DEMO PREVIEW · NOT FOR LITIGATION USE · Sample data, fictional project ·
Critical Path Partners →
QRAMM Maturity Self-Assessment
AACE International RP 122R-22 "Quantitative Risk Analysis Maturity Model" (Oct 13 2022, rev Apr 22 2024)
Tier 3 — Managed
Tier 2 plus scenario comparison (baseline vs mitigated) so the recovery delta is measured, OR a qualitative risk register integrated into the simulation per the Hulett risk-driver method (AACE RP 57R-09 (Hulett risk-driver method) / Hulett 2009). Iteration count is sized for stable percentiles.
Scenario comparison: baseline vs mitigated present
No qualitative risk register
Gaps to next tier
Add a qualitative risk register alongside the mitigation scenario (Hulett method).
Tag every risk with attributed_to (owner / contractor / concurrent / force_majeure) so the analyst can answer "which party owns each day of risk?".
Tier definitions in this badge are an interpretation of typical risk-maturity-model structure (CMMI-style: Initial / Defined / Managed / Optimized) mapped onto evidence the SRA result dict carries. They are NOT verbatim from AACE 122R-22 and require confirmation against the primary RP before use for external client submission. Primary citation: AACE International RP 122R-22 "Quantitative Risk Analysis Maturity Model" (Oct 13 2022, rev Apr 22 2024).
Forecast completion dates are produced by Monte Carlo simulation over the activity
duration distribution implied by the optimistic / most-likely / pessimistic percentages applied
to each incomplete activity's planned duration. A full CPM forward pass is executed per
iteration; percentiles are derived from the completion-day vector using
numpy.percentile(method='lower') to match Tool_11 browser parity.
Sensitivity (tornado) is the Pearson correlation between each activity's sampled-duration
vector and the final completion-day vector; impact = |corr| × planned duration.
Distribution: Triangular ·
Iterations: 5,000 ·
Random seed: 42 ·
Day basis: calendar days from data date.
Calendar-day basis means day offsets count every calendar day from the data date; working-day
basis converts to a simple 5-day workweek (Mon–Fri, no holidays).
Prepared by the schedule-risk-analysis skill in the CPP Scheduling Suite.
This dashboard is self-contained — all assets are inlined and it renders offline.