangular
  • Per-activity sensitivity: 282 ranked drivers (Pearson correlation tornado)
  • Critical-path flagging applied to sensitivity rows
Gaps To Next Level
  • Add at least one of: a mitigation scenario (baseline vs mitigated comparison), or a quantified risk register giving each risk a probability of occurring and a distribution of multiplicative impact factors mapped to the activities it affects (Hulett risk-driver method, AACE RP 57R-09).
  • No convergence diagnostics run
A-03

Probabilistic Completion Percentiles

8 percentiles · all listed
PercentileCompletion dateDay offsetΔ from deterministic
P102026-10-19329+12d
P252026-10-22332+15d
P502026-10-28336+19d
P752026-11-03340+23d
P802026-11-04341+24d
P852026-11-05342+25d
P902026-11-09344+27d
P952026-11-11346+29d

Δ is measured against the single-point deterministic CPM finish. A later percentile (red) is downside schedule risk, an earlier one upside. The color flags direction relative to the deterministic estimate. The P10–P90 spread itself is expected uncertainty, not a per-percentile alarm.

What these dates mean
  1. Commitment date: carry the P80 date, 2026-11-04. It holds in 80% of simulated outcomes. That implies 24 working days of schedule contingency over the deterministic finish of 2026-09-30.
  2. P50, 2026-10-28: the even-odds date. Half the iterations finish later. Quote it as an expectation, not a commitment.
  3. Deterministic finish, 2026-09-30: the single-point CPM date. The simulation achieves it in only 0% of iterations, so treat it as an optimistic bound, not a forecast.
A-04

Completion-day Distribution

histogram + cumulative S-curve · 5,000 samples
Completion-day histogram40 bins · n=5,000
Day 318.2, count 2Day 319.3, count 2Day 320.3, count 4Day 321.4, count 16Day 322.4, count 16Day 323.4, count 22Day 324.5, count 33Day 325.5, count 65Day 326.6, count 94Day 327.6, count 126Day 328.7, count 153Day 329.7, count 206Day 330.7, count 225Day 331.8, count 272Day 332.8, count 315Day 333.9, count 327Day 334.9, count 385Day 335.9, count 364Day 337.0, count 358Day 338.0, count 321Day 339.1, count 318Day 340.1, count 241Day 341.1, count 225Day 342.2, count 220Day 343.2, count 166Day 344.3, count 143Day 345.3, count 97Day 346.3, count 96Day 347.4, count 63Day 348.4, count 43Day 349.5, count 37Day 350.5, count 18Day 351.5, count 7Day 352.6, count 8Day 353.6, count 2Day 354.7, count 2Day 355.7, count 4Day 356.8, count 3Day 357.8, count 0Day 358.8, count 13183283393493590128257385DetP50P80P90Completion day offset from data dateIterations
Iteration count per bin P10-P90 band Deterministic P50 P80 P90
Cumulative S-curveP50 / P80 / P90 annotated
3183283393493590.000.250.500.751.00P50P80P90DetP(achieve)=0%Completion day offset from data dateCumulative probability
Cumulative probability (S-curve) P50 P80 P90 Deterministic callout

Probability of achieving the deterministic date 2026-09-30: 0% of 5,000 iterations finished on or before it.

A-05

Sensitivity, Tornado

every driver plotted · 282 drivers
Pearson correlation, activity duration vs completion day282 ranked drivers
drivers 1–28 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A2550x: corr=+0.599, R6 - RFI 60 Sprinkler Diesel PumpA2550x, R6 - RFI 60 Sprinkler Diesel Pump+0.599A4040: corr=+0.326, MEP Rough-insA4040, MEP Rough-ins+0.326CPA2610: corr=+0.284, Erect Structural SteelA2610, Erect Structural Steel+0.284A3060: corr=+0.233, L1, L2 & L3 Framing and Sheathing InstallationA3060, L1, L2 & L3 Framing and Sheathing Installation+0.233CPA4180: corr=+0.220, Mechanical, Electrical and Elevator CommissioningA4180, Mechanical, Electrical and Elevator Commissioning+0.220CPA2970: corr=+0.204, L2 & L3 Framing and Sheathing InstallationA2970, L2 & L3 Framing and Sheathing Installation+0.204CPA3240: corr=+0.204, Fire Spraying & Intumescent PaintA3240, Fire Spraying & Intumescent Paint+0.204CPA4030: corr=+0.177, New Partition FramingA4030, New Partition Framing+0.177CPA4240: corr=+0.166, Minor Deficiencies & Touch-upsA4240, Minor Deficiencies & Touch-ups+0.166CPA4050: corr=+0.163, Sprinkler Rough-insA4050, Sprinkler Rough-ins+0.163CPA4090: corr=+0.152, Taping and muddingA4090, Taping and mudding+0.152CPA4080: corr=+0.144, Drywall/Sheathing InstallationA4080, Drywall/Sheathing Installation+0.144CPA2880: corr=+0.142, L1, L2 & L3 Framing and Sheathing InstallationA2880, L1, L2 & L3 Framing and Sheathing Installation+0.142CPA2650: corr=+0.139, Install Level 2 & 3 DeckingA2650, Install Level 2 & 3 Decking+0.139A4190: corr=+0.126, Integrated TestingA4190, Integrated Testing+0.126CPA4070: corr=+0.124, Frames installationA4070, Frames installation+0.124CPA4060: corr=+0.123, BlockingA4060, Blocking+0.123CPA2710: corr=+0.072, Concrete Pour and Curing for SOGA2710, Concrete Pour and Curing for SOG+0.072A4120: corr=+0.071, Final Terminations and Fixtures InstallationA4120, Final Terminations and Fixtures Installation+0.071CPA2550: corr=+0.070, Form and Pour Grade BeamsA2550, Form and Pour Grade Beams+0.070A4110: corr=+0.068, Tile and Rubber Flooring InstallationA4110, Tile and Rubber Flooring Installation+0.068CPA2750: corr=+0.065, L1, L2 & L3 Framing and Sheathing InstallationA2750, L1, L2 & L3 Framing and Sheathing Installation+0.065CPA2670: corr=+0.050, Rebar and Prep Work for Slab on DeckA2670, Rebar and Prep Work for Slab on Deck+0.050A2440: corr=+0.048, Formwork Remaining Pad Footing (Ramp)A2440, Formwork Remaining Pad Footing (Ramp)+0.048A2690: corr=+0.046, Final Grading and Vapor Barrier for SOGA2690, Final Grading and Vapor Barrier for SOG+0.046A3420: corr=-0.042, Fire Spraying & Intumescent PaintA3420, Fire Spraying & Intumescent Paint-0.042A2480: corr=+0.037, Concrete for Remaining Pad Footings (Ramp)A2480, Concrete for Remaining Pad Footings (Ramp)+0.037A1380x: corr=+0.037, Metal Shelving (R1)A1380x, Metal Shelving (R1)+0.037Pearson correlation (activity duration vs completion day)
drivers 29–56 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A2930: corr=+0.037, L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)A2930, L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)+0.037A3290: corr=-0.036, Mech. & Plumbing rough-insA3290, Mech. & Plumbing rough-ins-0.036A3250: corr=+0.035, Fire Spraying & Intumescent Paint InspectionA3250, Fire Spraying & Intumescent Paint Inspection+0.035CPA2130: corr=-0.035, 22 40 00 - Plumbing FixturesA2130, 22 40 00 - Plumbing Fixtures-0.035A4520: corr=-0.035, Setup Temporary HoardingA4520, Setup Temporary Hoarding-0.035CPA2180: corr=-0.034, 26 09 23 - Lighting ControlA2180, 26 09 23 - Lighting Control-0.034A4100: corr=+0.033, PaintingA4100, Painting+0.033CPA1870: corr=+0.033, ACT & ACBA1870, ACT & ACB+0.033A3760: corr=-0.032, Plumbing Washroom Fixtures InstallationA3760, Plumbing Washroom Fixtures Installation-0.032A3360: corr=+0.032, Drywall Taping and MuddingA3360, Drywall Taping and Mudding+0.032A1760: corr=-0.031, Exterior Wall CladdingA1760, Exterior Wall Cladding-0.031A3440: corr=-0.029, New partition framingA3440, New partition framing-0.029A3860: corr=+0.029, Concrete Vertical PiersA3860, Concrete Vertical Piers+0.029A2120: corr=+0.028, 20 05 10 - Electric Heat Tracing (below significance threshold: statistically indistinguishable from zero)A2120, 20 05 10 - Electric Heat Tracing+0.028A1270: corr=+0.026, Tiling Data sheet and samples (below significance threshold: statistically indistinguishable from zero)A1270, Tiling Data sheet and samples+0.026A1470.1: corr=+0.026, 23 37 13 - Diffuser and Grilles Shop Drawings (R1) (below significance threshold: statistically indistinguishable from zero)A1470.1, 23 37 13 - Diffuser and Grilles Shop Drawings (R1)+0.026A1770: corr=+0.025, Fire-resistive Material (below significance threshold: statistically indistinguishable from zero)A1770, Fire-resistive Material+0.025A2940: corr=-0.025, Exterior Cladding Site Measure and Scanning (below significance threshold: statistically indistinguishable from zero)A2940, Exterior Cladding Site Measure and Scanning-0.025A2730: corr=-0.025, Stairs B Installation @ North Side (below significance threshold: statistically indistinguishable from zero)A2730, Stairs B Installation @ North Side-0.025A2150: corr=-0.024, 26 50 00 - Lighting Fixtures (below significance threshold: statistically indistinguishable from zero)A2150, 26 50 00 - Lighting Fixtures-0.024A3340: corr=+0.024, ACT Baffles Mock-ups (below significance threshold: statistically indistinguishable from zero)A3340, ACT Baffles Mock-ups+0.024A1310: corr=-0.023, Paint Drawdowns (below significance threshold: statistically indistinguishable from zero)A1310, Paint Drawdowns-0.023A4820: corr=+0.023, Concrete Floor Sealer (below significance threshold: statistically indistinguishable from zero)A4820, Concrete Floor Sealer+0.023CPA2790: corr=+0.023, L1, L2 & L3 Air Vapour Barrier Installation (below significance threshold: statistically indistinguishable from zero)A2790, L1, L2 & L3 Air Vapour Barrier Installation+0.023A2080: corr=-0.023, 23 00 00 - Unit Heater (below significance threshold: statistically indistinguishable from zero)A2080, 23 00 00 - Unit Heater-0.023A3880: corr=+0.023, Structural Steel erection including expansion plates (below significance threshold: statistically indistinguishable from zero)A3880, Structural Steel erection including expansion plates+0.023A2990: corr=-0.023, Glazing Site Measure and Scanning (below significance threshold: statistically indistinguishable from zero)A2990, Glazing Site Measure and Scanning-0.023A2540: corr=-0.023, Compaction Inspection (below significance threshold: statistically indistinguishable from zero)A2540, Compaction Inspection-0.023Pearson correlation (activity duration vs completion day)
drivers 57–84 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A3910: corr=-0.022, Interior Finishes (below significance threshold: statistically indistinguishable from zero)A3910, Interior Finishes-0.022A3330: corr=+0.022, Door frames Installation (below significance threshold: statistically indistinguishable from zero)A3330, Door frames Installation+0.022A3210: corr=-0.022, Electrical and Mechanical Room (below significance threshold: statistically indistinguishable from zero)A3210, Electrical and Mechanical Room-0.022A2040: corr=+0.022, 22 13 29 - Sump Pumps (below significance threshold: statistically indistinguishable from zero)A2040, 22 13 29 - Sump Pumps+0.022A1330: corr=-0.022, Fall Arrest Anchors and Horizontal Lines (below significance threshold: statistically indistinguishable from zero)A1330, Fall Arrest Anchors and Horizontal Lines-0.022A3280: corr=-0.021, New partition framing (below significance threshold: statistically indistinguishable from zero)A3280, New partition framing-0.021A3650: corr=+0.021, Door and Hardware Installation (below significance threshold: statistically indistinguishable from zero)A3650, Door and Hardware Installation+0.021A4450: corr=-0.021, Plywood Blocking (below significance threshold: statistically indistinguishable from zero)A4450, Plywood Blocking-0.021CPA4690: corr=-0.021, Electrical Fixtures (below significance threshold: statistically indistinguishable from zero)A4690, Electrical Fixtures-0.021A3840: corr=+0.021, Elevator Testing and Commissioning (below significance threshold: statistically indistinguishable from zero)A3840, Elevator Testing and Commissioning+0.021A1170: corr=+0.021, Air Barrier System Data Sheet and Mockup (below significance threshold: statistically indistinguishable from zero)A1170, Air Barrier System Data Sheet and Mockup+0.021A4650: corr=-0.021, Painting (below significance threshold: statistically indistinguishable from zero)A4650, Painting-0.021A1200: corr=-0.020, Hollow Metal Frames & Doors Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1200, Hollow Metal Frames & Doors Shop Drawings-0.020A1940: corr=-0.020, Sprinkler & Standpipe Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1940, Sprinkler & Standpipe Shop Drawings-0.020A1990: corr=-0.020, 23 21 16 - Air Separator (below significance threshold: statistically indistinguishable from zero)A1990, 23 21 16 - Air Separator-0.020A4160: corr=-0.020, Landscape Installations (below significance threshold: statistically indistinguishable from zero)A4160, Landscape Installations-0.020A1530.1: corr=+0.020, 20 05 10 - Electric Heat Tracing (R1) (below significance threshold: statistically indistinguishable from zero)A1530.1, 20 05 10 - Electric Heat Tracing (R1)+0.020A4220: corr=-0.020, Final Cleaning (below significance threshold: statistically indistinguishable from zero)A4220, Final Cleaning-0.020A2890: corr=+0.019, L1 Masonry Wall Installation (below significance threshold: statistically indistinguishable from zero)A2890, L1 Masonry Wall Installation+0.019A3770: corr=-0.019, Corner Guards and Wall Protection Installation (below significance threshold: statistically indistinguishable from zero)A3770, Corner Guards and Wall Protection Installation-0.019A3540: corr=-0.019, Painting (below significance threshold: statistically indistinguishable from zero)A3540, Painting-0.019A3350: corr=-0.019, Gypsum board Installation (below significance threshold: statistically indistinguishable from zero)A3350, Gypsum board Installation-0.019A2420: corr=+0.019, Form and Pour North Exit Stair (below significance threshold: statistically indistinguishable from zero)A2420, Form and Pour North Exit Stair+0.019A3390: corr=+0.019, Interior Aluminum/Glazing Screens Installation (below significance threshold: statistically indistinguishable from zero)A3390, Interior Aluminum/Glazing Screens Installation+0.019A4730: corr=-0.019, Steel Joist Reinforcement Installation (below significance threshold: statistically indistinguishable from zero)A4730, Steel Joist Reinforcement Installation-0.019A3870: corr=-0.018, Removal of Existing Facade for Tie In (below significance threshold: statistically indistinguishable from zero)A3870, Removal of Existing Facade for Tie In-0.018A1320: corr=-0.018, Washroom accessories and Partitions Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1320, Washroom accessories and Partitions Shop Drawings-0.018A3220: corr=+0.018, Mech. and Elec. Equipment Installation (below significance threshold: statistically indistinguishable from zero)A3220, Mech. and Elec. Equipment Installation+0.018Pearson correlation (activity duration vs completion day)
drivers 85–112 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A2630: corr=+0.018, Install Roof Anchors (below significance threshold: statistically indistinguishable from zero)A2630, Install Roof Anchors+0.018A3810: corr=-0.018, Install Controller at Machine Room (below significance threshold: statistically indistinguishable from zero)A3810, Install Controller at Machine Room-0.018A4720: corr=-0.018, Existing Column Reinforcement (below significance threshold: statistically indistinguishable from zero)A4720, Existing Column Reinforcement-0.018A1620: corr=+0.018, Landscape Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1620, Landscape Shop Drawings+0.018A2680: corr=+0.017, Concrete pour for slab on deck level 2 & 3 (below significance threshold: statistically indistinguishable from zero)A2680, Concrete pour for slab on deck level 2 & 3+0.017A4370: corr=+0.017, Underground Mechanical Installation (DCW, Sprinkler) (below significance threshold: statistically indistinguishable from zero)A4370, Underground Mechanical Installation (DCW, Sprinkler)+0.017A4150: corr=-0.017, New Exterior Paved Areas and Sidewalks (below significance threshold: statistically indistinguishable from zero)A4150, New Exterior Paved Areas and Sidewalks-0.017A3020: corr=+0.017, Exterior Cladding Site Measure and Scanning (below significance threshold: statistically indistinguishable from zero)A3020, Exterior Cladding Site Measure and Scanning+0.017A4810: corr=-0.016, Self Levelling (below significance threshold: statistically indistinguishable from zero)A4810, Self Levelling-0.016A3380: corr=+0.016, Interior Aluminum/Glazing Screens Mock-up (below significance threshold: statistically indistinguishable from zero)A3380, Interior Aluminum/Glazing Screens Mock-up+0.016A2800: corr=-0.016, AVB Inspection (below significance threshold: statistically indistinguishable from zero)A2800, AVB Inspection-0.016A1610: corr=+0.016, Concrete Mix for Hardscapes (below significance threshold: statistically indistinguishable from zero)A1610, Concrete Mix for Hardscapes+0.016A3510: corr=-0.016, Drywall Taping and Mudding (below significance threshold: statistically indistinguishable from zero)A3510, Drywall Taping and Mudding-0.016A2810: corr=-0.016, Aluminum & Metal Panel Cladding Mock-up (below significance threshold: statistically indistinguishable from zero)A2810, Aluminum & Metal Panel Cladding Mock-up-0.016A4600: corr=+0.016, Stud Framing (below significance threshold: statistically indistinguishable from zero)A4600, Stud Framing+0.016A3190: corr=-0.016, Hoisting Roof Equipment (below significance threshold: statistically indistinguishable from zero)A3190, Hoisting Roof Equipment-0.016A4790: corr=-0.016, Existing Column Reinforcement (below significance threshold: statistically indistinguishable from zero)A4790, Existing Column Reinforcement-0.016A3450: corr=-0.016, Mech. & Plumbing rough-ins (below significance threshold: statistically indistinguishable from zero)A3450, Mech. & Plumbing rough-ins-0.016A2000: corr=-0.016, 23 21 16 - Expansion Tanks (below significance threshold: statistically indistinguishable from zero)A2000, 23 21 16 - Expansion Tanks-0.016A4800: corr=-0.015, Flatness Survey @ Floor Slab (below significance threshold: statistically indistinguishable from zero)A4800, Flatness Survey @ Floor Slab-0.015A2560x: corr=+0.015, R7 - SP 3 & 4 - 3rd Floor Fan Coil Units Scope (below significance threshold: statistically indistinguishable from zero)A2560x, R7 - SP 3 & 4 - 3rd Floor Fan Coil Units Scope+0.015A1590.1: corr=-0.015, 26 09 23 - Lighting Control (R1) (below significance threshold: statistically indistinguishable from zero)A1590.1, 26 09 23 - Lighting Control (R1)-0.015A2010: corr=-0.015, 23 57 00 - Heat Exchangers (below significance threshold: statistically indistinguishable from zero)A2010, 23 57 00 - Heat Exchangers-0.015A3630: corr=-0.014, Gypsum board Installation (below significance threshold: statistically indistinguishable from zero)A3630, Gypsum board Installation-0.014A3130: corr=-0.014, Exterior Cladding Shop Fabrication (below significance threshold: statistically indistinguishable from zero)A3130, Exterior Cladding Shop Fabrication-0.014A2110: corr=+0.014, 23 74 13 - Air Source Heat Pump (below significance threshold: statistically indistinguishable from zero)A2110, 23 74 13 - Air Source Heat Pump+0.014A4040x: corr=+0.014, MEP Rough-ins + Sprinkler (below significance threshold: statistically indistinguishable from zero)A4040x, MEP Rough-ins + Sprinkler+0.014CPA3090: corr=-0.014, Glazing Site Measure and Scanning (below significance threshold: statistically indistinguishable from zero)A3090, Glazing Site Measure and Scanning-0.014Pearson correlation (activity duration vs completion day)
drivers 113–140 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A2190: corr=-0.014, 28 31 00 - Fire Alarm (below significance threshold: statistically indistinguishable from zero)A2190, 28 31 00 - Fire Alarm-0.014A3500: corr=-0.014, Gypsum board Installation (below significance threshold: statistically indistinguishable from zero)A3500, Gypsum board Installation-0.014A4710: corr=-0.014, Relocation of Interferences (below significance threshold: statistically indistinguishable from zero)A4710, Relocation of Interferences-0.014A2140: corr=-0.014, 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes (below significance threshold: statistically indistinguishable from zero)A2140, 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes-0.014A3890: corr=-0.014, Envelope (below significance threshold: statistically indistinguishable from zero)A3890, Envelope-0.014A1930: corr=-0.014, Hydraulic Lift (below significance threshold: statistically indistinguishable from zero)A1930, Hydraulic Lift-0.014A3230: corr=+0.014, Fire Spraying & Intumescent Paint Mock-up (below significance threshold: statistically indistinguishable from zero)A3230, Fire Spraying & Intumescent Paint Mock-up+0.014A3000: corr=-0.014, Glazing Shop Fabrication (below significance threshold: statistically indistinguishable from zero)A3000, Glazing Shop Fabrication-0.014A2070: corr=+0.014, 23 00 00 - Exhaust Fans (below significance threshold: statistically indistinguishable from zero)A2070, 23 00 00 - Exhaust Fans+0.014A1110.1: corr=-0.013, Structural Reinforcement + Decking Shop Drawings (R1) (below significance threshold: statistically indistinguishable from zero)A1110.1, Structural Reinforcement + Decking Shop Drawings (R1)-0.013CPA3370: corr=+0.013, Door and Hardware Installation (below significance threshold: statistically indistinguishable from zero)A3370, Door and Hardware Installation+0.013A3160: corr=-0.013, Roof Penetration Layout (below significance threshold: statistically indistinguishable from zero)A3160, Roof Penetration Layout-0.013A3180: corr=-0.013, Roof Inspection (below significance threshold: statistically indistinguishable from zero)A3180, Roof Inspection-0.013A3490: corr=+0.013, Door frames Installation (below significance threshold: statistically indistinguishable from zero)A3490, Door frames Installation+0.013A2770: corr=-0.013, L1 Masonry Wall installation (below significance threshold: statistically indistinguishable from zero)A2770, L1 Masonry Wall installation-0.013A2090x: corr=+0.013, Metal Shelving (below significance threshold: statistically indistinguishable from zero)A2090x, Metal Shelving+0.013A1890: corr=-0.013, Flooring (below significance threshold: statistically indistinguishable from zero)A1890, Flooring-0.013A2100: corr=+0.013, 23 00 00 - Wall Fin Heater (below significance threshold: statistically indistinguishable from zero)A2100, 23 00 00 - Wall Fin Heater+0.013A4670: corr=-0.013, Electrical and Mechanical Make Safe (below significance threshold: statistically indistinguishable from zero)A4670, Electrical and Mechanical Make Safe-0.013A3140: corr=+0.013, L1, L2 & L3 Cladding Installation (EW2, EW2A) (below significance threshold: statistically indistinguishable from zero)A3140, L1, L2 & L3 Cladding Installation (EW2, EW2A)+0.013A3570: corr=+0.013, New wall partition framing (below significance threshold: statistically indistinguishable from zero)A3570, New wall partition framing+0.013A1350: corr=-0.013, Sprinkler & Standpipe Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1350, Sprinkler & Standpipe Shop Drawings-0.013A5230: corr=+0.012, Footings and Piers Along GL-B.1 (Successor to CO-005) (below significance threshold: statistically indistinguishable from zero)A5230, Footings and Piers Along GL-B.1 (Successor to CO-005)+0.012A1520: corr=-0.012, 23 74 13 - Air Source Heat Pump (below significance threshold: statistically indistinguishable from zero)A1520, 23 74 13 - Air Source Heat Pump-0.012A2580: corr=+0.012, Underground Drainage (below significance threshold: statistically indistinguishable from zero)A2580, Underground Drainage+0.012A2530.1: corr=+0.012, Backfilling to U/S of Grade Beams (GL AA) (below significance threshold: statistically indistinguishable from zero)A2530.1, Backfilling to U/S of Grade Beams (GL AA)+0.012A4470: corr=-0.012, Taping Drywall (below significance threshold: statistically indistinguishable from zero)A4470, Taping Drywall-0.012CPA2570: corr=+0.012, Footing Vapor Barrier & Insulation (below significance threshold: statistically indistinguishable from zero)A2570, Footing Vapor Barrier & Insulation+0.012Pearson correlation (activity duration vs completion day)
drivers 141–168 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A2700: corr=+0.012, Rebar Installation for SOG (below significance threshold: statistically indistinguishable from zero)A2700, Rebar Installation for SOG+0.012A3260: corr=-0.012, Seal Concrete Floor (below significance threshold: statistically indistinguishable from zero)A3260, Seal Concrete Floor-0.012CPA3520: corr=-0.012, Door and Hardware Installation (below significance threshold: statistically indistinguishable from zero)A3520, Door and Hardware Installation-0.012A3560: corr=-0.012, Seal concrete Floor (below significance threshold: statistically indistinguishable from zero)A3560, Seal concrete Floor-0.012A4610: corr=+0.012, MEP Rough-ins (below significance threshold: statistically indistinguishable from zero)A4610, MEP Rough-ins+0.012A3110: corr=-0.012, L1, L2 & L3 Exterior Glazing Installation (W09a, W09b) (below significance threshold: statistically indistinguishable from zero)A3110, L1, L2 & L3 Exterior Glazing Installation (W09a, W09b)-0.012A3600: corr=+0.012, Sprinkler Rough-ins (below significance threshold: statistically indistinguishable from zero)A3600, Sprinkler Rough-ins+0.012A3940: corr=-0.012, Existing Slab Removal and Trenching (below significance threshold: statistically indistinguishable from zero)A3940, Existing Slab Removal and Trenching-0.012A1690: corr=+0.012, Structural Reinforcement (below significance threshold: statistically indistinguishable from zero)A1690, Structural Reinforcement+0.012CPA1680: corr=+0.012, Structural Steel (below significance threshold: statistically indistinguishable from zero)A1680, Structural Steel+0.012A4480: corr=+0.011, Paint (below significance threshold: statistically indistinguishable from zero)A4480, Paint+0.011CPA1810: corr=-0.011, Flush Wood Doors (below significance threshold: statistically indistinguishable from zero)A1810, Flush Wood Doors-0.011A3310: corr=-0.011, Sprinkler Rough-ins (below significance threshold: statistically indistinguishable from zero)A3310, Sprinkler Rough-ins-0.011A1830: corr=+0.011, Aluminum Framed Glazing Systems (below significance threshold: statistically indistinguishable from zero)A1830, Aluminum Framed Glazing Systems+0.011A2720: corr=-0.010, Tactile Attention Indicators Mock-up (below significance threshold: statistically indistinguishable from zero)A2720, Tactile Attention Indicators Mock-up-0.010A2820: corr=-0.010, Glazing Site Measure and Scanning (below significance threshold: statistically indistinguishable from zero)A2820, Glazing Site Measure and Scanning-0.010A2740: corr=+0.010, Cold-Formed Metal Framing Mock (below significance threshold: statistically indistinguishable from zero)A2740, Cold-Formed Metal Framing Mock+0.010A4380: corr=+0.010, Backfilling and Concrete for SOG (below significance threshold: statistically indistinguishable from zero)A4380, Backfilling and Concrete for SOG+0.010A1860: corr=+0.010, Tiling (below significance threshold: statistically indistinguishable from zero)A1860, Tiling+0.010A2560: corr=+0.010, Below Grade Vapour Barrier Mock-up (below significance threshold: statistically indistinguishable from zero)A2560, Below Grade Vapour Barrier Mock-up+0.010A2030: corr=-0.010, 23 81 26 - Split System (below significance threshold: statistically indistinguishable from zero)A2030, 23 81 26 - Split System-0.010A1300: corr=+0.010, Flooring Data Sheets and Samples (below significance threshold: statistically indistinguishable from zero)A1300, Flooring Data Sheets and Samples+0.010A1700: corr=+0.010, Cold-formed Metal Framing (below significance threshold: statistically indistinguishable from zero)A1700, Cold-formed Metal Framing+0.010A4570: corr=-0.010, Joist Interferences Relocation (below significance threshold: statistically indistinguishable from zero)A4570, Joist Interferences Relocation-0.010A4550: corr=-0.010, Existing Exterior Wall Demo (New Building Must be Erected and Enclosed) (below significance threshold: statistically indistinguishable from zero)A4550, Existing Exterior Wall Demo (New Building Must be Erected and Enclosed)-0.010A3470: corr=-0.009, Sprinkler Rough-ins (below significance threshold: statistically indistinguishable from zero)A3470, Sprinkler Rough-ins-0.009A4230: corr=-0.009, Close-out Documents & Training (below significance threshold: statistically indistinguishable from zero)A4230, Close-out Documents & Training-0.009A4530: corr=+0.009, Electrical and Mechanical Make Safe (below significance threshold: statistically indistinguishable from zero)A4530, Electrical and Mechanical Make Safe+0.009Pearson correlation (activity duration vs completion day)
drivers 169–196 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A1720: corr=+0.009, Millwork (below significance threshold: statistically indistinguishable from zero)A1720, Millwork+0.009A3640: corr=-0.009, Drywall Taping and Mudding (below significance threshold: statistically indistinguishable from zero)A3640, Drywall Taping and Mudding-0.009A4500: corr=+0.009, CNC Machine Relocation (Cash Allowance) (below significance threshold: statistically indistinguishable from zero)A4500, CNC Machine Relocation (Cash Allowance)+0.009CPA2780: corr=-0.009, Above Grade Vapour Mock-up (below significance threshold: statistically indistinguishable from zero)A2780, Above Grade Vapour Mock-up-0.009A4620: corr=+0.009, Plywood Blocking (below significance threshold: statistically indistinguishable from zero)A4620, Plywood Blocking+0.009A3730: corr=+0.009, Millwork Mock-up (below significance threshold: statistically indistinguishable from zero)A3730, Millwork Mock-up+0.009A2900: corr=-0.009, Air Vapor Barrier Installation (below significance threshold: statistically indistinguishable from zero)A2900, Air Vapor Barrier Installation-0.009A1780: corr=+0.009, Hollow Metal Frames (below significance threshold: statistically indistinguishable from zero)A1780, Hollow Metal Frames+0.009A3700: corr=-0.009, Tiling & Rubber & Carpet Flooring Mock-up (below significance threshold: statistically indistinguishable from zero)A3700, Tiling & Rubber & Carpet Flooring Mock-up-0.009A4510: corr=-0.008, Metal Shelving Installation (below significance threshold: statistically indistinguishable from zero)A4510, Metal Shelving Installation-0.008A2760: corr=+0.008, Masonry Mock-up (below significance threshold: statistically indistinguishable from zero)A2760, Masonry Mock-up+0.008A2960: corr=-0.008, L2 & L3 Cladding Installation (EW2) (below significance threshold: statistically indistinguishable from zero)A2960, L2 & L3 Cladding Installation (EW2)-0.008A4420: corr=-0.008, Steel Joist Reinforcement Installation (below significance threshold: statistically indistinguishable from zero)A4420, Steel Joist Reinforcement Installation-0.008CPA2860: corr=-0.008, Exterior Cladding Shop Fabrication (below significance threshold: statistically indistinguishable from zero)A2860, Exterior Cladding Shop Fabrication-0.008A1670: corr=+0.008, Masonry and Mortar (below significance threshold: statistically indistinguishable from zero)A1670, Masonry and Mortar+0.008A2020: corr=+0.008, 22 33 00 - Electric Domestic Water Heaters (below significance threshold: statistically indistinguishable from zero)A2020, 22 33 00 - Electric Domestic Water Heaters+0.008A3680: corr=-0.008, Misc. Metals Mock-up (below significance threshold: statistically indistinguishable from zero)A3680, Misc. Metals Mock-up-0.008A1260: corr=+0.008, Stud framing and Gypsum Board Data Sheets (below significance threshold: statistically indistinguishable from zero)A1260, Stud framing and Gypsum Board Data Sheets+0.008A3660: corr=-0.008, Interior Glazing Installation (below significance threshold: statistically indistinguishable from zero)A3660, Interior Glazing Installation-0.008A1360.2: corr=+0.008, 23 82 19 - Fan Coil Units (R2) (below significance threshold: statistically indistinguishable from zero)A1360.2, 23 82 19 - Fan Coil Units (R2)+0.008A3270: corr=+0.008, New Stair A Installation (below significance threshold: statistically indistinguishable from zero)A3270, New Stair A Installation+0.008A1790: corr=+0.007, Hollow Metal Doors (below significance threshold: statistically indistinguishable from zero)A1790, Hollow Metal Doors+0.007A3590: corr=-0.007, Electrical, FA & Comms rough-ins (below significance threshold: statistically indistinguishable from zero)A3590, Electrical, FA & Comms rough-ins-0.007A3620: corr=-0.007, Door frames Installation (below significance threshold: statistically indistinguishable from zero)A3620, Door frames Installation-0.007A2840: corr=-0.007, L1, L2, L3 Exterior Glazing Installation (W05) (below significance threshold: statistically indistinguishable from zero)A2840, L1, L2, L3 Exterior Glazing Installation (W05)-0.007A3820: corr=-0.007, Rails and Elevator Car installation (below significance threshold: statistically indistinguishable from zero)A3820, Rails and Elevator Car installation-0.007A2950: corr=-0.007, Exterior Cladding Shop Fabrication (below significance threshold: statistically indistinguishable from zero)A2950, Exterior Cladding Shop Fabrication-0.007A4460: corr=+0.007, Drywall Installation (below significance threshold: statistically indistinguishable from zero)A4460, Drywall Installation+0.007CPPearson correlation (activity duration vs completion day)
drivers 197–224 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A1710: corr=+0.007, Misc. Metals (below significance threshold: statistically indistinguishable from zero)A1710, Misc. Metals+0.007A3200: corr=+0.007, Roof Anchor System Installation (below significance threshold: statistically indistinguishable from zero)A3200, Roof Anchor System Installation+0.007A1740: corr=+0.006, TPO Roofing (Bridge) (below significance threshold: statistically indistinguishable from zero)A1740, TPO Roofing (Bridge)+0.006A1540.1: corr=-0.006, 22 40 00 - Plumbing Fixtures (R1) (below significance threshold: statistically indistinguishable from zero)A1540.1, 22 40 00 - Plumbing Fixtures (R1)-0.006A3150: corr=-0.006, Roof Parapet Framing (below significance threshold: statistically indistinguishable from zero)A3150, Roof Parapet Framing-0.006A1850: corr=+0.006, Stud framing & gypsum board (below significance threshold: statistically indistinguishable from zero)A1850, Stud framing & gypsum board+0.006A2620: corr=+0.006, Structural Steel Inspection (below significance threshold: statistically indistinguishable from zero)A2620, Structural Steel Inspection+0.0062170: corr=-0.006, 26 50 00 - Emergency Lighting & Exit Signs (below significance threshold: statistically indistinguishable from zero)2170, 26 50 00 - Emergency Lighting & Exit Signs-0.006A3690: corr=-0.006, Misc. Metals installation (below significance threshold: statistically indistinguishable from zero)A3690, Misc. Metals installation-0.006A4660: corr=-0.006, Setup Temporary Hoarding (below significance threshold: statistically indistinguishable from zero)A4660, Setup Temporary Hoarding-0.006A1800: corr=+0.006, Interior Aluminum Screens (below significance threshold: statistically indistinguishable from zero)A1800, Interior Aluminum Screens+0.006A1130: corr=-0.006, Misc. Metals Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1130, Misc. Metals Shop Drawings-0.006A3580: corr=+0.006, Mech. & Plumbing rough-ins (below significance threshold: statistically indistinguishable from zero)A3580, Mech. & Plumbing rough-ins+0.006A3530: corr=+0.006, Interior Glazing Installation (below significance threshold: statistically indistinguishable from zero)A3530, Interior Glazing Installation+0.006A4780: corr=+0.006, New Columns Installation (below significance threshold: statistically indistinguishable from zero)A4780, New Columns Installation+0.006A3740: corr=-0.006, Millwork Installation (below significance threshold: statistically indistinguishable from zero)A3740, Millwork Installation-0.006A3100: corr=+0.006, Glazing Shop Fabrication (below significance threshold: statistically indistinguishable from zero)A3100, Glazing Shop Fabrication+0.006A3830: corr=-0.005, Power to controller, Phone lines and Comms (below significance threshold: statistically indistinguishable from zero)A3830, Power to controller, Phone lines and Comms-0.005A1480.1: corr=+0.005, 23 00 00 - Exhaust Fans (R1) (below significance threshold: statistically indistinguishable from zero)A1480.1, 23 00 00 - Exhaust Fans (R1)+0.005A1840: corr=-0.005, Finished Hardware (below significance threshold: statistically indistinguishable from zero)A1840, Finished Hardware-0.005A4580: corr=+0.005, New Columns Installation (below significance threshold: statistically indistinguishable from zero)A4580, New Columns Installation+0.005A3460: corr=-0.005, Electrical, FA & Comms rough-ins (below significance threshold: statistically indistinguishable from zero)A3460, Electrical, FA & Comms rough-ins-0.005A1460.1: corr=+0.005, 23 25 00 - Water Treatment (R1) (below significance threshold: statistically indistinguishable from zero)A1460.1, 23 25 00 - Water Treatment (R1)+0.005A1900: corr=+0.005, Paint Drawdowns (below significance threshold: statistically indistinguishable from zero)A1900, Paint Drawdowns+0.005A1500: corr=-0.005, 23 52 16 - Heating Boilers (below significance threshold: statistically indistinguishable from zero)A1500, 23 52 16 - Heating Boilers-0.005A4760: corr=-0.005, Trench Backfill (below significance threshold: statistically indistinguishable from zero)A4760, Trench Backfill-0.005A3070: corr=-0.005, L1, L2 & L3 Air Vapor Barrier Installation (below significance threshold: statistically indistinguishable from zero)A3070, L1, L2 & L3 Air Vapor Barrier Installation-0.005A3050: corr=-0.005, Horizontal Shading Louvers (below significance threshold: statistically indistinguishable from zero)A3050, Horizontal Shading Louvers-0.005Pearson correlation (activity duration vs completion day)
drivers 225–252 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A2060: corr=-0.004, 23 37 13 - Diffuser and Grilles (below significance threshold: statistically indistinguishable from zero)A2060, 23 37 13 - Diffuser and Grilles-0.004A4010: corr=-0.004, Underground Plumbing Rough-ins (below significance threshold: statistically indistinguishable from zero)A4010, Underground Plumbing Rough-ins-0.004A4540: corr=+0.004, Interior Demolition (below significance threshold: statistically indistinguishable from zero)A4540, Interior Demolition+0.004A1210: corr=+0.004, Interior Aluminum Screen (below significance threshold: statistically indistinguishable from zero)A1210, Interior Aluminum Screen+0.004A4590: corr=+0.004, Steel Joist Reinforcement Installation (below significance threshold: statistically indistinguishable from zero)A4590, Steel Joist Reinforcement Installation+0.004CPA2200: corr=-0.004, Concrete for Hardscape (below significance threshold: statistically indistinguishable from zero)A2200, Concrete for Hardscape-0.004A4170: corr=-0.004, Fire Alarm Verification (below significance threshold: statistically indistinguishable from zero)A4170, Fire Alarm Verification-0.004A3550: corr=-0.004, Fire Spraying & Intumescent Paint (below significance threshold: statistically indistinguishable from zero)A3550, Fire Spraying & Intumescent Paint-0.004A4770: corr=-0.004, Concrete Slab Infill (below significance threshold: statistically indistinguishable from zero)A4770, Concrete Slab Infill-0.004A3320: corr=-0.004, Blocking Installation (below significance threshold: statistically indistinguishable from zero)A3320, Blocking Installation-0.004A1250: corr=-0.004, Finished Hardware Schedule (below significance threshold: statistically indistinguishable from zero)A1250, Finished Hardware Schedule-0.004A3010: corr=-0.003, L2 & L3 Exterior Glazing Installation (W08a, W08b) (below significance threshold: statistically indistinguishable from zero)A3010, L2 & L3 Exterior Glazing Installation (W08a, W08b)-0.003A3170: corr=+0.003, Install Built-up Roof (below significance threshold: statistically indistinguishable from zero)A3170, Install Built-up Roof+0.003A2050: corr=-0.003, 23 25 00 - Water Treatment (below significance threshold: statistically indistinguishable from zero)A2050, 23 25 00 - Water Treatment-0.003A2920: corr=-0.003, Glazing Shop Fabrication (below significance threshold: statistically indistinguishable from zero)A2920, Glazing Shop Fabrication-0.003A3720: corr=-0.003, Ceiling/Wall Fixtures Installation (below significance threshold: statistically indistinguishable from zero)A3720, Ceiling/Wall Fixtures Installation-0.003A2660: corr=+0.003, Install Temporary Hoarding for Slab on Deck (below significance threshold: statistically indistinguishable from zero)A2660, Install Temporary Hoarding for Slab on Deck+0.003A1920: corr=-0.003, Fall Arrest Anchors and Horizontal Lines (below significance threshold: statistically indistinguishable from zero)A1920, Fall Arrest Anchors and Horizontal Lines-0.003A4680: corr=-0.003, Interior Demolition (below significance threshold: statistically indistinguishable from zero)A4680, Interior Demolition-0.003A3030: corr=-0.003, Exterior Cladding Shop Fabrication (below significance threshold: statistically indistinguishable from zero)A3030, Exterior Cladding Shop Fabrication-0.003A3900: corr=+0.002, Interior M&E Rough in (below significance threshold: statistically indistinguishable from zero)A3900, Interior M&E Rough in+0.002A2590: corr=+0.002, Backfilling to U/S of SOG (below significance threshold: statistically indistinguishable from zero)A2590, Backfilling to U/S of SOG+0.002A2910: corr=-0.002, Glazing Site Measure and Scanning (below significance threshold: statistically indistinguishable from zero)A2910, Glazing Site Measure and Scanning-0.002A3430: corr=+0.002, Seal concrete Floor (below significance threshold: statistically indistinguishable from zero)A3430, Seal concrete Floor+0.002A2850: corr=+0.002, Exterior Cladding Site Measure and Scanning (below significance threshold: statistically indistinguishable from zero)A2850, Exterior Cladding Site Measure and Scanning+0.002A1970: corr=+0.002, 23 21 23 - Pumps (below significance threshold: statistically indistinguishable from zero)A1970, 23 21 23 - Pumps+0.002A1180: corr=+0.002, Exterior Wall Cladding Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1180, Exterior Wall Cladding Shop Drawings+0.002A3400: corr=-0.002, Paint Mock-up (below significance threshold: statistically indistinguishable from zero)A3400, Paint Mock-up-0.002Pearson correlation (activity duration vs completion day)
drivers 253–280 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A1140: corr=+0.002, Millwork Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1140, Millwork Shop Drawings+0.002A4640: corr=+0.002, Taping Drywall (below significance threshold: statistically indistinguishable from zero)A4640, Taping Drywall+0.002A4490: corr=-0.002, Finishes (below significance threshold: statistically indistinguishable from zero)A4490, Finishes-0.002CPA4430: corr=+0.002, Stud Framing (below significance threshold: statistically indistinguishable from zero)A4430, Stud Framing+0.002CPA1950: corr=-0.002, 23 82 19 - Fan Coil Units (below significance threshold: statistically indistinguishable from zero)A1950, 23 82 19 - Fan Coil Units-0.002A3120: corr=-0.002, Exterior Cladding Site Measure and Scanning (below significance threshold: statistically indistinguishable from zero)A3120, Exterior Cladding Site Measure and Scanning-0.002A3300: corr=+0.002, Electrical, FA & Comms rough-ins (below significance threshold: statistically indistinguishable from zero)A3300, Electrical, FA & Comms rough-ins+0.002A2210: corr=-0.001, Landscape (unit pavers, furniture, etc) (below significance threshold: statistically indistinguishable from zero)A2210, Landscape (unit pavers, furniture, etc)-0.001A1820: corr=+0.001, Coiling Doors (below significance threshold: statistically indistinguishable from zero)A1820, Coiling Doors+0.001A4630: corr=-0.001, Drywall Installation (below significance threshold: statistically indistinguishable from zero)A4630, Drywall Installation-0.001A1910: corr=+0.001, Washroom accessories and Partitions (below significance threshold: statistically indistinguishable from zero)A1910, Washroom accessories and Partitions+0.001A2640: corr=-0.001, Install Roof Decking (below significance threshold: statistically indistinguishable from zero)A2640, Install Roof Decking-0.001A3040: corr=+0.001, L2 & L3 Cladding Installation (EW2) (below significance threshold: statistically indistinguishable from zero)A3040, L2 & L3 Cladding Installation (EW2)+0.001A4400: corr=+0.001, Existing Columns Reinforcement (below significance threshold: statistically indistinguishable from zero)A4400, Existing Columns Reinforcement+0.001CPA2870: corr=-0.001, L1, L2 & L3 Cladding Installation (EW2a) (below significance threshold: statistically indistinguishable from zero)A2870, L1, L2 & L3 Cladding Installation (EW2a)-0.001A1980: corr=+0.001, 23 25 00 - Buffer Tanks (below significance threshold: statistically indistinguishable from zero)A1980, 23 25 00 - Buffer Tanks+0.001A2830: corr=-0.001, Glazing Shop Fabrication (below significance threshold: statistically indistinguishable from zero)A2830, Glazing Shop Fabrication-0.001A3410: corr=+0.001, Painting (below significance threshold: statistically indistinguishable from zero)A3410, Painting+0.001A2090: corr=+0.001, 23 52 16 - Heating Boilers (below significance threshold: statistically indistinguishable from zero)A2090, 23 52 16 - Heating Boilers+0.001A4560: corr=-0.001, Review Interferences with Steel Joist (below significance threshold: statistically indistinguishable from zero)A4560, Review Interferences with Steel Joist-0.001A3670: corr=+0.001, Painting (below significance threshold: statistically indistinguishable from zero)A3670, Painting+0.001A3850: corr=+0.001, Foundations (below significance threshold: statistically indistinguishable from zero)A3850, Foundations+0.001A2160: corr=-0.001, 27 10 00 - Structural Cabling System (Fiber Optic Cable) (below significance threshold: statistically indistinguishable from zero)A2160, 27 10 00 - Structural Cabling System (Fiber Optic Cable)-0.001A1240: corr=+0.000, Aluminum Framed Glazing System Shop Drawings (below significance threshold: statistically indistinguishable from zero)A1240, Aluminum Framed Glazing System Shop Drawings+0.000A1730: corr=-0.000, Built-up Roofing (below significance threshold: statistically indistinguishable from zero)A1730, Built-up Roofing-0.000A3710: corr=+0.000, Tiling and rubber flooring Installation (below significance threshold: statistically indistinguishable from zero)A3710, Tiling and rubber flooring Installation+0.000A2980: corr=-0.000, L2 & L3 Air Vapor Barrier Installation (below significance threshold: statistically indistinguishable from zero)A2980, L2 & L3 Air Vapor Barrier Installation-0.000A1750: corr=-0.000, Air Barrier System (below significance threshold: statistically indistinguishable from zero)A1750, Air Barrier System-0.000Pearson correlation (activity duration vs completion day)
drivers 281–282 of 282 (ranked by |correlation|)
-0.60-0.30+0.00+0.30+0.60A1960: corr=+0.000, 23 74 13 - Air Handling Units (below significance threshold: statistically indistinguishable from zero)A1960, 23 74 13 - Air Handling Units+0.000A3750: corr=-0.000, Washroom Partitions and Accessories Installation (below significance threshold: statistically indistinguishable from zero)A3750, Washroom Partitions and Accessories Installation-0.000Pearson correlation (activity duration vs completion day)
Positive correlation (longer duration → later finish) Negative correlation On critical path Below significance threshold (shaded: noise, not signal)

At 5,000 iterations, a |correlation| below the two-sided 95% significance threshold of 1.96/√n ≈ 0.028 is not statistically distinguishable from zero. 241 of 282 drivers fall below the threshold and are shaded; they remain plotted because the register is never truncated, but their order within the shaded band is noise, not ranking.

A-06

Ranked Sensitivity Drivers

282 drivers · all listed
SENSRanked duration-sensitivity drivers (Pearson correlation)
282 drivers, all listedExport CSV
RankCodeActivityPlanned dur.CorrelationImpact
1A2550xR6 - RFI 60 Sprinkler Diesel Pump41.0d+0.59924.55
2A4040CPMEP Rough-ins23.0d+0.3267.50
3A2610Erect Structural Steel20.0d+0.2845.67
4A213022 40 00 - Plumbing Fixtures100.0d-0.0353.52
5A3060CPL1, L2 & L3 Framing and Sheathing Installation15.0d+0.2333.49
6A218026 09 23 - Lighting Control100.0d-0.0343.42
7A4180CPMechanical, Electrical and Elevator Commissioning15.0d+0.2203.30
8A211023 74 13 - Air Source Heat Pump224.0d+0.0143.19
9A3240CPFire Spraying & Intumescent Paint15.0d+0.2043.06
10A2970CPL2 & L3 Framing and Sheathing Installation14.0d+0.2042.86
11A212020 05 10 - Electric Heat Tracing100.0d+0.0282.77
12A215026 50 00 - Lighting Fixtures100.0d-0.0242.42
13A4030CPNew Partition Framing13.0d+0.1772.30
14A4050CPSprinkler Rough-ins13.0d+0.1632.12
15A1760Exterior Wall Cladding60.0d-0.0311.85
16A199023 21 16 - Air Separator91.0d-0.0201.84
17A4240CPMinor Deficiencies & Touch-ups11.0d+0.1661.83
18A208023 00 00 - Unit Heater78.0d-0.0231.78
19A4090CPTaping and mudding10.0d+0.1521.52
20A4080CPDrywall/Sheathing Installation10.0d+0.1441.44
21A2880CPL1, L2 & L3 Framing and Sheathing Installation10.0d+0.1421.42
22A200023 21 16 - Expansion Tanks91.0d-0.0161.42
23A2650Install Level 2 & 3 Decking10.0d+0.1391.39
24A1930Hydraulic Lift101.0d-0.0141.38
25A201023 57 00 - Heat Exchangers91.0d-0.0151.34
26A214026 27 26 - Wiring Devices, Service Poles, & Floor Boxes91.0d-0.0141.27
27A4190CPIntegrated Testing10.0d+0.1261.26
28A219028 31 00 - Fire Alarm82.0d-0.0141.15
29A210023 00 00 - Wall Fin Heater90.0d+0.0131.15
30A1870ACT & ACB30.0d+0.0331.00
31A4070CPFrames installation8.0d+0.1241.00
32A207023 00 00 - Exhaust Fans72.0d+0.0140.98
33A2930L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)26.0d+0.0370.96
34A203023 81 26 - Split System97.0d-0.0100.96
35A4060CPBlocking7.0d+0.1230.86
36A1830Aluminum Framed Glazing Systems80.0d+0.0110.85
37A1810Flush Wood Doors75.0d-0.0110.82
38A1890Flooring61.0d-0.0130.79
39A202022 33 00 - Electric Domestic Water Heaters91.0d+0.0080.72
40A1330Fall Arrest Anchors and Horizontal Lines31.0d-0.0220.67
41A204022 13 29 - Sump Pumps28.0d+0.0220.62
42A1470.123 37 13 - Diffuser and Grilles Shop Drawings (R1)24.0d+0.0260.62
43217026 50 00 - Emergency Lighting & Exit Signs91.0d-0.0060.55
44A1800Interior Aluminum Screens90.0d+0.0060.53
45A1770Fire-resistive Material21.0d+0.0250.53
46A1710Misc. Metals80.0d+0.0070.52
47A1840Finished Hardware91.0d-0.0050.48
48A1720Millwork51.0d+0.0090.48
49A2560xR7 - SP 3 & 4 - 3rd Floor Fan Coil Units Scope30.0d+0.0150.45
50A1790Hollow Metal Doors61.0d+0.0070.45
51A206023 37 13 - Diffuser and Grilles100.0d-0.0040.45
52A2420Form and Pour North Exit Stair23.0d+0.0190.43
53A1380xMetal Shelving (R1)10.0d+0.0370.37
54A2730Stairs B Installation @ North Side15.0d-0.0250.37
55A2710Concrete Pour and Curing for SOG5.0d+0.0720.36
56A3290Mech. & Plumbing rough-ins10.0d-0.0360.36
57A1780Hollow Metal Frames41.0d+0.0090.36
58A4120CPFinal Terminations and Fixtures Installation5.0d+0.0710.35
59A1690CPStructural Reinforcement30.0d+0.0120.35
60A2550Form and Pour Grade Beams5.0d+0.0700.35
61A3890Envelope25.0d-0.0140.34
62A3880Structural Steel erection including expansion plates15.0d+0.0230.34
63A4110CPTile and Rubber Flooring Installation5.0d+0.0680.34
64A205023 25 00 - Water Treatment100.0d-0.0030.34
65A4150New Exterior Paved Areas and Sidewalks20.0d-0.0170.34
66A1940Sprinkler & Standpipe Shop Drawings16.0d-0.0200.32
67A2750CPL1, L2 & L3 Framing and Sheathing Installation5.0d+0.0650.32
68A3360Drywall Taping and Mudding10.0d+0.0320.32
69A3140L1, L2 & L3 Cladding Installation (EW2, EW2A)25.0d+0.0130.32
70A3840Elevator Testing and Commissioning15.0d+0.0210.31
71A1860Tiling31.0d+0.0100.31
72A3440New partition framing10.0d-0.0290.29
73A3130Exterior Cladding Shop Fabrication20.0d-0.0140.29
74A3000Glazing Shop Fabrication21.0d-0.0140.29
75A4730Steel Joist Reinforcement Installation15.0d-0.0190.28
76A2090xMetal Shelving21.0d+0.0130.27
77A1270Tiling Data sheet and samples10.0d+0.0260.26
78A3210Electrical and Mechanical Room11.0d-0.0220.24
79A1310Paint Drawdowns10.0d-0.0230.23
80A1680Structural Steel20.0d+0.0120.23
81A197023 21 23 - Pumps100.0d+0.0020.22
82A3280New partition framing10.0d-0.0210.21
83A3650Door and Hardware Installation10.0d+0.0210.21
84A3420Fire Spraying & Intumescent Paint5.0d-0.0420.21
85A1200Hollow Metal Frames & Doors Shop Drawings10.0d-0.0200.20
86A1620Landscape Shop Drawings11.0d+0.0180.20
87A4160Landscape Installations10.0d-0.0200.20
88A1530.120 05 10 - Electric Heat Tracing (R1)10.0d+0.0200.20
89A1740TPO Roofing (Bridge)30.0d+0.0060.19
90A195023 82 19 - Fan Coil Units109.0d-0.0020.19
91A2580Underground Drainage15.0d+0.0120.19
92A1320Washroom accessories and Partitions Shop Drawings10.0d-0.0180.18
93A3690Misc. Metals installation30.0d-0.0060.18
94A3220Mech. and Elec. Equipment Installation10.0d+0.0180.18
95A2630Install Roof Anchors10.0d+0.0180.18
96A4720Existing Column Reinforcement10.0d-0.0180.18
97A1610Concrete Mix for Hardscapes11.0d+0.0160.18
98A4370Underground Mechanical Installation (DCW, Sprinkler)10.0d+0.0170.17
99A2960L2 & L3 Cladding Installation (EW2)20.0d-0.0080.17
100A1920Fall Arrest Anchors and Horizontal Lines60.0d-0.0030.17
101A2860Exterior Cladding Shop Fabrication20.0d-0.0080.17
102A3510Drywall Taping and Mudding10.0d-0.0160.16
103A3760Plumbing Washroom Fixtures Installation5.0d-0.0320.16
104A3450Mech. & Plumbing rough-ins10.0d-0.0160.16
105A1590.126 09 23 - Lighting Control (R1)10.0d-0.0150.15
106A2840L1, L2, L3 Exterior Glazing Installation (W05)21.0d-0.0070.15
107A2440Formwork Remaining Pad Footing (Ramp)3.0d+0.0480.14
108A1820Coiling Doors100.0d+0.0010.14
109A3860Concrete Vertical Piers5.0d+0.0290.14
110A4710Relocation of Interferences10.0d-0.0140.14
111A198023 25 00 - Buffer Tanks131.0d+0.0010.14
112A2690Final Grading and Vapor Barrier for SOG3.0d+0.0460.14
113A1360.223 82 19 - Fan Coil Units (R2)18.0d+0.0080.14
114A2950Exterior Cladding Shop Fabrication20.0d-0.0070.14
115A3570New wall partition framing10.0d+0.0130.13
116A1350Sprinkler & Standpipe Shop Drawings10.0d-0.0130.13
117A152023 74 13 - Air Source Heat Pump10.0d-0.0120.12
118A150023 52 16 - Heating Boilers26.0d-0.0050.12
119A3520Door and Hardware Installation10.0d-0.0120.12
120A4500CPCNC Machine Relocation (Cash Allowance)13.0d+0.0090.12
121A1540.122 40 00 - Plumbing Fixtures (R1)19.0d-0.0060.12
122A3600Sprinkler Rough-ins10.0d+0.0120.12
123A3100Glazing Shop Fabrication21.0d+0.0060.12
124A2790L1, L2 & L3 Air Vapour Barrier Installation5.0d+0.0230.12
125A4810Self Levelling7.0d-0.0160.12
126A3330Door frames Installation5.0d+0.0220.11
127A216027 10 00 - Structural Cabling System (Fiber Optic Cable)194.0d-0.0010.11
128A1700Cold-formed Metal Framing11.0d+0.0100.11
129A3310Sprinkler Rough-ins10.0d-0.0110.11
130A4690Electrical Fixtures5.0d-0.0210.11
131A1170Air Barrier System Data Sheet and Mockup5.0d+0.0210.10
132A3170Install Built-up Roof30.0d+0.0030.10
133A3630Gypsum board Installation7.0d-0.0140.10
134A4100CPPainting3.0d+0.0330.10
135A2670Rebar and Prep Work for Slab on Deck2.0d+0.0500.10
136A1300Flooring Data Sheets and Samples10.0d+0.0100.10
137A4220Final Cleaning5.0d-0.0200.10
138A2890L1 Masonry Wall Installation5.0d+0.0190.10
139A3470Sprinkler Rough-ins10.0d-0.0090.09
140A3350Gypsum board Installation5.0d-0.0190.09
141A3390Interior Aluminum/Glazing Screens Installation5.0d+0.0190.09
142A3640Drywall Taping and Mudding10.0d-0.0090.09
143A2210Landscape (unit pavers, furniture, etc)60.0d-0.0010.09
144A4470CPTaping Drywall7.0d-0.0120.09
145A209023 52 16 - Heating Boilers100.0d+0.0010.08
146A1460.123 25 00 - Water Treatment (R1)17.0d+0.0050.08
147A3190Hoisting Roof Equipment5.0d-0.0160.08
148A4790Existing Column Reinforcement5.0d-0.0160.08
149A1480.123 00 00 - Exhaust Fans (R1)15.0d+0.0050.08
150A1260Stud framing and Gypsum Board Data Sheets10.0d+0.0080.08
151A3270New Stair A Installation10.0d+0.0080.08
152A1210Interior Aluminum Screen18.0d+0.0040.07
153A4040xCPMEP Rough-ins + Sprinkler5.0d+0.0140.07
154A3590Electrical, FA & Comms rough-ins10.0d-0.0070.07
155A3500Gypsum board Installation5.0d-0.0140.07
156A3820Rails and Elevator Car installation10.0d-0.0070.07
157A3850Foundations116.0d+0.0010.07
158A4420CPSteel Joist Reinforcement Installation8.0d-0.0080.07
159A3370Door and Hardware Installation5.0d+0.0130.07
160A4450CPPlywood Blocking3.0d-0.0210.06
161A5230Footings and Piers Along GL-B.1 (Successor to CO-005)5.0d+0.0120.06
162A3110L1, L2 & L3 Exterior Glazing Installation (W09a, W09b)5.0d-0.0120.06
163A1130Misc. Metals Shop Drawings10.0d-0.0060.06
164A3580Mech. & Plumbing rough-ins10.0d+0.0060.06
165A3940Existing Slab Removal and Trenching5.0d-0.0120.06
166A2920Glazing Shop Fabrication19.0d-0.0030.06
167A3770Corner Guards and Wall Protection Installation3.0d-0.0190.06
168A3540Painting3.0d-0.0190.06
169A1900Paint Drawdowns11.0d+0.0050.05
170A4580New Columns Installation10.0d+0.0050.05
171A3030Exterior Cladding Shop Fabrication20.0d-0.0030.05
172A3460Electrical, FA & Comms rough-ins10.0d-0.0050.05
173A4380Backfilling and Concrete for SOG5.0d+0.0100.05
174A2570Footing Vapor Barrier & Insulation4.0d+0.0120.05
175A4600Stud Framing3.0d+0.0160.05
176A4570Joist Interferences Relocation5.0d-0.0100.05
177A4550Existing Exterior Wall Demo (New Building Must be Erected and Enclosed)5.0d-0.0100.05
178A3260CPSeal Concrete Floor4.0d-0.0120.05
179A4610MEP Rough-ins4.0d+0.0120.05
180A4230Close-out Documents & Training5.0d-0.0090.05
181A2900Air Vapor Barrier Installation5.0d-0.0090.04
182A4010Underground Plumbing Rough-ins10.0d-0.0040.04
183A4540Interior Demolition10.0d+0.0040.04
184A4650Painting2.0d-0.0210.04
185A1110.1CPStructural Reinforcement + Decking Shop Drawings (R1)3.0d-0.0130.04
186A1670Masonry and Mortar5.0d+0.0080.04
187A1180Exterior Wall Cladding Shop Drawings18.0d+0.0020.04
188A4770Concrete Slab Infill11.0d-0.0040.04
189A4590CPSteel Joist Reinforcement Installation10.0d+0.0040.04
190A3490Door frames Installation3.0d+0.0130.04
191A3660Interior Glazing Installation5.0d-0.0080.04
192A2480Concrete for Remaining Pad Footings (Ramp)1.0d+0.0370.04
193A1850Stud framing & gypsum board6.0d+0.0060.04
194A3870Removal of Existing Facade for Tie In2.0d-0.0180.04
195A4170Fire Alarm Verification10.0d-0.0040.04
196A3250CPFire Spraying & Intumescent Paint Inspection1.0d+0.0350.04
197A1250Finished Hardware Schedule10.0d-0.0040.04
198A3620Door frames Installation5.0d-0.0070.04
199A2680Concrete pour for slab on deck level 2 & 32.0d+0.0170.03
200A4520CPSetup Temporary Hoarding1.0d-0.0350.03
201A4480CPPaint3.0d+0.0110.03
202A1910Washroom accessories and Partitions26.0d+0.0010.03
203A4460CPDrywall Installation5.0d+0.0070.03
204A3200Roof Anchor System Installation5.0d+0.0070.03
205A3150Roof Parapet Framing5.0d-0.0060.03
206A4800Flatness Survey @ Floor Slab2.0d-0.0150.03
207A3720Ceiling/Wall Fixtures Installation10.0d-0.0030.03
208A3530Interior Glazing Installation5.0d+0.0060.03
209A4780New Columns Installation5.0d+0.0060.03
210A3740Millwork Installation5.0d-0.0060.03
211A4530Electrical and Mechanical Make Safe3.0d+0.0090.03
212A3070L1, L2 & L3 Air Vapor Barrier Installation6.0d-0.0050.03
213A4620Plywood Blocking3.0d+0.0090.03
214A3830Power to controller, Phone lines and Comms5.0d-0.0050.03
215A3160Roof Penetration Layout2.0d-0.0130.03
216A2770L1 Masonry Wall installation2.0d-0.0130.03
217A4510Metal Shelving Installation3.0d-0.0080.03
218A4670Electrical and Mechanical Make Safe2.0d-0.0130.03
219A2940Exterior Cladding Site Measure and Scanning1.0d-0.0250.02
220A3900Interior M&E Rough in10.0d+0.0020.02
221A3340ACT Baffles Mock-ups1.0d+0.0240.02
222A4820CPConcrete Floor Sealer1.0d+0.0230.02
223A4760Trench Backfill5.0d-0.0050.02
224A3040L2 & L3 Cladding Installation (EW2)20.0d+0.0010.02
225A3050Horizontal Shading Louvers5.0d-0.0050.02
226A2990Glazing Site Measure and Scanning1.0d-0.0230.02
227A2540Compaction Inspection1.0d-0.0230.02
228A3910Interior Finishes1.0d-0.0220.02
229A1140Millwork Shop Drawings10.0d+0.0020.02
230A2870L1, L2 & L3 Cladding Installation (EW2a)20.0d-0.0010.02
231A2200Concrete for Hardscape5.0d-0.0040.02
232A3550Fire Spraying & Intumescent Paint5.0d-0.0040.02
233A3810Install Controller at Machine Room1.0d-0.0180.02
234A2830Glazing Shop Fabrication19.0d-0.0010.02
235A3010L2 & L3 Exterior Glazing Installation (W08a, W08b)5.0d-0.0030.02
236A3300Electrical, FA & Comms rough-ins10.0d+0.0020.02
237A3020Exterior Cladding Site Measure and Scanning1.0d+0.0170.02
238A3380Interior Aluminum/Glazing Screens Mock-up1.0d+0.0160.02
239A2800AVB Inspection1.0d-0.0160.02
240A2810Aluminum & Metal Panel Cladding Mock-up1.0d-0.0160.02
241A4680Interior Demolition6.0d-0.0030.02
242A3090Glazing Site Measure and Scanning1.0d-0.0140.01
243A2660Install Temporary Hoarding for Slab on Deck5.0d+0.0030.01
244A3230Fire Spraying & Intumescent Paint Mock-up1.0d+0.0140.01
245A3180Roof Inspection1.0d-0.0130.01
246A2530.1Backfilling to U/S of Grade Beams (GL AA)1.0d+0.0120.01
247A1730Built-up Roofing31.0d-0.0000.01
248A2700Rebar Installation for SOG1.0d+0.0120.01
249A3560Seal concrete Floor1.0d-0.0120.01
250A2590Backfilling to U/S of SOG5.0d+0.0020.01
251A196023 74 13 - Air Handling Units180.0d+0.0000.01
252A3320Blocking Installation3.0d-0.0040.01
253A2720Tactile Attention Indicators Mock-up1.0d-0.0100.01
254A2820Glazing Site Measure and Scanning1.0d-0.0100.01
255A4640Taping Drywall5.0d+0.0020.01
256A2740Cold-Formed Metal Framing Mock1.0d+0.0100.01
257A2560Below Grade Vapour Barrier Mock-up1.0d+0.0100.01
258A4490CPFinishes5.0d-0.0020.01
259A2780Above Grade Vapour Mock-up1.0d-0.0090.01
260A3730Millwork Mock-up1.0d+0.0090.01
261A3700Tiling & Rubber & Carpet Flooring Mock-up1.0d-0.0090.01
262A2760Masonry Mock-up1.0d+0.0080.01
263A3680Misc. Metals Mock-up1.0d-0.0080.01
264A3400Paint Mock-up3.0d-0.0020.01
265A2620Structural Steel Inspection1.0d+0.0060.01
266A2640Install Roof Decking5.0d-0.0010.01
267A3670Painting10.0d+0.0010.01
268A4660Setup Temporary Hoarding1.0d-0.0060.01
269A4430CPStud Framing3.0d+0.0020.01
270A3430Seal concrete Floor2.0d+0.0020.00
271A1240Aluminum Framed Glazing System Shop Drawings11.0d+0.0000.00
272A3410Painting5.0d+0.0010.00
273A4560Review Interferences with Steel Joist5.0d-0.0010.00
274A4630Drywall Installation3.0d-0.0010.00
275A3710Tiling and rubber flooring Installation10.0d+0.0000.00
276A2910Glazing Site Measure and Scanning1.0d-0.0020.00
277A4400CPExisting Columns Reinforcement2.0d+0.0010.00
278A2850Exterior Cladding Site Measure and Scanning1.0d+0.0020.00
279A2980L2 & L3 Air Vapor Barrier Installation5.0d-0.0000.00
280A3120Exterior Cladding Site Measure and Scanning1.0d-0.0020.00
281A1750Air Barrier System10.0d-0.0000.00
282A3750Washroom Partitions and Accessories Installation5.0d-0.0000.00

Impact = |correlation| × planned duration. Critical-path activities flagged CP. † At 5,000 iterations, entries with |correlation| below 1.96/√n ≈ 0.028 are not statistically distinguishable from zero; 241 of 282 listed drivers carry the marker. Their rank order is noise, not signal.

A-07

Schedule Recovery, Baseline vs Mitigated

not run, no recovery scenario defined

A mitigated re-run was not in scope for this analysis; CPP runs this comparison when a recovery scenario is defined.

A-08

Methodology

basis, distribution, percentile method

Forecast completion dates are produced by Monte Carlo simulation over the activity duration distribution implied by the optimistic / most-likely / pessimistic percentages applied to each incomplete activity's planned duration. A full CPM forward pass is executed per iteration. Percentiles are derived from the completion-day vector using numpy.percentile(method='nearest') (harmonized across the engine in v2.8.x), which reports an actual simulation trial rather than an interpolated value, so each percentile traces back to a real, reproducible iteration. Sensitivity (tornado) is the Pearson correlation between each activity's sampled-duration vector and the final completion-day vector. Impact = |corr| × planned duration on the legacy PERT/Triangular path, or |corr| × posterior σ on the Bayesian-posterior path (when historical_snapshots was supplied). The active prior shape is reported per row in the sensitivity CSV's prior_method column. Statistical significance of the correlations: at n = 5,000 iterations, the two-sided 95% critical value for a Pearson correlation differing from zero is approximately 1.96/√n ≈ 0.028. Drivers whose |correlation| falls below that threshold are statistically indistinguishable from zero; they are shaded in the tornado (A-05) and marked † in the ranking (A-06) but remain fully listed.

Distribution: Triangular · Iterations: 5,000 · Random seed: 42 · Day basis: working days from data date. Working-day basis counts only the project’s own working days, read from the calendar loaded with this XER, so its workweek and its holiday exceptions are both honoured. The corresponding completion dates are the true calendar dates on which those working-day offsets fall.

Prepared by the schedule-risk-analysis skill in the CPP Scheduling Suite. This dashboard is self-contained. All assets are inlined and it renders offline.

A-09

Reproducibility Manifest

provenance
Generated
2026-09-09 07:05:14
Data Date
2025-07-01
Random Seed
42
Iterations (baseline)
5,000
Iterations (mitigated)
Percentile method
numpy nearest
Input files: Ontario_Community_College_current.xer SHA-256 7ed1cd8309b1752af74ec9c8d2fa11fbc9a58d4e065630a2589809ed3780ca10
Schedule Risk Analysis · Generated 2026-09-09 07:05:14 · Project Ontario Community College - B2 (Demo Data) · Run Monte Carlo · 5,000 iterations · Engine cpm-engine v2.9.43Self-contained · Reproducible