Larchmere Library and Community Hub (Demo Data) Monte Carlo simulation results · Basis: working days
Summary of Findings
The schedule's forecast finish of 3 September 2026 is not reached in any of the 5,000 simulated runs: the even-odds (P50) finish is 25 September 2026, 15 working days later, and the 80% confidence (P80) finish is 1 October 2026, 19 working days later.
Holding 19 working days of schedule contingency behind 3 September 2026 covers 80% of the simulated runs; the decision asked of the reader is whether to carry that contingency or to act on the work that drives it (section 2). Read 1 October 2026 as a planning scenario, not a commitment: no convergence diagnostics were run and the duration range is one illustrative range applied to every activity, not calibrated to this project.
Every duration and contingency in this report is in working days on the project calendar. The update was filed at data date 5 August 2025 but records actual progress up to 14 October 2025, so it is read and rescheduled at 15 October 2025: the file shows a finish of 24 June 2026, and its logic at the corrected date gives 3 September 2026, the forecast finish used throughout (section 4).
What Drives the Risk
The finish moves most with the four curtain wall and windows activities (A2380, A2260, A2340 and A2300), all on the critical path: in the runs where that work takes longer, the finish comes later.
The finish follows the four curtain wall and windows activities more closely than any other work
Correlation measures how closely the finish follows an activity across the 5,000 runs: 0 means no link, and 1 means the finish moves in step with it. After them, the next strongest are A4410 Owner furniture and fit-out (by others) at 0.22 and A4380 Deficiency correction at 0.20. All ten of the strongest drivers sit on the critical path. This is the first place to look for a firmer estimate or a recovery measure.
Of the 252 activities modelled, 56 have a correlation strong enough to tell apart from chance at 5,000 runs (above 0.028); the rest are noise. The tornado chart (exhibit A-05) and the full ranking (exhibit A-06) list all 252.
No risk register was supplied, so the drivers are the activities’ own duration ranges, not named risk events.
How Much Contingency Is Needed
Holding 19 working days of contingency behind the forecast finish covers 80% of the simulated runs; 15 working days covers half of them.
Every simulated finish falls after the 3 September 2026 forecast; 80% fall on or before 1 October 2026
| Confidence | Finish on or before | Contingency over the forecast finish |
|---|---|---|
| 10% (P10) | 21 September 2026 | 11 working days |
| 25% (P25) | 23 September 2026 | 13 working days |
| 50% (P50) | 25 September 2026 | 15 working days |
| 75% (P75) | 30 September 2026 | 18 working days |
| 80% (P80) | 1 October 2026 | 19 working days |
| 85% (P85) | 1 October 2026 | 19 working days |
| 90% (P90) | 2 October 2026 | 20 working days |
| 95% (P95) | 6 October 2026 | 22 working days |
The P10 to P90 range is 9 working days wide: the spread the plan carries on these inputs, not a series of separate alarms.
Each activity can run up to 30% longer than planned but only 10% shorter, so the simulated finishes lean later than the forecast.
How Far the Figures Can Be Relied On
The figures come from 5,000 simulated runs of the schedule’s own logic, with one illustrative duration range on every activity: the result shows how the plan responds to uncertainty, not a forecast calibrated to this project.
How the Run Was Made
Each run draws the remaining duration of every incomplete activity from a Triangular distribution between 90% and 130% of its planned duration, most likely 100%, and recalculates the schedule forward through its logic. The percentile dates are actual runs from the 5,000, not interpolated values. The run used random seed 42, so it reproduces exactly.
Where the Inputs Came From
The range is one illustrative range applied to every activity alike: it is not calibrated to this project, and no activity-specific estimates were supplied.
Durations are drawn independently for each activity. A shared cause that delays several activities at once, such as weather across trades, is not modelled, and independent sampling understates that kind of linked delay, so the true spread may be wider than shown.
Convergence and the Anchor Check
No convergence diagnostics were run, so whether 5,000 runs settle the P80 to the day is not tested; that is one reason the P80 is a planning scenario.
Anchor check: run without uncertainty, the simulation network reproduces the 3 September 2026 forecast exactly, so every date starts from the schedule’s own logic.
What the Model Cannot See
The simulation network carries logic, durations and constraint floors only, with no resource levelling or progress override modelling. Completed work is held at its actual dates. Each activity’s duration is read on its own calendar, but the pass does not step it through that calendar’s days off, so on a schedule that mixes calendars the percentile dates are approximate.
Against the five maturity levels AACE RP 122R-22 names, the run reads at Level 2 of 5, Ad-hoc; exhibit A-02 sets out what the next level needs.
How the Schedule Was Read
Data date corrected.
This update has actual dates after its data date of 05-Aug-2025 00:00.
The latest is A2910's actual finish, 14-Oct-2025 17:00, so this report moves the data date to the start of the next day, 15-Oct-2025, and reschedules the update as P6 does.
62 activities had actual dates after 05-Aug-2025.
102 activities that hadn't started were forecast to start before 15-Oct-2025; they now start on or after it.
The file reports a finish of 24-Jun-2026.
At the corrected data date its logic gives 03-Sep-2026, 49 working days after the file's finish on the project calendar. This report uses 03-Sep-2026.
Critical path: the driving path.
The update of 15-Oct-2025 has negative float.
It measures float to its Must Finish By of 01-May-2026, and its logic finishes on 03-Sep-2026, and constraints hold dates earlier than its logic allows (Start On on 1 activity), so 171 unfinished activities have total float below zero.
Total float of zero or less marks 171 activities, but only 50 of them are on the driving path: the chains of driving relationships into the forecast finish, where each predecessor leaves no working day before its successor.
The other 121 sit on paths that can slip 1 to 77 working days before they move the forecast finish, so a delay to one of them moves the finish only once it uses up that margin.
This report counts an activity in this update as critical only when it is unfinished and on the driving path, and where chains tie, all of them count.
Basis of Measurement
The Evidence
The exhibits behind these findings follow in full, each under its drawing code:
- A-01Headline Risk Metrics
- A-02QRAMM-Aligned Maturity Reading
- A-03Probabilistic Completion Percentiles
- A-04Completion-day Distribution
- A-05Sensitivity, Tornado
- A-06Ranked Sensitivity Drivers
- A-07Schedule Recovery, Baseline vs Mitigated
- A-08Methodology
- A-09Reproducibility Manifest
Headline Risk Metrics
Monte Carlo · 5,000 iterationsQRAMM-Aligned Maturity Reading
five levels · informed by AACE RP 122R-22Illustrative three-point inputs (one range, 90% / 100% / 130% of each remaining duration, applied to every activity and not calibrated to this project) with documented distribution choice, sufficient iteration count, and per-activity sensitivity (Pearson correlation tornado) showing which activities drive the completion-day variance. The analysis stands on its own but is still a one-off, with nothing to compare it against.
AACE 122R-22 names five levels of maturity: Level 1 Reactive, Level 2 Ad-hoc, Level 3 Centralized, Level 4 Dynamic, Level 5 Adaptive.
Reference: AACE International RP 122R-22, "Quantitative Risk Analysis Maturity Model" (QRAMM), rev. October 13 2022 (editorial revision April 22 2024); TCM Framework 7.6 Risk Management, 3.3 Investment Decision Making.
- Iteration count: 5,000
- Baseline P50 / P80 produced: 25-Sep-2026 / 01-Oct-2026
- Three-point inputs: opt 90% / ml 100% / pes 130%, one illustrative range applied to every activity (not calibrated to this project)
- Distribution: Triangular
- Per-activity sensitivity: 252 ranked drivers (Pearson correlation tornado)
- Critical-path flagging applied to sensitivity rows
- Add at least one of: a mitigation scenario (baseline vs mitigated comparison), or a quantified risk register giving each risk a probability of occurring and a distribution of multiplicative impact factors mapped to the activities it affects (Hulett risk-driver method, AACE RP 57R-09).
- No convergence diagnostics run
This is a QRAMM-aligned reading, not a QRAMM score. AACE 122R-22 assesses the quantitative-risk capability of an organization: the RP states it is not a maturity model for assessing the depth of capability for any particular QRA method, and that it provides guidelines rather than a standard. What is scored here is one simulation run, placed by CPP on the five named levels of the RP so the reader can see how far this deliverable goes. The level criteria are CPP's, written in terms of evidence the run carries, and are not verbatim RP text. Reference: AACE International RP 122R-22, "Quantitative Risk Analysis Maturity Model" (QRAMM), rev. October 13 2022 (editorial revision April 22 2024); TCM Framework 7.6 Risk Management, 3.3 Investment Decision Making.
Probabilistic Completion Percentiles
8 percentiles · all listed| Percentile | Completion date | Day offset | Δ from deterministic |
|---|---|---|---|
| P10 | 21-Sep-2026 | 234 | +11 wd |
| P25 | 23-Sep-2026 | 236 | +13 wd |
| P50 | 25-Sep-2026 | 238 | +15 wd |
| P75 | 30-Sep-2026 | 241 | +18 wd |
| P80 | 01-Oct-2026 | 242 | +19 wd |
| P85 | 01-Oct-2026 | 242 | +19 wd |
| P90 | 02-Oct-2026 | 243 | +20 wd |
| P95 | 06-Oct-2026 | 245 | +22 wd |
Δ is measured against the single-point deterministic CPM finish. A later percentile (red) is downside schedule risk, an earlier one upside. The color flags direction relative to the deterministic estimate. The P10–P90 spread itself is expected uncertainty, not a per-percentile alarm.
- P80, 01-Oct-2026: a planning scenario, not a commitment, because no convergence diagnostics were run. It holds in 80% of simulated outcomes. That implies 19 working days of schedule contingency over the deterministic finish of 03-Sep-2026.
- P50, 25-Sep-2026: the even-odds date. Half the iterations finish later. Quote it as an expectation, not a commitment.
- Deterministic finish, 03-Sep-2026: the single-point CPM date. The simulation achieves it in only 0% of iterations, so treat it as an optimistic bound, not a forecast.
Completion-day Distribution
histogram + cumulative S-curve · 5,000 samplesProbability of achieving the deterministic date 03-Sep-2026: 0% of 5,000 iterations finished on or before it.
Sensitivity, Tornado
every driver plotted · 252 drivers| CP | Activity | Pearson correlation, activity duration vs completion day -0.380+0.38 | r |
|---|---|---|---|
| CP | A2380, Curtain wall and windows, West elevation | +0.382 | |
| CP | A2260, Curtain wall and windows, North elevation | +0.372 | |
| CP | A2340, Curtain wall and windows, South elevation | +0.361 | |
| CP | A2300, Curtain wall and windows, East elevation | +0.358 | |
| CP | A4410, Owner furniture and fit-out (by others) | +0.216 | |
| CP | A4380, Deficiency correction | +0.203 | |
| CP | A2250, Exterior sheathing and air/vapour barrier, North elevation | +0.203 | |
| CP | A4880, Owner audio-visual rough-in (by others) | +0.189 | |
| CP | A3620, Doors, hardware and millwork Level 2 Zone D | +0.171 | |
| CP | A3610, Flooring Level 2 Zone D | +0.166 | |
| CP | A2660, Drywall board Level 1 Zone A | +0.127 | |
| CP | A4340, Substantial performance certification | +0.122 | |
| CP | A3150, Electrical in-wall rough-in Level 2 Zone A | +0.122 | |
| CP | A1990, Erect structural steel Level 2 Zone D | +0.122 | |
| CP | A3180, Drywall board Level 2 Zone A | +0.122 | |
| CP | A4330, Deficiency review with the consultant | +0.114 | |
| CP | A4450, Ceiling grid Level 1 Zone B | +0.114 | |
| CP | A3630, Final paint and finishes Level 2 Zone D | +0.100 | |
| CP | A3100, Doors, hardware and millwork Level 1 Zone D | +0.099 | |
| CP | A2670, Tape, mud and sand Level 1 Zone A | +0.096 | |
| CP | A3090, Flooring Level 1 Zone D | +0.096 | |
| CP | A4440, Ceiling MEP devices and tiles Level 1 Zone A | +0.090 | |
| CP | A3190, Tape, mud and sand Level 2 Zone A | +0.087 | |
| CP | A2020, Erect structural steel Level 3 Zone A | +0.085 | |
| CP | A4530, Ceiling grid Level 2 Zone B | +0.079 | |
| CP | A2140, Erect structural steel Roof Zone A | +0.077 | |
| CP | A4490, Ceiling grid Level 1 Zone D | +0.077 | |
| CP | A4570, Ceiling grid Level 2 Zone D | +0.076 | |
| CP | A4900, Punch list Level 2 | +0.074 | |
| CP | A4480, Ceiling MEP devices and tiles Level 1 Zone C | +0.072 | |
| CP | A4540, Ceiling MEP devices and tiles Level 2 Zone B | +0.070 | |
| CP | A4520, Ceiling MEP devices and tiles Level 2 Zone A | +0.068 | |
| CP | A4500, Ceiling MEP devices and tiles Level 1 Zone D | +0.067 | |
| CP | A4510, Ceiling grid Level 2 Zone A | +0.065 | |
| CP | A4460, Ceiling MEP devices and tiles Level 1 Zone B | +0.064 | |
| CP | A4550, Ceiling grid Level 2 Zone C | +0.063 | |
| CP | A4470, Ceiling grid Level 1 Zone C | +0.061 | |
| CP | A4560, Ceiling MEP devices and tiles Level 2 Zone C | +0.057 | |
| CP | A4580, Ceiling MEP devices and tiles Level 2 Zone D | +0.054 | |
| CP | A1960, Erect structural steel Level 2 Zone C | +0.047 | |
| CP | A4430, Ceiling grid Level 1 Zone A | +0.047 | |
| A4720, Metal panel cladding, South elevation | -0.040 | ||
| A3330, Prime paint Level 2 Zone B | -0.040 | ||
| CP | A4800, Special inspection of Level 2 steel connections | +0.040 | |
| A4310, Fire department inspection | -0.037 | ||
| CP | A2680, Prime paint Level 1 Zone A | +0.036 | |
| CP | A3200, Prime paint Level 2 Zone A | +0.033 | |
| A2120, Metal deck Level 3 Zone D | +0.032 | ||
| A2850, Final paint and finishes Level 1 Zone B | +0.032 | ||
| A2230, Steel stairs and railings | -0.031 | ||
| A3410, Electrical in-wall rough-in Level 2 Zone C | +0.031 | ||
| A2710, Doors, hardware and millwork Level 1 Zone A | -0.030 | ||
| A4360, Owner training | -0.029 | ||
| A4090, Drywall board Level 3 Zone D | +0.029 | ||
| A3460, Prime paint Level 2 Zone C | +0.028 | ||
| A2520, Sprinkler mains and risers | +0.028 | ||
| A2200, Erect structural steel Roof Zone D | -0.028 | ||
| A2170, Metal deck Roof Zone B | -0.027 | ||
| A4840, ESA rough-in inspection Level 3 | +0.027 | ||
| A4020, Final paint and finishes Level 3 Zone C | -0.027 | ||
| A4250, Fire alarm verification | +0.026 | ||
| A3140, Plumbing in-wall rough-in Level 2 Zone A | +0.026 | ||
| A3970, Tape, mud and sand Level 3 Zone C | -0.026 | ||
| A2480, Ductwork mains Level 1 | +0.025 | ||
| A4740, Metal panel cladding, West elevation | +0.025 | ||
| A4270, Test, adjust and balance | +0.024 | ||
| A3690, In-wall services inspection Level 3 Zone A | -0.024 | ||
| A4730, Masonry veneer, West elevation | -0.024 | ||
| A1980, Concrete topping Level 2 Zone C | +0.024 | ||
| A3840, Tape, mud and sand Level 3 Zone B | -0.023 | ||
| A2450, Roof drains and leaders | -0.023 | ||
| A2400, Sealants and flashings, West elevation | -0.023 | ||
| A4370, Operation and maintenance manuals | -0.022 | ||
| A3900, Layout and partition framing Level 3 Zone C | +0.022 | ||
| A4130, Flooring Level 3 Zone D | +0.021 | ||
| A4700, Metal panel cladding, East elevation | +0.021 | ||
| A2160, Erect structural steel Roof Zone B | -0.021 | ||
| A2580, Elevator rails, machine and car install | +0.020 | ||
| A3850, Prime paint Level 3 Zone B | -0.020 | ||
| A4000, Flooring Level 3 Zone C | -0.020 | ||
| A2920, Drywall board Level 1 Zone C | +0.020 | ||
| A1940, Metal deck Level 2 Zone B | +0.020 | ||
| A4040, Mechanical in-wall rough-in Level 3 Zone D | -0.020 | ||
| A3520, Mechanical in-wall rough-in Level 2 Zone D | +0.019 | ||
| A3390, Mechanical in-wall rough-in Level 2 Zone C | -0.019 | ||
| A4170, Concrete curbs and sidewalks | -0.019 | ||
| A3020, Electrical in-wall rough-in Level 1 Zone D | +0.018 | ||
| A3370, Final paint and finishes Level 2 Zone B | +0.018 | ||
| A4140, Doors, hardware and millwork Level 3 Zone D | -0.018 | ||
| A2090, Metal deck Level 3 Zone C | -0.018 | ||
| A3740, Flooring Level 3 Zone A | +0.018 | ||
| A3660, Plumbing in-wall rough-in Level 3 Zone A | -0.017 | ||
| A4680, Metal panel cladding, North elevation | +0.017 | ||
| A3480, Flooring Level 2 Zone C | +0.017 | ||
| A3790, Plumbing in-wall rough-in Level 3 Zone B | +0.017 | ||
| A3230, Doors, hardware and millwork Level 2 Zone A | +0.017 | ||
| A4190, Asphalt paving | -0.017 | ||
| A2650, In-wall services inspection Level 1 Zone A | +0.016 | ||
| A3820, In-wall services inspection Level 3 Zone B | -0.016 | ||
| A4030, Layout and partition framing Level 3 Zone D | -0.016 | ||
| A4350, Final cleaning | -0.016 | ||
| A3920, Plumbing in-wall rough-in Level 3 Zone C | -0.016 | ||
| A2420, Roof flashings and penetrations | -0.015 | ||
| A2940, Prime paint Level 1 Zone C | +0.015 | ||
| A4820, ESA rough-in inspection Level 1 | -0.015 | ||
| A3240, Final paint and finishes Level 2 Zone A | +0.015 | ||
| A3550, Sprinkler branch piping Level 2 Zone D | +0.015 | ||
| A1650, Backfill and compact at foundations | +0.014 | ||
| A4830, ESA rough-in inspection Level 2 | -0.014 | ||
| A3960, Drywall board Level 3 Zone C | +0.014 | ||
| A4010, Doors, hardware and millwork Level 3 Zone C | +0.013 | ||
| A3670, Electrical in-wall rough-in Level 3 Zone A | -0.013 | ||
| A4050, Plumbing in-wall rough-in Level 3 Zone D | -0.013 | ||
| A3910, Mechanical in-wall rough-in Level 3 Zone C | -0.013 | ||
| A4810, Roof membrane flood test | +0.013 | ||
| A3420, Sprinkler branch piping Level 2 Zone C | +0.013 | ||
| A2410, Roof insulation and membrane | -0.013 | ||
| A3380, Layout and partition framing Level 2 Zone C | +0.013 | ||
| A2810, Prime paint Level 1 Zone B | -0.012 | ||
| A3870, Flooring Level 3 Zone B | +0.012 | ||
| A2610, Mechanical in-wall rough-in Level 1 Zone A | -0.012 | ||
| A2030, Metal deck Level 3 Zone A | -0.012 | ||
| A4100, Tape, mud and sand Level 3 Zone D | -0.012 | ||
| A3170, In-wall services inspection Level 2 Zone A | -0.012 | ||
| A3560, In-wall services inspection Level 2 Zone D | +0.012 | ||
| A4850, Temporary heat and enclosures for winter work | -0.012 | ||
| A3310, Drywall board Level 2 Zone B | +0.012 | ||
| A3320, Tape, mud and sand Level 2 Zone B | -0.012 | ||
| A3060, Tape, mud and sand Level 1 Zone D | -0.012 | ||
| A4210, Line painting and signage | +0.012 | ||
| A4400, Seasonal commissioning of heating and cooling | +0.012 | ||
| A2720, Final paint and finishes Level 1 Zone A | +0.011 | ||
| A3430, In-wall services inspection Level 2 Zone C | -0.011 | ||
| A2180, Erect structural steel Roof Zone C | +0.011 | ||
| A3890, Final paint and finishes Level 3 Zone B | -0.011 | ||
| A2500, Ductwork mains Level 3 | +0.011 | ||
| A3040, In-wall services inspection Level 1 Zone D | +0.011 | ||
| A2040, Concrete topping Level 3 Zone A | -0.011 | ||
| A4650, Ceiling grid Level 3 Zone D | +0.010 | ||
| A3780, Mechanical in-wall rough-in Level 3 Zone B | +0.010 | ||
| A2100, Concrete topping Level 3 Zone C | -0.010 | ||
| A2190, Metal deck Roof Zone C | +0.010 | ||
| A4220, Exterior stairs and barrier-free ramp | +0.010 | ||
| A3030, Sprinkler branch piping Level 1 Zone D | +0.010 | ||
| A3280, Electrical in-wall rough-in Level 2 Zone B | -0.010 | ||
| A3270, Plumbing in-wall rough-in Level 2 Zone B | -0.010 | ||
| A3950, In-wall services inspection Level 3 Zone C | +0.009 | ||
| A4060, Electrical in-wall rough-in Level 3 Zone D | -0.009 | ||
| A2150, Metal deck Roof Zone A | +0.009 | ||
| A3050, Drywall board Level 1 Zone D | -0.009 | ||
| A4070, Sprinkler branch piping Level 3 Zone D | -0.009 | ||
| A2330, Exterior sheathing and air/vapour barrier, South elevation | +0.009 | ||
| A4200, Landscaping and sod | -0.009 | ||
| A4180, Site lighting bases and poles | -0.009 | ||
| A2360, Sealants and flashings, South elevation | -0.009 | ||
| A4420, Owner IT and security installation (by others) | +0.008 | ||
| A4160, Granular base for parking and drive | -0.008 | ||
| A2430, Rooftop unit curbs | -0.008 | ||
| A3880, Doors, hardware and millwork Level 3 Zone B | -0.008 | ||
| A3930, Electrical in-wall rough-in Level 3 Zone C | +0.008 | ||
| A2990, Layout and partition framing Level 1 Zone D | -0.008 | ||
| A4320, Occupancy permit inspection | -0.008 | ||
| A4690, Masonry veneer, East elevation | -0.008 | ||
| CP | A3120, Layout and partition framing Level 2 Zone A | -0.008 | |
| A4620, Ceiling MEP devices and tiles Level 3 Zone B | +0.008 | ||
| A3650, Mechanical in-wall rough-in Level 3 Zone A | -0.008 | ||
| A3800, Electrical in-wall rough-in Level 3 Zone B | -0.008 | ||
| A2130, Concrete topping Level 3 Zone D | +0.007 | ||
| A2240, Elevator shaft masonry | +0.007 | ||
| A2370, Exterior sheathing and air/vapour barrier, West elevation | -0.007 | ||
| A3350, Flooring Level 2 Zone B | +0.007 | ||
| A3490, Doors, hardware and millwork Level 2 Zone C | +0.007 | ||
| A2010, Concrete topping Level 2 Zone D | -0.007 | ||
| A2000, Metal deck Level 2 Zone D | -0.007 | ||
| A4670, Masonry veneer, North elevation | +0.007 | ||
| A3010, Plumbing in-wall rough-in Level 1 Zone D | +0.007 | ||
| A3640, Layout and partition framing Level 3 Zone A | -0.007 | ||
| A2060, Metal deck Level 3 Zone B | -0.007 | ||
| A4610, Ceiling grid Level 3 Zone B | +0.007 | ||
| A3830, Drywall board Level 3 Zone B | +0.007 | ||
| A4150, Final paint and finishes Level 3 Zone D | -0.007 | ||
| A2320, Sealants and flashings, East elevation | -0.006 | ||
| A4390, Landscape establishment and warranty maintenance | -0.006 | ||
| CP | A3110, Final paint and finishes Level 1 Zone D | -0.006 | |
| A3440, Drywall board Level 2 Zone C | +0.006 | ||
| A2210, Metal deck Roof Zone D | -0.006 | ||
| A4110, Prime paint Level 3 Zone D | +0.006 | ||
| A3160, Sprinkler branch piping Level 2 Zone A | +0.006 | ||
| A3360, Doors, hardware and millwork Level 2 Zone B | +0.006 | ||
| A3260, Mechanical in-wall rough-in Level 2 Zone B | -0.006 | ||
| A4230, Entrance canopy steel and soffit | +0.006 | ||
| A3700, Drywall board Level 3 Zone A | +0.006 | ||
| A2830, Flooring Level 1 Zone B | +0.005 | ||
| A2700, Flooring Level 1 Zone A | +0.005 | ||
| A2290, Exterior sheathing and air/vapour barrier, East elevation | -0.005 | ||
| A4630, Ceiling grid Level 3 Zone C | -0.005 | ||
| A2050, Erect structural steel Level 3 Zone B | -0.005 | ||
| A1950, Concrete topping Level 2 Zone B | -0.005 | ||
| A4890, Punch list Level 1 | -0.005 | ||
| A3580, Tape, mud and sand Level 2 Zone D | -0.005 | ||
| A3810, Sprinkler branch piping Level 3 Zone B | -0.004 | ||
| A3710, Tape, mud and sand Level 3 Zone A | -0.004 | ||
| A3510, Layout and partition framing Level 2 Zone D | +0.004 | ||
| A3300, In-wall services inspection Level 2 Zone B | -0.004 | ||
| A4640, Ceiling MEP devices and tiles Level 3 Zone C | -0.004 | ||
| A3570, Drywall board Level 2 Zone D | -0.004 | ||
| A3290, Sprinkler branch piping Level 2 Zone B | +0.004 | ||
| A4710, Masonry veneer, South elevation | +0.004 | ||
| A4870, Second framing crew mobilized for Level 2 | -0.004 | ||
| A4260, Sprinkler flush and hydrostatic test | -0.004 | ||
| A2440, Set rooftop air handling units | -0.004 | ||
| A4590, Ceiling grid Level 3 Zone A | -0.004 | ||
| A3720, Prime paint Level 3 Zone A | +0.004 | ||
| A4860, Winter enclosure of open curtain wall openings | -0.004 | ||
| A4910, Punch list Level 3 | -0.003 | ||
| A4600, Ceiling MEP devices and tiles Level 3 Zone A | +0.003 | ||
| A3760, Final paint and finishes Level 3 Zone A | +0.003 | ||
| A4290, Mechanical commissioning | +0.003 | ||
| A2080, Erect structural steel Level 3 Zone C | +0.003 | ||
| A3980, Prime paint Level 3 Zone C | +0.003 | ||
| A2280, Sealants and flashings, North elevation | +0.003 | ||
| A3540, Electrical in-wall rough-in Level 2 Zone D | -0.003 | ||
| A2840, Doors, hardware and millwork Level 1 Zone B | -0.003 | ||
| A2980, Final paint and finishes Level 1 Zone C | +0.003 | ||
| A1970, Metal deck Level 2 Zone C | +0.003 | ||
| A3750, Doors, hardware and millwork Level 3 Zone A | -0.002 | ||
| A3400, Plumbing in-wall rough-in Level 2 Zone C | +0.002 | ||
| A2490, Ductwork mains Level 2 | +0.002 | ||
| A1890, Slab on grade Zone D | +0.002 | ||
| A2960, Flooring Level 1 Zone C | +0.002 | ||
| A2590, Elevator inspection and licence (TSSA) | -0.002 | ||
| A3070, Prime paint Level 1 Zone D | -0.002 | ||
| A2970, Doors, hardware and millwork Level 1 Zone C | -0.002 | ||
| A4660, Ceiling MEP devices and tiles Level 3 Zone D | -0.002 | ||
| A3220, Flooring Level 2 Zone A | +0.002 | ||
| A2930, Tape, mud and sand Level 1 Zone C | -0.002 | ||
| A2110, Erect structural steel Level 3 Zone D | -0.002 | ||
| A3130, Mechanical in-wall rough-in Level 2 Zone A | +0.001 | ||
| A3680, Sprinkler branch piping Level 3 Zone A | -0.001 | ||
| A3500, Final paint and finishes Level 2 Zone C | +0.001 | ||
| A2800, Tape, mud and sand Level 1 Zone B | -0.001 | ||
| A3250, Layout and partition framing Level 2 Zone B | -0.001 | ||
| A3450, Tape, mud and sand Level 2 Zone C | +0.001 | ||
| A2070, Concrete topping Level 3 Zone B | +0.001 | ||
| A4280, Building automation functional testing | 0.000 | ||
| A3770, Layout and partition framing Level 3 Zone B | 0.000 | ||
| A3590, Prime paint Level 2 Zone D | 0.000 | ||
| A3000, Mechanical in-wall rough-in Level 1 Zone D | 0.000 | ||
| A4080, In-wall services inspection Level 3 Zone D | 0.000 | ||
| A3530, Plumbing in-wall rough-in Level 2 Zone D | 0.000 | ||
| A2790, Drywall board Level 1 Zone B | 0.000 | ||
| A3940, Sprinkler branch piping Level 3 Zone C | 0.000 |
At 5,000 iterations, a |correlation| below the two-sided 95% significance threshold of 1.96/√n ≈ 0.028 is not statistically distinguishable from zero. 196 of 252 drivers fall below the threshold and are shaded; they remain plotted because the register is never truncated, but their order within the shaded band is noise, not ranking.
Ranked Sensitivity Drivers
252 drivers · all listed| Rank | Code | Activity | Planned dur. (wd) | Correlation | Impact (wd) |
|---|---|---|---|---|---|
| 1 | A2380CP | Curtain wall and windows, West elevation | 15.0 | +0.382 | 5.72 |
| 2 | A2260CP | Curtain wall and windows, North elevation | 15.0 | +0.372 | 5.57 |
| 3 | A2340CP | Curtain wall and windows, South elevation | 15.0 | +0.361 | 5.42 |
| 4 | A2300CP | Curtain wall and windows, East elevation | 15.0 | +0.358 | 5.37 |
| 5 | A4410CP | Owner furniture and fit-out (by others) | 15.0 | +0.216 | 3.24 |
| 6 | A4380CP | Deficiency correction | 15.0 | +0.203 | 3.05 |
| 7 | A2250CP | Exterior sheathing and air/vapour barrier, North elevation | 8.0 | +0.203 | 1.63 |
| 8 | A4880CP | Owner audio-visual rough-in (by others) | 8.0 | +0.189 | 1.51 |
| 9 | A3620CP | Doors, hardware and millwork Level 2 Zone D | 7.0 | +0.171 | 1.20 |
| 10 | A3610CP | Flooring Level 2 Zone D | 7.0 | +0.166 | 1.16 |
| 11 | A2660CP | Drywall board Level 1 Zone A | 5.0 | +0.127 | 0.64 |
| 12 | A4340CP | Substantial performance certification | 5.0 | +0.122 | 0.61 |
| 13 | A3150CP | Electrical in-wall rough-in Level 2 Zone A | 5.0 | +0.122 | 0.61 |
| 14 | A1990CP | Erect structural steel Level 2 Zone D | 4.0 | +0.122 | 0.49 |
| 15 | A3180CP | Drywall board Level 2 Zone A | 5.0 | +0.122 | 0.61 |
| 16 | A4330CP | Deficiency review with the consultant | 5.0 | +0.114 | 0.57 |
| 17 | A4450CP | Ceiling grid Level 1 Zone B | 3.0 | +0.114 | 0.34 |
| 18 | A3630CP | Final paint and finishes Level 2 Zone D | 5.0 | +0.100 | 0.50 |
| 19 | A3100CP | Doors, hardware and millwork Level 1 Zone D | 4.0 | +0.099 | 0.40 |
| 20 | A2670CP | Tape, mud and sand Level 1 Zone A | 4.0 | +0.096 | 0.38 |
| 21 | A3090CP | Flooring Level 1 Zone D | 4.0 | +0.096 | 0.38 |
| 22 | A4440CP | Ceiling MEP devices and tiles Level 1 Zone A | 3.0 | +0.090 | 0.27 |
| 23 | A3190CP | Tape, mud and sand Level 2 Zone A | 4.0 | +0.087 | 0.35 |
| 24 | A2020CP | Erect structural steel Level 3 Zone A | 4.0 | +0.085 | 0.34 |
| 25 | A4530CP | Ceiling grid Level 2 Zone B | 3.0 | +0.079 | 0.24 |
| 26 | A2140CP | Erect structural steel Roof Zone A | 4.0 | +0.077 | 0.31 |
| 27 | A4490CP | Ceiling grid Level 1 Zone D | 3.0 | +0.077 | 0.23 |
| 28 | A4570CP | Ceiling grid Level 2 Zone D | 3.0 | +0.076 | 0.23 |
| 29 | A4900CP | Punch list Level 2 | 3.0 | +0.074 | 0.22 |
| 30 | A4480CP | Ceiling MEP devices and tiles Level 1 Zone C | 3.0 | +0.072 | 0.22 |
| 31 | A4540CP | Ceiling MEP devices and tiles Level 2 Zone B | 3.0 | +0.070 | 0.21 |
| 32 | A4520CP | Ceiling MEP devices and tiles Level 2 Zone A | 3.0 | +0.068 | 0.20 |
| 33 | A4500CP | Ceiling MEP devices and tiles Level 1 Zone D | 3.0 | +0.067 | 0.20 |
| 34 | A4510CP | Ceiling grid Level 2 Zone A | 3.0 | +0.065 | 0.20 |
| 35 | A4460CP | Ceiling MEP devices and tiles Level 1 Zone B | 3.0 | +0.064 | 0.19 |
| 36 | A4550CP | Ceiling grid Level 2 Zone C | 3.0 | +0.063 | 0.19 |
| 37 | A4470CP | Ceiling grid Level 1 Zone C | 3.0 | +0.061 | 0.18 |
| 38 | A4560CP | Ceiling MEP devices and tiles Level 2 Zone C | 3.0 | +0.057 | 0.17 |
| 39 | A4580CP | Ceiling MEP devices and tiles Level 2 Zone D | 3.0 | +0.054 | 0.16 |
| 40 | A1960CP | Erect structural steel Level 2 Zone C | 2.0 | +0.047 | 0.09 |
| 41 | A4430CP | Ceiling grid Level 1 Zone A | 3.0 | +0.047 | 0.14 |
| 42 | A4720 | Metal panel cladding, South elevation | 8.0 | -0.040 | 0.32 |
| 43 | A3330 | Prime paint Level 2 Zone B | 2.0 | -0.040 | 0.08 |
| 44 | A4800CP | Special inspection of Level 2 steel connections | 2.0 | +0.040 | 0.08 |
| 45 | A4310 | Fire department inspection | 2.0 | -0.037 | 0.07 |
| 46 | A2680CP | Prime paint Level 1 Zone A | 2.0 | +0.036 | 0.07 |
| 47 | A3200CP | Prime paint Level 2 Zone A | 2.0 | +0.033 | 0.07 |
| 48 | A2120 | Metal deck Level 3 Zone D | 3.0 | +0.032 | 0.10 |
| 49 | A2850 | Final paint and finishes Level 1 Zone B | 3.0 | +0.032 | 0.10 |
| 50 | A2230 | Steel stairs and railings | 8.0 | -0.031 | 0.25 |
| 51 | A3410 | Electrical in-wall rough-in Level 2 Zone C | 5.0 | +0.031 | 0.15 |
| 52 | A2710 | Doors, hardware and millwork Level 1 Zone A | 4.0 | -0.030 | 0.12 |
| 53 | A4360 | Owner training | 5.0 | -0.029 | 0.15 |
| 54 | A4090 | Drywall board Level 3 Zone D | 5.0 | +0.029 | 0.14 |
| 55 | A3460 | Prime paint Level 2 Zone C | 2.0 | +0.028 | 0.06 |
| 56 | A2520 | Sprinkler mains and risers | 1.0 | +0.028 | 0.03 |
| 57 | A2200 | Erect structural steel Roof Zone D | 4.0 | -0.028† | 0.11 |
| 58 | A2170 | Metal deck Roof Zone B | 3.0 | -0.027† | 0.08 |
| 59 | A4840 | ESA rough-in inspection Level 3 | 1.0 | +0.027† | 0.03 |
| 60 | A4020 | Final paint and finishes Level 3 Zone C | 3.0 | -0.027† | 0.08 |
| 61 | A4250 | Fire alarm verification | 3.0 | +0.026† | 0.08 |
| 62 | A3140 | Plumbing in-wall rough-in Level 2 Zone A | 4.0 | +0.026† | 0.10 |
| 63 | A3970 | Tape, mud and sand Level 3 Zone C | 4.0 | -0.026† | 0.10 |
| 64 | A2480 | Ductwork mains Level 1 | 1.0 | +0.025† | 0.03 |
| 65 | A4740 | Metal panel cladding, West elevation | 8.0 | +0.025† | 0.20 |
| 66 | A4270 | Test, adjust and balance | 10.0 | +0.024† | 0.24 |
| 67 | A3690 | In-wall services inspection Level 3 Zone A | 1.0 | -0.024† | 0.02 |
| 68 | A4730 | Masonry veneer, West elevation | 10.0 | -0.024† | 0.24 |
| 69 | A1980 | Concrete topping Level 2 Zone C | 3.0 | +0.024† | 0.07 |
| 70 | A3840 | Tape, mud and sand Level 3 Zone B | 4.0 | -0.023† | 0.09 |
| 71 | A2450 | Roof drains and leaders | 4.0 | -0.023† | 0.09 |
| 72 | A2400 | Sealants and flashings, West elevation | 4.0 | -0.023† | 0.09 |
| 73 | A4370 | Operation and maintenance manuals | 10.0 | -0.022† | 0.22 |
| 74 | A3900 | Layout and partition framing Level 3 Zone C | 6.0 | +0.022† | 0.13 |
| 75 | A4130 | Flooring Level 3 Zone D | 4.0 | +0.021† | 0.09 |
| 76 | A4700 | Metal panel cladding, East elevation | 8.0 | +0.021† | 0.17 |
| 77 | A2160 | Erect structural steel Roof Zone B | 4.0 | -0.021† | 0.08 |
| 78 | A2580 | Elevator rails, machine and car install | 20.0 | +0.020† | 0.41 |
| 79 | A3850 | Prime paint Level 3 Zone B | 2.0 | -0.020† | 0.04 |
| 80 | A4000 | Flooring Level 3 Zone C | 4.0 | -0.020† | 0.08 |
| 81 | A2920 | Drywall board Level 1 Zone C | 5.0 | +0.020† | 0.10 |
| 82 | A1940 | Metal deck Level 2 Zone B | 1.0 | +0.020† | 0.02 |
| 83 | A4040 | Mechanical in-wall rough-in Level 3 Zone D | 5.0 | -0.020† | 0.10 |
| 84 | A3520 | Mechanical in-wall rough-in Level 2 Zone D | 5.0 | +0.019† | 0.10 |
| 85 | A3390 | Mechanical in-wall rough-in Level 2 Zone C | 5.0 | -0.019† | 0.10 |
| 86 | A4170 | Concrete curbs and sidewalks | 8.0 | -0.019† | 0.15 |
| 87 | A3020 | Electrical in-wall rough-in Level 1 Zone D | 5.0 | +0.018† | 0.09 |
| 88 | A3370 | Final paint and finishes Level 2 Zone B | 3.0 | +0.018† | 0.05 |
| 89 | A4140 | Doors, hardware and millwork Level 3 Zone D | 4.0 | -0.018† | 0.07 |
| 90 | A2090 | Metal deck Level 3 Zone C | 3.0 | -0.018† | 0.05 |
| 91 | A3740 | Flooring Level 3 Zone A | 4.0 | +0.018† | 0.07 |
| 92 | A3660 | Plumbing in-wall rough-in Level 3 Zone A | 4.0 | -0.017† | 0.07 |
| 93 | A4680 | Metal panel cladding, North elevation | 8.0 | +0.017† | 0.14 |
| 94 | A3480 | Flooring Level 2 Zone C | 4.0 | +0.017† | 0.07 |
| 95 | A3790 | Plumbing in-wall rough-in Level 3 Zone B | 4.0 | +0.017† | 0.07 |
| 96 | A3230 | Doors, hardware and millwork Level 2 Zone A | 4.0 | +0.017† | 0.07 |
| 97 | A4190 | Asphalt paving | 4.0 | -0.017† | 0.07 |
| 98 | A2650 | In-wall services inspection Level 1 Zone A | 1.0 | +0.016† | 0.02 |
| 99 | A3820 | In-wall services inspection Level 3 Zone B | 1.0 | -0.016† | 0.02 |
| 100 | A4030 | Layout and partition framing Level 3 Zone D | 6.0 | -0.016† | 0.10 |
| 101 | A4350 | Final cleaning | 5.0 | -0.016† | 0.08 |
| 102 | A3920 | Plumbing in-wall rough-in Level 3 Zone C | 4.0 | -0.016† | 0.06 |
| 103 | A2420 | Roof flashings and penetrations | 5.0 | -0.015† | 0.08 |
| 104 | A2940 | Prime paint Level 1 Zone C | 2.0 | +0.015† | 0.03 |
| 105 | A4820 | ESA rough-in inspection Level 1 | 1.0 | -0.015† | 0.02 |
| 106 | A3240 | Final paint and finishes Level 2 Zone A | 3.0 | +0.015† | 0.04 |
| 107 | A3550 | Sprinkler branch piping Level 2 Zone D | 4.0 | +0.015† | 0.06 |
| 108 | A1650 | Backfill and compact at foundations | 1.0 | +0.014† | 0.01 |
| 109 | A4830 | ESA rough-in inspection Level 2 | 1.0 | -0.014† | 0.01 |
| 110 | A3960 | Drywall board Level 3 Zone C | 5.0 | +0.014† | 0.07 |
| 111 | A4010 | Doors, hardware and millwork Level 3 Zone C | 4.0 | +0.013† | 0.05 |
| 112 | A3670 | Electrical in-wall rough-in Level 3 Zone A | 5.0 | -0.013† | 0.07 |
| 113 | A4050 | Plumbing in-wall rough-in Level 3 Zone D | 4.0 | -0.013† | 0.05 |
| 114 | A3910 | Mechanical in-wall rough-in Level 3 Zone C | 5.0 | -0.013† | 0.06 |
| 115 | A4810 | Roof membrane flood test | 1.0 | +0.013† | 0.01 |
| 116 | A3420 | Sprinkler branch piping Level 2 Zone C | 4.0 | +0.013† | 0.05 |
| 117 | A2410 | Roof insulation and membrane | 12.0 | -0.013† | 0.15 |
| 118 | A3380 | Layout and partition framing Level 2 Zone C | 6.0 | +0.013† | 0.08 |
| 119 | A2810 | Prime paint Level 1 Zone B | 2.0 | -0.012† | 0.02 |
| 120 | A3870 | Flooring Level 3 Zone B | 4.0 | +0.012† | 0.05 |
| 121 | A2610 | Mechanical in-wall rough-in Level 1 Zone A | 5.0 | -0.012† | 0.06 |
| 122 | A2030 | Metal deck Level 3 Zone A | 3.0 | -0.012† | 0.04 |
| 123 | A4100 | Tape, mud and sand Level 3 Zone D | 4.0 | -0.012† | 0.05 |
| 124 | A3170 | In-wall services inspection Level 2 Zone A | 1.0 | -0.012† | 0.01 |
| 125 | A3560 | In-wall services inspection Level 2 Zone D | 1.0 | +0.012† | 0.01 |
| 126 | A4850 | Temporary heat and enclosures for winter work | 15.0 | -0.012† | 0.18 |
| 127 | A3310 | Drywall board Level 2 Zone B | 5.0 | +0.012† | 0.06 |
| 128 | A3320 | Tape, mud and sand Level 2 Zone B | 4.0 | -0.012† | 0.05 |
| 129 | A3060 | Tape, mud and sand Level 1 Zone D | 4.0 | -0.012† | 0.05 |
| 130 | A4210 | Line painting and signage | 2.0 | +0.012† | 0.02 |
| 131 | A4400 | Seasonal commissioning of heating and cooling | 50.0 | +0.012† | 0.58 |
| 132 | A2720 | Final paint and finishes Level 1 Zone A | 3.0 | +0.011† | 0.03 |
| 133 | A3430 | In-wall services inspection Level 2 Zone C | 1.0 | -0.011† | 0.01 |
| 134 | A2180 | Erect structural steel Roof Zone C | 4.0 | +0.011† | 0.05 |
| 135 | A3890 | Final paint and finishes Level 3 Zone B | 3.0 | -0.011† | 0.03 |
| 136 | A2500 | Ductwork mains Level 3 | 8.0 | +0.011† | 0.09 |
| 137 | A3040 | In-wall services inspection Level 1 Zone D | 1.0 | +0.011† | 0.01 |
| 138 | A2040 | Concrete topping Level 3 Zone A | 3.0 | -0.011† | 0.03 |
| 139 | A4650 | Ceiling grid Level 3 Zone D | 3.0 | +0.010† | 0.03 |
| 140 | A3780 | Mechanical in-wall rough-in Level 3 Zone B | 5.0 | +0.010† | 0.05 |
| 141 | A2100 | Concrete topping Level 3 Zone C | 3.0 | -0.010† | 0.03 |
| 142 | A2190 | Metal deck Roof Zone C | 3.0 | +0.010† | 0.03 |
| 143 | A4220 | Exterior stairs and barrier-free ramp | 6.0 | +0.010† | 0.06 |
| 144 | A3030 | Sprinkler branch piping Level 1 Zone D | 4.0 | +0.010† | 0.04 |
| 145 | A3280 | Electrical in-wall rough-in Level 2 Zone B | 5.0 | -0.010† | 0.05 |
| 146 | A3270 | Plumbing in-wall rough-in Level 2 Zone B | 4.0 | -0.010† | 0.04 |
| 147 | A3950 | In-wall services inspection Level 3 Zone C | 1.0 | +0.009† | 0.01 |
| 148 | A4060 | Electrical in-wall rough-in Level 3 Zone D | 5.0 | -0.009† | 0.05 |
| 149 | A2150 | Metal deck Roof Zone A | 3.0 | +0.009† | 0.03 |
| 150 | A3050 | Drywall board Level 1 Zone D | 5.0 | -0.009† | 0.05 |
| 151 | A4070 | Sprinkler branch piping Level 3 Zone D | 4.0 | -0.009† | 0.04 |
| 152 | A2330 | Exterior sheathing and air/vapour barrier, South elevation | 8.0 | +0.009† | 0.07 |
| 153 | A4200 | Landscaping and sod | 8.0 | -0.009† | 0.07 |
| 154 | A4180 | Site lighting bases and poles | 6.0 | -0.009† | 0.05 |
| 155 | A2360 | Sealants and flashings, South elevation | 4.0 | -0.009† | 0.03 |
| 156 | A4420 | Owner IT and security installation (by others) | 10.0 | +0.008† | 0.08 |
| 157 | A4160 | Granular base for parking and drive | 6.0 | -0.008† | 0.05 |
| 158 | A2430 | Rooftop unit curbs | 3.0 | -0.008† | 0.02 |
| 159 | A3880 | Doors, hardware and millwork Level 3 Zone B | 4.0 | -0.008† | 0.03 |
| 160 | A3930 | Electrical in-wall rough-in Level 3 Zone C | 5.0 | +0.008† | 0.04 |
| 161 | A2990 | Layout and partition framing Level 1 Zone D | 6.0 | -0.008† | 0.05 |
| 162 | A4320 | Occupancy permit inspection | 3.0 | -0.008† | 0.02 |
| 163 | A4690 | Masonry veneer, East elevation | 10.0 | -0.008† | 0.08 |
| 164 | A3120CP | Layout and partition framing Level 2 Zone A | 6.0 | -0.008† | 0.05 |
| 165 | A4620 | Ceiling MEP devices and tiles Level 3 Zone B | 3.0 | +0.008† | 0.02 |
| 166 | A3650 | Mechanical in-wall rough-in Level 3 Zone A | 5.0 | -0.008† | 0.04 |
| 167 | A3800 | Electrical in-wall rough-in Level 3 Zone B | 5.0 | -0.008† | 0.04 |
| 168 | A2130 | Concrete topping Level 3 Zone D | 3.0 | +0.007† | 0.02 |
| 169 | A2240 | Elevator shaft masonry | 1.0 | +0.007† | 0.01 |
| 170 | A2370 | Exterior sheathing and air/vapour barrier, West elevation | 8.0 | -0.007† | 0.06 |
| 171 | A3350 | Flooring Level 2 Zone B | 4.0 | +0.007† | 0.03 |
| 172 | A3490 | Doors, hardware and millwork Level 2 Zone C | 4.0 | +0.007† | 0.03 |
| 173 | A2010 | Concrete topping Level 2 Zone D | 3.0 | -0.007† | 0.02 |
| 174 | A2000 | Metal deck Level 2 Zone D | 3.0 | -0.007† | 0.02 |
| 175 | A4670 | Masonry veneer, North elevation | 10.0 | +0.007† | 0.07 |
| 176 | A3010 | Plumbing in-wall rough-in Level 1 Zone D | 4.0 | +0.007† | 0.03 |
| 177 | A3640 | Layout and partition framing Level 3 Zone A | 6.0 | -0.007† | 0.04 |
| 178 | A2060 | Metal deck Level 3 Zone B | 3.0 | -0.007† | 0.02 |
| 179 | A4610 | Ceiling grid Level 3 Zone B | 3.0 | +0.007† | 0.02 |
| 180 | A3830 | Drywall board Level 3 Zone B | 5.0 | +0.007† | 0.03 |
| 181 | A4150 | Final paint and finishes Level 3 Zone D | 3.0 | -0.007† | 0.02 |
| 182 | A2320 | Sealants and flashings, East elevation | 4.0 | -0.006† | 0.03 |
| 183 | A4390 | Landscape establishment and warranty maintenance | 60.0 | -0.006† | 0.39 |
| 184 | A3110CP | Final paint and finishes Level 1 Zone D | 3.0 | -0.006† | 0.02 |
| 185 | A3440 | Drywall board Level 2 Zone C | 5.0 | +0.006† | 0.03 |
| 186 | A2210 | Metal deck Roof Zone D | 3.0 | -0.006† | 0.02 |
| 187 | A4110 | Prime paint Level 3 Zone D | 2.0 | +0.006† | 0.01 |
| 188 | A3160 | Sprinkler branch piping Level 2 Zone A | 4.0 | +0.006† | 0.02 |
| 189 | A3360 | Doors, hardware and millwork Level 2 Zone B | 4.0 | +0.006† | 0.02 |
| 190 | A3260 | Mechanical in-wall rough-in Level 2 Zone B | 5.0 | -0.006† | 0.03 |
| 191 | A4230 | Entrance canopy steel and soffit | 5.0 | +0.006† | 0.03 |
| 192 | A3700 | Drywall board Level 3 Zone A | 5.0 | +0.006† | 0.03 |
| 193 | A2830 | Flooring Level 1 Zone B | 4.0 | +0.005† | 0.02 |
| 194 | A2700 | Flooring Level 1 Zone A | 4.0 | +0.005† | 0.02 |
| 195 | A2290 | Exterior sheathing and air/vapour barrier, East elevation | 8.0 | -0.005† | 0.04 |
| 196 | A4630 | Ceiling grid Level 3 Zone C | 3.0 | -0.005† | 0.02 |
| 197 | A2050 | Erect structural steel Level 3 Zone B | 4.0 | -0.005† | 0.02 |
| 198 | A1950 | Concrete topping Level 2 Zone B | 3.0 | -0.005† | 0.01 |
| 199 | A4890 | Punch list Level 1 | 3.0 | -0.005† | 0.01 |
| 200 | A3580 | Tape, mud and sand Level 2 Zone D | 4.0 | -0.005† | 0.02 |
| 201 | A3810 | Sprinkler branch piping Level 3 Zone B | 4.0 | -0.004† | 0.02 |
| 202 | A3710 | Tape, mud and sand Level 3 Zone A | 4.0 | -0.004† | 0.02 |
| 203 | A3510 | Layout and partition framing Level 2 Zone D | 6.0 | +0.004† | 0.03 |
| 204 | A3300 | In-wall services inspection Level 2 Zone B | 1.0 | -0.004† | 0.00 |
| 205 | A4640 | Ceiling MEP devices and tiles Level 3 Zone C | 3.0 | -0.004† | 0.01 |
| 206 | A3570 | Drywall board Level 2 Zone D | 5.0 | -0.004† | 0.02 |
| 207 | A3290 | Sprinkler branch piping Level 2 Zone B | 4.0 | +0.004† | 0.02 |
| 208 | A4710 | Masonry veneer, South elevation | 10.0 | +0.004† | 0.04 |
| 209 | A4870 | Second framing crew mobilized for Level 2 | 2.0 | -0.004† | 0.01 |
| 210 | A4260 | Sprinkler flush and hydrostatic test | 3.0 | -0.004† | 0.01 |
| 211 | A2440 | Set rooftop air handling units | 3.0 | -0.004† | 0.01 |
| 212 | A4590 | Ceiling grid Level 3 Zone A | 3.0 | -0.004† | 0.01 |
| 213 | A3720 | Prime paint Level 3 Zone A | 2.0 | +0.004† | 0.01 |
| 214 | A4860 | Winter enclosure of open curtain wall openings | 5.0 | -0.004† | 0.02 |
| 215 | A4910 | Punch list Level 3 | 3.0 | -0.003† | 0.01 |
| 216 | A4600 | Ceiling MEP devices and tiles Level 3 Zone A | 3.0 | +0.003† | 0.01 |
| 217 | A3760 | Final paint and finishes Level 3 Zone A | 3.0 | +0.003† | 0.01 |
| 218 | A4290 | Mechanical commissioning | 10.0 | +0.003† | 0.03 |
| 219 | A2080 | Erect structural steel Level 3 Zone C | 4.0 | +0.003† | 0.01 |
| 220 | A3980 | Prime paint Level 3 Zone C | 2.0 | +0.003† | 0.01 |
| 221 | A2280 | Sealants and flashings, North elevation | 4.0 | +0.003† | 0.01 |
| 222 | A3540 | Electrical in-wall rough-in Level 2 Zone D | 5.0 | -0.003† | 0.01 |
| 223 | A2840 | Doors, hardware and millwork Level 1 Zone B | 4.0 | -0.003† | 0.01 |
| 224 | A2980 | Final paint and finishes Level 1 Zone C | 3.0 | +0.003† | 0.01 |
| 225 | A1970 | Metal deck Level 2 Zone C | 3.0 | +0.003† | 0.01 |
| 226 | A3750 | Doors, hardware and millwork Level 3 Zone A | 4.0 | -0.002† | 0.01 |
| 227 | A3400 | Plumbing in-wall rough-in Level 2 Zone C | 4.0 | +0.002† | 0.01 |
| 228 | A2490 | Ductwork mains Level 2 | 8.0 | +0.002† | 0.02 |
| 229 | A1890 | Slab on grade Zone D | 1.0 | +0.002† | 0.00 |
| 230 | A2960 | Flooring Level 1 Zone C | 4.0 | +0.002† | 0.01 |
| 231 | A2590 | Elevator inspection and licence (TSSA) | 2.0 | -0.002† | 0.00 |
| 232 | A3070 | Prime paint Level 1 Zone D | 2.0 | -0.002† | 0.00 |
| 233 | A2970 | Doors, hardware and millwork Level 1 Zone C | 4.0 | -0.002† | 0.01 |
| 234 | A4660 | Ceiling MEP devices and tiles Level 3 Zone D | 3.0 | -0.002† | 0.01 |
| 235 | A3220 | Flooring Level 2 Zone A | 4.0 | +0.002† | 0.01 |
| 236 | A2930 | Tape, mud and sand Level 1 Zone C | 4.0 | -0.002† | 0.01 |
| 237 | A2110 | Erect structural steel Level 3 Zone D | 4.0 | -0.002† | 0.01 |
| 238 | A3130 | Mechanical in-wall rough-in Level 2 Zone A | 5.0 | +0.001† | 0.01 |
| 239 | A3680 | Sprinkler branch piping Level 3 Zone A | 4.0 | -0.001† | 0.00 |
| 240 | A3500 | Final paint and finishes Level 2 Zone C | 3.0 | +0.001† | 0.00 |
| 241 | A2800 | Tape, mud and sand Level 1 Zone B | 4.0 | -0.001† | 0.00 |
| 242 | A3250 | Layout and partition framing Level 2 Zone B | 6.0 | -0.001† | 0.00 |
| 243 | A3450 | Tape, mud and sand Level 2 Zone C | 4.0 | +0.001† | 0.00 |
| 244 | A2070 | Concrete topping Level 3 Zone B | 3.0 | +0.001† | 0.00 |
| 245 | A4280 | Building automation functional testing | 8.0 | 0.000† | 0.00 |
| 246 | A3770 | Layout and partition framing Level 3 Zone B | 6.0 | 0.000† | 0.00 |
| 247 | A3590 | Prime paint Level 2 Zone D | 2.0 | 0.000† | 0.00 |
| 248 | A3000 | Mechanical in-wall rough-in Level 1 Zone D | 5.0 | 0.000† | 0.00 |
| 249 | A4080 | In-wall services inspection Level 3 Zone D | 1.0 | 0.000† | 0.00 |
| 250 | A3530 | Plumbing in-wall rough-in Level 2 Zone D | 4.0 | 0.000† | 0.00 |
| 251 | A2790 | Drywall board Level 1 Zone B | 5.0 | 0.000† | 0.00 |
| 252 | A3940 | Sprinkler branch piping Level 3 Zone C | 4.0 | 0.000† | 0.00 |
Ranked by |correlation|, the same order as the tornado chart; planned duration and impact are in working days. Impact = |correlation| × planned duration. Critical-path activities flagged CP. † At 5,000 iterations, entries with |correlation| below 1.96/√n ≈ 0.028 are not statistically distinguishable from zero; 196 of 252 listed drivers carry the marker. Their rank order is noise, not signal.
Schedule Recovery, Baseline vs Mitigated
not run, no recovery scenario definedA mitigated re-run was not in scope for this analysis; CPP runs this comparison when a recovery scenario is defined.
Methodology
basis, distribution, percentile methodForecast completion dates are produced by Monte Carlo simulation over the activity duration distribution implied by the optimistic / most-likely / pessimistic percentages applied to each incomplete activity's planned duration. A full CPM forward pass is executed per iteration. Percentiles are derived from the completion-day vector using numpy.percentile(method='nearest'), which reports an actual simulation trial rather than an interpolated value, so each percentile traces back to a real, reproducible iteration. Sensitivity (tornado) is the Pearson correlation between each activity's sampled-duration vector and the final completion-day vector. Impact = |corr| × planned duration on the legacy PERT/Triangular path, or |corr| × posterior σ on the Bayesian-posterior path (when historical_snapshots was supplied). The active prior shape is reported per row in the sensitivity CSV's prior_method column. Statistical significance of the correlations: at n = 5,000 iterations, the two-sided 95% critical value for a Pearson correlation differing from zero is approximately 1.96/√n ≈ 0.028. Drivers whose |correlation| falls below that threshold are statistically indistinguishable from zero; they are shaded in the tornado (A-05) and marked † in the ranking (A-06) but remain fully listed.
Distribution: Triangular · Iterations: 5,000 · Random seed: 42 · Day basis: working days from data date. Working-day basis counts only the project’s own working days, read from the calendar loaded with this XER, so its workweek and its holiday exceptions are both honoured. The corresponding completion dates are the true calendar dates on which those working-day offsets fall. Each activity's duration is read on its own P6 calendar, but the pass does not step it through that calendar's own days off, so on a schedule that mixes calendars the percentile dates are approximate.
Prepared by the schedule-risk-analysis skill in the CPP Scheduling Suite. This dashboard is self-contained. All assets are inlined and it renders offline.