Project
Ontario Community College - B2 (Demo Data)
| Window | Period | Shift (wd) | Cumulative vs Baseline (wd) | CP Activities | CP Duration Growth | Slipped Activities |
|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | +21 wd | +21 wd | 39 | 12 | 264 |
| Window | Period | Owner | Contractor | Concurrent | Force Majeure | Unattributed | Window Shift (wd) | Finish Driver |
|---|---|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | +7 wd | +14 wd | — | — | — | +21 wd | A4240 target_end_date |
| Cumulative | project totals | +7 wd | +14 wd | 0 wd | 0 wd | 0 wd | +21 wd | — |
| Window | Period | Duration (wd) | Shift (wd) | Velocity (wd/wd) | Δ Acceleration | Midpoint Date | Half-Period Slip (wd) |
|---|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | 62 wd | +21 wd | +0.339 | — | 16-May-2025 | +10.5 wd |
| Code | Activity | Baseline Period | Actual Period | Progress (wd) | Gain (wd) | Extended (wd) | Void (wd) |
|---|---|---|---|---|---|---|---|
| A1160 | TPO Roofing Shop Drawings | 2025-06-10 → 2025-06-23 | 2025-07-09 → 2025-08-26 | 0 wd | 0 wd | 35 wd | 10 wd |
| A3930 | Interior Demoilition | 2025-06-18 → 2025-07-09 | 2025-07-21 → 2025-09-02 | 0 wd | 0 wd | 31 wd | 15 wd |
| A1460 | 23 25 00 - Water Treatment (R0) | 2025-06-26 → 2025-07-10 | 2025-06-26 → 2025-08-12 | 10 wd | 0 wd | 23 wd | 0 wd |
| A1280 | ACT Data sheet and Sample | 2025-07-16 → 2025-07-29 | 2025-07-23 → 2025-08-27 | 5 wd | 0 wd | 21 wd | 5 wd |
| A2500 | Install Rebar for Piers | 2025-08-01 → 2025-08-08 | 2025-07-29 → 2025-09-08 | 6 wd | 3 wd | 20 wd | 0 wd |
| A1120 | Cold-formed Metal Framing Shop Drawings | 2025-06-10 → 2025-06-23 | 2025-06-26 → 2025-07-23 | 0 wd | 0 wd | 19 wd | 10 wd |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | 2025-07-09 → 2025-07-22 | 2025-07-09 → 2025-08-12 | 10 wd | 0 wd | 15 wd | 0 wd |
| A2520 | Form and Pour Foundation Piers | 2025-08-11 → 2025-08-15 | 2025-08-11 → 2025-09-08 | 5 wd | 0 wd | 15 wd | 0 wd |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | 2025-06-10 → 2025-06-23 | 2025-06-20 → 2025-07-14 | 2 wd | 0 wd | 14 wd | 8 wd |
| A1090 | Masonry and Mortar Samples & Data Sheets | 2025-07-16 → 2025-07-29 | 2025-06-10 → 2025-08-18 | 10 wd | 25 wd | 14 wd | 0 wd |
| A2530 | Backfilling to U/S of Grade Beams | 2025-08-18 → 2025-08-22 | 2025-08-11 → 2025-09-12 | 5 wd | 5 wd | 14 wd | 0 wd |
| A1230 | Coiling Doors | 2025-07-16 → 2025-07-29 | 2025-08-05 → 2025-08-21 | 0 wd | 0 wd | 13 wd | 10 wd |
| A2280 | Under Pinning Inspection | 2025-06-24 → 2025-06-24 | 2025-06-23 → 2025-07-14 | 1 wd | 1 wd | 13 wd | 0 wd |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | 2025-07-15 → 2025-07-28 | 2025-07-15 → 2025-08-14 | 10 wd | 0 wd | 13 wd | 0 wd |
| A1580 | 26 50 00 - Lighting Fixtures | 2025-06-27 → 2025-07-11 | 2025-08-01 → 2025-08-18 | 0 wd | 0 wd | 12 wd | 10 wd |
| A1590 | 26 09 23 - Lighting Control (R0) | 2025-06-17 → 2025-06-30 | 2025-08-01 → 2025-08-18 | 0 wd | 0 wd | 12 wd | 10 wd |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | 2025-06-27 → 2025-07-11 | 2025-06-27 → 2025-07-29 | 10 wd | 0 wd | 12 wd | 0 wd |
| A1050 | Ductbank Underpinning Drawing | 2025-06-03 → 2025-06-16 | 2025-06-16 → 2025-06-30 | 1 wd | 0 wd | 10 wd | 9 wd |
| A1060 | Foundation Concrete Rebar Shop Drawing | 2025-06-10 → 2025-06-23 | 2025-05-29 → 2025-07-08 | 10 wd | 8 wd | 10 wd | 0 wd |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 2025-06-11 → 2025-06-24 | 2025-06-11 → 2025-07-08 | 10 wd | 0 wd | 9 wd | 0 wd |
| A1370 | 23 74 13 - Air Handling Units (R0) | 2025-06-26 → 2025-07-10 | 2025-06-26 → 2025-07-21 | 10 wd | 0 wd | 7 wd | 0 wd |
| A1080 | Bentonite Waterstop Data Sheet | 2025-06-10 → 2025-06-23 | 2025-06-09 → 2025-07-02 | 10 wd | 1 wd | 6 wd | 0 wd |
| A1290 | Suspended Metal Soffits | 2025-07-16 → 2025-07-29 | 2025-08-28 → 2025-09-04 | 0 wd | 0 wd | 5 wd | 10 wd |
| A1660 | Bentonite Waterstop | 2025-06-24 → 2025-06-30 | 2025-07-03 → 2025-07-09 | 0 wd | 0 wd | 5 wd | 5 wd |
| A1510 | 23 00 00 - Wall Fin Heater | 2025-07-22 → 2025-08-05 | 2025-07-22 → 2025-08-12 | 11 wd | 0 wd | 5 wd | 0 wd |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | 2025-07-11 → 2025-07-24 | 2025-07-11 → 2025-07-31 | 10 wd | 0 wd | 5 wd | 0 wd |
| A1220 | Flush Wood Doors Sample | 2025-07-16 → 2025-07-29 | 2025-08-26 → 2025-08-27 | 0 wd | 0 wd | 2 wd | 10 wd |
| A1070 | Foundation Concrete Mix Design | 2025-06-10 → 2025-06-23 | 2025-06-13 → 2025-06-25 | 7 wd | 0 wd | 2 wd | 3 wd |
| A1650 | Foundation Concrete Mix Design | 2025-06-24 → 2025-06-25 | 2025-06-26 → 2025-06-27 | 0 wd | 0 wd | 2 wd | 2 wd |
| A1680 IN-PROGRESS | Structural Steel | 2025-06-24 → 2025-07-29 | 2025-09-04 → — | 0 wd | 0 wd | 1 wd | 25 wd |
| A1130 IN-PROGRESS | Misc. Metals Shop Drawings | 2025-07-09 → 2025-07-22 | 2025-08-26 → — | 0 wd | 0 wd | 1 wd | 10 wd |
| A1330 IN-PROGRESS | Fall Arrest Anchors and Horizontal Lines | 2025-07-16 → 2025-07-29 | 2025-08-14 → — | 0 wd | 0 wd | 1 wd | 10 wd |
| A1110 | Structural Reinforcement + Decking Shop Drawings | 2025-06-10 → 2025-06-23 | 2025-08-01 → 2025-08-01 | 0 wd | 0 wd | 1 wd | 10 wd |
| A1500 IN-PROGRESS | 23 52 16 - Heating Boilers | 2025-07-09 → 2025-07-22 | 2025-09-12 → — | 0 wd | 0 wd | 1 wd | 10 wd |
| A1190 | Fire-resistive Material Data Sheet | 2025-06-24 → 2025-07-08 | 2025-06-27 → 2025-07-09 | 7 wd | 0 wd | 1 wd | 3 wd |
| A1040 | Permit (Not Required Per Ontario Community College) | 2025-05-15 → 2025-05-15 | 2025-05-16 → 2025-05-16 | 0 wd | 0 wd | 1 wd | 1 wd |
| A1030 | IFC Drawings Released | 2025-05-14 → 2025-05-14 | 2025-05-15 → 2025-05-15 | 0 wd | 0 wd | 1 wd | 1 wd |
| A3920 | Setup Temporary Hoarding | 2025-06-17 → 2025-06-17 | 2025-07-04 → 2025-07-04 | 0 wd | 0 wd | 1 wd | 1 wd |
| A2510 | Supply of Embedment & Ankors | 2025-06-24 → 2025-06-24 | 2025-08-22 → 2025-08-22 | 0 wd | 0 wd | 1 wd | 1 wd |
| A1150 | Built-up Roofing Shop Drawings | 2025-06-24 → 2025-07-08 | 2025-06-19 → 2025-07-09 | 10 wd | 3 wd | 1 wd | 0 wd |
| A2600 | Compaction Inspection | 2025-04-02 → 2025-09-19 | 2025-08-15 → 2025-08-15 | 1 wd | 0 wd | 0 wd | 94 wd |
| A2390 | Subgrade Inspection | 2025-04-02 → 2025-07-25 | 2025-07-22 → 2025-07-22 | 1 wd | 0 wd | 0 wd | 76 wd |
| A3320 | Blocking Installation | 2025-04-02 → 2026-04-09 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A3480 | Blocking Installation | 2025-04-02 → 2026-04-23 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A3610 | Blocking Installation | 2025-04-02 → 2026-05-04 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A2660 | Install Temporary Hoarding for Slab on Deck | 2025-04-02 → 2025-11-03 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A3180 | Roof Inspection | 2025-04-02 → 2025-12-19 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A2620 | Structural Steel Inspection | 2025-04-02 → 2025-10-20 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | 2025-04-02 → 2026-02-25 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A3250 | Fire Spraying & Intumecent Paint Inspection | 2025-04-02 → 2026-02-25 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A2540 | Compaction Inspection | 2025-04-02 → 2025-08-22 | — → — | 0 wd | 0 wd | 0 wd | 62 wd |
| A2150 IN-PROGRESS | 26 50 00 - Lighting Fixtures | 2025-07-14 → 2025-11-19 | 2025-08-19 → — | 1 wd | 0 wd | 0 wd | 26 wd |
| A2230 | Ontario Community College Auto Show | 2025-05-05 → 2025-06-09 | 2025-06-09 → 2025-06-09 | 1 wd | 0 wd | 0 wd | 24 wd |
| A2450 | Rebar for Pad Footings | 2025-07-09 → 2025-07-29 | 2025-07-23 → 2025-07-24 | 2 wd | 0 wd | 0 wd | 10 wd |
| A1180 IN-PROGRESS | Exterior Wall Cladding Shop Drawings | 2025-07-30 → 2025-08-13 | 2025-08-11 → — | 1 wd | 0 wd | 0 wd | 8 wd |
| A1210 IN-PROGRESS | Interior Aluminum Screen | 2025-07-16 → 2025-07-29 | 2025-07-25 → — | 1 wd | 0 wd | 0 wd | 7 wd |
| A3940 | Existing Slab Removal and Trenching | 2025-06-17 → 2025-06-23 | — → — | 0 wd | 0 wd | 0 wd | 5 wd |
| A1170 | Air Barrier System Data Sheet and Mockup | 2025-06-24 → 2025-07-08 | — → — | 0 wd | 0 wd | 0 wd | 5 wd |
| A1700 | Cold-formed Metal Framing | 2025-06-24 → 2025-07-08 | — → — | 0 wd | 0 wd | 0 wd | 5 wd |
| A1740 | TPO Roofing (Bridge) | 2025-06-24 → 2025-08-06 | — → — | 0 wd | 0 wd | 0 wd | 5 wd |
| A1690 | Structural Reinforcement | 2025-06-24 → 2025-09-18 | — → — | 0 wd | 0 wd | 0 wd | 5 wd |
| A2140 IN-PROGRESS | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 2025-07-02 → 2025-11-07 | 2025-07-09 → — | 1 wd | 0 wd | 0 wd | 5 wd |
| A2420 IN-PROGRESS | Form and Pour North Exit Stair | 2025-07-30 → 2025-09-25 | 2025-08-04 → — | 1 wd | 0 wd | 0 wd | 3 wd |
| A2220 | Testing and Inspection Cash Allowance Expenditure | 2025-06-26 → 2025-06-26 | — → — | 0 wd | 0 wd | 0 wd | 1 wd |
| A2240 | Construction Site Setup. Fencing and Temp Facilities | 2025-06-10 → 2025-06-16 | 2025-06-10 → 2025-06-16 | 5 wd | 0 wd | 0 wd | 0 wd |
| A1000 | Tender Closing | 2025-04-01 → 2025-04-29 | 2025-04-01 → 2025-04-29 | 20 wd | 0 wd | 0 wd | 0 wd |
| A1010 | Contract Award | 2025-05-02 → 2025-05-02 | 2025-05-02 → 2025-05-02 | 1 wd | 0 wd | 0 wd | 0 wd |
| A2270 | Excavation for Under Pinning | 2025-06-23 → 2025-06-23 | 2025-06-23 → 2025-06-23 | 1 wd | 0 wd | 0 wd | 0 wd |
| A2250 | Tree Removal, Protection and Equipment Mobilization | 2025-06-17 → 2025-06-17 | 2025-06-17 → 2025-06-17 | 1 wd | 0 wd | 0 wd | 0 wd |
| A2260 | Top Soil Stripping | 2025-06-18 → 2025-06-20 | 2025-06-18 → 2025-06-20 | 3 wd | 0 wd | 0 wd | 0 wd |
| A2300 | Setup Hoarding @ Vestibule F100 | 2025-06-17 → 2025-06-18 | 2025-06-17 → 2025-06-18 | 2 wd | 0 wd | 0 wd | 0 wd |
| A2310 | Relocate FAA | 2025-06-17 → 2025-06-18 | 2025-06-16 → 2025-06-17 | 1 wd | 1 wd | 0 wd | 0 wd |
| A2320 | Demolition of Existing Vestibule F100 | 2025-06-19 → 2025-06-25 | 2025-06-18 → 2025-06-25 | 5 wd | 1 wd | 0 wd | 0 wd |
| A2290 | Existing Structure Under Pinning | 2025-06-27 → 2025-07-18 | 2025-06-24 → 2025-07-15 | 12 wd | 3 wd | 0 wd | 0 wd |
| A2330 | Gas Meter and Pipe Relocation Investigation | 2025-06-17 → 2025-06-19 | 2025-06-17 → 2025-06-19 | 3 wd | 0 wd | 0 wd | 0 wd |
| A2340 | Gas Meter and pipe Relocation | 2025-06-20 → 2025-06-23 | 2025-06-20 → 2025-06-23 | 2 wd | 0 wd | 0 wd | 0 wd |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | 2025-06-23 → 2025-07-07 | 2025-06-23 → 2025-07-07 | 10 wd | 0 wd | 0 wd | 0 wd |
| A2360 | Ductbank Shoring | 2025-07-08 → 2025-07-21 | 2025-06-23 → 2025-07-08 | 1 wd | 10 wd | 0 wd | 0 wd |
| A1020 | Subcontract Award | 2025-05-05 → 2025-06-02 | 2025-05-05 → 2025-06-02 | 20 wd | 0 wd | 0 wd | 0 wd |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | 2025-07-10 → 2025-07-16 | 2025-07-07 → 2025-07-11 | 2 wd | 3 wd | 0 wd | 0 wd |
| A1340 | Hydraulic Lift Shop Drawings | 2025-07-02 → 2025-07-15 | 2025-06-26 → 2025-07-09 | 6 wd | 3 wd | 0 wd | 0 wd |
| A1630 | Ductbank Underpinning | 2025-06-17 → 2025-06-23 | 2025-05-28 → 2025-05-28 | 0 wd | 1 wd | 0 wd | 0 wd |
| A1640 | Foundation Concrete Rebar | 2025-06-24 → 2025-07-08 | 2025-06-13 → 2025-06-13 | 0 wd | 1 wd | 0 wd | 0 wd |
| A3780 | Layout for Elevator Cylinder | 2025-06-23 → 2025-06-23 | 2025-06-23 → 2025-06-23 | 1 wd | 0 wd | 0 wd | 0 wd |
| A3790 | Drilling Elevator Cylinder from Grade | 2025-06-24 → 2025-06-24 | 2025-06-24 → 2025-06-24 | 1 wd | 0 wd | 0 wd | 0 wd |
| A3800 | Install Steel Casing into the ground | 2025-06-25 → 2025-06-25 | 2025-06-25 → 2025-06-25 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1360 | 23 82 19 - Fan Coil Units (R0) | 2025-06-19 → 2025-07-03 | 2025-06-19 → 2025-07-03 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1380 | 23 21 23 - Pumps (R0) | 2025-06-24 → 2025-07-08 | 2025-06-24 → 2025-07-04 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1390 | 23 25 00 - Buffer Tanks | 2025-06-24 → 2025-07-08 | 2025-06-24 → 2025-07-03 | 7 wd | 0 wd | 0 wd | 0 wd |
| A1400 | 23 21 16 - Air Separator | 2025-06-24 → 2025-07-08 | 2025-06-24 → 2025-07-03 | 7 wd | 0 wd | 0 wd | 0 wd |
| A1410 | 23 21 16 - Expansion Tanks | 2025-06-24 → 2025-07-08 | 2025-06-24 → 2025-07-03 | 7 wd | 0 wd | 0 wd | 0 wd |
| A1420 | 23 57 00 - Heat Exchangers | 2025-06-23 → 2025-07-07 | 2025-06-23 → 2025-07-03 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1430 | 22 33 00 - Electric Domestic Water Heaters | 2025-06-19 → 2025-07-03 | 2025-06-19 → 2025-07-03 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1440 | 23 81 26 - Split System | 2025-06-12 → 2025-06-30 | 2025-06-12 → 2025-06-30 | 13 wd | 0 wd | 0 wd | 0 wd |
| A1450 | 22 13 29 - Sump Pumps (R0) | 2025-06-09 → 2025-06-20 | 2025-05-27 → 2025-06-02 | 0 wd | 5 wd | 0 wd | 0 wd |
| A1480 | 23 00 00 - Exhaust Fans (R0) | 2025-07-22 → 2025-08-05 | 2025-07-22 → 2025-07-22 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1490 | 23 00 00 - Unit Heater | 2025-07-22 → 2025-08-05 | 2025-07-22 → 2025-07-22 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1520 IN-PROGRESS | 23 74 13 - Air Source Heat Pump | 2025-06-26 → 2025-07-10 | 2025-06-26 → — | 3 wd | 0 wd | 0 wd | 0 wd |
| A1980 IN-PROGRESS | 23 25 00 - Buffer Tanks | 2025-07-04 → 2025-12-24 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A1990 IN-PROGRESS | 23 21 16 - Air Separator | 2025-07-04 → 2025-11-11 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2000 IN-PROGRESS | 23 21 16 - Expansion Tanks | 2025-07-04 → 2025-11-11 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2010 IN-PROGRESS | 23 57 00 - Heat Exchangers | 2025-07-04 → 2025-11-11 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2020 IN-PROGRESS | 22 33 00 - Electric Domestic Water Heaters | 2025-07-04 → 2025-11-11 | 2025-07-04 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2030 IN-PROGRESS | 23 81 26 - Split System | 2025-07-10 → 2025-11-17 | 2025-07-10 → — | 1 wd | 0 wd | 0 wd | 0 wd |
| A2040 IN-PROGRESS | 22 13 29 - Sump Pumps | 2025-06-19 → 2025-08-08 | 2025-06-19 → — | 8 wd | 0 wd | 0 wd | 0 wd |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 2025-07-11 → 2025-07-24 | 2025-07-11 → 2025-07-22 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | 2025-06-11 → 2025-06-24 | 2025-06-11 → 2025-06-17 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2190 IN-PROGRESS | 28 31 00 - Fire Alarm | 2025-07-02 → 2025-11-07 | 2025-06-18 → — | 0 wd | 9 wd | 0 wd | 0 wd |
| A2160 IN-PROGRESS | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 2025-07-25 → 2026-04-30 | 2025-07-23 → — | 0 wd | 1 wd | 0 wd | 0 wd |
| A2370 | Bulk Excavation to U/S of Footings | 2025-07-21 → 2025-07-25 | 2025-07-16 → 2025-07-22 | 2 wd | 3 wd | 0 wd | 0 wd |
| A2380 | Bulk Excavation to U/S North Stair Footing | 2025-07-28 → 2025-07-28 | 2025-07-23 → 2025-07-23 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2400 | Subgrade Preparation | 2025-07-28 → 2025-07-28 | 2025-07-23 → 2025-07-23 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2410 | Soil Bearing Capacity Inspection | 2025-07-29 → 2025-07-29 | 2025-07-24 → 2025-07-24 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | 2025-07-28 → 2025-07-28 | 2025-07-23 → 2025-07-23 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2460 | Rebar Inspection | 2025-07-30 → 2025-07-30 | 2025-07-25 → 2025-07-25 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | 2025-07-31 → 2025-07-31 | 2025-07-28 → 2025-07-28 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2490 | Concrete Field Testing | 2025-07-31 → 2025-07-31 | 2025-07-28 → 2025-07-28 | 0 wd | 1 wd | 0 wd | 0 wd |
| Activity | Min TF | Max TF | First TF≤0 Window | Recovery (Δd / count) | Slip Velocity |
|---|---|---|---|---|---|
| A1000 | +2.0 wd | +2.0 wd | — | — | · +0.00 wd/win |
| A1010 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A1020 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A1060 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A1110 | +5.0 wd | +5.0 wd | — | — | · +0.00 wd/win |
| A1110.1 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A1640 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A1690 | +0.0 wd | +5.0 wd | Current | — | ▼ -5.00 wd/win |
| A2220 | +0.0 wd | +89.0 wd | Baseline | +89.0 wd (1) | ▲ +89.00 wd/win |
| A2230 | +3.0 wd | +3.0 wd | — | — | · +0.00 wd/win |
| A2240 | +3.0 wd | +3.0 wd | — | — | · +0.00 wd/win |
| A2250 | +4.0 wd | +4.0 wd | — | — | · +0.00 wd/win |
| A2260 | +4.0 wd | +4.0 wd | — | — | · +0.00 wd/win |
| A2290 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2300 | +3.0 wd | +3.0 wd | — | — | · +0.00 wd/win |
| A2310 | +3.0 wd | +3.0 wd | — | — | · +0.00 wd/win |
| A2320 | +3.0 wd | +3.0 wd | — | — | · +0.00 wd/win |
| A2350 | +4.0 wd | +4.0 wd | — | — | · +0.00 wd/win |
| A2360 | +4.0 wd | +4.0 wd | — | — | · +0.00 wd/win |
| A2370 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2390 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2400 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2430 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2440 | +5.0 wd | +43.0 wd | — | +38.0 wd (1) | ▲ +38.00 wd/win |
| A2450 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2460 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2470 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2480 | +5.0 wd | +316.0 wd | — | +311.0 wd (1) | ▲ +311.00 wd/win |
| A2490 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2500 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2520 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2530 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2540 | +0.0 wd | +43.0 wd | Baseline | +43.0 wd (1) | ▲ +43.00 wd/win |
| A2550 | +0.0 wd | +43.0 wd | Baseline | +43.0 wd (1) | ▲ +43.00 wd/win |
| A2560 | +3.0 wd | +71.0 wd | — | +68.0 wd (1) | ▲ +68.00 wd/win |
| A2570 | +0.0 wd | +68.0 wd | Baseline | +68.0 wd (1) | ▲ +68.00 wd/win |
| A2580 | +4.0 wd | +39.0 wd | — | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2590 | +0.0 wd | +39.0 wd | Baseline | +39.0 wd (1) | ▲ +39.00 wd/win |
| A2610 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2620 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2650 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2660 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2670 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2680 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2690 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2700 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2710 | +0.0 wd | +35.0 wd | Baseline | +35.0 wd (1) | ▲ +35.00 wd/win |
| A2740 | +4.0 wd | +4.0 wd | — | — | · +0.00 wd/win |
| A2750 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2880 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A2970 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A3060 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A3070 | +1.0 wd | +5.0 wd | — | — | ▼ -4.00 wd/win |
| A3210 | +0.0 wd | +6.0 wd | Baseline | +6.0 wd (1) | ▲ +6.00 wd/win |
| A3220 | +0.0 wd | +6.0 wd | Baseline | +6.0 wd (1) | ▲ +6.00 wd/win |
| A3240 | +0.0 wd | +5.0 wd | Current | — | ▼ -5.00 wd/win |
| A3250 | +0.0 wd | +5.0 wd | Current | — | ▼ -5.00 wd/win |
| A3260 | +0.0 wd | +5.0 wd | Current | — | ▼ -5.00 wd/win |
| A3280 | +1.0 wd | +5.0 wd | — | — | ▼ -4.00 wd/win |
| A3290 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3440 | +3.0 wd | +7.0 wd | — | — | ▼ -4.00 wd/win |
| A3450 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3570 | +3.0 wd | +7.0 wd | — | — | ▼ -4.00 wd/win |
| A3580 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3590 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3610 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3620 | +3.0 wd | +7.0 wd | — | — | ▼ -4.00 wd/win |
| A3630 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3640 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3650 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3660 | +5.0 wd | +6.0 wd | — | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3670 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3710 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3720 | +5.0 wd | +6.0 wd | — | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3750 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3760 | +0.0 wd | +1.0 wd | Baseline | +1.0 wd (1) | ▲ +1.00 wd/win |
| A3980 | +5.0 wd | +5.0 wd | — | — | · +0.00 wd/win |
| A4030 | +0.0 wd | +117.0 wd | Current | — | ▼ -117.00 wd/win |
| A4040 | +0.0 wd | +12.0 wd | Current | — | ▼ -12.00 wd/win |
| A4040x | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4050 | +0.0 wd | +182.0 wd | Current | — | ▼ -182.00 wd/win |
| A4060 | +0.0 wd | +126.0 wd | Current | — | ▼ -126.00 wd/win |
| A4070 | +0.0 wd | +131.0 wd | Current | — | ▼ -131.00 wd/win |
| A4080 | +0.0 wd | +12.0 wd | Current | — | ▼ -12.00 wd/win |
| A4090 | +0.0 wd | +12.0 wd | Current | — | ▼ -12.00 wd/win |
| A4100 | +0.0 wd | +12.0 wd | Current | — | ▼ -12.00 wd/win |
| A4110 | +0.0 wd | +12.0 wd | Current | — | ▼ -12.00 wd/win |
| A4120 | +0.0 wd | +12.0 wd | Current | — | ▼ -12.00 wd/win |
| A4170 | +5.0 wd | +16.0 wd | — | — | ▼ -11.00 wd/win |
| A4180 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A4190 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A4200 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A4210 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A4220 | +5.0 wd | +5.0 wd | — | — | · +0.00 wd/win |
| A4240 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A4250 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A4260 | +0.0 wd | +0.0 wd | Baseline | — | · +0.00 wd/win |
| A4400 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4420 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4430 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4450 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4460 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4470 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4480 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4490 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4500 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4520 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4590 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| A4820 | +0.0 wd | +0.0 wd | Current | — | · +0.00 wd/win |
| Code | Activity | Total Slip | Windows Touched |
|---|---|---|---|
| A4070 CP | Frames installation | +180 wd | 1 |
| A4060 CP | Blocking | +170 wd | 1 |
| A4050 CP | Sprinkler Rough-ins | +165 wd | 1 |
| A4030 CP | New Partition Framing | +145 wd | 1 |
| A3850 | Foundations | +127 wd | 1 |
| A3860 | Concrete Vertical Piers | +127 wd | 1 |
| A3870 | Removal of Existing Facade for Tie In | +127 wd | 1 |
| A3880 | Structural Steel erection including expansion plates | +95 wd | 1 |
| A3890 | Envelope | +95 wd | 1 |
| A3900 | Interior M&E Rough in | +85 wd | 1 |
| A1950 | 23 82 19 - Fan Coil Units | +69 wd | 1 |
| A3910 | Interior Finishes | +66 wd | 1 |
| A2730 | Stairs B Installation @ North Side | +60 wd | 1 |
| A1710 | Misc. Metals | +60 wd | 1 |
| A2720 | Tactile Attention Indicators Mock-up | +60 wd | 1 |
| A3270 | New Stair A Installation | +59 wd | 1 |
| A2540 | Compaction Inspection | +58 wd | 1 |
| A2090 | 23 52 16 - Heating Boilers | +55 wd | 1 |
| A3940 | Existing Slab Removal and Trenching | +54 wd | 1 |
| A2050 | 23 25 00 - Water Treatment | +54 wd | 1 |
| A2180 | 26 09 23 - Lighting Control | +53 wd | 1 |
| A1130 | Misc. Metals Shop Drawings | +51 wd | 1 |
| A1500 | 23 52 16 - Heating Boilers | +46 wd | 1 |
| A2060 | 23 37 13 - Diffuser and Grilles | +46 wd | 1 |
| A1160 | TPO Roofing Shop Drawings | +45 wd | 1 |
| A1680 | Structural Steel | +45 wd | 1 |
| A1740 | TPO Roofing (Bridge) | +44 wd | 1 |
| A2580 | Underground Drainage | +43 wd | 1 |
| A2510 | Supply of Embedment & Ankors | +42 wd | 1 |
| A4040 CP | MEP Rough-ins | +41 wd | 1 |
| A1970 | 23 21 23 - Pumps | +39 wd | 1 |
| A2590 | Backfilling to U/S of SOG | +39 wd | 1 |
| A2750 CP | L1, L2 & L3 Framing and Sheathing Installation | +38 wd | 1 |
| A2880 CP | L1, L2 & L3 Framing and Sheathing Installation | +38 wd | 1 |
| A2790 | L1, L2 & L3 Air Vapour Barrier Installation | +38 wd | 1 |
| A2820 | Glazing Site Measure and Scanning | +38 wd | 1 |
| A2740 | Cold-Formed Metal Framing Mock | +38 wd | 1 |
| A2780 | Above Grade Vapour Mock-up | +38 wd | 1 |
| A2800 | AVB Inspection | +38 wd | 1 |
| A3930 | Interior Demoilition | +38 wd | 1 |
| A1960 | 23 74 13 - Air Handling Units | +35 wd | 1 |
| A2120 | 20 05 10 - Electric Heat Tracing | +34 wd | 1 |
| A1590 | 26 09 23 - Lighting Control (R0) | +34 wd | 1 |
| A4080 CP | Drywall/Sheathing Installation | +33 wd | 1 |
| A4090 CP | Taping and mudding | +33 wd | 1 |
| A4110 CP | Tile and Rubber Flooring Installation | +33 wd | 1 |
| A4100 CP | Painting | +33 wd | 1 |
| A4120 CP | Final Terminations and Fixtures Installation | +33 wd | 1 |
| A2130 | 22 40 00 - Plumbing Fixtures | +33 wd | 1 |
| A4170 | Fire Alarm Verification | +32 wd | 1 |
| A3170 | Install Built-up Roof | +30 wd | 1 |
| A3180 | Roof Inspection | +30 wd | 1 |
| A3110 | L1, L2 & L3 Exterior Glazing Installation (W09a, W09b) | +29 wd | 1 |
| A2930 | L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) | +29 wd | 1 |
| A2840 | L1, L2, L3 Exterior Glazing Installation (W05) | +29 wd | 1 |
| A3010 | L2 & L3 Exterior Glazing Installation (W08a, W08b) | +29 wd | 1 |
| A3260 CP | Seal Concrete Floor | +29 wd | 1 |
| A3430 | Seal concrete Floor | +29 wd | 1 |
| A3280 | New partition framing | +29 wd | 1 |
| A3330 | Door frames Installation | +29 wd | 1 |
| A3440 | New partition framing | +29 wd | 1 |
| A3560 | Seal concrete Floor | +29 wd | 1 |
| A3420 | Fire Spraying & Intumecent Paint | +29 wd | 1 |
| A3550 | Fire Spraying & Intumecent Paint | +29 wd | 1 |
| A3210 | Electrical and Mechanical Room | +29 wd | 1 |
| A3220 | Mech. and Elec. Equipment Installation | +29 wd | 1 |
| A2850 | Exterior Cladding Site Measure and Scanning | +29 wd | 1 |
| A2940 | Exterior Cladding Site Measure and Scanning | +29 wd | 1 |
| A3020 | Exterior Cladding Site Measure and Scanning | +29 wd | 1 |
| A3100 | Glazing Shop Fabrication | +29 wd | 1 |
| A3120 | Exterior Cladding Site Measure and Scanning | +29 wd | 1 |
| A3680 | Misc. Metals Mock-up | +29 wd | 1 |
| A2810 | Aluminum & Metal Panel Cladding Mock-up | +29 wd | 1 |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | +29 wd | 1 |
| A3250 CP | Fire Spraying & Intumecent Paint Inspection | +29 wd | 1 |
| A2960 | L2 & L3 Cladding Installation (EW2) | +28 wd | 1 |
| A2870 | L1, L2 & L3 Cladding Installation (EW2a) | +28 wd | 1 |
| A3040 | L2 & L3 Cladding Installation (EW2) | +28 wd | 1 |
| A3050 | Horizontal Shading Louvers | +28 wd | 1 |
| A2900 | Air Vapor Barrier Installation | +28 wd | 1 |
| A3140 | L1, L2 & L3 Cladding Installation (EW2, EW2A) | +28 wd | 1 |
| A3070 | L1, L2 & L3 Air Vapor Barrier Installation | +28 wd | 1 |
| A3490 | Door frames Installation | +28 wd | 1 |
| A3520 | Door and Hardware Installation | +28 wd | 1 |
| A3620 | Door frames Installation | +28 wd | 1 |
| A3570 | New wall partition framing | +28 wd | 1 |
| A3240 CP | Fire Spraying & Intumecent Paint | +28 wd | 1 |
| A1110 | Structural Reinforcement + Decking Shop Drawings | +28 wd | 1 |
| A3690 | Misc. Metals installation | +28 wd | 1 |
| A2860 | Exterior Cladding Shop Fabrication | +28 wd | 1 |
| A2910 | Glazing Site Measure and Scanning | +28 wd | 1 |
| A2950 | Exterior Cladding Shop Fabrication | +28 wd | 1 |
| A3000 | Glazing Shop Fabrication | +28 wd | 1 |
| A3030 | Exterior Cladding Shop Fabrication | +28 wd | 1 |
| A3130 | Exterior Cladding Shop Fabrication | +28 wd | 1 |
| A2440 | Formwork Remaining Pad Footing (Ramp) | +28 wd | 1 |
| A2970 CP | L2 & L3 Framing and Sheathing Installation | +27 wd | 1 |
| A3060 CP | L1, L2 & L3 Framing and Sheathing Installation | +27 wd | 1 |
| A2980 | L2 & L3 Air Vapor Barrier Installation | +27 wd | 1 |
| A2830 | Glazing Shop Fabrication | +27 wd | 1 |
| A2920 | Glazing Shop Fabrication | +27 wd | 1 |
| A2990 | Glazing Site Measure and Scanning | +27 wd | 1 |
| A3090 | Glazing Site Measure and Scanning | +27 wd | 1 |
| A3230 | Fire Spraying & Intumecent Paint Mock-up | +27 wd | 1 |
| A3410 | Painting | +26 wd | 1 |
| A3300 | Electrical, FA & Comms rough-ins | +26 wd | 1 |
| A3320 | Blocking Installation | +26 wd | 1 |
| A3350 | Gypsum board Installation | +26 wd | 1 |
| A3360 | Drywall Taping and Mudding | +26 wd | 1 |
| A3390 | Interior Aluminum/Glazing Screens Installation | +26 wd | 1 |
| A3370 | Door and Hardware Installation | +26 wd | 1 |
| A1290 | Suspended Metal Soffits | +26 wd | 1 |
| A1820 | Coiling Doors | +26 wd | 1 |
| A3810 | Install Controller at Machine Room | +26 wd | 1 |
| A3820 | Rails and Elevator Car installation | +26 wd | 1 |
| A3830 | Power to controller, Phone lines and Comms | +26 wd | 1 |
| A3840 | Elevator Testing and Commissioning | +26 wd | 1 |
| A3380 | Interior Aluminum/Glazing Screens Mock-up | +26 wd | 1 |
| A3340 | ACT Baffles Mock-ups | +26 wd | 1 |
| A3400 | Paint Mock-up | +26 wd | 1 |
| A1580 | 26 50 00 - Lighting Fixtures | +26 wd | 1 |
| A1870 | ACT & ACB | +25 wd | 1 |
| A2150 | 26 50 00 - Lighting Fixtures | +25 wd | 1 |
| A3290 | Mech. & Plumbing rough-ins | +24 wd | 1 |
| A3480 | Blocking Installation | +24 wd | 1 |
| A3610 | Blocking Installation | +24 wd | 1 |
| A3310 | Sprinkler Rough-ins | +24 wd | 1 |
| A3540 | Painting | +23 wd | 1 |
| A3450 | Mech. & Plumbing rough-ins | +23 wd | 1 |
| A3500 | Gypsum board Installation | +23 wd | 1 |
| A3460 | Electrical, FA & Comms rough-ins | +23 wd | 1 |
| A3510 | Drywall Taping and Mudding | +23 wd | 1 |
| A3530 | Interior Glazing Installation | +23 wd | 1 |
| A3590 | Electrical, FA & Comms rough-ins | +23 wd | 1 |
| A3580 | Mech. & Plumbing rough-ins | +23 wd | 1 |
| A3470 | Sprinkler Rough-ins | +23 wd | 1 |
| A3600 | Sprinkler Rough-ins | +23 wd | 1 |
| A1690 CP | Structural Reinforcement | +23 wd | 1 |
| A1460 | 23 25 00 - Water Treatment (R0) | +23 wd | 1 |
| A4240 CP | Minor Deficiencies & Touch-ups | +22 wd | 1 |
| A1700 | Cold-formed Metal Framing | +22 wd | 1 |
| A4260 CP | Total Completion | +21 wd | 1 |
| A4220 | Final Cleaning | +21 wd | 1 |
| A1120 | Cold-formed Metal Framing Shop Drawings | +21 wd | 1 |
| A1220 | Flush Wood Doors Sample | +21 wd | 1 |
| A1280 | ACT Data sheet and Sample | +21 wd | 1 |
| A1330 | Fall Arrest Anchors and Horizontal Lines | +21 wd | 1 |
| A4180 CP | Mechanical, Electrical and Elevator Commissioning | +21 wd | 1 |
| A4190 CP | Integrated Testing | +21 wd | 1 |
| A4250 CP | Ready-To-Take Over | +21 wd | 1 |
| A4230 | Close-out Documents & Training | +21 wd | 1 |
| A3750 | Washroom Partitions and Accessories Installation | +20 wd | 1 |
| A2640 | Install Roof Decking | +20 wd | 1 |
| A2630 | Install Roof Anchors | +20 wd | 1 |
| A3720 | Ceiling/Wall Fixtures Installation | +20 wd | 1 |
| A3740 | Millwork Installation | +20 wd | 1 |
| A3710 | Tiling and rubber flooring Installation | +20 wd | 1 |
| A3670 | Painting | +20 wd | 1 |
| A3770 | Corner Guards and Wall Protection Installation | +20 wd | 1 |
| A3660 | Interior Glazing Installation | +20 wd | 1 |
| A3650 | Door and Hardware Installation | +20 wd | 1 |
| A3630 | Gypsum board Installation | +20 wd | 1 |
| A3640 | Drywall Taping and Mudding | +20 wd | 1 |
| A1810 | Flush Wood Doors | +20 wd | 1 |
| A1920 | Fall Arrest Anchors and Horizontal Lines | +20 wd | 1 |
| A4210 CP | Occupancy | +20 wd | 1 |
| A3150 | Roof Parapet Framing | +20 wd | 1 |
| A3160 | Roof Penetration Layout | +20 wd | 1 |
| A3760 | Plumbing Washroom Fixtures Installation | +20 wd | 1 |
| A3730 | Millwork Mock-up | +20 wd | 1 |
| A3700 | Tiling & Rubber & Carpet Flooring Mock-up | +20 wd | 1 |
| A2500 | Install Rebar for Piers | +20 wd | 1 |
| A4200 CP | Substaintial Performance | +19 wd | 1 |
| A1230 | Coiling Doors | +17 wd | 1 |
| A4150 | New Exterior Paved Areas and Sidewalks | +15 wd | 1 |
| A4160 | Landscape Installations | +15 wd | 1 |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | +15 wd | 1 |
| A2520 | Form and Pour Foundation Piers | +15 wd | 1 |
| A1090 | Masonry and Mortar Samples & Data Sheets | +14 wd | 1 |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | +14 wd | 1 |
| A2530 | Backfilling to U/S of Grade Beams | +14 wd | 1 |
| A1670 | Masonry and Mortar | +13 wd | 1 |
| A2280 | Under Pinning Inspection | +13 wd | 1 |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | +13 wd | 1 |
| A3920 | Setup Temporary Hoarding | +12 wd | 1 |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | +12 wd | 1 |
| A1060 | Foundation Concrete Rebar Shop Drawing | +10 wd | 1 |
| A1050 | Ductbank Underpinning Drawing | +10 wd | 1 |
| A2550 | Form and Pour Grade Beams | +10 wd | 1 |
| A2560 | Below Grade Vapour Barrier Mock-up | +10 wd | 1 |
| A2570 | Footing Vapor Barrier & Insulation | +10 wd | 1 |
| A2610 | Erect Structural Steel | +9 wd | 1 |
| A2650 | Install Level 2 & 3 Decking | +9 wd | 1 |
| A2660 | Install Temporary Hoarding for Slab on Deck | +9 wd | 1 |
| A2620 | Structural Steel Inspection | +9 wd | 1 |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | +9 wd | 1 |
| A1210 | Interior Aluminum Screen | +8 wd | 1 |
| A1180 | Exterior Wall Cladding Shop Drawings | +7 wd | 1 |
| A1760 | Exterior Wall Cladding | +7 wd | 1 |
| A1800 | Interior Aluminum Screens | +7 wd | 1 |
| A1370 | 23 74 13 - Air Handling Units (R0) | +7 wd | 1 |
| A2670 | Rebar and Prep Work for Slab on Deck | +6 wd | 1 |
| A1080 | Bentonite Waterstop Data Sheet | +6 wd | 1 |
| A1660 | Bentonite Waterstop | +6 wd | 1 |
| A2680 | Concrete pour for slab on deck level 2 & 3 | +5 wd | 1 |
| A2690 | Final Grading and Vapor Barrier for SOG | +5 wd | 1 |
| A1510 | 23 00 00 - Wall Fin Heater | +5 wd | 1 |
| A1520 | 23 74 13 - Air Source Heat Pump | +5 wd | 1 |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | +5 wd | 1 |
| A2070 | 23 00 00 - Exhaust Fans | +5 wd | 1 |
| A2080 | 23 00 00 - Unit Heater | +5 wd | 1 |
| A2100 | 23 00 00 - Wall Fin Heater | +5 wd | 1 |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | +5 wd | 1 |
| A2710 | Concrete Pour and Curing for SOG | +3 wd | 1 |
| A2700 | Rebar Installation for SOG | +3 wd | 1 |
| A2220 | Testing and Inspection Cash Allowance Expenditure | +3 wd | 1 |
| A2420 | Form and Pour North Exit Stair | +3 wd | 1 |
| A1070 | Foundation Concrete Mix Design | +2 wd | 1 |
| A1650 | Foundation Concrete Mix Design | +2 wd | 1 |
| A1040 | Permit (Not Required Per Ontario Community College) | +1 wd | 1 |
| A1030 | IFC Drawings Released | +1 wd | 1 |
| A1150 | Built-up Roofing Shop Drawings | +1 wd | 1 |
| A1190 | Fire-resistive Material Data Sheet | +1 wd | 1 |
| A1730 | Built-up Roofing | +1 wd | 1 |
| A1770 | Fire-resistive Material | +1 wd | 1 |
| A2310 | Relocate FAA | -1 wd | 1 |
| A1380 | 23 21 23 - Pumps (R0) | -2 wd | 1 |
| A1420 | 23 57 00 - Heat Exchangers | -2 wd | 1 |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | -2 wd | 1 |
| A2290 | Existing Structure Under Pinning | -3 wd | 1 |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | -3 wd | 1 |
| A3190 | Hoisting Roof Equipment | -3 wd | 1 |
| A3200 | Roof Anchor System Installation | -3 wd | 1 |
| A1390 | 23 25 00 - Buffer Tanks | -3 wd | 1 |
| A1400 | 23 21 16 - Air Separator | -3 wd | 1 |
| A1410 | 23 21 16 - Expansion Tanks | -3 wd | 1 |
| A2110 | 23 74 13 - Air Source Heat Pump | -3 wd | 1 |
| A2370 | Bulk Excavation to U/S of Footings | -3 wd | 1 |
| A2380 | Bulk Excavation to U/S North Stair Footing | -3 wd | 1 |
| A2390 | Subgrade Inspection | -3 wd | 1 |
| A2400 | Subgrade Preparation | -3 wd | 1 |
| A2410 | Soil Bearing Capacity Inspection | -3 wd | 1 |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | -3 wd | 1 |
| A2450 | Rebar for Pad Footings | -3 wd | 1 |
| A2460 | Rebar Inspection | -3 wd | 1 |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | -3 wd | 1 |
| A2490 | Concrete Field Testing | -3 wd | 1 |
| A1340 | Hydraulic Lift Shop Drawings | -4 wd | 1 |
| A1930 | Hydraulic Lift | -4 wd | 1 |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | -5 wd | 1 |
| A4010 | Underground Plumbing Rough-ins | -6 wd | 1 |
| A2360 | Ductbank Shoring | -9 wd | 1 |
| A2190 | 28 31 00 - Fire Alarm | -9 wd | 1 |
| A1480 | 23 00 00 - Exhaust Fans (R0) | -10 wd | 1 |
| A1490 | 23 00 00 - Unit Heater | -10 wd | 1 |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | -12 wd | 1 |
| A1450 | 22 13 29 - Sump Pumps (R0) | -14 wd | 1 |
| A1640 | Foundation Concrete Rebar | -16 wd | 1 |
| A1630 | Ductbank Underpinning | -18 wd | 1 |
| A2480 | Concrete for Remaining Pad Footings (Ramp) | -22 wd | 1 |
| A2600 | Compaction Inspection | -24 wd | 1 |
| Code | Activity | Prior Duration | Later Duration | Growth |
|---|---|---|---|---|
| A4240 | Minor Deficiencies & Touch-ups | 10.0 wd | 11.0 wd | +1.0 wd |
| A4040 | MEP Rough-ins | 19.0 wd | 20.0 wd | +1.0 wd |
| A3240 | Fire Spraying & Intumecent Paint | 5.0 wd | 6.0 wd | +1.0 wd |
| A4200 | Substaintial Performance | 1.0 wd | 0.0 wd | +-1.0 wd |
| A4260 | Total Completion | 1.0 wd | 0.0 wd | +-1.0 wd |
| A4210 | Occupancy | 1.0 wd | 0.0 wd | +-1.0 wd |
| A4250 | Ready-To-Take Over | 1.0 wd | 0.0 wd | +-1.0 wd |
| A4060 | Blocking | 10.0 wd | 5.0 wd | +-5.0 wd |
| A2970 | L2 & L3 Framing and Sheathing Installation | 25.0 wd | 14.0 wd | +-11.0 wd |
| A4080 | Drywall/Sheathing Installation | 38.0 wd | 10.0 wd | +-28.0 wd |
| A1690 | Structural Reinforcement | 61.0 wd | 30.0 wd | +-31.0 wd |
| A3250 | Fire Spraying & Intumecent Paint Inspection | 228.0 wd | 1.0 wd | +-227.0 wd |
| Code | Activity | Prior Finish | Later Finish | Slip | Responsible Party | Cause Notes |
|---|---|---|---|---|---|---|
| A4070 CP | Frames installation | 02-Oct-2025 | 19-Jun-2026 | +180 wd | Contractor | Frame installation at the end of the delayed interior chain |
| A4060 CP | Blocking | 09-Oct-2025 | 12-Jun-2026 | +170 wd | Contractor | Blocking follows sprinkler rough-in in the interior chain |
| A4050 CP | Sprinkler Rough-ins | 09-Oct-2025 | 05-Jun-2026 | +165 wd | Contractor | Sprinkler rough-in follows partition framing; trade stacking on remobilization |
| A4030 CP | New Partition Framing | 25-Sep-2025 | 23-Apr-2026 | +145 wd | Contractor | Framing crew availability following remobilization |
| A3850 | Foundations | 22-Aug-2025 | 24-Feb-2026 | +127 wd | Owner | Differing site condition at the existing facade tie-in |
| A3860 | Concrete Vertical Piers | 29-Aug-2025 | 04-Mar-2026 | +127 wd | Owner | Follows delayed foundations at the tie-in |
| A3870 | Removal of Existing Facade for Tie In | 03-Sep-2025 | 06-Mar-2026 | +127 wd | Owner | Existing facade removal held for tie-in condition resolution |
| A3880 | Structural Steel erection including expansion plates | 10-Nov-2025 | 27-Mar-2026 | +95 wd | — | — |
| A3890 | Envelope | 15-Dec-2025 | 01-May-2026 | +95 wd | — | — |
| A3900 | Interior M&E Rough in | 14-Jan-2026 | 15-May-2026 | +85 wd | — | — |
| A1950 | 23 82 19 - Fan Coil Units | 25-Nov-2025 | 06-Mar-2026 | +69 wd | — | — |
| A3910 | Interior Finishes | 11-Feb-2026 | 19-May-2026 | +66 wd | — | — |
| A2730 | Stairs B Installation @ North Side | 21-Nov-2025 | 18-Feb-2026 | +60 wd | — | — |
| A1710 | Misc. Metals | 31-Oct-2025 | 27-Jan-2026 | +60 wd | — | — |
| A2720 | Tactile Attention Indicators Mock-up | 03-Nov-2025 | 28-Jan-2026 | +60 wd | — | — |
| A3270 | New Stair A Installation | 17-Nov-2025 | 10-Feb-2026 | +59 wd | — | — |
| A2540 | Compaction Inspection | 22-Aug-2025 | 14-Nov-2025 | +58 wd | — | — |
| A2090 | 23 52 16 - Heating Boilers | 28-Nov-2025 | 18-Feb-2026 | +55 wd | — | — |
| A3940 | Existing Slab Removal and Trenching | 23-Jun-2025 | 09-Sep-2025 | +54 wd | Contractor | Resequenced slab removal and trenching |
| A2050 | 23 25 00 - Water Treatment | 11-Nov-2025 | 28-Jan-2026 | +54 wd | — | — |
| A2180 | 26 09 23 - Lighting Control | 07-Nov-2025 | 23-Jan-2026 | +53 wd | — | — |
| A1130 | Misc. Metals Shop Drawings | 22-Jul-2025 | 02-Oct-2025 | +51 wd | Contractor | Late misc. metals submittal |
| A1500 | 23 52 16 - Heating Boilers | 22-Jul-2025 | 25-Sep-2025 | +46 wd | — | — |
| A2060 | 23 37 13 - Diffuser and Grilles | 04-Dec-2025 | 10-Feb-2026 | +46 wd | — | — |
| A1160 | TPO Roofing Shop Drawings | 23-Jun-2025 | 26-Aug-2025 | +45 wd | Owner | Owner-directed revision to the roofing assembly; resubmittal and re-review cycle |
| A1680 | Structural Steel | 29-Jul-2025 | 01-Oct-2025 | +45 wd | — | — |
| A1740 | TPO Roofing (Bridge) | 06-Aug-2025 | 08-Oct-2025 | +44 wd | — | — |
| A2580 | Underground Drainage | 08-Sep-2025 | 07-Nov-2025 | +43 wd | — | — |
| A2510 | Supply of Embedment & Ankors | 24-Jun-2025 | 22-Aug-2025 | +42 wd | — | — |
| A4040 CP | MEP Rough-ins | 25-Mar-2026 | 22-May-2026 | +41 wd | Contractor | MEP rough-in trade coordination; stacked trades after remobilization |
| A1970 | 23 21 23 - Pumps | 14-Nov-2025 | 12-Jan-2026 | +39 wd | — | — |
| A2590 | Backfilling to U/S of SOG | 19-Sep-2025 | 14-Nov-2025 | +39 wd | — | — |
| A2750 CP | L1, L2 & L3 Framing and Sheathing Installation | 05-Dec-2025 | 30-Jan-2026 | +38 wd | — | — |
| A2880 CP | L1, L2 & L3 Framing and Sheathing Installation | 19-Dec-2025 | 13-Feb-2026 | +38 wd | — | — |
| A2790 | L1, L2 & L3 Air Vapour Barrier Installation | 12-Dec-2025 | 06-Feb-2026 | +38 wd | — | — |
| A2820 | Glazing Site Measure and Scanning | 08-Dec-2025 | 02-Feb-2026 | +38 wd | — | — |
| A2740 | Cold-Formed Metal Framing Mock | 01-Dec-2025 | 26-Jan-2026 | +38 wd | — | — |
| A2780 | Above Grade Vapour Mock-up | 08-Dec-2025 | 02-Feb-2026 | +38 wd | — | — |
| A2800 | AVB Inspection | 08-Dec-2025 | 02-Feb-2026 | +38 wd | — | — |
| A3930 | Interior Demoilition | 09-Jul-2025 | 02-Sep-2025 | +38 wd | — | — |
| A1960 | 23 74 13 - Air Handling Units | 27-Mar-2026 | 15-May-2026 | +35 wd | — | — |
| A2120 | 20 05 10 - Electric Heat Tracing | 28-Nov-2025 | 19-Jan-2026 | +34 wd | — | — |
| A1590 | 26 09 23 - Lighting Control (R0) | 30-Jun-2025 | 18-Aug-2025 | +34 wd | — | — |
| A4080 CP | Drywall/Sheathing Installation | 19-May-2026 | 06-Jul-2026 | +33 wd | — | — |
| A4090 CP | Taping and mudding | 02-Jun-2026 | 20-Jul-2026 | +33 wd | — | — |
| A4110 CP | Tile and Rubber Flooring Installation | 12-Jun-2026 | 30-Jul-2026 | +33 wd | — | — |
| A4100 CP | Painting | 05-Jun-2026 | 23-Jul-2026 | +33 wd | — | — |
| A4120 CP | Final Terminations and Fixtures Installation | 19-Jun-2026 | 06-Aug-2026 | +33 wd | — | — |
| A2130 | 22 40 00 - Plumbing Fixtures | 02-Dec-2025 | 20-Jan-2026 | +33 wd | — | — |
| A4170 | Fire Alarm Verification | 07-Jul-2026 | 20-Aug-2026 | +32 wd | — | — |
| A3170 | Install Built-up Roof | 19-Dec-2025 | 03-Feb-2026 | +30 wd | — | — |
| A3180 | Roof Inspection | 19-Dec-2025 | 03-Feb-2026 | +30 wd | — | — |
| A3110 | L1, L2 & L3 Exterior Glazing Installation (W09a, W09b) | 26-Mar-2026 | 06-May-2026 | +29 wd | — | — |
| A2930 | L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) | 12-Mar-2026 | 22-Apr-2026 | +29 wd | — | — |
| A2840 | L1, L2, L3 Exterior Glazing Installation (W05) | 05-Mar-2026 | 15-Apr-2026 | +29 wd | — | — |
| A3010 | L2 & L3 Exterior Glazing Installation (W08a, W08b) | 05-Mar-2026 | 15-Apr-2026 | +29 wd | — | — |
| A3260 CP | Seal Concrete Floor | 04-Mar-2026 | 14-Apr-2026 | +29 wd | — | — |
| A3430 | Seal concrete Floor | 06-Mar-2026 | 16-Apr-2026 | +29 wd | — | — |
| A3280 | New partition framing | 18-Mar-2026 | 28-Apr-2026 | +29 wd | — | — |
| A3330 | Door frames Installation | 25-Mar-2026 | 05-May-2026 | +29 wd | — | — |
| A3440 | New partition framing | 01-Apr-2026 | 12-May-2026 | +29 wd | — | — |
| A3560 | Seal concrete Floor | 12-Mar-2026 | 22-Apr-2026 | +29 wd | — | — |
| A3420 | Fire Spraying & Intumecent Paint | 04-Mar-2026 | 14-Apr-2026 | +29 wd | — | — |
| A3550 | Fire Spraying & Intumecent Paint | 11-Mar-2026 | 21-Apr-2026 | +29 wd | — | — |
| A3210 | Electrical and Mechanical Room | 04-Mar-2026 | 14-Apr-2026 | +29 wd | — | — |
| A3220 | Mech. and Elec. Equipment Installation | 18-Mar-2026 | 28-Apr-2026 | +29 wd | — | — |
| A2850 | Exterior Cladding Site Measure and Scanning | 06-Mar-2026 | 16-Apr-2026 | +29 wd | — | — |
| A2940 | Exterior Cladding Site Measure and Scanning | 13-Mar-2026 | 23-Apr-2026 | +29 wd | — | — |
| A3020 | Exterior Cladding Site Measure and Scanning | 06-Mar-2026 | 16-Apr-2026 | +29 wd | — | — |
| A3100 | Glazing Shop Fabrication | 19-Mar-2026 | 29-Apr-2026 | +29 wd | — | — |
| A3120 | Exterior Cladding Site Measure and Scanning | 27-Mar-2026 | 07-May-2026 | +29 wd | — | — |
| A3680 | Misc. Metals Mock-up | 02-Apr-2026 | 13-May-2026 | +29 wd | — | — |
| A2810 | Aluminum & Metal Panel Cladding Mock-up | 06-Mar-2026 | 16-Apr-2026 | +29 wd | — | — |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | 25-Feb-2026 | 08-Apr-2026 | +29 wd | — | — |
| A3250 CP | Fire Spraying & Intumecent Paint Inspection | 25-Feb-2026 | 08-Apr-2026 | +29 wd | — | — |
| A2960 | L2 & L3 Cladding Installation (EW2) | 11-May-2026 | 19-Jun-2026 | +28 wd | — | — |
| A2870 | L1, L2 & L3 Cladding Installation (EW2a) | 04-May-2026 | 12-Jun-2026 | +28 wd | — | — |
| A3040 | L2 & L3 Cladding Installation (EW2) | 04-May-2026 | 12-Jun-2026 | +28 wd | — | — |
| A3050 | Horizontal Shading Louvers | 11-May-2026 | 19-Jun-2026 | +28 wd | — | — |
| A2900 | Air Vapor Barrier Installation | 13-Jan-2026 | 23-Feb-2026 | +28 wd | — | — |
| A3140 | L1, L2 & L3 Cladding Installation (EW2, EW2A) | 02-Jun-2026 | 13-Jul-2026 | +28 wd | — | — |
| A3070 | L1, L2 & L3 Air Vapor Barrier Installation | 25-Feb-2026 | 07-Apr-2026 | +28 wd | — | — |
| A3490 | Door frames Installation | 07-Apr-2026 | 15-May-2026 | +28 wd | — | — |
| A3520 | Door and Hardware Installation | 21-Apr-2026 | 01-Jun-2026 | +28 wd | — | — |
| A3620 | Door frames Installation | 23-Apr-2026 | 03-Jun-2026 | +28 wd | — | — |
| A3570 | New wall partition framing | 16-Apr-2026 | 27-May-2026 | +28 wd | — | — |
| A3240 CP | Fire Spraying & Intumecent Paint | 25-Feb-2026 | 07-Apr-2026 | +28 wd | Owner | Fire-spray application held for owner inspector availability |
| A1110 | Structural Reinforcement + Decking Shop Drawings | 23-Jun-2025 | 01-Aug-2025 | +28 wd | — | — |
| A3690 | Misc. Metals installation | 29-May-2026 | 09-Jul-2026 | +28 wd | — | — |
| A2860 | Exterior Cladding Shop Fabrication | 06-Apr-2026 | 14-May-2026 | +28 wd | — | — |
| A2910 | Glazing Site Measure and Scanning | 07-Jan-2026 | 17-Feb-2026 | +28 wd | — | — |
| A2950 | Exterior Cladding Shop Fabrication | 13-Apr-2026 | 22-May-2026 | +28 wd | — | — |
| A3000 | Glazing Shop Fabrication | 26-Feb-2026 | 08-Apr-2026 | +28 wd | — | — |
| A3030 | Exterior Cladding Shop Fabrication | 06-Apr-2026 | 14-May-2026 | +28 wd | — | — |
| A3130 | Exterior Cladding Shop Fabrication | 27-Apr-2026 | 05-Jun-2026 | +28 wd | — | — |
| A2440 | Formwork Remaining Pad Footing (Ramp) | 30-Jul-2025 | 09-Sep-2025 | +28 wd | — | — |
| A2970 CP | L2 & L3 Framing and Sheathing Installation | 27-Jan-2026 | 09-Mar-2026 | +27 wd | — | — |
| A3060 CP | L1, L2 & L3 Framing and Sheathing Installation | 18-Feb-2026 | 30-Mar-2026 | +27 wd | — | — |
| A2980 | L2 & L3 Air Vapor Barrier Installation | 03-Feb-2026 | 16-Mar-2026 | +27 wd | — | — |
| A2830 | Glazing Shop Fabrication | 21-Jan-2026 | 02-Mar-2026 | +27 wd | — | — |
| A2920 | Glazing Shop Fabrication | 04-Feb-2026 | 17-Mar-2026 | +27 wd | — | — |
| A2990 | Glazing Site Measure and Scanning | 28-Jan-2026 | 10-Mar-2026 | +27 wd | — | — |
| A3090 | Glazing Site Measure and Scanning | 19-Feb-2026 | 31-Mar-2026 | +27 wd | — | — |
| A3230 | Fire Spraying & Intumecent Paint Mock-up | 19-Feb-2026 | 31-Mar-2026 | +27 wd | — | — |
| A3410 | Painting | 07-May-2026 | 15-Jun-2026 | +26 wd | — | — |
| A3300 | Electrical, FA & Comms rough-ins | 06-Apr-2026 | 12-May-2026 | +26 wd | — | — |
| A3320 | Blocking Installation | 09-Apr-2026 | 15-May-2026 | +26 wd | — | — |
| A3350 | Gypsum board Installation | 16-Apr-2026 | 25-May-2026 | +26 wd | — | — |
| A3360 | Drywall Taping and Mudding | 30-Apr-2026 | 08-Jun-2026 | +26 wd | — | — |
| A3390 | Interior Aluminum/Glazing Screens Installation | 07-May-2026 | 15-Jun-2026 | +26 wd | — | — |
| A3370 | Door and Hardware Installation | 07-May-2026 | 15-Jun-2026 | +26 wd | — | — |
| A1290 | Suspended Metal Soffits | 29-Jul-2025 | 04-Sep-2025 | +26 wd | — | — |
| A1820 | Coiling Doors | 05-Dec-2025 | 14-Jan-2026 | +26 wd | — | — |
| A3810 | Install Controller at Machine Room | 08-May-2026 | 16-Jun-2026 | +26 wd | — | — |
| A3820 | Rails and Elevator Car installation | 25-May-2026 | 30-Jun-2026 | +26 wd | — | — |
| A3830 | Power to controller, Phone lines and Comms | 01-Jun-2026 | 08-Jul-2026 | +26 wd | — | — |
| A3840 | Elevator Testing and Commissioning | 22-Jun-2026 | 29-Jul-2026 | +26 wd | — | — |
| A3380 | Interior Aluminum/Glazing Screens Mock-up | 01-May-2026 | 09-Jun-2026 | +26 wd | — | — |
| A3340 | ACT Baffles Mock-ups | 10-Apr-2026 | 19-May-2026 | +26 wd | — | — |
| A3400 | Paint Mock-up | 05-May-2026 | 11-Jun-2026 | +26 wd | — | — |
| A1580 | 26 50 00 - Lighting Fixtures | 11-Jul-2025 | 18-Aug-2025 | +26 wd | — | — |
| A1870 | ACT & ACB | 11-Sep-2025 | 17-Oct-2025 | +25 wd | — | — |
| A2150 | 26 50 00 - Lighting Fixtures | 19-Nov-2025 | 25-Dec-2025 | +25 wd | — | — |
| A3290 | Mech. & Plumbing rough-ins | 01-Apr-2026 | 05-May-2026 | +24 wd | — | — |
| A3480 | Blocking Installation | 23-Apr-2026 | 28-May-2026 | +24 wd | — | — |
| A3610 | Blocking Installation | 04-May-2026 | 08-Jun-2026 | +24 wd | — | — |
| A3310 | Sprinkler Rough-ins | 01-Apr-2026 | 05-May-2026 | +24 wd | — | — |
| A3540 | Painting | 20-May-2026 | 22-Jun-2026 | +23 wd | — | — |
| A3450 | Mech. & Plumbing rough-ins | 16-Apr-2026 | 20-May-2026 | +23 wd | — | — |
| A3500 | Gypsum board Installation | 30-Apr-2026 | 03-Jun-2026 | +23 wd | — | — |
| A3460 | Electrical, FA & Comms rough-ins | 20-Apr-2026 | 22-May-2026 | +23 wd | — | — |
| A3510 | Drywall Taping and Mudding | 14-May-2026 | 17-Jun-2026 | +23 wd | — | — |
| A3530 | Interior Glazing Installation | 22-May-2026 | 24-Jun-2026 | +23 wd | — | — |
| A3590 | Electrical, FA & Comms rough-ins | 27-Apr-2026 | 29-May-2026 | +23 wd | — | — |
| A3580 | Mech. & Plumbing rough-ins | 09-Apr-2026 | 12-May-2026 | +23 wd | — | — |
| A3470 | Sprinkler Rough-ins | 16-Apr-2026 | 20-May-2026 | +23 wd | — | — |
| A3600 | Sprinkler Rough-ins | 09-Apr-2026 | 12-May-2026 | +23 wd | — | — |
| A1690 CP | Structural Reinforcement | 18-Sep-2025 | 22-Oct-2025 | +23 wd | — | — |
| A1460 | 23 25 00 - Water Treatment (R0) | 10-Jul-2025 | 12-Aug-2025 | +23 wd | — | — |
| A4240 CP | Minor Deficiencies & Touch-ups | 28-Aug-2026 | 30-Sep-2026 | +22 wd | Contractor | Deficiency and touch-up re-work extended by finishing crew quality issues |
| A1700 | Cold-formed Metal Framing | 08-Jul-2025 | 07-Aug-2025 | +22 wd | — | — |
| A4260 CP | Total Completion | 31-Aug-2026 | 30-Sep-2026 | +21 wd | — | — |
| A4220 | Final Cleaning | 05-Aug-2026 | 03-Sep-2026 | +21 wd | — | — |
| A1120 | Cold-formed Metal Framing Shop Drawings | 23-Jun-2025 | 23-Jul-2025 | +21 wd | — | — |
| A1220 | Flush Wood Doors Sample | 29-Jul-2025 | 27-Aug-2025 | +21 wd | — | — |
| A1280 | ACT Data sheet and Sample | 29-Jul-2025 | 27-Aug-2025 | +21 wd | — | — |
| A1330 | Fall Arrest Anchors and Horizontal Lines | 29-Jul-2025 | 27-Aug-2025 | +21 wd | — | — |
| A4180 CP | Mechanical, Electrical and Elevator Commissioning | 29-Jul-2026 | 27-Aug-2026 | +21 wd | — | — |
| A4190 CP | Integrated Testing | 12-Aug-2026 | 11-Sep-2026 | +21 wd | — | — |
| A4250 CP | Ready-To-Take Over | 31-Aug-2026 | 30-Sep-2026 | +21 wd | — | — |
| A4230 | Close-out Documents & Training | 05-Aug-2026 | 03-Sep-2026 | +21 wd | — | — |
| A3750 | Washroom Partitions and Accessories Installation | 08-Jul-2026 | 05-Aug-2026 | +20 wd | — | — |
| A2640 | Install Roof Decking | 14-Nov-2025 | 12-Dec-2025 | +20 wd | — | — |
| A2630 | Install Roof Anchors | 07-Nov-2025 | 05-Dec-2025 | +20 wd | — | — |
| A3720 | Ceiling/Wall Fixtures Installation | 30-Jun-2026 | 29-Jul-2026 | +20 wd | — | — |
| A3740 | Millwork Installation | 23-Jun-2026 | 22-Jul-2026 | +20 wd | — | — |
| A3710 | Tiling and rubber flooring Installation | 30-Jun-2026 | 29-Jul-2026 | +20 wd | — | — |
| A3670 | Painting | 16-Jun-2026 | 15-Jul-2026 | +20 wd | — | — |
| A3770 | Corner Guards and Wall Protection Installation | 06-Jul-2026 | 03-Aug-2026 | +20 wd | — | — |
| A3660 | Interior Glazing Installation | 09-Jun-2026 | 08-Jul-2026 | +20 wd | — | — |
| A3650 | Door and Hardware Installation | 16-Jun-2026 | 15-Jul-2026 | +20 wd | — | — |
| A3630 | Gypsum board Installation | 19-May-2026 | 16-Jun-2026 | +20 wd | — | — |
| A3640 | Drywall Taping and Mudding | 02-Jun-2026 | 30-Jun-2026 | +20 wd | — | — |
| A1810 | Flush Wood Doors | 14-Nov-2025 | 12-Dec-2025 | +20 wd | — | — |
| A1920 | Fall Arrest Anchors and Horizontal Lines | 24-Oct-2025 | 21-Nov-2025 | +20 wd | — | — |
| A4210 CP | Occupancy | 13-Aug-2026 | 11-Sep-2026 | +20 wd | — | — |
| A3150 | Roof Parapet Framing | 21-Nov-2025 | 19-Dec-2025 | +20 wd | — | — |
| A3160 | Roof Penetration Layout | 18-Nov-2025 | 16-Dec-2025 | +20 wd | — | — |
| A3760 | Plumbing Washroom Fixtures Installation | 08-Jul-2026 | 05-Aug-2026 | +20 wd | — | — |
| A3730 | Millwork Mock-up | 17-Jun-2026 | 16-Jul-2026 | +20 wd | — | — |
| A3700 | Tiling & Rubber & Carpet Flooring Mock-up | 17-Jun-2026 | 16-Jul-2026 | +20 wd | — | — |
| A2500 | Install Rebar for Piers | 08-Aug-2025 | 08-Sep-2025 | +20 wd | — | — |
| A4200 CP | Substaintial Performance | 14-Aug-2026 | 11-Sep-2026 | +19 wd | — | — |
| A1230 | Coiling Doors | 29-Jul-2025 | 21-Aug-2025 | +17 wd | — | — |
| A4150 | New Exterior Paved Areas and Sidewalks | 08-May-2026 | 01-Jun-2026 | +15 wd | — | — |
| A4160 | Landscape Installations | 25-May-2026 | 15-Jun-2026 | +15 wd | — | — |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | 22-Jul-2025 | 12-Aug-2025 | +15 wd | — | — |
| A2520 | Form and Pour Foundation Piers | 15-Aug-2025 | 08-Sep-2025 | +15 wd | — | — |
| A1090 | Masonry and Mortar Samples & Data Sheets | 29-Jul-2025 | 18-Aug-2025 | +14 wd | — | — |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | 23-Jun-2025 | 14-Jul-2025 | +14 wd | — | — |
| A2530 | Backfilling to U/S of Grade Beams | 22-Aug-2025 | 12-Sep-2025 | +14 wd | — | — |
| A1670 | Masonry and Mortar | 06-Aug-2025 | 25-Aug-2025 | +13 wd | — | — |
| A2280 | Under Pinning Inspection | 24-Jun-2025 | 14-Jul-2025 | +13 wd | — | — |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | 28-Jul-2025 | 14-Aug-2025 | +13 wd | — | — |
| A3920 | Setup Temporary Hoarding | 17-Jun-2025 | 04-Jul-2025 | +12 wd | — | — |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | 11-Jul-2025 | 29-Jul-2025 | +12 wd | — | — |
| A1060 | Foundation Concrete Rebar Shop Drawing | 23-Jun-2025 | 08-Jul-2025 | +10 wd | — | — |
| A1050 | Ductbank Underpinning Drawing | 16-Jun-2025 | 30-Jun-2025 | +10 wd | — | — |
| A2550 | Form and Pour Grade Beams | 08-Sep-2025 | 22-Sep-2025 | +10 wd | — | — |
| A2560 | Below Grade Vapour Barrier Mock-up | 09-Sep-2025 | 23-Sep-2025 | +10 wd | — | — |
| A2570 | Footing Vapor Barrier & Insulation | 12-Sep-2025 | 26-Sep-2025 | +10 wd | — | — |
| A2610 | Erect Structural Steel | 20-Oct-2025 | 31-Oct-2025 | +9 wd | — | — |
| A2650 | Install Level 2 & 3 Decking | 03-Nov-2025 | 14-Nov-2025 | +9 wd | — | — |
| A2660 | Install Temporary Hoarding for Slab on Deck | 03-Nov-2025 | 14-Nov-2025 | +9 wd | — | — |
| A2620 | Structural Steel Inspection | 20-Oct-2025 | 31-Oct-2025 | +9 wd | — | — |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 24-Jun-2025 | 08-Jul-2025 | +9 wd | — | — |
| A1210 | Interior Aluminum Screen | 29-Jul-2025 | 08-Aug-2025 | +8 wd | — | — |
| A1180 | Exterior Wall Cladding Shop Drawings | 13-Aug-2025 | 22-Aug-2025 | +7 wd | — | — |
| A1760 | Exterior Wall Cladding | 07-Nov-2025 | 18-Nov-2025 | +7 wd | — | — |
| A1800 | Interior Aluminum Screens | 05-Dec-2025 | 16-Dec-2025 | +7 wd | — | — |
| A1370 | 23 74 13 - Air Handling Units (R0) | 10-Jul-2025 | 21-Jul-2025 | +7 wd | — | — |
| A2670 | Rebar and Prep Work for Slab on Deck | 10-Nov-2025 | 18-Nov-2025 | +6 wd | — | — |
| A1080 | Bentonite Waterstop Data Sheet | 23-Jun-2025 | 02-Jul-2025 | +6 wd | — | — |
| A1660 | Bentonite Waterstop | 30-Jun-2025 | 09-Jul-2025 | +6 wd | — | — |
| A2680 | Concrete pour for slab on deck level 2 & 3 | 13-Nov-2025 | 20-Nov-2025 | +5 wd | — | — |
| A2690 | Final Grading and Vapor Barrier for SOG | 18-Nov-2025 | 25-Nov-2025 | +5 wd | — | — |
| A1510 | 23 00 00 - Wall Fin Heater | 05-Aug-2025 | 12-Aug-2025 | +5 wd | — | — |
| A1520 | 23 74 13 - Air Source Heat Pump | 10-Jul-2025 | 17-Jul-2025 | +5 wd | — | — |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | 24-Jul-2025 | 31-Jul-2025 | +5 wd | — | — |
| A2070 | 23 00 00 - Exhaust Fans | 11-Dec-2025 | 18-Dec-2025 | +5 wd | — | — |
| A2080 | 23 00 00 - Unit Heater | 11-Dec-2025 | 18-Dec-2025 | +5 wd | — | — |
| A2100 | 23 00 00 - Wall Fin Heater | 11-Dec-2025 | 18-Dec-2025 | +5 wd | — | — |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 07-Nov-2025 | 14-Nov-2025 | +5 wd | — | — |
| A2710 | Concrete Pour and Curing for SOG | 28-Nov-2025 | 03-Dec-2025 | +3 wd | — | — |
| A2700 | Rebar Installation for SOG | 21-Nov-2025 | 26-Nov-2025 | +3 wd | — | — |
| A2220 | Testing and Inspection Cash Allowance Expenditure | 26-Jun-2025 | 02-Jul-2025 | +3 wd | — | — |
| A2420 | Form and Pour North Exit Stair | 25-Sep-2025 | 30-Sep-2025 | +3 wd | — | — |
| A1070 | Foundation Concrete Mix Design | 23-Jun-2025 | 25-Jun-2025 | +2 wd | — | — |
| A1650 | Foundation Concrete Mix Design | 25-Jun-2025 | 27-Jun-2025 | +2 wd | — | — |
| A1040 | Permit (Not Required Per Ontario Community College) | 15-May-2025 | 16-May-2025 | +1 wd | — | — |
| A1030 | IFC Drawings Released | 14-May-2025 | 15-May-2025 | +1 wd | — | — |
| A1150 | Built-up Roofing Shop Drawings | 08-Jul-2025 | 09-Jul-2025 | +1 wd | — | — |
| A1190 | Fire-resistive Material Data Sheet | 08-Jul-2025 | 09-Jul-2025 | +1 wd | — | — |
| A1730 | Built-up Roofing | 20-Aug-2025 | 21-Aug-2025 | +1 wd | — | — |
| A1770 | Fire-resistive Material | 06-Aug-2025 | 07-Aug-2025 | +1 wd | — | — |
| A2230 | Ontario Community College Auto Show | 09-Jun-2025 | 09-Jun-2025 | 0 wd | — | — |
| A2320 | Demolition of Existing Vestibule F100 | 25-Jun-2025 | 25-Jun-2025 | 0 wd | — | — |
| A1170 | Air Barrier System Data Sheet and Mockup | 08-Jul-2025 | 08-Jul-2025 | 0 wd | — | — |
| A2310 | Relocate FAA | 18-Jun-2025 | 17-Jun-2025 | -1 wd | — | — |
| A1380 | 23 21 23 - Pumps (R0) | 08-Jul-2025 | 04-Jul-2025 | -2 wd | — | — |
| A1420 | 23 57 00 - Heat Exchangers | 07-Jul-2025 | 03-Jul-2025 | -2 wd | — | — |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 24-Jul-2025 | 22-Jul-2025 | -2 wd | — | — |
| A2290 | Existing Structure Under Pinning | 18-Jul-2025 | 15-Jul-2025 | -3 wd | — | — |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | 16-Jul-2025 | 11-Jul-2025 | -3 wd | — | — |
| A3190 | Hoisting Roof Equipment | 17-Jun-2026 | 12-Jun-2026 | -3 wd | — | — |
| A3200 | Roof Anchor System Installation | 24-Jun-2026 | 19-Jun-2026 | -3 wd | — | — |
| A1390 | 23 25 00 - Buffer Tanks | 08-Jul-2025 | 03-Jul-2025 | -3 wd | — | — |
| A1400 | 23 21 16 - Air Separator | 08-Jul-2025 | 03-Jul-2025 | -3 wd | — | — |
| A1410 | 23 21 16 - Expansion Tanks | 08-Jul-2025 | 03-Jul-2025 | -3 wd | — | — |
| A2110 | 23 74 13 - Air Source Heat Pump | 10-Jun-2026 | 05-Jun-2026 | -3 wd | — | — |
| A2370 | Bulk Excavation to U/S of Footings | 25-Jul-2025 | 22-Jul-2025 | -3 wd | — | — |
| A2380 | Bulk Excavation to U/S North Stair Footing | 28-Jul-2025 | 23-Jul-2025 | -3 wd | — | — |
| A2390 | Subgrade Inspection | 25-Jul-2025 | 22-Jul-2025 | -3 wd | — | — |
| A2400 | Subgrade Preparation | 28-Jul-2025 | 23-Jul-2025 | -3 wd | — | — |
| A2410 | Soil Bearing Capacity Inspection | 29-Jul-2025 | 24-Jul-2025 | -3 wd | — | — |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | 28-Jul-2025 | 23-Jul-2025 | -3 wd | — | — |
| A2450 | Rebar for Pad Footings | 29-Jul-2025 | 24-Jul-2025 | -3 wd | — | — |
| A2460 | Rebar Inspection | 30-Jul-2025 | 25-Jul-2025 | -3 wd | — | — |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | 31-Jul-2025 | 28-Jul-2025 | -3 wd | — | — |
| A2490 | Concrete Field Testing | 31-Jul-2025 | 28-Jul-2025 | -3 wd | — | — |
| A1340 | Hydraulic Lift Shop Drawings | 15-Jul-2025 | 09-Jul-2025 | -4 wd | — | — |
| A1930 | Hydraulic Lift | 05-Dec-2025 | 01-Dec-2025 | -4 wd | — | — |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | 24-Jun-2025 | 17-Jun-2025 | -5 wd | — | — |
| A4010 | Underground Plumbing Rough-ins | 23-Jul-2025 | 15-Jul-2025 | -6 wd | — | — |
| A2360 | Ductbank Shoring | 21-Jul-2025 | 08-Jul-2025 | -9 wd | — | — |
| A2190 | 28 31 00 - Fire Alarm | 07-Nov-2025 | 27-Oct-2025 | -9 wd | — | — |
| A1480 | 23 00 00 - Exhaust Fans (R0) | 05-Aug-2025 | 22-Jul-2025 | -10 wd | — | — |
| A1490 | 23 00 00 - Unit Heater | 05-Aug-2025 | 22-Jul-2025 | -10 wd | — | — |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 30-Apr-2026 | 14-Apr-2026 | -12 wd | — | — |
| A1450 | 22 13 29 - Sump Pumps (R0) | 20-Jun-2025 | 02-Jun-2025 | -14 wd | — | — |
| A1640 | Foundation Concrete Rebar | 08-Jul-2025 | 13-Jun-2025 | -16 wd | — | — |
| A1630 | Ductbank Underpinning | 23-Jun-2025 | 28-May-2025 | -18 wd | — | — |
| A2480 | Concrete for Remaining Pad Footings (Ramp) | 01-Aug-2025 | 02-Jul-2025 | -22 wd | — | — |
| A2600 | Compaction Inspection | 19-Sep-2025 | 15-Aug-2025 | -24 wd | — | — |