CPP
CRITICAL PATH PARTNERSForensic Schedule Analysis
DWG · FDA-01 / SHEET A-00
Windows Analysis · AACE MIP 3.3
Forensic Delay Analysis

Ontario Community College - B2 (Demo Data) 1 window analyzed: Baseline → Current

Project
Ontario Community College - B2 (Demo Data)
Prepared By
Dana Fitkowski · Critical Path Partners
Window Period
01-Apr-2025 → 01-Jul-2025
Generated
15-Jul-2026
Baseline → Final Slip (wd)
+21 wd
Completion delay · 0 slip-days unattributed
Window Shifts
+21 wd
Windows
1
Attribution
100.0%
Baseline → Final Slip (wd)
+21 wd
Cumulative vs baseline completion (working days)
Sum of Window Shifts (wd)
+21 wd
Signed shift across all windows (working days)
Windows Analyzed
1
Baseline → Current
Attribution Complete
100.0%
fully attributed
A-01

Windows Overview

per-window shift and cumulative vs baseline, working days
WindowPeriodShift (wd)Cumulative vs Baseline (wd)CP ActivitiesCP Duration GrowthSlipped Activities
Baseline → Current01-Apr-2025 → 01-Jul-2025+21 wd+21 wd3912264
A-02

Window Shift Trend

signed completion shift per window (working days)
Window slip (working days)1 window
21 wd10 wd0 wd+21 wdBaseline → Current
Window slip (positive = delay)+21 wd total window shift
A-03

Cumulative Attribution Summary

party share of project slip-days
Attribution by responsible party (wd)21 wd total
Owner7 wdContractor14 wdConcurrent0 wdForce Majeure0 wdUnattributed0 wd
Attributed party share21 wd total project slip
Owner
7 wd
Contractor
14 wd
Concurrent
0 wd
Force Majeure
0 wd
A-04

Concurrent Delay Matrix

per-window × per-party attribution grid
Each cell = working days attributed to that party in that window (Window Shift (wd)). Column totals equal the cumulative party share across the project; the grand total equals the project completion shift in working days (AACE 29R-03 §4.1 conservation rule). The Finish Driver column names the activity and date field the shift was measured on.
WindowPeriodOwnerContractorConcurrentForce MajeureUnattributedWindow Shift (wd)Finish Driver
Baseline → Current01-Apr-2025 → 01-Jul-2025+7 wd+14 wd+21 wdA4240
target_end_date
Cumulativeproject totals+7 wd+14 wd0 wd0 wd0 wd+21 wd
~CASCADE = window had no CP duration growth; attribution inferred from dominant CP slip party. !UNATTRIBUTED = the dominant share of the window shift dropped to Unattributed (no named responsible party). Reference: AACE RP 29R-03 §4.2.B (concurrent delay apportionment).
A-05

Slip Velocity & Acceleration

per-window slip-rate trend
Velocity = signed completion shift (working days) ÷ window duration (working days on the same calendar). Acceleration = change in velocity vs the prior window. Half-period estimate (working days) assumes uniform deterioration within the window.
Mean Velocity (wd/wd)
+0.339
working-days slip / working-day elapsed
Max-Velocity Window
fastest deterioration
Accelerating Windows
0
velocity increasing
Decelerating Windows
0
velocity decreasing
WindowPeriodDuration (wd)Shift (wd)Velocity (wd/wd)Δ AccelerationMidpoint DateHalf-Period Slip (wd)
Baseline → Current01-Apr-2025 → 01-Jul-202562 wd+21 wd+0.33916-May-2025+10.5 wd
Caveat (cite in any expert report): Slip velocity is a working-day/working-day rate: numerator = working-day completion shift, denominator = working days between data dates on the same calendar (see basis). Midpoint estimates assume uniform deterioration within the window. Actual slip events may have clustered at any point inside the window — the midpoint is a probabilistic centroid, not an observed event date. Cite this caveat in any expert report that quotes the half-period estimate. Velocity is a per-window average rate, not an instantaneous one; acceleration is a finite difference between successive averages and is sensitive to window-length disparity (sign and direction are reliable, magnitude less so).
Recovery windows (negative shift) detected: 0. Reference: AACE RP 29R-03 §3.3 (Windows Analysis — MIP 3.3 Observational / Dynamic).
A-06

WOET — Worked-vs-On-time Execution Timeline

4-state day classification
4-state day classification of as-built execution against the baseline plan. All day counts below are working days on each activity’s P6 calendar (weekends and holidays excluded). Reference date: 2025-07-01. Activities classified: 117. On-time-or-better: 25.0% (Progress 19.9% + Gain). Slipped: 75.0% (Extended + Void).
Progress (wd)
372 wd
19.9% on plan
Gain (wd)
5.0% ahead
Extended (wd)
375 wd
20.1% slipped
Void (wd)
1026 wd
55.0% unrecovered
A-06Worst-affected activities (sorted Extended → Void — full list)
117 classified activities — all listedExport CSV
CodeActivityBaseline PeriodActual PeriodProgress (wd)Gain (wd)Extended (wd)Void (wd)
A1160TPO Roofing Shop Drawings2025-06-10 → 2025-06-232025-07-09 → 2025-08-260 wd0 wd35 wd10 wd
A3930Interior Demoilition2025-06-18 → 2025-07-092025-07-21 → 2025-09-020 wd0 wd31 wd15 wd
A146023 25 00 - Water Treatment (R0)2025-06-26 → 2025-07-102025-06-26 → 2025-08-1210 wd0 wd23 wd0 wd
A1280ACT Data sheet and Sample2025-07-16 → 2025-07-292025-07-23 → 2025-08-275 wd0 wd21 wd5 wd
A2500Install Rebar for Piers2025-08-01 → 2025-08-082025-07-29 → 2025-09-086 wd3 wd20 wd0 wd
A1120Cold-formed Metal Framing Shop Drawings2025-06-10 → 2025-06-232025-06-26 → 2025-07-230 wd0 wd19 wd10 wd
A153020 05 10 - Electric Heat Tracing (R0)2025-07-09 → 2025-07-222025-07-09 → 2025-08-1210 wd0 wd15 wd0 wd
A2520Form and Pour Foundation Piers2025-08-11 → 2025-08-152025-08-11 → 2025-09-085 wd0 wd15 wd0 wd
A1100Structural Steel Framing and Steel Deck Shop Drawings (R0)2025-06-10 → 2025-06-232025-06-20 → 2025-07-142 wd0 wd14 wd8 wd
A1090Masonry and Mortar Samples & Data Sheets2025-07-16 → 2025-07-292025-06-10 → 2025-08-1810 wd25 wd14 wd0 wd
A2530Backfilling to U/S of Grade Beams2025-08-18 → 2025-08-222025-08-11 → 2025-09-125 wd5 wd14 wd0 wd
A1230Coiling Doors2025-07-16 → 2025-07-292025-08-05 → 2025-08-210 wd0 wd13 wd10 wd
A2280Under Pinning Inspection2025-06-24 → 2025-06-242025-06-23 → 2025-07-141 wd1 wd13 wd0 wd
A147023 37 13 - Diffuser and Grilles Shop Drawings (R0)2025-07-15 → 2025-07-282025-07-15 → 2025-08-1410 wd0 wd13 wd0 wd
A158026 50 00 - Lighting Fixtures2025-06-27 → 2025-07-112025-08-01 → 2025-08-180 wd0 wd12 wd10 wd
A159026 09 23 - Lighting Control (R0)2025-06-17 → 2025-06-302025-08-01 → 2025-08-180 wd0 wd12 wd10 wd
A156026 50 00 - Emergency Lighting & Exit Signs2025-06-27 → 2025-07-112025-06-27 → 2025-07-2910 wd0 wd12 wd0 wd
A1050Ductbank Underpinning Drawing2025-06-03 → 2025-06-162025-06-16 → 2025-06-301 wd0 wd10 wd9 wd
A1060Foundation Concrete Rebar Shop Drawing2025-06-10 → 2025-06-232025-05-29 → 2025-07-0810 wd8 wd10 wd0 wd
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes2025-06-11 → 2025-06-242025-06-11 → 2025-07-0810 wd0 wd9 wd0 wd
A137023 74 13 - Air Handling Units (R0)2025-06-26 → 2025-07-102025-06-26 → 2025-07-2110 wd0 wd7 wd0 wd
A1080Bentonite Waterstop Data Sheet2025-06-10 → 2025-06-232025-06-09 → 2025-07-0210 wd1 wd6 wd0 wd
A1290Suspended Metal Soffits2025-07-16 → 2025-07-292025-08-28 → 2025-09-040 wd0 wd5 wd10 wd
A1660Bentonite Waterstop 2025-06-24 → 2025-06-302025-07-03 → 2025-07-090 wd0 wd5 wd5 wd
A151023 00 00 - Wall Fin Heater2025-07-22 → 2025-08-052025-07-22 → 2025-08-1211 wd0 wd5 wd0 wd
A154022 40 00 - Plumbing Fixtures (R0)2025-07-11 → 2025-07-242025-07-11 → 2025-07-3110 wd0 wd5 wd0 wd
A1220Flush Wood Doors Sample2025-07-16 → 2025-07-292025-08-26 → 2025-08-270 wd0 wd2 wd10 wd
A1070Foundation Concrete Mix Design2025-06-10 → 2025-06-232025-06-13 → 2025-06-257 wd0 wd2 wd3 wd
A1650Foundation Concrete Mix Design2025-06-24 → 2025-06-252025-06-26 → 2025-06-270 wd0 wd2 wd2 wd
A1680 IN-PROGRESSStructural Steel 2025-06-24 → 2025-07-292025-09-04 → —0 wd0 wd1 wd25 wd
A1130 IN-PROGRESSMisc. Metals Shop Drawings2025-07-09 → 2025-07-222025-08-26 → —0 wd0 wd1 wd10 wd
A1330 IN-PROGRESSFall Arrest Anchors and Horizontal Lines2025-07-16 → 2025-07-292025-08-14 → —0 wd0 wd1 wd10 wd
A1110Structural Reinforcement + Decking Shop Drawings2025-06-10 → 2025-06-232025-08-01 → 2025-08-010 wd0 wd1 wd10 wd
A1500 IN-PROGRESS23 52 16 - Heating Boilers2025-07-09 → 2025-07-222025-09-12 → —0 wd0 wd1 wd10 wd
A1190Fire-resistive Material Data Sheet2025-06-24 → 2025-07-082025-06-27 → 2025-07-097 wd0 wd1 wd3 wd
A1040Permit (Not Required Per Ontario Community College)2025-05-15 → 2025-05-152025-05-16 → 2025-05-160 wd0 wd1 wd1 wd
A1030IFC Drawings Released2025-05-14 → 2025-05-142025-05-15 → 2025-05-150 wd0 wd1 wd1 wd
A3920Setup Temporary Hoarding2025-06-17 → 2025-06-172025-07-04 → 2025-07-040 wd0 wd1 wd1 wd
A2510Supply of Embedment & Ankors2025-06-24 → 2025-06-242025-08-22 → 2025-08-220 wd0 wd1 wd1 wd
A1150Built-up Roofing Shop Drawings2025-06-24 → 2025-07-082025-06-19 → 2025-07-0910 wd3 wd1 wd0 wd
A2600Compaction Inspection2025-04-02 → 2025-09-192025-08-15 → 2025-08-151 wd0 wd0 wd94 wd
A2390Subgrade Inspection2025-04-02 → 2025-07-252025-07-22 → 2025-07-221 wd0 wd0 wd76 wd
A3320Blocking Installation2025-04-02 → 2026-04-09— → —0 wd0 wd0 wd62 wd
A3480Blocking Installation2025-04-02 → 2026-04-23— → —0 wd0 wd0 wd62 wd
A3610Blocking Installation2025-04-02 → 2026-05-04— → —0 wd0 wd0 wd62 wd
A2660Install Temporary Hoarding for Slab on Deck2025-04-02 → 2025-11-03— → —0 wd0 wd0 wd62 wd
A3180Roof Inspection2025-04-02 → 2025-12-19— → —0 wd0 wd0 wd62 wd
A2620Structural Steel Inspection2025-04-02 → 2025-10-20— → —0 wd0 wd0 wd62 wd
A3080L1, L2 & L3 Air Vapor Barrier Inspection2025-04-02 → 2026-02-25— → —0 wd0 wd0 wd62 wd
A3250Fire Spraying & Intumecent Paint Inspection2025-04-02 → 2026-02-25— → —0 wd0 wd0 wd62 wd
A2540Compaction Inspection2025-04-02 → 2025-08-22— → —0 wd0 wd0 wd62 wd
A2150 IN-PROGRESS26 50 00 - Lighting Fixtures2025-07-14 → 2025-11-192025-08-19 → —1 wd0 wd0 wd26 wd
A2230Ontario Community College Auto Show2025-05-05 → 2025-06-092025-06-09 → 2025-06-091 wd0 wd0 wd24 wd
A2450Rebar for Pad Footings2025-07-09 → 2025-07-292025-07-23 → 2025-07-242 wd0 wd0 wd10 wd
A1180 IN-PROGRESSExterior Wall Cladding Shop Drawings2025-07-30 → 2025-08-132025-08-11 → —1 wd0 wd0 wd8 wd
A1210 IN-PROGRESSInterior Aluminum Screen2025-07-16 → 2025-07-292025-07-25 → —1 wd0 wd0 wd7 wd
A3940Existing Slab Removal and Trenching2025-06-17 → 2025-06-23— → —0 wd0 wd0 wd5 wd
A1170Air Barrier System Data Sheet and Mockup2025-06-24 → 2025-07-08— → —0 wd0 wd0 wd5 wd
A1700Cold-formed Metal Framing 2025-06-24 → 2025-07-08— → —0 wd0 wd0 wd5 wd
A1740TPO Roofing (Bridge)2025-06-24 → 2025-08-06— → —0 wd0 wd0 wd5 wd
A1690Structural Reinforcement2025-06-24 → 2025-09-18— → —0 wd0 wd0 wd5 wd
A2140 IN-PROGRESS26 27 26 - Wiring Devices, Service Poles, & Floor Boxes2025-07-02 → 2025-11-072025-07-09 → —1 wd0 wd0 wd5 wd
A2420 IN-PROGRESSForm and Pour North Exit Stair2025-07-30 → 2025-09-252025-08-04 → —1 wd0 wd0 wd3 wd
A2220Testing and Inspection Cash Allowance Expenditure2025-06-26 → 2025-06-26— → —0 wd0 wd0 wd1 wd
A2240Construction Site Setup. Fencing and Temp Facilities2025-06-10 → 2025-06-162025-06-10 → 2025-06-165 wd0 wd0 wd0 wd
A1000Tender Closing2025-04-01 → 2025-04-292025-04-01 → 2025-04-2920 wd0 wd0 wd0 wd
A1010Contract Award2025-05-02 → 2025-05-022025-05-02 → 2025-05-021 wd0 wd0 wd0 wd
A2270Excavation for Under Pinning2025-06-23 → 2025-06-232025-06-23 → 2025-06-231 wd0 wd0 wd0 wd
A2250Tree Removal, Protection and Equipment Mobilization2025-06-17 → 2025-06-172025-06-17 → 2025-06-171 wd0 wd0 wd0 wd
A2260Top Soil Stripping2025-06-18 → 2025-06-202025-06-18 → 2025-06-203 wd0 wd0 wd0 wd
A2300Setup Hoarding @ Vestibule F1002025-06-17 → 2025-06-182025-06-17 → 2025-06-182 wd0 wd0 wd0 wd
A2310Relocate FAA2025-06-17 → 2025-06-182025-06-16 → 2025-06-171 wd1 wd0 wd0 wd
A2320Demolition of Existing Vestibule F1002025-06-19 → 2025-06-252025-06-18 → 2025-06-255 wd1 wd0 wd0 wd
A2290Existing Structure Under Pinning2025-06-27 → 2025-07-182025-06-24 → 2025-07-1512 wd3 wd0 wd0 wd
A2330Gas Meter and Pipe Relocation Investigation2025-06-17 → 2025-06-192025-06-17 → 2025-06-193 wd0 wd0 wd0 wd
A2340Gas Meter and pipe Relocation2025-06-20 → 2025-06-232025-06-20 → 2025-06-232 wd0 wd0 wd0 wd
A2350Daylighting of Existing Hydro Ductbank & Services2025-06-23 → 2025-07-072025-06-23 → 2025-07-0710 wd0 wd0 wd0 wd
A2360Ductbank Shoring 2025-07-08 → 2025-07-212025-06-23 → 2025-07-081 wd10 wd0 wd0 wd
A1020Subcontract Award2025-05-05 → 2025-06-022025-05-05 → 2025-06-0220 wd0 wd0 wd0 wd
A3960Vinyl Flooring Abatement (Cash Allowance)2025-07-10 → 2025-07-162025-07-07 → 2025-07-112 wd3 wd0 wd0 wd
A1340Hydraulic Lift Shop Drawings2025-07-02 → 2025-07-152025-06-26 → 2025-07-096 wd3 wd0 wd0 wd
A1630Ductbank Underpinning 2025-06-17 → 2025-06-232025-05-28 → 2025-05-280 wd1 wd0 wd0 wd
A1640Foundation Concrete Rebar 2025-06-24 → 2025-07-082025-06-13 → 2025-06-130 wd1 wd0 wd0 wd
A3780Layout for Elevator Cylinder2025-06-23 → 2025-06-232025-06-23 → 2025-06-231 wd0 wd0 wd0 wd
A3790Drilling Elevator Cylinder from Grade2025-06-24 → 2025-06-242025-06-24 → 2025-06-241 wd0 wd0 wd0 wd
A3800Install Steel Casing into the ground2025-06-25 → 2025-06-252025-06-25 → 2025-06-251 wd0 wd0 wd0 wd
A136023 82 19 - Fan Coil Units (R0)2025-06-19 → 2025-07-032025-06-19 → 2025-07-0310 wd0 wd0 wd0 wd
A138023 21 23 - Pumps (R0)2025-06-24 → 2025-07-082025-06-24 → 2025-07-048 wd0 wd0 wd0 wd
A139023 25 00 - Buffer Tanks2025-06-24 → 2025-07-082025-06-24 → 2025-07-037 wd0 wd0 wd0 wd
A140023 21 16 - Air Separator2025-06-24 → 2025-07-082025-06-24 → 2025-07-037 wd0 wd0 wd0 wd
A141023 21 16 - Expansion Tanks2025-06-24 → 2025-07-082025-06-24 → 2025-07-037 wd0 wd0 wd0 wd
A142023 57 00 - Heat Exchangers2025-06-23 → 2025-07-072025-06-23 → 2025-07-038 wd0 wd0 wd0 wd
A143022 33 00 - Electric Domestic Water Heaters2025-06-19 → 2025-07-032025-06-19 → 2025-07-0310 wd0 wd0 wd0 wd
A144023 81 26 - Split System2025-06-12 → 2025-06-302025-06-12 → 2025-06-3013 wd0 wd0 wd0 wd
A145022 13 29 - Sump Pumps (R0)2025-06-09 → 2025-06-202025-05-27 → 2025-06-020 wd5 wd0 wd0 wd
A148023 00 00 - Exhaust Fans (R0)2025-07-22 → 2025-08-052025-07-22 → 2025-07-221 wd0 wd0 wd0 wd
A149023 00 00 - Unit Heater2025-07-22 → 2025-08-052025-07-22 → 2025-07-221 wd0 wd0 wd0 wd
A1520 IN-PROGRESS23 74 13 - Air Source Heat Pump2025-06-26 → 2025-07-102025-06-26 → —3 wd0 wd0 wd0 wd
A1980 IN-PROGRESS23 25 00 - Buffer Tanks2025-07-04 → 2025-12-242025-07-04 → —1 wd0 wd0 wd0 wd
A1990 IN-PROGRESS23 21 16 - Air Separator2025-07-04 → 2025-11-112025-07-04 → —1 wd0 wd0 wd0 wd
A2000 IN-PROGRESS23 21 16 - Expansion Tanks2025-07-04 → 2025-11-112025-07-04 → —1 wd0 wd0 wd0 wd
A2010 IN-PROGRESS23 57 00 - Heat Exchangers2025-07-04 → 2025-11-112025-07-04 → —1 wd0 wd0 wd0 wd
A2020 IN-PROGRESS22 33 00 - Electric Domestic Water Heaters2025-07-04 → 2025-11-112025-07-04 → —1 wd0 wd0 wd0 wd
A2030 IN-PROGRESS23 81 26 - Split System2025-07-10 → 2025-11-172025-07-10 → —1 wd0 wd0 wd0 wd
A2040 IN-PROGRESS22 13 29 - Sump Pumps2025-06-19 → 2025-08-082025-06-19 → —8 wd0 wd0 wd0 wd
A157027 10 00 - Structural Cabling System (Fiber Optic Cable)2025-07-11 → 2025-07-242025-07-11 → 2025-07-228 wd0 wd0 wd0 wd
A160028 31 00 - Fire Alarm Shop Drawings and Data Sheets2025-06-11 → 2025-06-242025-06-11 → 2025-06-175 wd0 wd0 wd0 wd
A2190 IN-PROGRESS28 31 00 - Fire Alarm2025-07-02 → 2025-11-072025-06-18 → —0 wd9 wd0 wd0 wd
A2160 IN-PROGRESS27 10 00 - Structural Cabling System (Fiber Optic Cable)2025-07-25 → 2026-04-302025-07-23 → —0 wd1 wd0 wd0 wd
A2370Bulk Excavation to U/S of Footings2025-07-21 → 2025-07-252025-07-16 → 2025-07-222 wd3 wd0 wd0 wd
A2380Bulk Excavation to U/S North Stair Footing2025-07-28 → 2025-07-282025-07-23 → 2025-07-230 wd1 wd0 wd0 wd
A2400Subgrade Preparation2025-07-28 → 2025-07-282025-07-23 → 2025-07-230 wd1 wd0 wd0 wd
A2410Soil Bearing Capacity Inspection2025-07-29 → 2025-07-292025-07-24 → 2025-07-240 wd1 wd0 wd0 wd
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)2025-07-28 → 2025-07-282025-07-23 → 2025-07-230 wd1 wd0 wd0 wd
A2460Rebar Inspection2025-07-30 → 2025-07-302025-07-25 → 2025-07-250 wd1 wd0 wd0 wd
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)2025-07-31 → 2025-07-312025-07-28 → 2025-07-280 wd1 wd0 wd0 wd
A2490Concrete Field Testing2025-07-31 → 2025-07-312025-07-28 → 2025-07-280 wd1 wd0 wd0 wd
117 classified activities — full list shown. Reference: Per-day execution-classification overlay on AACE RP 29R-03 §3.3 (Windows Analysis, MIP 3.3). A CPP-disclosed enhancement, NOT itself AACE-defined. Day counts are working days on each activity P6 calendar (weekends and holidays excluded), not calendar days.
A-07

Float Burndown Across Windows

per-activity total-float erosion timeline
Per-activity total-float erosion timeline for all 109 critical and near-critical activities (every activity at or below 5 working days total float in at least one of 2 snapshots, ordered by minimum TF). Forensic answer to which activities burned float to zero, when did they cross, and which ones recovered? Pure post-processing of analyst-supplied CPM snapshots. No additional schedule logic runs here.
Activities Tracked
critical + near-critical, all listed
Crossed TF=0
83
burned to zero float
Recovery Events
34
TF increase observed
Snapshots
Baseline / Current
Float Burndown — 109 activities / 2 windowsTF=0Total Float (wd)BaselineCurrentLegend — 83 of 109 activities crossed TF=0A1000 [above-float]A1010 [crossed-zero]A1020 [crossed-zero]A1060 [crossed-zero]A1110 [above-float]A1110.1 [crossed-zero]A1640 [crossed-zero]A1690 [crossed-zero]A2220 [crossed-zero]A2230 [above-float]A2240 [above-float]A2250 [above-float]A2260 [above-float]A2290 [crossed-zero]A2300 [above-float]A2310 [above-float]A2320 [above-float]A2350 [above-float]A2360 [above-float]A2370 [crossed-zero]A2390 [crossed-zero]A2400 [crossed-zero]A2430 [crossed-zero]A2440 [above-float]A2450 [crossed-zero]A2460 [crossed-zero]A2470 [crossed-zero]A2480 [above-float]A2490 [crossed-zero]A2500 [crossed-zero]A2520 [crossed-zero]A2530 [crossed-zero]A2540 [crossed-zero]A2550 [crossed-zero]A2560 [above-float]A2570 [crossed-zero]A2580 [above-float]A2590 [crossed-zero]A2610 [crossed-zero]A2620 [crossed-zero]A2650 [crossed-zero]A2660 [crossed-zero]A2670 [crossed-zero]A2680 [crossed-zero]A2690 [crossed-zero]A2700 [crossed-zero]A2710 [crossed-zero]A2740 [above-float]A2750 [crossed-zero]A2880 [crossed-zero]A2970 [crossed-zero]A3060 [crossed-zero]A3070 [above-float]A3210 [crossed-zero]A3220 [crossed-zero]A3240 [crossed-zero]A3250 [crossed-zero]A3260 [crossed-zero]A3280 [above-float]A3290 [crossed-zero]A3440 [above-float]A3450 [crossed-zero]A3570 [above-float]A3580 [crossed-zero]A3590 [crossed-zero]A3610 [crossed-zero]A3620 [above-float]A3630 [crossed-zero]A3640 [crossed-zero]A3650 [crossed-zero]A3660 [above-float]A3670 [crossed-zero]A3710 [crossed-zero]A3720 [above-float]A3750 [crossed-zero]A3760 [crossed-zero]A3980 [above-float]A4030 [crossed-zero]A4040 [crossed-zero]A4040x [crossed-zero]A4050 [crossed-zero]A4060 [crossed-zero]A4070 [crossed-zero]A4080 [crossed-zero]A4090 [crossed-zero]A4100 [crossed-zero]A4110 [crossed-zero]A4120 [crossed-zero]A4170 [above-float]A4180 [crossed-zero]A4190 [crossed-zero]A4200 [crossed-zero]A4210 [crossed-zero]A4220 [above-float]A4240 [crossed-zero]A4250 [crossed-zero]A4260 [crossed-zero]A4400 [crossed-zero]A4420 [crossed-zero]A4430 [crossed-zero]A4450 [crossed-zero]A4460 [crossed-zero]A4470 [crossed-zero]A4480 [crossed-zero]A4490 [crossed-zero]A4500 [crossed-zero]A4520 [crossed-zero]A4590 [crossed-zero]A4820 [crossed-zero]CPP compute_float_burndown v2.9.38 — Post-processing of analyst-supplied CPM snapshots. Forensic use: analyst-verified only.
A-07Float burndown register — 109 activities (full list)
109 activities tracked — all listedExport CSV
ActivityMin TFMax TFFirst TF≤0 WindowRecovery (Δd / count)Slip Velocity
A1000+2.0 wd+2.0 wd· +0.00 wd/win
A1010+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A1020+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A1060+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A1110+5.0 wd+5.0 wd· +0.00 wd/win
A1110.1+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A1640+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A1690+0.0 wd+5.0 wdCurrent▼ -5.00 wd/win
A2220+0.0 wd+89.0 wdBaseline+89.0 wd (1)▲ +89.00 wd/win
A2230+3.0 wd+3.0 wd· +0.00 wd/win
A2240+3.0 wd+3.0 wd· +0.00 wd/win
A2250+4.0 wd+4.0 wd· +0.00 wd/win
A2260+4.0 wd+4.0 wd· +0.00 wd/win
A2290+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2300+3.0 wd+3.0 wd· +0.00 wd/win
A2310+3.0 wd+3.0 wd· +0.00 wd/win
A2320+3.0 wd+3.0 wd· +0.00 wd/win
A2350+4.0 wd+4.0 wd· +0.00 wd/win
A2360+4.0 wd+4.0 wd· +0.00 wd/win
A2370+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2390+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2400+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2430+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2440+5.0 wd+43.0 wd+38.0 wd (1)▲ +38.00 wd/win
A2450+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2460+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2470+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2480+5.0 wd+316.0 wd+311.0 wd (1)▲ +311.00 wd/win
A2490+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2500+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2520+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2530+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2540+0.0 wd+43.0 wdBaseline+43.0 wd (1)▲ +43.00 wd/win
A2550+0.0 wd+43.0 wdBaseline+43.0 wd (1)▲ +43.00 wd/win
A2560+3.0 wd+71.0 wd+68.0 wd (1)▲ +68.00 wd/win
A2570+0.0 wd+68.0 wdBaseline+68.0 wd (1)▲ +68.00 wd/win
A2580+4.0 wd+39.0 wd+35.0 wd (1)▲ +35.00 wd/win
A2590+0.0 wd+39.0 wdBaseline+39.0 wd (1)▲ +39.00 wd/win
A2610+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2620+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2650+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2660+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2670+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2680+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2690+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2700+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2710+0.0 wd+35.0 wdBaseline+35.0 wd (1)▲ +35.00 wd/win
A2740+4.0 wd+4.0 wd· +0.00 wd/win
A2750+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2880+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A2970+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A3060+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A3070+1.0 wd+5.0 wd▼ -4.00 wd/win
A3210+0.0 wd+6.0 wdBaseline+6.0 wd (1)▲ +6.00 wd/win
A3220+0.0 wd+6.0 wdBaseline+6.0 wd (1)▲ +6.00 wd/win
A3240+0.0 wd+5.0 wdCurrent▼ -5.00 wd/win
A3250+0.0 wd+5.0 wdCurrent▼ -5.00 wd/win
A3260+0.0 wd+5.0 wdCurrent▼ -5.00 wd/win
A3280+1.0 wd+5.0 wd▼ -4.00 wd/win
A3290+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3440+3.0 wd+7.0 wd▼ -4.00 wd/win
A3450+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3570+3.0 wd+7.0 wd▼ -4.00 wd/win
A3580+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3590+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3610+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3620+3.0 wd+7.0 wd▼ -4.00 wd/win
A3630+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3640+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3650+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3660+5.0 wd+6.0 wd+1.0 wd (1)▲ +1.00 wd/win
A3670+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3710+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3720+5.0 wd+6.0 wd+1.0 wd (1)▲ +1.00 wd/win
A3750+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3760+0.0 wd+1.0 wdBaseline+1.0 wd (1)▲ +1.00 wd/win
A3980+5.0 wd+5.0 wd· +0.00 wd/win
A4030+0.0 wd+117.0 wdCurrent▼ -117.00 wd/win
A4040+0.0 wd+12.0 wdCurrent▼ -12.00 wd/win
A4040x+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4050+0.0 wd+182.0 wdCurrent▼ -182.00 wd/win
A4060+0.0 wd+126.0 wdCurrent▼ -126.00 wd/win
A4070+0.0 wd+131.0 wdCurrent▼ -131.00 wd/win
A4080+0.0 wd+12.0 wdCurrent▼ -12.00 wd/win
A4090+0.0 wd+12.0 wdCurrent▼ -12.00 wd/win
A4100+0.0 wd+12.0 wdCurrent▼ -12.00 wd/win
A4110+0.0 wd+12.0 wdCurrent▼ -12.00 wd/win
A4120+0.0 wd+12.0 wdCurrent▼ -12.00 wd/win
A4170+5.0 wd+16.0 wd▼ -11.00 wd/win
A4180+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A4190+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A4200+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A4210+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A4220+5.0 wd+5.0 wd· +0.00 wd/win
A4240+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A4250+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A4260+0.0 wd+0.0 wdBaseline· +0.00 wd/win
A4400+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4420+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4430+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4450+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4460+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4470+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4480+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4490+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4500+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4520+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4590+0.0 wd+0.0 wdCurrent· +0.00 wd/win
A4820+0.0 wd+0.0 wdCurrent· +0.00 wd/win
Caveat (cite in any expert report): Float burndown is post-processing of analyst-supplied CPM snapshots. Accuracy depends on the quality of the underlying schedule updates. Recovery events (TF increase) may reflect legitimate scope removal, schedule optimization, or activity deletion — analyst must verify. Slip velocity is a linear average; actual burndown may be non-linear. CPP first-mover at per-activity float-timeline granularity (2026-05-09); methodology not yet formally published in AACE/SCL literature.
Method: compute_float_burndown (engine v2.9.38). The complete critical and near-critical set is listed (no top-N truncation), ordered by minimum TF observed across the snapshot series; near-critical activities (TF ≤ 5 wd in any window) are included.
A-08

Cumulative Activity Slip Register

sum of signed slip across all windows
A-08Most-slipped first — full list (261 activities)
261 rows — all listedExport CSV
Sum of signed slip across all windows per activity. Most-slipped first.
CodeActivityTotal SlipWindows Touched
A4070 CPFrames installation+180 wd1
A4060 CPBlocking+170 wd1
A4050 CPSprinkler Rough-ins+165 wd1
A4030 CPNew Partition Framing+145 wd1
A3850Foundations+127 wd1
A3860Concrete Vertical Piers+127 wd1
A3870Removal of Existing Facade for Tie In+127 wd1
A3880Structural Steel erection including expansion plates +95 wd1
A3890Envelope +95 wd1
A3900Interior M&E Rough in +85 wd1
A195023 82 19 - Fan Coil Units+69 wd1
A3910Interior Finishes+66 wd1
A2730Stairs B Installation @ North Side+60 wd1
A1710Misc. Metals +60 wd1
A2720Tactile Attention Indicators Mock-up+60 wd1
A3270New Stair A Installation+59 wd1
A2540Compaction Inspection+58 wd1
A209023 52 16 - Heating Boilers+55 wd1
A3940Existing Slab Removal and Trenching+54 wd1
A205023 25 00 - Water Treatment+54 wd1
A218026 09 23 - Lighting Control+53 wd1
A1130Misc. Metals Shop Drawings+51 wd1
A150023 52 16 - Heating Boilers+46 wd1
A206023 37 13 - Diffuser and Grilles+46 wd1
A1160TPO Roofing Shop Drawings+45 wd1
A1680Structural Steel +45 wd1
A1740TPO Roofing (Bridge)+44 wd1
A2580Underground Drainage+43 wd1
A2510Supply of Embedment & Ankors+42 wd1
A4040 CPMEP Rough-ins+41 wd1
A197023 21 23 - Pumps+39 wd1
A2590Backfilling to U/S of SOG+39 wd1
A2750 CPL1, L2 & L3 Framing and Sheathing Installation+38 wd1
A2880 CPL1, L2 & L3 Framing and Sheathing Installation+38 wd1
A2790L1, L2 & L3 Air Vapour Barrier Installation+38 wd1
A2820Glazing Site Measure and Scanning+38 wd1
A2740Cold-Formed Metal Framing Mock+38 wd1
A2780Above Grade Vapour Mock-up+38 wd1
A2800AVB Inspection+38 wd1
A3930Interior Demoilition+38 wd1
A196023 74 13 - Air Handling Units+35 wd1
A212020 05 10 - Electric Heat Tracing+34 wd1
A159026 09 23 - Lighting Control (R0)+34 wd1
A4080 CPDrywall/Sheathing Installation+33 wd1
A4090 CPTaping and mudding+33 wd1
A4110 CPTile and Rubber Flooring Installation+33 wd1
A4100 CPPainting+33 wd1
A4120 CPFinal Terminations and Fixtures Installation+33 wd1
A213022 40 00 - Plumbing Fixtures+33 wd1
A4170Fire Alarm Verification+32 wd1
A3170Install Built-up Roof+30 wd1
A3180Roof Inspection+30 wd1
A3110L1, L2 & L3 Exterior Glazing Installation (W09a, W09b)+29 wd1
A2930L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)+29 wd1
A2840L1, L2, L3 Exterior Glazing Installation (W05)+29 wd1
A3010L2 & L3 Exterior Glazing Installation (W08a, W08b)+29 wd1
A3260 CPSeal Concrete Floor+29 wd1
A3430Seal concrete Floor+29 wd1
A3280New partition framing+29 wd1
A3330Door frames Installation+29 wd1
A3440New partition framing+29 wd1
A3560Seal concrete Floor+29 wd1
A3420Fire Spraying & Intumecent Paint+29 wd1
A3550Fire Spraying & Intumecent Paint+29 wd1
A3210Electrical and Mechanical Room +29 wd1
A3220Mech. and Elec. Equipment Installation+29 wd1
A2850Exterior Cladding Site Measure and Scanning+29 wd1
A2940Exterior Cladding Site Measure and Scanning+29 wd1
A3020Exterior Cladding Site Measure and Scanning+29 wd1
A3100Glazing Shop Fabrication+29 wd1
A3120Exterior Cladding Site Measure and Scanning+29 wd1
A3680Misc. Metals Mock-up+29 wd1
A2810Aluminum & Metal Panel Cladding Mock-up+29 wd1
A3080L1, L2 & L3 Air Vapor Barrier Inspection+29 wd1
A3250 CPFire Spraying & Intumecent Paint Inspection+29 wd1
A2960L2 & L3 Cladding Installation (EW2)+28 wd1
A2870L1, L2 & L3 Cladding Installation (EW2a)+28 wd1
A3040L2 & L3 Cladding Installation (EW2)+28 wd1
A3050Horizontal Shading Louvers+28 wd1
A2900Air Vapor Barrier Installation+28 wd1
A3140L1, L2 & L3 Cladding Installation (EW2, EW2A)+28 wd1
A3070L1, L2 & L3 Air Vapor Barrier Installation+28 wd1
A3490Door frames Installation+28 wd1
A3520Door and Hardware Installation+28 wd1
A3620Door frames Installation+28 wd1
A3570New wall partition framing+28 wd1
A3240 CPFire Spraying & Intumecent Paint+28 wd1
A1110Structural Reinforcement + Decking Shop Drawings+28 wd1
A3690Misc. Metals installation+28 wd1
A2860Exterior Cladding Shop Fabrication+28 wd1
A2910Glazing Site Measure and Scanning+28 wd1
A2950Exterior Cladding Shop Fabrication+28 wd1
A3000Glazing Shop Fabrication+28 wd1
A3030Exterior Cladding Shop Fabrication+28 wd1
A3130Exterior Cladding Shop Fabrication+28 wd1
A2440Formwork Remaining Pad Footing (Ramp)+28 wd1
A2970 CPL2 & L3 Framing and Sheathing Installation+27 wd1
A3060 CPL1, L2 & L3 Framing and Sheathing Installation+27 wd1
A2980L2 & L3 Air Vapor Barrier Installation+27 wd1
A2830Glazing Shop Fabrication+27 wd1
A2920Glazing Shop Fabrication+27 wd1
A2990Glazing Site Measure and Scanning+27 wd1
A3090Glazing Site Measure and Scanning+27 wd1
A3230Fire Spraying & Intumecent Paint Mock-up+27 wd1
A3410Painting+26 wd1
A3300Electrical, FA & Comms rough-ins+26 wd1
A3320Blocking Installation+26 wd1
A3350Gypsum board Installation+26 wd1
A3360Drywall Taping and Mudding+26 wd1
A3390Interior Aluminum/Glazing Screens Installation+26 wd1
A3370Door and Hardware Installation+26 wd1
A1290Suspended Metal Soffits+26 wd1
A1820Coiling Doors+26 wd1
A3810Install Controller at Machine Room+26 wd1
A3820Rails and Elevator Car installation+26 wd1
A3830Power to controller, Phone lines and Comms+26 wd1
A3840Elevator Testing and Commissioning+26 wd1
A3380Interior Aluminum/Glazing Screens Mock-up+26 wd1
A3340ACT Baffles Mock-ups+26 wd1
A3400Paint Mock-up+26 wd1
A158026 50 00 - Lighting Fixtures+26 wd1
A1870ACT & ACB +25 wd1
A215026 50 00 - Lighting Fixtures+25 wd1
A3290Mech. & Plumbing rough-ins+24 wd1
A3480Blocking Installation+24 wd1
A3610Blocking Installation+24 wd1
A3310Sprinkler Rough-ins+24 wd1
A3540Painting+23 wd1
A3450Mech. & Plumbing rough-ins+23 wd1
A3500Gypsum board Installation+23 wd1
A3460Electrical, FA & Comms rough-ins+23 wd1
A3510Drywall Taping and Mudding+23 wd1
A3530Interior Glazing Installation+23 wd1
A3590Electrical, FA & Comms rough-ins+23 wd1
A3580Mech. & Plumbing rough-ins+23 wd1
A3470Sprinkler Rough-ins+23 wd1
A3600Sprinkler Rough-ins+23 wd1
A1690 CPStructural Reinforcement+23 wd1
A146023 25 00 - Water Treatment (R0)+23 wd1
A4240 CPMinor Deficiencies & Touch-ups+22 wd1
A1700Cold-formed Metal Framing +22 wd1
A4260 CPTotal Completion +21 wd1
A4220Final Cleaning +21 wd1
A1120Cold-formed Metal Framing Shop Drawings+21 wd1
A1220Flush Wood Doors Sample+21 wd1
A1280ACT Data sheet and Sample+21 wd1
A1330Fall Arrest Anchors and Horizontal Lines+21 wd1
A4180 CPMechanical, Electrical and Elevator Commissioning+21 wd1
A4190 CPIntegrated Testing+21 wd1
A4250 CPReady-To-Take Over+21 wd1
A4230Close-out Documents & Training+21 wd1
A3750Washroom Partitions and Accessories Installation+20 wd1
A2640Install Roof Decking+20 wd1
A2630Install Roof Anchors +20 wd1
A3720Ceiling/Wall Fixtures Installation+20 wd1
A3740Millwork Installation+20 wd1
A3710Tiling and rubber flooring Installation+20 wd1
A3670Painting+20 wd1
A3770Corner Guards and Wall Protection Installation+20 wd1
A3660Interior Glazing Installation+20 wd1
A3650Door and Hardware Installation+20 wd1
A3630Gypsum board Installation+20 wd1
A3640Drywall Taping and Mudding+20 wd1
A1810Flush Wood Doors +20 wd1
A1920Fall Arrest Anchors and Horizontal Lines+20 wd1
A4210 CPOccupancy+20 wd1
A3150Roof Parapet Framing+20 wd1
A3160Roof Penetration Layout+20 wd1
A3760Plumbing Washroom Fixtures Installation+20 wd1
A3730Millwork Mock-up+20 wd1
A3700Tiling & Rubber & Carpet Flooring Mock-up+20 wd1
A2500Install Rebar for Piers+20 wd1
A4200 CPSubstaintial Performance+19 wd1
A1230Coiling Doors+17 wd1
A4150New Exterior Paved Areas and Sidewalks +15 wd1
A4160Landscape Installations+15 wd1
A153020 05 10 - Electric Heat Tracing (R0)+15 wd1
A2520Form and Pour Foundation Piers+15 wd1
A1090Masonry and Mortar Samples & Data Sheets+14 wd1
A1100Structural Steel Framing and Steel Deck Shop Drawings (R0)+14 wd1
A2530Backfilling to U/S of Grade Beams+14 wd1
A1670Masonry and Mortar+13 wd1
A2280Under Pinning Inspection+13 wd1
A147023 37 13 - Diffuser and Grilles Shop Drawings (R0)+13 wd1
A3920Setup Temporary Hoarding+12 wd1
A156026 50 00 - Emergency Lighting & Exit Signs+12 wd1
A1060Foundation Concrete Rebar Shop Drawing+10 wd1
A1050Ductbank Underpinning Drawing+10 wd1
A2550Form and Pour Grade Beams+10 wd1
A2560Below Grade Vapour Barrier Mock-up+10 wd1
A2570Footing Vapor Barrier & Insulation+10 wd1
A2610Erect Structural Steel+9 wd1
A2650Install Level 2 & 3 Decking+9 wd1
A2660Install Temporary Hoarding for Slab on Deck+9 wd1
A2620Structural Steel Inspection+9 wd1
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes+9 wd1
A1210Interior Aluminum Screen+8 wd1
A1180Exterior Wall Cladding Shop Drawings+7 wd1
A1760Exterior Wall Cladding+7 wd1
A1800Interior Aluminum Screens+7 wd1
A137023 74 13 - Air Handling Units (R0)+7 wd1
A2670Rebar and Prep Work for Slab on Deck+6 wd1
A1080Bentonite Waterstop Data Sheet+6 wd1
A1660Bentonite Waterstop +6 wd1
A2680Concrete pour for slab on deck level 2 & 3+5 wd1
A2690Final Grading and Vapor Barrier for SOG+5 wd1
A151023 00 00 - Wall Fin Heater+5 wd1
A152023 74 13 - Air Source Heat Pump+5 wd1
A154022 40 00 - Plumbing Fixtures (R0)+5 wd1
A207023 00 00 - Exhaust Fans+5 wd1
A208023 00 00 - Unit Heater+5 wd1
A210023 00 00 - Wall Fin Heater+5 wd1
A214026 27 26 - Wiring Devices, Service Poles, & Floor Boxes+5 wd1
A2710Concrete Pour and Curing for SOG+3 wd1
A2700Rebar Installation for SOG+3 wd1
A2220Testing and Inspection Cash Allowance Expenditure+3 wd1
A2420Form and Pour North Exit Stair+3 wd1
A1070Foundation Concrete Mix Design+2 wd1
A1650Foundation Concrete Mix Design+2 wd1
A1040Permit (Not Required Per Ontario Community College)+1 wd1
A1030IFC Drawings Released+1 wd1
A1150Built-up Roofing Shop Drawings+1 wd1
A1190Fire-resistive Material Data Sheet+1 wd1
A1730Built-up Roofing +1 wd1
A1770Fire-resistive Material +1 wd1
A2310Relocate FAA-1 wd1
A138023 21 23 - Pumps (R0)-2 wd1
A142023 57 00 - Heat Exchangers-2 wd1
A157027 10 00 - Structural Cabling System (Fiber Optic Cable)-2 wd1
A2290Existing Structure Under Pinning-3 wd1
A3960Vinyl Flooring Abatement (Cash Allowance)-3 wd1
A3190Hoisting Roof Equipment-3 wd1
A3200Roof Anchor System Installation-3 wd1
A139023 25 00 - Buffer Tanks-3 wd1
A140023 21 16 - Air Separator-3 wd1
A141023 21 16 - Expansion Tanks-3 wd1
A211023 74 13 - Air Source Heat Pump-3 wd1
A2370Bulk Excavation to U/S of Footings-3 wd1
A2380Bulk Excavation to U/S North Stair Footing-3 wd1
A2390Subgrade Inspection-3 wd1
A2400Subgrade Preparation-3 wd1
A2410Soil Bearing Capacity Inspection-3 wd1
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)-3 wd1
A2450Rebar for Pad Footings-3 wd1
A2460Rebar Inspection-3 wd1
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)-3 wd1
A2490Concrete Field Testing-3 wd1
A1340Hydraulic Lift Shop Drawings-4 wd1
A1930Hydraulic Lift -4 wd1
A160028 31 00 - Fire Alarm Shop Drawings and Data Sheets-5 wd1
A4010Underground Plumbing Rough-ins-6 wd1
A2360Ductbank Shoring -9 wd1
A219028 31 00 - Fire Alarm-9 wd1
A148023 00 00 - Exhaust Fans (R0)-10 wd1
A149023 00 00 - Unit Heater-10 wd1
A216027 10 00 - Structural Cabling System (Fiber Optic Cable)-12 wd1
A145022 13 29 - Sump Pumps (R0)-14 wd1
A1640Foundation Concrete Rebar -16 wd1
A1630Ductbank Underpinning -18 wd1
A2480Concrete for Remaining Pad Footings (Ramp)-22 wd1
A2600Compaction Inspection-24 wd1
261 rows — full list shown.
A-09

Window 1 — Baseline → Current

01-Apr-2025 → 01-Jul-2025 · shift +21 wd
Window Shift (wd)+21 wd · CRITICALPeriod01-Apr-2025 → 01-Jul-2025
Newly Critical
activities added to CP
No Longer Critical
activities left CP
Slipped Activities
264
finish dates later
CP Duration Growth
CP activities grew
Completion-shift basis
The window shift is measured on the finish driver shown below. Scheduled finish (scd_end_date) is cross-checked but never used as the shift basis.
Shift basis
Latest activity finish
Finish activity
A4240
Date field used
target_end_date
Window shift (working days)
21 wd
Cumulative vs baseline (working days)
21 wd
Scheduled finish (prior)
31-Aug-2026
Scheduled finish (later)
30-Sep-2026
Basis vs project finish
Consistent
Critical-path duration growth (full list)
Direct delay — every day of duration growth on a CP activity is a day of project slip.
CodeActivityPrior DurationLater DurationGrowth
A4240Minor Deficiencies & Touch-ups10.0 wd11.0 wd+1.0 wd
A4040MEP Rough-ins19.0 wd20.0 wd+1.0 wd
A3240Fire Spraying & Intumecent Paint5.0 wd6.0 wd+1.0 wd
A4200Substaintial Performance1.0 wd0.0 wd+-1.0 wd
A4260Total Completion 1.0 wd0.0 wd+-1.0 wd
A4210Occupancy1.0 wd0.0 wd+-1.0 wd
A4250Ready-To-Take Over1.0 wd0.0 wd+-1.0 wd
A4060Blocking10.0 wd5.0 wd+-5.0 wd
A2970L2 & L3 Framing and Sheathing Installation25.0 wd14.0 wd+-11.0 wd
A4080Drywall/Sheathing Installation38.0 wd10.0 wd+-28.0 wd
A1690Structural Reinforcement61.0 wd30.0 wd+-31.0 wd
A3250Fire Spraying & Intumecent Paint Inspection228.0 wd1.0 wd+-227.0 wd
Newly Critical (28)
A1110.1Structural Reinforcement + Decking Shop Drawings (R1)
A1690Structural Reinforcement
A3240Fire Spraying & Intumecent Paint
A3250Fire Spraying & Intumecent Paint Inspection
A3260Seal Concrete Floor
A4030New Partition Framing
A4040MEP Rough-ins
A4040xMEP Rough-ins + Sprinkler
A4050Sprinkler Rough-ins
A4060Blocking
A4070Frames installation
A4080Drywall/Sheathing Installation
A4090Taping and mudding
A4100Painting
A4110Tile and Rubber Flooring Installation
A4120Final Terminations and Fixtures Installation
A4400Existing Columns Reinforcement
A4420Steel Joist Reinforcement Installation
A4430Stud Framing
A4450Plywood Blocking
A4460Drywall Installation
A4470Taping Drywall
A4480Paint
A4490Finishes
A4500CNC Machine Relocation (Cash Allowance)
A4520Setup Temporary Hoarding
A4590Steel Joist Reinforcement Installation
A4820Concrete Floor Sealer
No Longer Critical (44)
A1010Contract Award
A1020Subcontract Award
A1060Foundation Concrete Rebar Shop Drawing
A1640Foundation Concrete Rebar
A2220Testing and Inspection Cash Allowance Expenditure
A2290Existing Structure Under Pinning
A2370Bulk Excavation to U/S of Footings
A2390Subgrade Inspection
A2400Subgrade Preparation
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)
A2450Rebar for Pad Footings
A2460Rebar Inspection
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)
A2490Concrete Field Testing
A2500Install Rebar for Piers
A2520Form and Pour Foundation Piers
A2530Backfilling to U/S of Grade Beams
A2540Compaction Inspection
A2550Form and Pour Grade Beams
A2570Footing Vapor Barrier & Insulation
A2590Backfilling to U/S of SOG
A2610Erect Structural Steel
A2620Structural Steel Inspection
A2650Install Level 2 & 3 Decking
A2660Install Temporary Hoarding for Slab on Deck
A2670Rebar and Prep Work for Slab on Deck
A2680Concrete pour for slab on deck level 2 & 3
A2690Final Grading and Vapor Barrier for SOG
A2700Rebar Installation for SOG
A2710Concrete Pour and Curing for SOG
A3210Electrical and Mechanical Room
A3220Mech. and Elec. Equipment Installation
A3290Mech. & Plumbing rough-ins
A3450Mech. & Plumbing rough-ins
A3580Mech. & Plumbing rough-ins
A3590Electrical, FA & Comms rough-ins
A3610Blocking Installation
A3630Gypsum board Installation
A3640Drywall Taping and Mudding
A3650Door and Hardware Installation
A3670Painting
A3710Tiling and rubber flooring Installation
A3750Washroom Partitions and Accessories Installation
A3760Plumbing Washroom Fixtures Installation
Logic changes
Added
Removed
Type Changed
Lag Changed
Activity set changes
Added (87)
217026 50 00 - Emergency Lighting & Exit Signs
A1100.1Structural Steel Framing and Steel Deck Shop Drawings (R1)
A1100.2Structural Steel Framing and Steel Deck Shop Drawings (R2)
A1110.1Structural Reinforcement + Decking Shop Drawings (R1)
A12380.123 21 23 - Pumps (R1)
A1280.1ACB Data sheet and Sample
A1360.123 82 19 - Fan Coil Units (R1)
A1360.223 82 19 - Fan Coil Units (R2)
A1370,123 74 13 - Air Handling Units (R1)
A1370xMetal Shelving
A1380xMetal Shelving (R1)
A1450.122 13 29 - Sump Pumps (R1)
A1460.123 25 00 - Water Treatment (R1)
A1470.123 37 13 - Diffuser and Grilles Shop Drawings (R1)
A1480.123 00 00 - Exhaust Fans (R1)
A1530.120 05 10 - Electric Heat Tracing (R1)
A1540.122 40 00 - Plumbing Fixtures (R1)
A1590.126 09 23 - Lighting Control (R1)
A2090xMetal Shelving
A2410xRFI #17 Demo Clarification
A2420xPC-002 Demo Clarification Issuance
A2430xPCO-008 (Quote) Submission
A2440xCO-005 Issuance
A2450xCD-01 Water Room Demo (Elec. FACP) Issuance
A2460xCD-01 Fire Alarm Panel Relocation
A2470xWater Room Block Wall Demo
A2480xExisting Vestibule Slab Cutting
A2490xExisting Vestibule Slab Removal
A2500xR1 - RFI #19 & 20 – Existing DCW and Sanitary Line
A2510xR2 - RFI 06 - SI-002 Existing Gas Piping and Meter Relocation
A2520xR3 - RFI 45 - City of Barrie Water Department – Request to Review Drawings
A2530.1Backfilling to U/S of Grade Beams (GL AA)
A2530xR4 - PC-004 Grade Beam Rebar
A2540xR5 - RFI #39R2 Jewelery Workshop Interior Fitout
A2550xR6 - RFI 60 Sprinkler Diesel Pump
A2560xR7 - SP 3 & 4 - 3rd Floor Fan Coil Units Scope
A4040xMEP Rough-ins + Sprinkler
A4310Mobilize Temporary Student Washrooms
A4340Electrical and Mechanical Make Safe
A4370Underground Mechanical Installation (DCW, Sprinkler)
A4380Backfilling and Concrete for SOG
A4390Review Interferences with Steel Joist
A4400Existing Columns Reinforcement
A4410Joist Interferences Relocation
A4420Steel Joist Reinforcement Installation
A4430Stud Framing
A4450Plywood Blocking
A4460Drywall Installation
A4470Taping Drywall
A4480Paint
A4490Finishes
A4500CNC Machine Relocation (Cash Allowance)
A4510Metal Shelving Installation
A4520Setup Temporary Hoarding
A4530Electrical and Mechanical Make Safe
A4540Interior Demoilition
A4550Existing Exterior Wall Demo (New Building Must be Erected and Enclosed)
A4560Review Interferences with Steel Joist
A4570Joist Interferences Relocation
A4580New Columns Installation
A4590Steel Joist Reinforcement Installation
A4600Stud Framing
A4610MEP Rough-ins
A4620Plywood Blocking
A4630Drywall Installation
A4640Taping Drywall
A4650Painting
A4660Setup Temporary Hoarding
A4670Electrical and Mechanical Make Safe
A4680Interior Demoilition
A4690Electrical Fixtures
A4700Review Interferences with Steel Joist
A4710Relocation of Interferences
A4720Existing Column Reinforcement
A4730Steel Joist Reinforcement Installation
A4740Concrete Scanning & Cutting
A4760Trench Backfill
A4770Concrete Slab Infill
A4780New Columns Installation
A4790Existing Column Reinforcement
A4800Flatness Survey @ Floor Slab
A4810Self Levelling
A4820Concrete Floor Sealer
A5070Removal of Existing Water and Sanitary
A5220Weather Impact (Rain) - August 28, 2025
A5230Footings and Piers Along GL-B.1 (Successor to CO-005)
A5250Weather Impact (Rain) - September 04, 2025
Removed (10)
A1880Suspended Metal Soffits
A217026 50 00 - Lighting Fixtures & Controls
A3950Relocation of Interferences with Structural Reinforcement (Cash Allowance)
A3970Existing Roof Demolition
A3980Structural Joist and Column Reinforcement
A3990Fire Spraying
A4000New Roof Installation
A4020Concrete Patching and infills
A4130Equipment Relocation to final location
A4140Removal & Disposal of Existing HRAC Equipment
A-09Slip register — 264 activities (full list)
264 activities — all listedExport CSV
Attribution basis complete: every root-cause slip carries a responsible party. Cascade recipients of the same events are listed without independent attribution.
CodeActivityPrior FinishLater FinishSlipResponsible PartyCause Notes
A4070 CPFrames installation02-Oct-202519-Jun-2026+180 wdContractorFrame installation at the end of the delayed interior chain
A4060 CPBlocking09-Oct-202512-Jun-2026+170 wdContractorBlocking follows sprinkler rough-in in the interior chain
A4050 CPSprinkler Rough-ins09-Oct-202505-Jun-2026+165 wdContractorSprinkler rough-in follows partition framing; trade stacking on remobilization
A4030 CPNew Partition Framing25-Sep-202523-Apr-2026+145 wdContractorFraming crew availability following remobilization
A3850Foundations22-Aug-202524-Feb-2026+127 wdOwnerDiffering site condition at the existing facade tie-in
A3860Concrete Vertical Piers29-Aug-202504-Mar-2026+127 wdOwnerFollows delayed foundations at the tie-in
A3870Removal of Existing Facade for Tie In03-Sep-202506-Mar-2026+127 wdOwnerExisting facade removal held for tie-in condition resolution
A3880Structural Steel erection including expansion plates 10-Nov-202527-Mar-2026+95 wd
A3890Envelope 15-Dec-202501-May-2026+95 wd
A3900Interior M&E Rough in 14-Jan-202615-May-2026+85 wd
A195023 82 19 - Fan Coil Units25-Nov-202506-Mar-2026+69 wd
A3910Interior Finishes11-Feb-202619-May-2026+66 wd
A2730Stairs B Installation @ North Side21-Nov-202518-Feb-2026+60 wd
A1710Misc. Metals 31-Oct-202527-Jan-2026+60 wd
A2720Tactile Attention Indicators Mock-up03-Nov-202528-Jan-2026+60 wd
A3270New Stair A Installation17-Nov-202510-Feb-2026+59 wd
A2540Compaction Inspection22-Aug-202514-Nov-2025+58 wd
A209023 52 16 - Heating Boilers28-Nov-202518-Feb-2026+55 wd
A3940Existing Slab Removal and Trenching23-Jun-202509-Sep-2025+54 wdContractorResequenced slab removal and trenching
A205023 25 00 - Water Treatment11-Nov-202528-Jan-2026+54 wd
A218026 09 23 - Lighting Control07-Nov-202523-Jan-2026+53 wd
A1130Misc. Metals Shop Drawings22-Jul-202502-Oct-2025+51 wdContractorLate misc. metals submittal
A150023 52 16 - Heating Boilers22-Jul-202525-Sep-2025+46 wd
A206023 37 13 - Diffuser and Grilles04-Dec-202510-Feb-2026+46 wd
A1160TPO Roofing Shop Drawings23-Jun-202526-Aug-2025+45 wdOwnerOwner-directed revision to the roofing assembly; resubmittal and re-review cycle
A1680Structural Steel 29-Jul-202501-Oct-2025+45 wd
A1740TPO Roofing (Bridge)06-Aug-202508-Oct-2025+44 wd
A2580Underground Drainage08-Sep-202507-Nov-2025+43 wd
A2510Supply of Embedment & Ankors24-Jun-202522-Aug-2025+42 wd
A4040 CPMEP Rough-ins25-Mar-202622-May-2026+41 wdContractorMEP rough-in trade coordination; stacked trades after remobilization
A197023 21 23 - Pumps14-Nov-202512-Jan-2026+39 wd
A2590Backfilling to U/S of SOG19-Sep-202514-Nov-2025+39 wd
A2750 CPL1, L2 & L3 Framing and Sheathing Installation05-Dec-202530-Jan-2026+38 wd
A2880 CPL1, L2 & L3 Framing and Sheathing Installation19-Dec-202513-Feb-2026+38 wd
A2790L1, L2 & L3 Air Vapour Barrier Installation12-Dec-202506-Feb-2026+38 wd
A2820Glazing Site Measure and Scanning08-Dec-202502-Feb-2026+38 wd
A2740Cold-Formed Metal Framing Mock01-Dec-202526-Jan-2026+38 wd
A2780Above Grade Vapour Mock-up08-Dec-202502-Feb-2026+38 wd
A2800AVB Inspection08-Dec-202502-Feb-2026+38 wd
A3930Interior Demoilition09-Jul-202502-Sep-2025+38 wd
A196023 74 13 - Air Handling Units27-Mar-202615-May-2026+35 wd
A212020 05 10 - Electric Heat Tracing28-Nov-202519-Jan-2026+34 wd
A159026 09 23 - Lighting Control (R0)30-Jun-202518-Aug-2025+34 wd
A4080 CPDrywall/Sheathing Installation19-May-202606-Jul-2026+33 wd
A4090 CPTaping and mudding02-Jun-202620-Jul-2026+33 wd
A4110 CPTile and Rubber Flooring Installation12-Jun-202630-Jul-2026+33 wd
A4100 CPPainting05-Jun-202623-Jul-2026+33 wd
A4120 CPFinal Terminations and Fixtures Installation19-Jun-202606-Aug-2026+33 wd
A213022 40 00 - Plumbing Fixtures02-Dec-202520-Jan-2026+33 wd
A4170Fire Alarm Verification07-Jul-202620-Aug-2026+32 wd
A3170Install Built-up Roof19-Dec-202503-Feb-2026+30 wd
A3180Roof Inspection19-Dec-202503-Feb-2026+30 wd
A3110L1, L2 & L3 Exterior Glazing Installation (W09a, W09b)26-Mar-202606-May-2026+29 wd
A2930L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03)12-Mar-202622-Apr-2026+29 wd
A2840L1, L2, L3 Exterior Glazing Installation (W05)05-Mar-202615-Apr-2026+29 wd
A3010L2 & L3 Exterior Glazing Installation (W08a, W08b)05-Mar-202615-Apr-2026+29 wd
A3260 CPSeal Concrete Floor04-Mar-202614-Apr-2026+29 wd
A3430Seal concrete Floor06-Mar-202616-Apr-2026+29 wd
A3280New partition framing18-Mar-202628-Apr-2026+29 wd
A3330Door frames Installation25-Mar-202605-May-2026+29 wd
A3440New partition framing01-Apr-202612-May-2026+29 wd
A3560Seal concrete Floor12-Mar-202622-Apr-2026+29 wd
A3420Fire Spraying & Intumecent Paint04-Mar-202614-Apr-2026+29 wd
A3550Fire Spraying & Intumecent Paint11-Mar-202621-Apr-2026+29 wd
A3210Electrical and Mechanical Room 04-Mar-202614-Apr-2026+29 wd
A3220Mech. and Elec. Equipment Installation18-Mar-202628-Apr-2026+29 wd
A2850Exterior Cladding Site Measure and Scanning06-Mar-202616-Apr-2026+29 wd
A2940Exterior Cladding Site Measure and Scanning13-Mar-202623-Apr-2026+29 wd
A3020Exterior Cladding Site Measure and Scanning06-Mar-202616-Apr-2026+29 wd
A3100Glazing Shop Fabrication19-Mar-202629-Apr-2026+29 wd
A3120Exterior Cladding Site Measure and Scanning27-Mar-202607-May-2026+29 wd
A3680Misc. Metals Mock-up02-Apr-202613-May-2026+29 wd
A2810Aluminum & Metal Panel Cladding Mock-up06-Mar-202616-Apr-2026+29 wd
A3080L1, L2 & L3 Air Vapor Barrier Inspection25-Feb-202608-Apr-2026+29 wd
A3250 CPFire Spraying & Intumecent Paint Inspection25-Feb-202608-Apr-2026+29 wd
A2960L2 & L3 Cladding Installation (EW2)11-May-202619-Jun-2026+28 wd
A2870L1, L2 & L3 Cladding Installation (EW2a)04-May-202612-Jun-2026+28 wd
A3040L2 & L3 Cladding Installation (EW2)04-May-202612-Jun-2026+28 wd
A3050Horizontal Shading Louvers11-May-202619-Jun-2026+28 wd
A2900Air Vapor Barrier Installation13-Jan-202623-Feb-2026+28 wd
A3140L1, L2 & L3 Cladding Installation (EW2, EW2A)02-Jun-202613-Jul-2026+28 wd
A3070L1, L2 & L3 Air Vapor Barrier Installation25-Feb-202607-Apr-2026+28 wd
A3490Door frames Installation07-Apr-202615-May-2026+28 wd
A3520Door and Hardware Installation21-Apr-202601-Jun-2026+28 wd
A3620Door frames Installation23-Apr-202603-Jun-2026+28 wd
A3570New wall partition framing16-Apr-202627-May-2026+28 wd
A3240 CPFire Spraying & Intumecent Paint25-Feb-202607-Apr-2026+28 wdOwnerFire-spray application held for owner inspector availability
A1110Structural Reinforcement + Decking Shop Drawings23-Jun-202501-Aug-2025+28 wd
A3690Misc. Metals installation29-May-202609-Jul-2026+28 wd
A2860Exterior Cladding Shop Fabrication06-Apr-202614-May-2026+28 wd
A2910Glazing Site Measure and Scanning07-Jan-202617-Feb-2026+28 wd
A2950Exterior Cladding Shop Fabrication13-Apr-202622-May-2026+28 wd
A3000Glazing Shop Fabrication26-Feb-202608-Apr-2026+28 wd
A3030Exterior Cladding Shop Fabrication06-Apr-202614-May-2026+28 wd
A3130Exterior Cladding Shop Fabrication27-Apr-202605-Jun-2026+28 wd
A2440Formwork Remaining Pad Footing (Ramp)30-Jul-202509-Sep-2025+28 wd
A2970 CPL2 & L3 Framing and Sheathing Installation27-Jan-202609-Mar-2026+27 wd
A3060 CPL1, L2 & L3 Framing and Sheathing Installation18-Feb-202630-Mar-2026+27 wd
A2980L2 & L3 Air Vapor Barrier Installation03-Feb-202616-Mar-2026+27 wd
A2830Glazing Shop Fabrication21-Jan-202602-Mar-2026+27 wd
A2920Glazing Shop Fabrication04-Feb-202617-Mar-2026+27 wd
A2990Glazing Site Measure and Scanning28-Jan-202610-Mar-2026+27 wd
A3090Glazing Site Measure and Scanning19-Feb-202631-Mar-2026+27 wd
A3230Fire Spraying & Intumecent Paint Mock-up19-Feb-202631-Mar-2026+27 wd
A3410Painting07-May-202615-Jun-2026+26 wd
A3300Electrical, FA & Comms rough-ins06-Apr-202612-May-2026+26 wd
A3320Blocking Installation09-Apr-202615-May-2026+26 wd
A3350Gypsum board Installation16-Apr-202625-May-2026+26 wd
A3360Drywall Taping and Mudding30-Apr-202608-Jun-2026+26 wd
A3390Interior Aluminum/Glazing Screens Installation07-May-202615-Jun-2026+26 wd
A3370Door and Hardware Installation07-May-202615-Jun-2026+26 wd
A1290Suspended Metal Soffits29-Jul-202504-Sep-2025+26 wd
A1820Coiling Doors05-Dec-202514-Jan-2026+26 wd
A3810Install Controller at Machine Room08-May-202616-Jun-2026+26 wd
A3820Rails and Elevator Car installation25-May-202630-Jun-2026+26 wd
A3830Power to controller, Phone lines and Comms01-Jun-202608-Jul-2026+26 wd
A3840Elevator Testing and Commissioning22-Jun-202629-Jul-2026+26 wd
A3380Interior Aluminum/Glazing Screens Mock-up01-May-202609-Jun-2026+26 wd
A3340ACT Baffles Mock-ups10-Apr-202619-May-2026+26 wd
A3400Paint Mock-up05-May-202611-Jun-2026+26 wd
A158026 50 00 - Lighting Fixtures11-Jul-202518-Aug-2025+26 wd
A1870ACT & ACB 11-Sep-202517-Oct-2025+25 wd
A215026 50 00 - Lighting Fixtures19-Nov-202525-Dec-2025+25 wd
A3290Mech. & Plumbing rough-ins01-Apr-202605-May-2026+24 wd
A3480Blocking Installation23-Apr-202628-May-2026+24 wd
A3610Blocking Installation04-May-202608-Jun-2026+24 wd
A3310Sprinkler Rough-ins01-Apr-202605-May-2026+24 wd
A3540Painting20-May-202622-Jun-2026+23 wd
A3450Mech. & Plumbing rough-ins16-Apr-202620-May-2026+23 wd
A3500Gypsum board Installation30-Apr-202603-Jun-2026+23 wd
A3460Electrical, FA & Comms rough-ins20-Apr-202622-May-2026+23 wd
A3510Drywall Taping and Mudding14-May-202617-Jun-2026+23 wd
A3530Interior Glazing Installation22-May-202624-Jun-2026+23 wd
A3590Electrical, FA & Comms rough-ins27-Apr-202629-May-2026+23 wd
A3580Mech. & Plumbing rough-ins09-Apr-202612-May-2026+23 wd
A3470Sprinkler Rough-ins16-Apr-202620-May-2026+23 wd
A3600Sprinkler Rough-ins09-Apr-202612-May-2026+23 wd
A1690 CPStructural Reinforcement18-Sep-202522-Oct-2025+23 wd
A146023 25 00 - Water Treatment (R0)10-Jul-202512-Aug-2025+23 wd
A4240 CPMinor Deficiencies & Touch-ups28-Aug-202630-Sep-2026+22 wdContractorDeficiency and touch-up re-work extended by finishing crew quality issues
A1700Cold-formed Metal Framing 08-Jul-202507-Aug-2025+22 wd
A4260 CPTotal Completion 31-Aug-202630-Sep-2026+21 wd
A4220Final Cleaning 05-Aug-202603-Sep-2026+21 wd
A1120Cold-formed Metal Framing Shop Drawings23-Jun-202523-Jul-2025+21 wd
A1220Flush Wood Doors Sample29-Jul-202527-Aug-2025+21 wd
A1280ACT Data sheet and Sample29-Jul-202527-Aug-2025+21 wd
A1330Fall Arrest Anchors and Horizontal Lines29-Jul-202527-Aug-2025+21 wd
A4180 CPMechanical, Electrical and Elevator Commissioning29-Jul-202627-Aug-2026+21 wd
A4190 CPIntegrated Testing12-Aug-202611-Sep-2026+21 wd
A4250 CPReady-To-Take Over31-Aug-202630-Sep-2026+21 wd
A4230Close-out Documents & Training05-Aug-202603-Sep-2026+21 wd
A3750Washroom Partitions and Accessories Installation08-Jul-202605-Aug-2026+20 wd
A2640Install Roof Decking14-Nov-202512-Dec-2025+20 wd
A2630Install Roof Anchors 07-Nov-202505-Dec-2025+20 wd
A3720Ceiling/Wall Fixtures Installation30-Jun-202629-Jul-2026+20 wd
A3740Millwork Installation23-Jun-202622-Jul-2026+20 wd
A3710Tiling and rubber flooring Installation30-Jun-202629-Jul-2026+20 wd
A3670Painting16-Jun-202615-Jul-2026+20 wd
A3770Corner Guards and Wall Protection Installation06-Jul-202603-Aug-2026+20 wd
A3660Interior Glazing Installation09-Jun-202608-Jul-2026+20 wd
A3650Door and Hardware Installation16-Jun-202615-Jul-2026+20 wd
A3630Gypsum board Installation19-May-202616-Jun-2026+20 wd
A3640Drywall Taping and Mudding02-Jun-202630-Jun-2026+20 wd
A1810Flush Wood Doors 14-Nov-202512-Dec-2025+20 wd
A1920Fall Arrest Anchors and Horizontal Lines24-Oct-202521-Nov-2025+20 wd
A4210 CPOccupancy13-Aug-202611-Sep-2026+20 wd
A3150Roof Parapet Framing21-Nov-202519-Dec-2025+20 wd
A3160Roof Penetration Layout18-Nov-202516-Dec-2025+20 wd
A3760Plumbing Washroom Fixtures Installation08-Jul-202605-Aug-2026+20 wd
A3730Millwork Mock-up17-Jun-202616-Jul-2026+20 wd
A3700Tiling & Rubber & Carpet Flooring Mock-up17-Jun-202616-Jul-2026+20 wd
A2500Install Rebar for Piers08-Aug-202508-Sep-2025+20 wd
A4200 CPSubstaintial Performance14-Aug-202611-Sep-2026+19 wd
A1230Coiling Doors29-Jul-202521-Aug-2025+17 wd
A4150New Exterior Paved Areas and Sidewalks 08-May-202601-Jun-2026+15 wd
A4160Landscape Installations25-May-202615-Jun-2026+15 wd
A153020 05 10 - Electric Heat Tracing (R0)22-Jul-202512-Aug-2025+15 wd
A2520Form and Pour Foundation Piers15-Aug-202508-Sep-2025+15 wd
A1090Masonry and Mortar Samples & Data Sheets29-Jul-202518-Aug-2025+14 wd
A1100Structural Steel Framing and Steel Deck Shop Drawings (R0)23-Jun-202514-Jul-2025+14 wd
A2530Backfilling to U/S of Grade Beams22-Aug-202512-Sep-2025+14 wd
A1670Masonry and Mortar06-Aug-202525-Aug-2025+13 wd
A2280Under Pinning Inspection24-Jun-202514-Jul-2025+13 wd
A147023 37 13 - Diffuser and Grilles Shop Drawings (R0)28-Jul-202514-Aug-2025+13 wd
A3920Setup Temporary Hoarding17-Jun-202504-Jul-2025+12 wd
A156026 50 00 - Emergency Lighting & Exit Signs11-Jul-202529-Jul-2025+12 wd
A1060Foundation Concrete Rebar Shop Drawing23-Jun-202508-Jul-2025+10 wd
A1050Ductbank Underpinning Drawing16-Jun-202530-Jun-2025+10 wd
A2550Form and Pour Grade Beams08-Sep-202522-Sep-2025+10 wd
A2560Below Grade Vapour Barrier Mock-up09-Sep-202523-Sep-2025+10 wd
A2570Footing Vapor Barrier & Insulation12-Sep-202526-Sep-2025+10 wd
A2610Erect Structural Steel20-Oct-202531-Oct-2025+9 wd
A2650Install Level 2 & 3 Decking03-Nov-202514-Nov-2025+9 wd
A2660Install Temporary Hoarding for Slab on Deck03-Nov-202514-Nov-2025+9 wd
A2620Structural Steel Inspection20-Oct-202531-Oct-2025+9 wd
A155026 27 26 - Wiring Devices, Service Poles, & Floor Boxes24-Jun-202508-Jul-2025+9 wd
A1210Interior Aluminum Screen29-Jul-202508-Aug-2025+8 wd
A1180Exterior Wall Cladding Shop Drawings13-Aug-202522-Aug-2025+7 wd
A1760Exterior Wall Cladding07-Nov-202518-Nov-2025+7 wd
A1800Interior Aluminum Screens05-Dec-202516-Dec-2025+7 wd
A137023 74 13 - Air Handling Units (R0)10-Jul-202521-Jul-2025+7 wd
A2670Rebar and Prep Work for Slab on Deck10-Nov-202518-Nov-2025+6 wd
A1080Bentonite Waterstop Data Sheet23-Jun-202502-Jul-2025+6 wd
A1660Bentonite Waterstop 30-Jun-202509-Jul-2025+6 wd
A2680Concrete pour for slab on deck level 2 & 313-Nov-202520-Nov-2025+5 wd
A2690Final Grading and Vapor Barrier for SOG18-Nov-202525-Nov-2025+5 wd
A151023 00 00 - Wall Fin Heater05-Aug-202512-Aug-2025+5 wd
A152023 74 13 - Air Source Heat Pump10-Jul-202517-Jul-2025+5 wd
A154022 40 00 - Plumbing Fixtures (R0)24-Jul-202531-Jul-2025+5 wd
A207023 00 00 - Exhaust Fans11-Dec-202518-Dec-2025+5 wd
A208023 00 00 - Unit Heater11-Dec-202518-Dec-2025+5 wd
A210023 00 00 - Wall Fin Heater11-Dec-202518-Dec-2025+5 wd
A214026 27 26 - Wiring Devices, Service Poles, & Floor Boxes07-Nov-202514-Nov-2025+5 wd
A2710Concrete Pour and Curing for SOG28-Nov-202503-Dec-2025+3 wd
A2700Rebar Installation for SOG21-Nov-202526-Nov-2025+3 wd
A2220Testing and Inspection Cash Allowance Expenditure26-Jun-202502-Jul-2025+3 wd
A2420Form and Pour North Exit Stair25-Sep-202530-Sep-2025+3 wd
A1070Foundation Concrete Mix Design23-Jun-202525-Jun-2025+2 wd
A1650Foundation Concrete Mix Design25-Jun-202527-Jun-2025+2 wd
A1040Permit (Not Required Per Ontario Community College)15-May-202516-May-2025+1 wd
A1030IFC Drawings Released14-May-202515-May-2025+1 wd
A1150Built-up Roofing Shop Drawings08-Jul-202509-Jul-2025+1 wd
A1190Fire-resistive Material Data Sheet08-Jul-202509-Jul-2025+1 wd
A1730Built-up Roofing 20-Aug-202521-Aug-2025+1 wd
A1770Fire-resistive Material 06-Aug-202507-Aug-2025+1 wd
A2230Ontario Community College Auto Show09-Jun-202509-Jun-20250 wd
A2320Demolition of Existing Vestibule F10025-Jun-202525-Jun-20250 wd
A1170Air Barrier System Data Sheet and Mockup08-Jul-202508-Jul-20250 wd
A2310Relocate FAA18-Jun-202517-Jun-2025-1 wd
A138023 21 23 - Pumps (R0)08-Jul-202504-Jul-2025-2 wd
A142023 57 00 - Heat Exchangers07-Jul-202503-Jul-2025-2 wd
A157027 10 00 - Structural Cabling System (Fiber Optic Cable)24-Jul-202522-Jul-2025-2 wd
A2290Existing Structure Under Pinning18-Jul-202515-Jul-2025-3 wd
A3960Vinyl Flooring Abatement (Cash Allowance)16-Jul-202511-Jul-2025-3 wd
A3190Hoisting Roof Equipment17-Jun-202612-Jun-2026-3 wd
A3200Roof Anchor System Installation24-Jun-202619-Jun-2026-3 wd
A139023 25 00 - Buffer Tanks08-Jul-202503-Jul-2025-3 wd
A140023 21 16 - Air Separator08-Jul-202503-Jul-2025-3 wd
A141023 21 16 - Expansion Tanks08-Jul-202503-Jul-2025-3 wd
A211023 74 13 - Air Source Heat Pump10-Jun-202605-Jun-2026-3 wd
A2370Bulk Excavation to U/S of Footings25-Jul-202522-Jul-2025-3 wd
A2380Bulk Excavation to U/S North Stair Footing28-Jul-202523-Jul-2025-3 wd
A2390Subgrade Inspection25-Jul-202522-Jul-2025-3 wd
A2400Subgrade Preparation28-Jul-202523-Jul-2025-3 wd
A2410Soil Bearing Capacity Inspection29-Jul-202524-Jul-2025-3 wd
A2430Formwork for Pad Footing (GL:AG-AC & X1-A5)28-Jul-202523-Jul-2025-3 wd
A2450Rebar for Pad Footings29-Jul-202524-Jul-2025-3 wd
A2460Rebar Inspection30-Jul-202525-Jul-2025-3 wd
A2470Concrete for Pad Footings (GL:AG-AC & X1-A5)31-Jul-202528-Jul-2025-3 wd
A2490Concrete Field Testing31-Jul-202528-Jul-2025-3 wd
A1340Hydraulic Lift Shop Drawings15-Jul-202509-Jul-2025-4 wd
A1930Hydraulic Lift 05-Dec-202501-Dec-2025-4 wd
A160028 31 00 - Fire Alarm Shop Drawings and Data Sheets24-Jun-202517-Jun-2025-5 wd
A4010Underground Plumbing Rough-ins23-Jul-202515-Jul-2025-6 wd
A2360Ductbank Shoring 21-Jul-202508-Jul-2025-9 wd
A219028 31 00 - Fire Alarm07-Nov-202527-Oct-2025-9 wd
A148023 00 00 - Exhaust Fans (R0)05-Aug-202522-Jul-2025-10 wd
A149023 00 00 - Unit Heater05-Aug-202522-Jul-2025-10 wd
A216027 10 00 - Structural Cabling System (Fiber Optic Cable)30-Apr-202614-Apr-2026-12 wd
A145022 13 29 - Sump Pumps (R0)20-Jun-202502-Jun-2025-14 wd
A1640Foundation Concrete Rebar 08-Jul-202513-Jun-2025-16 wd
A1630Ductbank Underpinning 23-Jun-202528-May-2025-18 wd
A2480Concrete for Remaining Pad Footings (Ramp)01-Aug-202502-Jul-2025-22 wd
A2600Compaction Inspection19-Sep-202515-Aug-2025-24 wd
A-10

Provenance & Method

reproducibility manifest
Generated
15-Jul-2026
Method
Windows Analysis — AACE MIP 3.3
Engine
CPP v2.9.38
Prepared By
Dana Fitkowski
Organization
Critical Path Partners
Windows Analyzed
1 (Baseline → Current)
Prepared by Dana Fitkowski · Source: Critical Path Partners · Generated 15-Jul-2026 · CPP Engine v2.9.38Reproducible · AACE 29R-03 / SCL Protocol 2nd ed.