Larchmere Library and Community Hub (Demo Data) 1 window analyzed: Baseline → Current
Summary of Findings
Completion moved 86 working days later than the baseline, from 1 May 2026 to 3 September 2026, in one window. Of those, 55 working days are attributable to the Owner, 28 to the Contractor and 3 are not explained by any attribution rule.
Each figure is measured on the schedules themselves: progress against the earlier plan, then the changes each update made, every change by how far it moves the finish.
The Owner's causes account for 55 of the 86 working days
1 May 2026Forecast finish
3 September 2026
The update was filed at data date 5 August 2025 but records actual progress up to 14 October 2025, so the analysis reads it at 15 October 2025, as section 4 sets out.
The update has negative float, so its critical path is read as the driving path into the forecast finish; section 4 explains.
Why the Finish Moved
Every change between the schedules was measured for how far it moves the finish. Grouped by cause, the Owner's five causes account for 55 working days, the Contractor's five causes account for 28 working days and 3 working days are not explained by any rule.
Causes Attributable to the Owner
| Cause | Working days | Work running late | Update changes |
|---|---|---|---|
| Curtain wall: RFI-14 anchor and sill revision adds field work at every floor | 29 | 17 | 12 |
| Owner special inspection of the Level 2 connections, added in the update | 8 | 0 | 8 |
| Follows the Level 2 erection held for CD-03 | 7 | 7 | 0 |
| Owner audio-visual rough-in (work by others) inserted ahead of drywall | 6 | 0 | 6 |
| Envelope follows the roof steel held for CD-03 | 5 | 5 | 0 |
| Total | 55 |
Causes Attributable to the Contractor
| Cause | Working days | Work running late | Update changes |
|---|---|---|---|
| Level 2 finishing re-planned: flooring crew shared with another project | 8 | 0 | 8 |
| Envelope follows the roof steel delayed by the Zone B crew | 7 | 7 | 0 |
| Ceiling scope re-planned into two activities by the contractor | 6 | 0 | 6 |
| Follows Level 2 Zone B and its short-handed crew | 4 | 4 | 0 |
| Punch list activities added by the contractor | 3 | 0 | 3 |
| Total | 28 |
Not Explained by Any Rule
The remaining 3 working days come from progress on work no attribution rule covers. They are shown as unexplained rather than shared among the parties; a rule for the activities behind them would assign them.
Exhibit A-03 lists every cause in each window to a tenth of a working day, and the window detail lists the critical-path activities whose durations changed.
Who Is Responsible
55 working days are attributable to the Owner, 28 to the Contractor and 3 are not explained by any attribution rule. Each change takes the party of the attribution rule its activity matches, so responsibility follows the project record the rules are written from.
| Party | Working days | Share of the movement |
|---|---|---|
| Owner | 55 | 64% |
| Contractor | 28 | 33% |
| Not explained | 3 | 3% |
| Total | 86 | 100% |
No working days are assigned to concurrent delay.
The Attribution Rules
80 rules name the activities each party is responsible for. Grouped by cause they read as below; a cause whose activities did not move the finish carries no working days.
| Party | Cause | Rules | Moved the finish |
|---|---|---|---|
| Owner | Curtain wall: RFI-14 anchor and sill revision adds field work at every floor | 4 | 29 working days |
| Owner | Owner special inspection of the Level 2 connections, added in the update | 1 | 8 working days |
| Owner | Follows the Level 2 erection held for CD-03 | 2 | 7 working days |
| Owner | Owner audio-visual rough-in (work by others) inserted ahead of drywall | 1 | 6 working days |
| Owner | Envelope follows the roof steel held for CD-03 | 1 | 5 working days |
| Owner | CD-03 atrium framing revision: added steel detailed and fabricated before Level 2 erection | 1 | did not move the finish |
| Owner | Drywall waits on the weathertight date set by the envelope | 3 | did not move the finish |
| Owner | Level 2 erection held for the CD-03 atrium steel | 1 | did not move the finish |
| Owner | Unsuitable soil at Zone C; CD-02 engineered fill and re-inspection | 4 | did not move the finish |
| Contractor | Level 2 finishing re-planned: flooring crew shared with another project | 3 | 8 working days |
| Contractor | Envelope follows the roof steel delayed by the Zone B crew | 2 | 7 working days |
| Contractor | Ceiling scope re-planned into two activities by the contractor | 36 | 6 working days |
| Contractor | Follows Level 2 Zone B and its short-handed crew | 6 | 4 working days |
| Contractor | Punch list activities added by the contractor | 3 | 3 working days |
| Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope | 8 | did not move the finish |
| Contractor | Shaft masonry rework after a failed plumb check | 1 | did not move the finish |
| Contractor | Short-handed steel erection crew, Level 2 Zone B | 1 | did not move the finish |
| Contractor | Structural steel shop drawings submitted late by the fabricator | 2 | did not move the finish |
How Far the Figures Can Be Relied On
The figures are measured on the schedules themselves, change by change, and they add up to the whole movement of the finish.
Method: AACE 29R-03 MIP 3.3 (observational, dynamic, contemporaneous as-is). Each window is split in two, as AACE RP 29R-03 §2.3.D.2 describes: first the earlier schedule is progressed to the later data date on its own plan, then the later schedule’s actual progress and its own changes are applied: added and removed work, revised durations, calendars, constraints and logic. Each change is measured by how far it moves the finish, averaged over every order in which the changes could be applied, so the parts add up to the whole.
Allocation Coverage
96.5% of the movement is allocated to a party; 3 working days are not explained by any rule.
How the Schedules Were Read
Data date corrected.
This update has actual dates after its data date of 05-Aug-2025 00:00.
The latest is A2910's actual finish, 14-Oct-2025 17:00, so this report moves the data date to the start of the next day, 15-Oct-2025, and reschedules the update as P6 does.
62 activities had actual dates after 05-Aug-2025.
102 activities that hadn't started were forecast to start before 15-Oct-2025; they now start on or after it.
The file reports a finish of 24-Jun-2026.
At the corrected data date its logic gives 03-Sep-2026, 49 working days after the file's finish on the project calendar. This report uses 03-Sep-2026.
Critical path: the driving path.
The update of 15-Oct-2025 has negative float.
It measures float to its Must Finish By of 01-May-2026, and its logic finishes on 03-Sep-2026, and constraints hold dates earlier than its logic allows (Start On on 1 activity), so 171 unfinished activities have total float below zero.
Total float of zero or less marks 171 activities, but only 50 of them are on the driving path: the chains of driving relationships into the forecast finish, where each predecessor leaves no working day before its successor.
The other 121 sit on paths that can slip 1 to 77 working days before they move the forecast finish, so a delay to one of them moves the finish only once it uses up that margin.
This report counts an activity in this update as critical only when it is unfinished and on the driving path, and where chains tie, all of them count.
The baseline has no negative float, so its critical activities are those with total float of zero or less, and the newly and no-longer critical lists for the window from the baseline to the update of 15-Oct-2025 compare the two tests.
The attribution measures the movement of the finish cause by cause on the schedule itself, progress first and then the changes the update made, so work off the driving path carries a share only where its progress or change moves the finish, alone or with other changes.
Basis of Measurement
The Evidence
The exhibits behind these findings follow in full, each under its drawing code:
- A-01Windows Overview
- A-02Window Shift Trend
- A-03Cumulative Attribution Summary: every cause in each window
- A-04Concurrent Delay Matrix
- A-05Slip Velocity and Acceleration
- A-06Worked Versus On-Time Execution
- A-07Float Burndown Across Windows
- A-08Cumulative Activity Slip Register
- A-09Window 1 Detail: Baseline → Current
- A-10Provenance and Method
Windows Overview
per-window shift and cumulative vs baseline, working days| Window | Period | Shift (wd) | Cumulative vs Baseline (wd) | CP Activities | CP Duration Changes | Slipped Activities |
|---|---|---|---|---|---|---|
| Baseline → Current | 05-May-2025 → 15-Oct-2025 | +86 wd | +86 wd | 50 | 7 | 242 |
Criticality test: TF ≤ 0, or the driving path in a schedule with negative float.
Window Shift Trend
signed completion shift per window (working days)Cumulative Attribution Summary
party share of project slip-daysEach window is split in two. Progress against the plan is what the work actually done did to the finish, measured against the earlier schedule statused to its own plan. Changes the update made are its added and removed activities, changed durations of work not yet started, and changed links. Every change is measured on the schedule and carries the party of the attribution rule its activity matches; a cause whose delay overlaps another shares the overlap evenly. Changes no rule covers are shown as Unattributed, not shared among the parties. Each window adds up to its own movement.
| Cause | Party | Working days later |
|---|---|---|
| Progress against the plan | 43.0 | |
| Curtain wall: RFI-14 anchor and sill revision adds field work at every floor | Owner | 16.9 |
| Follows the Level 2 erection held for CD-03 | Owner | 7.1 |
| Envelope follows the roof steel delayed by the Zone B crew | Contractor | 6.4 |
| Envelope follows the roof steel held for CD-03 | Owner | 5.6 |
| Follows Level 2 Zone B and its short-handed crew | Contractor | 4.3 |
| Progress on work no attribution rule covers | Unattributed | 2.7 |
| Changes the update made | 43.0 | |
| Curtain wall: RFI-14 anchor and sill revision adds field work at every floor | Owner | 11.9 |
| Level 2 finishing re-planned: flooring crew shared with another project | Contractor | 8.1 |
| Owner special inspection of the Level 2 connections, added in the update | Owner | 7.9 |
| Ceiling scope re-planned into two activities by the contractor | Contractor | 6.3 |
| Owner audio-visual rough-in (work by others) inserted ahead of drywall | Owner | 5.7 |
| Punch list activities added by the contractor | Contractor | 3.1 |
Concurrent Delay Matrix
per-window × per-party attribution grid| Window | Period | Owner | Contractor | Concurrent | Force Majeure | Unattributed | Window Shift (wd) | Finish Driver |
|---|---|---|---|---|---|---|---|---|
| Baseline → Current | 05-May-2025 → 15-Oct-2025 | +55 wd | +28 wd | 0 | 0 | +3 wd | +86 wd | A1050 early_end_date |
| Cumulative | project totals | +55 wd | +28 wd | 0 wd | 0 wd | +3 wd | +86 wd | 0 |
Slip Velocity & Acceleration
per-window slip-rate trend| Window | Period | Duration (wd) | Shift (wd) | Velocity (wd/wd) | Δ Acceleration | Midpoint Date | Half-Period Slip (wd) |
|---|---|---|---|---|---|---|---|
| Baseline → Current | 05-May-2025 → 15-Oct-2025 | 112 wd | +86 wd | +0.768 | 25-Jul-2025 | +43.0 wd |
WOET: worked versus on-time execution timeline
4-state day classification| Code | Activity | Baseline Period | Actual Period | Progress (wd) | Gain (wd) | Extended (wd) | Void (wd) |
|---|---|---|---|---|---|---|---|
| A2240 IN-PROGRESS | Elevator shaft masonry | 02-Sep-2025 to 17-Sep-2025 | 25-Aug-2025, open | 12 wd | 5 wd | 19 wd | 0 wd |
| A1230 | Curtain wall and windows: fabricate and deliver | 17-Jun-2025 to 27-Aug-2025 | 14-Jul-2025 to 23-Sep-2025 | 32 wd | 0 wd | 18 wd | 18 wd |
| A1220 | Curtain wall and windows shop drawings: consultant review | 03-Jun-2025 to 16-Jun-2025 | 03-Jun-2025 to 11-Jul-2025 | 10 wd | 0 wd | 18 wd | 0 wd |
| A1780 | Footings Zone C | 29-Jul-2025 to 08-Aug-2025 | 06-Aug-2025 to 29-Aug-2025 | 3 wd | 0 wd | 15 wd | 5 wd |
| A1930 | Erect structural steel Level 2 Zone B | 18-Aug-2025 to 21-Aug-2025 | 25-Sep-2025 to 10-Oct-2025 | 0 wd | 0 wd | 12 wd | 4 wd |
| A1160 | Structural steel shop drawings: consultant review | 03-Jun-2025 to 16-Jun-2025 | 17-Jun-2025 to 30-Jun-2025 | 0 wd | 0 wd | 10 wd | 10 wd |
| A1170 | Structural steel: fabricate and deliver | 17-Jun-2025 to 06-Aug-2025 | 02-Jul-2025 to 20-Aug-2025 | 25 wd | 0 wd | 10 wd | 10 wd |
| A1800 | Foundation walls Zone C | 18-Aug-2025 to 29-Aug-2025 | 04-Sep-2025 to 17-Sep-2025 | 0 wd | 0 wd | 10 wd | 10 wd |
| A1860 | Foundation walls Zone D | 02-Sep-2025 to 15-Sep-2025 | 18-Sep-2025 to 01-Oct-2025 | 0 wd | 0 wd | 10 wd | 10 wd |
| A1150 | Structural steel shop drawings: prepare and submit | 05-May-2025 to 02-Jun-2025 | 05-May-2025 to 16-Jun-2025 | 20 wd | 0 wd | 10 wd | 0 wd |
| A1590 | Shoring along the north property line | 16-May-2025 to 28-May-2025 | 17-Jun-2025 to 26-Jun-2025 | 0 wd | 0 wd | 8 wd | 8 wd |
| A1840 | Footings Zone D | 11-Aug-2025 to 20-Aug-2025 | 02-Sep-2025 to 11-Sep-2025 | 0 wd | 0 wd | 8 wd | 8 wd |
| A2480 IN-PROGRESS | Ductwork mains Level 1 | 21-Aug-2025 to 02-Sep-2025 | 03-Oct-2025, open | 0 wd | 0 wd | 8 wd | 8 wd |
| A2520 IN-PROGRESS | Sprinkler mains and risers | 21-Aug-2025 to 02-Sep-2025 | 03-Oct-2025, open | 0 wd | 0 wd | 8 wd | 8 wd |
| A2510 | Domestic water risers | 21-Aug-2025 to 28-Aug-2025 | 03-Oct-2025 to 10-Oct-2025 | 0 wd | 0 wd | 6 wd | 6 wd |
| A2860 | Layout and partition framing Level 1 Zone C | 16-Sep-2025 to 23-Sep-2025 | 02-Oct-2025 to 09-Oct-2025 | 0 wd | 0 wd | 6 wd | 6 wd |
| A1650 IN-PROGRESS | Backfill and compact at foundations | 22-Sep-2025 to 29-Sep-2025 | 08-Oct-2025, open | 0 wd | 0 wd | 5 wd | 6 wd |
| A1820 | Underslab services Zone C | 02-Sep-2025 to 08-Sep-2025 | 18-Sep-2025 to 24-Sep-2025 | 0 wd | 0 wd | 5 wd | 5 wd |
| A1830 | Slab on grade Zone C | 09-Sep-2025 to 15-Sep-2025 | 25-Sep-2025 to 01-Oct-2025 | 0 wd | 0 wd | 5 wd | 5 wd |
| A1880 | Underslab services Zone D | 16-Sep-2025 to 22-Sep-2025 | 02-Oct-2025 to 08-Oct-2025 | 0 wd | 0 wd | 5 wd | 5 wd |
| A2870 | Mechanical in-wall rough-in Level 1 Zone C | 18-Sep-2025 to 24-Sep-2025 | 06-Oct-2025 to 10-Oct-2025 | 0 wd | 0 wd | 5 wd | 5 wd |
| A2890 | Electrical in-wall rough-in Level 1 Zone C | 18-Sep-2025 to 24-Sep-2025 | 06-Oct-2025 to 10-Oct-2025 | 0 wd | 0 wd | 5 wd | 5 wd |
| A1890 IN-PROGRESS | Slab on grade Zone D | 23-Sep-2025 to 29-Sep-2025 | 09-Oct-2025, open | 0 wd | 0 wd | 4 wd | 5 wd |
| A1810 | Waterproofing and perimeter drainage Zone C | 02-Sep-2025 to 05-Sep-2025 | 18-Sep-2025 to 23-Sep-2025 | 0 wd | 0 wd | 4 wd | 4 wd |
| A1870 | Waterproofing and perimeter drainage Zone D | 16-Sep-2025 to 19-Sep-2025 | 02-Oct-2025 to 07-Oct-2025 | 0 wd | 0 wd | 4 wd | 4 wd |
| A1900 | Erect structural steel Level 2 Zone A | 07-Aug-2025 to 12-Aug-2025 | 19-Sep-2025 to 24-Sep-2025 | 0 wd | 0 wd | 4 wd | 4 wd |
| A2880 | Plumbing in-wall rough-in Level 1 Zone C | 18-Sep-2025 to 23-Sep-2025 | 06-Oct-2025 to 09-Oct-2025 | 0 wd | 0 wd | 4 wd | 4 wd |
| A2900 | Sprinkler branch piping Level 1 Zone C | 18-Sep-2025 to 23-Sep-2025 | 06-Oct-2025 to 09-Oct-2025 | 0 wd | 0 wd | 4 wd | 4 wd |
| A1910 | Metal deck Level 2 Zone A | 13-Aug-2025 to 15-Aug-2025 | 25-Sep-2025 to 29-Sep-2025 | 0 wd | 0 wd | 3 wd | 3 wd |
| A1920 | Concrete topping Level 2 Zone A | 18-Aug-2025 to 20-Aug-2025 | 30-Sep-2025 to 02-Oct-2025 | 0 wd | 0 wd | 3 wd | 3 wd |
| A1960 IN-PROGRESS | Erect structural steel Level 2 Zone C | 02-Sep-2025 to 05-Sep-2025 | 14-Oct-2025, open | 0 wd | 0 wd | 2 wd | 4 wd |
| A1940 IN-PROGRESS | Metal deck Level 2 Zone B | 22-Aug-2025 to 26-Aug-2025 | 14-Oct-2025, open | 0 wd | 0 wd | 2 wd | 3 wd |
| A1640 | Municipal service connection inspection | 08-Jul-2025 to 09-Jul-2025 | 11-Jul-2025 to 14-Jul-2025 | 0 wd | 0 wd | 2 wd | 2 wd |
| A1090 | Site survey and building layout | 05-May-2025 to 07-May-2025 | 05-May-2025 to 09-May-2025 | 3 wd | 0 wd | 2 wd | 0 wd |
| A1790 | Footing inspection Zone C | 11-Aug-2025 to 11-Aug-2025 | 03-Sep-2025 to 03-Sep-2025 | 0 wd | 0 wd | 1 wd | 1 wd |
| A1850 | Footing inspection Zone D | 21-Aug-2025 to 21-Aug-2025 | 12-Sep-2025 to 12-Sep-2025 | 0 wd | 0 wd | 1 wd | 1 wd |
| A2910 | In-wall services inspection Level 1 Zone C | 25-Sep-2025 to 25-Sep-2025 | 14-Oct-2025 to 14-Oct-2025 | 0 wd | 0 wd | 1 wd | 1 wd |
| A2580 | Elevator rails, machine and car install | 18-Sep-2025 to 16-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 19 wd |
| A2260 | Curtain wall and windows, North elevation | 05-Sep-2025 to 22-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 12 wd |
| A2300 | Curtain wall and windows, East elevation | 23-Sep-2025 to 08-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 12 wd |
| A2250 | Exterior sheathing and air/vapour barrier, North elevation | 25-Aug-2025 to 04-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A2290 | Exterior sheathing and air/vapour barrier, East elevation | 05-Sep-2025 to 16-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A2330 | Exterior sheathing and air/vapour barrier, South elevation | 18-Sep-2025 to 29-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A2370 | Exterior sheathing and air/vapour barrier, West elevation | 02-Oct-2025 to 14-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A2490 | Ductwork mains Level 2 | 27-Aug-2025 to 08-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A2500 | Ductwork mains Level 3 | 28-Aug-2025 to 09-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A2410 | Roof insulation and membrane | 07-Oct-2025 to 23-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A2990 | Layout and partition framing Level 1 Zone D | 30-Sep-2025 to 07-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A3640 | Layout and partition framing Level 3 Zone A | 27-Aug-2025 to 04-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A3770 | Layout and partition framing Level 3 Zone B | 08-Sep-2025 to 15-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A3900 | Layout and partition framing Level 3 Zone C | 22-Sep-2025 to 29-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A4030 | Layout and partition framing Level 3 Zone D | 06-Oct-2025 to 14-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A4160 | Granular base for parking and drive | 30-Sep-2025 to 07-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A4180 | Site lighting bases and poles | 02-Oct-2025 to 09-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A2610 | Mechanical in-wall rough-in Level 1 Zone A | 03-Sep-2025 to 09-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A3000 | Mechanical in-wall rough-in Level 1 Zone D | 02-Oct-2025 to 08-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A3020 | Electrical in-wall rough-in Level 1 Zone D | 02-Oct-2025 to 08-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A3650 | Mechanical in-wall rough-in Level 3 Zone A | 10-Sep-2025 to 16-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A3670 | Electrical in-wall rough-in Level 3 Zone A | 29-Aug-2025 to 05-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A3780 | Mechanical in-wall rough-in Level 3 Zone B | 10-Sep-2025 to 16-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A3800 | Electrical in-wall rough-in Level 3 Zone B | 10-Sep-2025 to 16-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A3910 | Mechanical in-wall rough-in Level 3 Zone C | 24-Sep-2025 to 30-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A3930 | Electrical in-wall rough-in Level 3 Zone C | 24-Sep-2025 to 30-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A4040 | Mechanical in-wall rough-in Level 3 Zone D | 08-Oct-2025 to 15-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A4060 | Electrical in-wall rough-in Level 3 Zone D | 08-Oct-2025 to 15-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A4170 | Concrete curbs and sidewalks | 08-Oct-2025 to 20-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 5 wd |
| A1990 | Erect structural steel Level 2 Zone D | 16-Sep-2025 to 19-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2020 | Erect structural steel Level 3 Zone A | 13-Aug-2025 to 18-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2050 | Erect structural steel Level 3 Zone B | 22-Aug-2025 to 27-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2080 | Erect structural steel Level 3 Zone C | 08-Sep-2025 to 11-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2110 | Erect structural steel Level 3 Zone D | 22-Sep-2025 to 25-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2140 | Erect structural steel Roof Zone A | 19-Aug-2025 to 22-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2160 | Erect structural steel Roof Zone B | 28-Aug-2025 to 03-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2180 | Erect structural steel Roof Zone C | 12-Sep-2025 to 17-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2200 | Erect structural steel Roof Zone D | 26-Sep-2025 to 01-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2280 | Sealants and flashings, North elevation | 23-Sep-2025 to 26-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2320 | Sealants and flashings, East elevation | 03-Oct-2025 to 08-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2340 | Curtain wall and windows, South elevation | 09-Oct-2025 to 27-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A2450 | Roof drains and leaders | 09-Oct-2025 to 15-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A3010 | Plumbing in-wall rough-in Level 1 Zone D | 02-Oct-2025 to 07-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A3030 | Sprinkler branch piping Level 1 Zone D | 02-Oct-2025 to 07-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A3660 | Plumbing in-wall rough-in Level 3 Zone A | 29-Aug-2025 to 04-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A3680 | Sprinkler branch piping Level 3 Zone A | 29-Aug-2025 to 04-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A3790 | Plumbing in-wall rough-in Level 3 Zone B | 10-Sep-2025 to 15-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A3810 | Sprinkler branch piping Level 3 Zone B | 10-Sep-2025 to 15-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A3920 | Plumbing in-wall rough-in Level 3 Zone C | 24-Sep-2025 to 29-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A3940 | Sprinkler branch piping Level 3 Zone C | 24-Sep-2025 to 29-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A4050 | Plumbing in-wall rough-in Level 3 Zone D | 08-Oct-2025 to 14-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A4070 | Sprinkler branch piping Level 3 Zone D | 08-Oct-2025 to 14-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 4 wd |
| A1950 | Concrete topping Level 2 Zone B | 27-Aug-2025 to 29-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A1970 | Metal deck Level 2 Zone C | 08-Sep-2025 to 10-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A1980 | Concrete topping Level 2 Zone C | 11-Sep-2025 to 15-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2000 | Metal deck Level 2 Zone D | 22-Sep-2025 to 24-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2010 | Concrete topping Level 2 Zone D | 25-Sep-2025 to 29-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2030 | Metal deck Level 3 Zone A | 19-Aug-2025 to 21-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2040 | Concrete topping Level 3 Zone A | 22-Aug-2025 to 26-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2060 | Metal deck Level 3 Zone B | 28-Aug-2025 to 02-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2070 | Concrete topping Level 3 Zone B | 03-Sep-2025 to 05-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2090 | Metal deck Level 3 Zone C | 12-Sep-2025 to 16-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2100 | Concrete topping Level 3 Zone C | 17-Sep-2025 to 19-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2120 | Metal deck Level 3 Zone D | 26-Sep-2025 to 30-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2130 | Concrete topping Level 3 Zone D | 01-Oct-2025 to 03-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2150 | Metal deck Roof Zone A | 25-Aug-2025 to 27-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2170 | Metal deck Roof Zone B | 04-Sep-2025 to 08-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2190 | Metal deck Roof Zone C | 18-Sep-2025 to 22-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2210 | Metal deck Roof Zone D | 02-Oct-2025 to 06-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2430 | Rooftop unit curbs | 14-Oct-2025 to 16-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 2 wd |
| A2650 | In-wall services inspection Level 1 Zone A | 10-Sep-2025 to 10-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 1 wd |
| A3040 | In-wall services inspection Level 1 Zone D | 09-Oct-2025 to 09-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 1 wd |
| A3690 | In-wall services inspection Level 3 Zone A | 17-Sep-2025 to 17-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 1 wd |
| A3820 | In-wall services inspection Level 3 Zone B | 17-Sep-2025 to 17-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 1 wd |
| A3950 | In-wall services inspection Level 3 Zone C | 01-Oct-2025 to 01-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 1 wd |
| A4260 | Sprinkler flush and hydrostatic test | 15-Oct-2025 to 17-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 1 wd |
| A1000 | Notice to Proceed | 05-May-2025 to 05-May-2025 | 05-May-2025 to 05-May-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1010 | Building Permit Issued | 09-Jun-2025 to 09-Jun-2025 | 09-Jun-2025 to 09-Jun-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1030 | Permanent Power Available | 18-Sep-2025 to 18-Sep-2025 | 18-Sep-2025 to 18-Sep-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1070 | Mobilize site office and temporary facilities | 05-May-2025 to 09-May-2025 | 05-May-2025 to 09-May-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A1080 | Building permit review by the municipality | 05-May-2025 to 09-Jun-2025 | 05-May-2025 to 09-Jun-2025 | 25 wd | 0 wd | 0 wd | 0 wd |
| A1100 | Site fencing, hoarding and signage | 12-May-2025 to 15-May-2025 | 12-May-2025 to 15-May-2025 | 4 wd | 0 wd | 0 wd | 0 wd |
| A1120 | Reinforcing steel shop drawings: prepare and submit | 05-May-2025 to 16-May-2025 | 05-May-2025 to 16-May-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1130 | Reinforcing steel shop drawings: consultant review | 20-May-2025 to 29-May-2025 | 20-May-2025 to 29-May-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1140 | Reinforcing steel: fabricate and deliver | 30-May-2025 to 12-Jun-2025 | 30-May-2025 to 12-Jun-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1180 | Metal deck shop drawings: prepare and submit | 05-May-2025 to 16-May-2025 | 05-May-2025 to 16-May-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1190 | Metal deck shop drawings: consultant review | 20-May-2025 to 29-May-2025 | 20-May-2025 to 29-May-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1200 | Metal deck: fabricate and deliver | 30-May-2025 to 26-Jun-2025 | 30-May-2025 to 26-Jun-2025 | 20 wd | 0 wd | 0 wd | 0 wd |
| A1210 | Curtain wall and windows shop drawings: prepare and submit | 05-May-2025 to 02-Jun-2025 | 05-May-2025 to 02-Jun-2025 | 20 wd | 0 wd | 0 wd | 0 wd |
| A1240 | Roofing system shop drawings: prepare and submit | 05-May-2025 to 16-May-2025 | 05-May-2025 to 16-May-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1250 | Roofing system shop drawings: consultant review | 20-May-2025 to 02-Jun-2025 | 20-May-2025 to 02-Jun-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1260 | Roofing system: fabricate and deliver | 03-Jun-2025 to 23-Jun-2025 | 03-Jun-2025 to 23-Jun-2025 | 15 wd | 0 wd | 0 wd | 0 wd |
| A1270 | Rooftop air handling units shop drawings: prepare and submit | 05-May-2025 to 26-May-2025 | 05-May-2025 to 26-May-2025 | 15 wd | 0 wd | 0 wd | 0 wd |
| A1280 | Rooftop air handling units shop drawings: consultant review | 27-May-2025 to 09-Jun-2025 | 27-May-2025 to 09-Jun-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1290 | Rooftop air handling units: fabricate and deliver | 10-Jun-2025 to 27-Aug-2025 | 10-Jun-2025 to 27-Aug-2025 | 55 wd | 0 wd | 0 wd | 0 wd |
| A1300 | Boilers and pumps shop drawings: prepare and submit | 05-May-2025 to 16-May-2025 | 05-May-2025 to 16-May-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1310 | Boilers and pumps shop drawings: consultant review | 20-May-2025 to 02-Jun-2025 | 20-May-2025 to 02-Jun-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1320 | Boilers and pumps: fabricate and deliver | 03-Jun-2025 to 29-Jul-2025 | 03-Jun-2025 to 29-Jul-2025 | 40 wd | 0 wd | 0 wd | 0 wd |
| A1330 | Switchgear and transformers shop drawings: prepare and submit | 05-May-2025 to 26-May-2025 | 05-May-2025 to 26-May-2025 | 15 wd | 0 wd | 0 wd | 0 wd |
| A1340 | Switchgear and transformers shop drawings: consultant review | 27-May-2025 to 09-Jun-2025 | 27-May-2025 to 09-Jun-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1350 | Switchgear and transformers: fabricate and deliver | 10-Jun-2025 to 04-Sep-2025 | 10-Jun-2025 to 04-Sep-2025 | 60 wd | 0 wd | 0 wd | 0 wd |
| A1360 | Elevator shop drawings: prepare and submit | 05-May-2025 to 26-May-2025 | 05-May-2025 to 26-May-2025 | 15 wd | 0 wd | 0 wd | 0 wd |
| A1370 | Elevator shop drawings: consultant review | 27-May-2025 to 09-Jun-2025 | 27-May-2025 to 09-Jun-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1380 | Elevator: fabricate and deliver | 10-Jun-2025 to 11-Sep-2025 | 10-Jun-2025 to 11-Sep-2025 | 65 wd | 0 wd | 0 wd | 0 wd |
| A1390 | Doors, frames and hardware shop drawings: prepare and submit | 05-May-2025 to 26-May-2025 | 05-May-2025 to 26-May-2025 | 15 wd | 0 wd | 0 wd | 0 wd |
| A1400 | Doors, frames and hardware shop drawings: consultant review | 27-May-2025 to 09-Jun-2025 | 27-May-2025 to 09-Jun-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1410 | Doors, frames and hardware: fabricate and deliver | 10-Jun-2025 to 22-Jul-2025 | 10-Jun-2025 to 22-Jul-2025 | 30 wd | 0 wd | 0 wd | 0 wd |
| A1420 | Millwork shop drawings: prepare and submit | 05-May-2025 to 26-May-2025 | 05-May-2025 to 26-May-2025 | 15 wd | 0 wd | 0 wd | 0 wd |
| A1430 | Millwork shop drawings: consultant review | 27-May-2025 to 09-Jun-2025 | 27-May-2025 to 09-Jun-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1440 | Millwork: fabricate and deliver | 10-Jun-2025 to 22-Jul-2025 | 10-Jun-2025 to 22-Jul-2025 | 30 wd | 0 wd | 0 wd | 0 wd |
| A1450 | Fire alarm system shop drawings: prepare and submit | 05-May-2025 to 16-May-2025 | 05-May-2025 to 16-May-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1460 | Fire alarm system shop drawings: consultant review | 20-May-2025 to 29-May-2025 | 20-May-2025 to 29-May-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1470 | Fire alarm system: fabricate and deliver | 30-May-2025 to 26-Jun-2025 | 30-May-2025 to 26-Jun-2025 | 20 wd | 0 wd | 0 wd | 0 wd |
| A1480 | Plumbing fixtures shop drawings: prepare and submit | 05-May-2025 to 16-May-2025 | 05-May-2025 to 16-May-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1490 | Plumbing fixtures shop drawings: consultant review | 20-May-2025 to 29-May-2025 | 20-May-2025 to 29-May-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1500 | Plumbing fixtures: fabricate and deliver | 30-May-2025 to 04-Jul-2025 | 30-May-2025 to 04-Jul-2025 | 25 wd | 0 wd | 0 wd | 0 wd |
| A1510 | Lighting fixtures shop drawings: prepare and submit | 05-May-2025 to 16-May-2025 | 05-May-2025 to 16-May-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1520 | Lighting fixtures shop drawings: consultant review | 20-May-2025 to 29-May-2025 | 20-May-2025 to 29-May-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1530 | Lighting fixtures: fabricate and deliver | 30-May-2025 to 11-Jul-2025 | 30-May-2025 to 11-Jul-2025 | 30 wd | 0 wd | 0 wd | 0 wd |
| A1540 | Flooring shop drawings: prepare and submit | 05-May-2025 to 16-May-2025 | 05-May-2025 to 16-May-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1550 | Flooring shop drawings: consultant review | 20-May-2025 to 29-May-2025 | 20-May-2025 to 29-May-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1560 | Flooring: fabricate and deliver | 30-May-2025 to 04-Jul-2025 | 30-May-2025 to 04-Jul-2025 | 25 wd | 0 wd | 0 wd | 0 wd |
| A1570 | Remove existing asphalt and curbs | 10-Jun-2025 to 16-Jun-2025 | 10-Jun-2025 to 16-Jun-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A1580 | Strip and stockpile topsoil | 17-Jun-2025 to 19-Jun-2025 | 17-Jun-2025 to 19-Jun-2025 | 3 wd | 0 wd | 0 wd | 0 wd |
| A1600 | Bulk excavation | 20-Jun-2025 to 04-Jul-2025 | 20-Jun-2025 to 04-Jul-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1610 | Storm sewer and catch basins | 27-Jun-2025 to 09-Jul-2025 | 27-Jun-2025 to 09-Jul-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1620 | Sanitary service to property line | 27-Jun-2025 to 07-Jul-2025 | 27-Jun-2025 to 07-Jul-2025 | 6 wd | 0 wd | 0 wd | 0 wd |
| A1630 | Water service and fire line | 27-Jun-2025 to 07-Jul-2025 | 27-Jun-2025 to 07-Jul-2025 | 6 wd | 0 wd | 0 wd | 0 wd |
| A1660 | Footings Zone A | 07-Jul-2025 to 16-Jul-2025 | 07-Jul-2025 to 16-Jul-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1670 | Footing inspection Zone A | 17-Jul-2025 to 17-Jul-2025 | 17-Jul-2025 to 17-Jul-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1680 | Foundation walls Zone A | 18-Jul-2025 to 31-Jul-2025 | 18-Jul-2025 to 31-Jul-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1690 | Waterproofing and perimeter drainage Zone A | 01-Aug-2025 to 07-Aug-2025 | 01-Aug-2025 to 07-Aug-2025 | 4 wd | 0 wd | 0 wd | 0 wd |
| A1700 | Underslab services Zone A | 01-Aug-2025 to 08-Aug-2025 | 01-Aug-2025 to 08-Aug-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A1710 | Slab on grade Zone A | 11-Aug-2025 to 15-Aug-2025 | 11-Aug-2025 to 15-Aug-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A1720 | Footings Zone B | 17-Jul-2025 to 28-Jul-2025 | 17-Jul-2025 to 28-Jul-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1730 | Footing inspection Zone B | 29-Jul-2025 to 29-Jul-2025 | 29-Jul-2025 to 29-Jul-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1740 | Foundation walls Zone B | 01-Aug-2025 to 15-Aug-2025 | 01-Aug-2025 to 15-Aug-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1750 | Waterproofing and perimeter drainage Zone B | 18-Aug-2025 to 21-Aug-2025 | 18-Aug-2025 to 21-Aug-2025 | 4 wd | 0 wd | 0 wd | 0 wd |
| A1760 | Underslab services Zone B | 18-Aug-2025 to 22-Aug-2025 | 18-Aug-2025 to 22-Aug-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A1770 | Slab on grade Zone B | 25-Aug-2025 to 29-Aug-2025 | 25-Aug-2025 to 29-Aug-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2460 | Set boilers and pumps | 18-Aug-2025 to 22-Aug-2025 | 18-Aug-2025 to 22-Aug-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2470 | Mechanical room piping | 25-Aug-2025 to 10-Sep-2025 | 25-Aug-2025 to 10-Sep-2025 | 12 wd | 0 wd | 0 wd | 0 wd |
| A2530 | Set switchgear and transformers | 05-Sep-2025 to 11-Sep-2025 | 05-Sep-2025 to 11-Sep-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2540 | Utility connection and ESA inspection | 12-Sep-2025 to 18-Sep-2025 | 12-Sep-2025 to 18-Sep-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2550 | Feeders and distribution panels | 12-Sep-2025 to 29-Sep-2025 | 12-Sep-2025 to 29-Sep-2025 | 12 wd | 0 wd | 0 wd | 0 wd |
| A2560 | Fire alarm devices and panel | 27-Jun-2025 to 11-Jul-2025 | 27-Jun-2025 to 11-Jul-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A2570 | Building automation controls rough-in | 11-Sep-2025 to 01-Oct-2025 | 11-Sep-2025 to 01-Oct-2025 | 15 wd | 0 wd | 0 wd | 0 wd |
| A2600 | Layout and partition framing Level 1 Zone A | 18-Aug-2025 to 25-Aug-2025 | 18-Aug-2025 to 25-Aug-2025 | 6 wd | 0 wd | 0 wd | 0 wd |
| A2620 | Plumbing in-wall rough-in Level 1 Zone A | 20-Aug-2025 to 25-Aug-2025 | 20-Aug-2025 to 25-Aug-2025 | 4 wd | 0 wd | 0 wd | 0 wd |
| A2630 | Electrical in-wall rough-in Level 1 Zone A | 20-Aug-2025 to 26-Aug-2025 | 20-Aug-2025 to 26-Aug-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2640 | Sprinkler branch piping Level 1 Zone A | 20-Aug-2025 to 25-Aug-2025 | 20-Aug-2025 to 25-Aug-2025 | 4 wd | 0 wd | 0 wd | 0 wd |
| A2730 | Layout and partition framing Level 1 Zone B | 02-Sep-2025 to 09-Sep-2025 | 02-Sep-2025 to 09-Sep-2025 | 6 wd | 0 wd | 0 wd | 0 wd |
| A2740 | Mechanical in-wall rough-in Level 1 Zone B | 04-Sep-2025 to 10-Sep-2025 | 04-Sep-2025 to 10-Sep-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2750 | Plumbing in-wall rough-in Level 1 Zone B | 04-Sep-2025 to 09-Sep-2025 | 04-Sep-2025 to 09-Sep-2025 | 4 wd | 0 wd | 0 wd | 0 wd |
| A2760 | Electrical in-wall rough-in Level 1 Zone B | 04-Sep-2025 to 10-Sep-2025 | 04-Sep-2025 to 10-Sep-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2770 | Sprinkler branch piping Level 1 Zone B | 04-Sep-2025 to 09-Sep-2025 | 04-Sep-2025 to 09-Sep-2025 | 4 wd | 0 wd | 0 wd | 0 wd |
| A2780 | In-wall services inspection Level 1 Zone B | 11-Sep-2025 to 11-Sep-2025 | 11-Sep-2025 to 11-Sep-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| A4300 | Electrical commissioning | 30-Sep-2025 to 06-Oct-2025 | 30-Sep-2025 to 06-Oct-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
Float Burndown Across Windows
per-activity float-erosion register, drawing-sheet exhibitCriticality predates the window: 43 of 197 activities opened at TF ≤ 0 at Baseline, and 94 more demonstrably burned their float to zero as completion moved 86 working days later
Total float in working days (wd), read from the schedule of record at 2 CPM snapshots, Baseline through Current spanning 1 window, day math on the project working calendar. Criticality test: TF ≤ 0. Sign convention: negative Δ = float lost across the window. Finish driver A1050; completion Baseline → Current: 86 wd later. Register bands: TF ≤ 0 · 1-5 wd (near-critical) · 6-20 wd · over 20 wd.
60 further activities first appear with one observation only. No second reading exists, so a loss of float cannot be demonstrated for them and is not claimed here.
conservation: 43 + 94 + 60 + 0 = 197 · reconciles to the register below
Reading notes
- Not plotted above: 60 activities with zero net float movement · 44 held TF ≤ 0 at every observation (0 observed at multiple snapshots, 44 single-observation) · 16 held constant positive float. All 197 appear in the register below.
- Baseline band counts in the inset carry the register convention: the 60 single-observation entrants are imputed at their only reading. The movement panel plots observed pairs only.
- The horizontal scale breaks at 40 wd, marked with a drafting section break. Nothing is clipped: A3740 reaches 53 wd on the compressed segment.
- Band deltas conserve across the population: +94 − 39 − 22 − 33 = 0 over 197 activities.
- Method caveat (cite in any expert report): Float burndown is post-processing of analyst-supplied CPM snapshots. Accuracy depends on the quality of the underlying schedule updates. Recovery events (TF increase) may reflect legitimate scope removal, schedule optimization, or activity deletion, and the register does not say which. Slip velocity is a linear average; actual burndown may be non-linear. The per-activity float-timeline presentation is not yet published in AACE/SCL literature; it is disclosed here as a CPP enhancement to the cited observational method.
Activity register · all 197 activities TF FIRST / LAST · Δ · FIRST AT TF ≤ 0
| Activity | TF at Baseline (wd) | TF at Current (wd) | Δ (wd) | First at TF ≤ 0 | Movement |
|---|---|---|---|---|---|
| A1000 | 0 | 0 | 0 | Baseline | single observation |
| A1010 | 3 | 3 | 0 | never | single observation |
| A1020 | 0 | -86 | −86 | Baseline | lost |
| A1040 | 0 | -86 | −86 | Baseline | lost |
| A1050 | 0 | -86 | −86 | Baseline | lost |
| A1060 | 0 | -86 | −86 | Baseline | lost |
| A1080 | 3 | 3 | 0 | never | single observation |
| A1150 | 0 | 0 | 0 | Baseline | single observation |
| A1160 | 0 | 0 | 0 | Baseline | single observation |
| A1170 | 0 | 0 | 0 | Baseline | single observation |
| A1210 | 5 | 5 | 0 | never | single observation |
| A1220 | 5 | 5 | 0 | never | single observation |
| A1230 | 5 | 5 | 0 | never | single observation |
| A1570 | 3 | 3 | 0 | never | single observation |
| A1580 | 3 | 3 | 0 | never | single observation |
| A1600 | 3 | 3 | 0 | never | single observation |
| A1660 | 3 | 3 | 0 | never | single observation |
| A1670 | 3 | 3 | 0 | never | single observation |
| A1680 | 3 | 3 | 0 | never | single observation |
| A1740 | 5 | 5 | 0 | never | single observation |
| A1900 | 0 | 0 | 0 | Baseline | single observation |
| A1930 | 5 | 5 | 0 | never | single observation |
| A1960 | 7 | -86 | −93 | Current | lost |
| A1990 | 9 | -86 | −95 | Current | lost |
| A2020 | 0 | -86 | −86 | Baseline | lost |
| A2050 | 5 | -75 | −80 | Current | lost |
| A2080 | 7 | -64 | −71 | Current | lost |
| A2110 | 9 | -58 | −67 | Current | lost |
| A2140 | 0 | -86 | −86 | Baseline | lost |
| A2150 | 27 | -48 | −75 | Current | lost |
| A2160 | 5 | -75 | −80 | Current | lost |
| A2170 | 23 | -49 | −72 | Current | lost |
| A2180 | 7 | -64 | −71 | Current | lost |
| A2190 | 16 | -50 | −66 | Current | lost |
| A2200 | 9 | -58 | −67 | Current | lost |
| A2210 | 9 | -51 | −60 | Current | lost |
| A2250 | 0 | -86 | −86 | Baseline | lost |
| A2260 | 0 | -86 | −86 | Baseline | lost |
| A2290 | 4 | -79 | −83 | Current | lost |
| A2300 | 0 | -86 | −86 | Baseline | lost |
| A2330 | 7 | -72 | −79 | Current | lost |
| A2340 | 0 | -86 | −86 | Baseline | lost |
| A2370 | 9 | -70 | −79 | Current | lost |
| A2380 | 0 | -86 | −86 | Baseline | lost |
| A2410 | 9 | -51 | −60 | Current | lost |
| A2420 | 9 | -51 | −60 | Current | lost |
| A2480 | 44 | -9 | −53 | Current | lost |
| A2610 | 44 | -9 | −53 | Current | lost |
| A2650 | 44 | -9 | −53 | Current | lost |
| A2660 | 0 | -86 | −86 | Baseline | lost |
| A2670 | 0 | -86 | −86 | Baseline | lost |
| A2680 | 0 | -86 | −86 | Baseline | lost |
| A2690 | 0 | 0 | 0 | Baseline | single observation |
| A2700 | 6 | -77 | −83 | Current | lost |
| A2710 | 6 | -77 | −83 | Current | lost |
| A2720 | 6 | -77 | −83 | Current | lost |
| A2790 | 0 | -85 | −85 | Baseline | lost |
| A2800 | 0 | -85 | −85 | Baseline | lost |
| A2810 | 0 | -85 | −85 | Baseline | lost |
| A2820 | 0 | 0 | 0 | Baseline | single observation |
| A2830 | 4 | -80 | −84 | Current | lost |
| A2840 | 4 | -80 | −84 | Current | lost |
| A2850 | 4 | -80 | −84 | Current | lost |
| A2920 | 0 | -84 | −84 | Baseline | lost |
| A2930 | 0 | -84 | −84 | Baseline | lost |
| A2940 | 0 | -84 | −84 | Baseline | lost |
| A2950 | 0 | 0 | 0 | Baseline | single observation |
| A2960 | 2 | -83 | −85 | Current | lost |
| A2970 | 2 | -83 | −85 | Current | lost |
| A2980 | 2 | -83 | −85 | Current | lost |
| A3050 | 0 | -83 | −83 | Baseline | lost |
| A3060 | 0 | -83 | −83 | Baseline | lost |
| A3070 | 0 | -83 | −83 | Baseline | lost |
| A3080 | 0 | 0 | 0 | Baseline | single observation |
| A3090 | 0 | -86 | −86 | Baseline | lost |
| A3100 | 0 | -86 | −86 | Baseline | lost |
| A3110 | 0 | -86 | −86 | Baseline | lost |
| A3120 | 0 | -86 | −86 | Baseline | lost |
| A3130 | 3 | -79 | −82 | Current | lost |
| A3140 | 4 | -78 | −82 | Current | lost |
| A3150 | 3 | -86 | −89 | Current | lost |
| A3160 | 4 | -78 | −82 | Current | lost |
| A3170 | 3 | -79 | −82 | Current | lost |
| A3180 | 3 | -86 | −89 | Current | lost |
| A3190 | 3 | -86 | −89 | Current | lost |
| A3200 | 3 | -86 | −89 | Current | lost |
| A3210 | 3 | 3 | 0 | never | single observation |
| A3220 | 9 | -71 | −80 | Current | lost |
| A3230 | 9 | -71 | −80 | Current | lost |
| A3240 | 9 | -71 | −80 | Current | lost |
| A3250 | 0 | -79 | −79 | Baseline | lost |
| A3260 | 2 | -79 | −81 | Current | lost |
| A3270 | 3 | -78 | −81 | Current | lost |
| A3280 | 2 | -79 | −81 | Current | lost |
| A3290 | 3 | -78 | −81 | Current | lost |
| A3300 | 2 | -79 | −81 | Current | lost |
| A3310 | 2 | -85 | −87 | Current | lost |
| A3320 | 2 | -85 | −87 | Current | lost |
| A3330 | 2 | -85 | −87 | Current | lost |
| A3340 | 2 | 2 | 0 | never | single observation |
| A3350 | 6 | -74 | −80 | Current | lost |
| A3360 | 6 | -74 | −80 | Current | lost |
| A3370 | 6 | -74 | −80 | Current | lost |
| A3380 | 0 | -79 | −79 | Baseline | lost |
| A3390 | 1 | -79 | −80 | Current | lost |
| A3400 | 2 | -78 | −80 | Current | lost |
| A3410 | 1 | -79 | −80 | Current | lost |
| A3420 | 2 | -78 | −80 | Current | lost |
| A3430 | 1 | -79 | −80 | Current | lost |
| A3440 | 1 | -84 | −85 | Current | lost |
| A3450 | 1 | -84 | −85 | Current | lost |
| A3460 | 1 | -84 | −85 | Current | lost |
| A3470 | 1 | 1 | 0 | never | single observation |
| A3480 | 3 | -77 | −80 | Current | lost |
| A3490 | 3 | -77 | −80 | Current | lost |
| A3500 | 3 | -77 | −80 | Current | lost |
| A3510 | 0 | -79 | −79 | Baseline | lost |
| A3520 | 0 | -79 | −79 | Baseline | lost |
| A3530 | 1 | -78 | −79 | Current | lost |
| A3540 | 0 | -79 | −79 | Baseline | lost |
| A3550 | 1 | -78 | −79 | Current | lost |
| A3560 | 0 | -79 | −79 | Baseline | lost |
| A3570 | 0 | -83 | −83 | Baseline | lost |
| A3580 | 0 | -83 | −83 | Baseline | lost |
| A3590 | 0 | -83 | −83 | Baseline | lost |
| A3600 | 0 | 0 | 0 | Baseline | single observation |
| A3610 | 0 | -86 | −86 | Baseline | lost |
| A3620 | 0 | -86 | −86 | Baseline | lost |
| A3630 | 0 | -86 | −86 | Baseline | lost |
| A3700 | 47 | -20 | −67 | Current | lost |
| A3710 | 47 | -20 | −67 | Current | lost |
| A3720 | 47 | -20 | −67 | Current | lost |
| A3740 | 53 | -11 | −64 | Current | lost |
| A3750 | 53 | -11 | −64 | Current | lost |
| A3760 | 53 | -11 | −64 | Current | lost |
| A3830 | 47 | -19 | −66 | Current | lost |
| A3840 | 47 | -19 | −66 | Current | lost |
| A3850 | 47 | -19 | −66 | Current | lost |
| A3870 | 51 | -14 | −65 | Current | lost |
| A3880 | 51 | -14 | −65 | Current | lost |
| A3890 | 51 | -14 | −65 | Current | lost |
| A3960 | 47 | -18 | −65 | Current | lost |
| A3970 | 47 | -18 | −65 | Current | lost |
| A3980 | 47 | -18 | −65 | Current | lost |
| A4000 | 49 | -17 | −66 | Current | lost |
| A4010 | 49 | -17 | −66 | Current | lost |
| A4020 | 49 | -17 | −66 | Current | lost |
| A4090 | 47 | -17 | −64 | Current | lost |
| A4100 | 47 | -17 | −64 | Current | lost |
| A4110 | 47 | -17 | −64 | Current | lost |
| A4130 | 47 | -20 | −67 | Current | lost |
| A4140 | 47 | -20 | −67 | Current | lost |
| A4150 | 47 | -20 | −67 | Current | lost |
| A4250 | 47 | -20 | −67 | Current | lost |
| A4310 | 47 | -20 | −67 | Current | lost |
| A4320 | 47 | -20 | −67 | Current | lost |
| A4330 | 0 | -86 | −86 | Baseline | lost |
| A4340 | 0 | -86 | −86 | Baseline | lost |
| A4350 | 50 | -17 | −67 | Current | lost |
| A4370 | 10 | -76 | −86 | Current | lost |
| A4380 | 0 | -86 | −86 | Baseline | lost |
| A4410 | 0 | -86 | −86 | Baseline | lost |
| A4420 | 5 | -81 | −86 | Current | lost |
| A4430 | -86 | -86 | 0 | Current | single observation |
| A4440 | -86 | -86 | 0 | Current | single observation |
| A4450 | -86 | -86 | 0 | Current | single observation |
| A4460 | -86 | -86 | 0 | Current | single observation |
| A4470 | -86 | -86 | 0 | Current | single observation |
| A4480 | -86 | -86 | 0 | Current | single observation |
| A4490 | -86 | -86 | 0 | Current | single observation |
| A4500 | -86 | -86 | 0 | Current | single observation |
| A4510 | -86 | -86 | 0 | Current | single observation |
| A4520 | -86 | -86 | 0 | Current | single observation |
| A4530 | -86 | -86 | 0 | Current | single observation |
| A4540 | -86 | -86 | 0 | Current | single observation |
| A4550 | -86 | -86 | 0 | Current | single observation |
| A4560 | -86 | -86 | 0 | Current | single observation |
| A4570 | -86 | -86 | 0 | Current | single observation |
| A4580 | -86 | -86 | 0 | Current | single observation |
| A4590 | -20 | -20 | 0 | Current | single observation |
| A4600 | -20 | -20 | 0 | Current | single observation |
| A4610 | -20 | -20 | 0 | Current | single observation |
| A4620 | -20 | -20 | 0 | Current | single observation |
| A4630 | -20 | -20 | 0 | Current | single observation |
| A4640 | -20 | -20 | 0 | Current | single observation |
| A4650 | -20 | -20 | 0 | Current | single observation |
| A4660 | -20 | -20 | 0 | Current | single observation |
| A4800 | -86 | -86 | 0 | Current | single observation |
| A4810 | -51 | -51 | 0 | Current | single observation |
| A4830 | -79 | -79 | 0 | Current | single observation |
| A4850 | -45 | -45 | 0 | Current | single observation |
| A4860 | -70 | -70 | 0 | Current | single observation |
| A4870 | -69 | -69 | 0 | Current | single observation |
| A4880 | -86 | -86 | 0 | Current | single observation |
| A4890 | -20 | -20 | 0 | Current | single observation |
| A4900 | -86 | -86 | 0 | Current | single observation |
| A4910 | -20 | -20 | 0 | Current | single observation |
Cumulative Activity Slip Register
sum of signed slip across all windows| Code | Activity | Total Slip | Windows Touched |
|---|---|---|---|
| A1040 CP | Substantial Performance of the Work | +86 wd | 1 |
| A1050 CP | Ready for Owner Takeover | +86 wd | 1 |
| A1060 CP | Total Performance of the Work | +86 wd | 1 |
| A4330 CP | Deficiency review with the consultant | +86 wd | 1 |
| A4340 CP | Substantial performance certification | +86 wd | 1 |
| A4370 | Operation and maintenance manuals | +86 wd | 1 |
| A4380 CP | Deficiency correction | +86 wd | 1 |
| A4410 CP | Owner furniture and fit-out (by others) | +86 wd | 1 |
| A4420 | Owner IT and security installation (by others) | +86 wd | 1 |
| A3630 CP | Final paint and finishes Level 2 Zone D | +83 wd | 1 |
| A3620 CP | Doors, hardware and millwork Level 2 Zone D | +81 wd | 1 |
| A3610 CP | Flooring Level 2 Zone D | +78 wd | 1 |
| A3220 | Flooring Level 2 Zone A | +75 wd | 1 |
| A3230 | Doors, hardware and millwork Level 2 Zone A | +75 wd | 1 |
| A3240 | Final paint and finishes Level 2 Zone A | +75 wd | 1 |
| A3350 | Flooring Level 2 Zone B | +75 wd | 1 |
| A3360 | Doors, hardware and millwork Level 2 Zone B | +75 wd | 1 |
| A3370 | Final paint and finishes Level 2 Zone B | +75 wd | 1 |
| A3480 | Flooring Level 2 Zone C | +75 wd | 1 |
| A3490 | Doors, hardware and millwork Level 2 Zone C | +75 wd | 1 |
| A3500 | Final paint and finishes Level 2 Zone C | +75 wd | 1 |
| A3180 CP | Drywall board Level 2 Zone A | +74 wd | 1 |
| A3190 CP | Tape, mud and sand Level 2 Zone A | +74 wd | 1 |
| A3200 CP | Prime paint Level 2 Zone A | +74 wd | 1 |
| A3310 | Drywall board Level 2 Zone B | +73 wd | 1 |
| A3320 | Tape, mud and sand Level 2 Zone B | +73 wd | 1 |
| A3330 | Prime paint Level 2 Zone B | +73 wd | 1 |
| A3440 | Drywall board Level 2 Zone C | +72 wd | 1 |
| A3450 | Tape, mud and sand Level 2 Zone C | +72 wd | 1 |
| A3460 | Prime paint Level 2 Zone C | +72 wd | 1 |
| A3570 | Drywall board Level 2 Zone D | +71 wd | 1 |
| A3580 | Tape, mud and sand Level 2 Zone D | +71 wd | 1 |
| A3590 | Prime paint Level 2 Zone D | +71 wd | 1 |
| A3090 CP | Flooring Level 1 Zone D | +67 wd | 1 |
| A3100 CP | Doors, hardware and millwork Level 1 Zone D | +67 wd | 1 |
| A3110 CP | Final paint and finishes Level 1 Zone D | +67 wd | 1 |
| A3120 CP | Layout and partition framing Level 2 Zone A | +67 wd | 1 |
| A3130 | Mechanical in-wall rough-in Level 2 Zone A | +67 wd | 1 |
| A3140 | Plumbing in-wall rough-in Level 2 Zone A | +67 wd | 1 |
| A3150 CP | Electrical in-wall rough-in Level 2 Zone A | +67 wd | 1 |
| A3160 | Sprinkler branch piping Level 2 Zone A | +67 wd | 1 |
| A3170 | In-wall services inspection Level 2 Zone A | +67 wd | 1 |
| A3250 | Layout and partition framing Level 2 Zone B | +67 wd | 1 |
| A3260 | Mechanical in-wall rough-in Level 2 Zone B | +67 wd | 1 |
| A3270 | Plumbing in-wall rough-in Level 2 Zone B | +67 wd | 1 |
| A3280 | Electrical in-wall rough-in Level 2 Zone B | +67 wd | 1 |
| A3290 | Sprinkler branch piping Level 2 Zone B | +67 wd | 1 |
| A3300 | In-wall services inspection Level 2 Zone B | +67 wd | 1 |
| A3380 | Layout and partition framing Level 2 Zone C | +67 wd | 1 |
| A3390 | Mechanical in-wall rough-in Level 2 Zone C | +67 wd | 1 |
| A3400 | Plumbing in-wall rough-in Level 2 Zone C | +67 wd | 1 |
| A3410 | Electrical in-wall rough-in Level 2 Zone C | +67 wd | 1 |
| A3420 | Sprinkler branch piping Level 2 Zone C | +67 wd | 1 |
| A3430 | In-wall services inspection Level 2 Zone C | +67 wd | 1 |
| A3510 | Layout and partition framing Level 2 Zone D | +67 wd | 1 |
| A3520 | Mechanical in-wall rough-in Level 2 Zone D | +67 wd | 1 |
| A3530 | Plumbing in-wall rough-in Level 2 Zone D | +67 wd | 1 |
| A3540 | Electrical in-wall rough-in Level 2 Zone D | +67 wd | 1 |
| A3550 | Sprinkler branch piping Level 2 Zone D | +67 wd | 1 |
| A3560 | In-wall services inspection Level 2 Zone D | +67 wd | 1 |
| A4130 | Flooring Level 3 Zone D | +67 wd | 1 |
| A4140 | Doors, hardware and millwork Level 3 Zone D | +67 wd | 1 |
| A4150 | Final paint and finishes Level 3 Zone D | +67 wd | 1 |
| A4250 | Fire alarm verification | +67 wd | 1 |
| A4310 | Fire department inspection | +67 wd | 1 |
| A4320 | Occupancy permit inspection | +67 wd | 1 |
| A4350 | Final cleaning | +67 wd | 1 |
| A2960 | Flooring Level 1 Zone C | +66 wd | 1 |
| A2970 | Doors, hardware and millwork Level 1 Zone C | +66 wd | 1 |
| A2980 | Final paint and finishes Level 1 Zone C | +66 wd | 1 |
| A4000 | Flooring Level 3 Zone C | +66 wd | 1 |
| A4010 | Doors, hardware and millwork Level 3 Zone C | +66 wd | 1 |
| A4020 | Final paint and finishes Level 3 Zone C | +66 wd | 1 |
| A2830 | Flooring Level 1 Zone B | +65 wd | 1 |
| A2840 | Doors, hardware and millwork Level 1 Zone B | +65 wd | 1 |
| A2850 | Final paint and finishes Level 1 Zone B | +65 wd | 1 |
| A3870 | Flooring Level 3 Zone B | +65 wd | 1 |
| A3880 | Doors, hardware and millwork Level 3 Zone B | +65 wd | 1 |
| A3890 | Final paint and finishes Level 3 Zone B | +65 wd | 1 |
| A2700 | Flooring Level 1 Zone A | +64 wd | 1 |
| A2710 | Doors, hardware and millwork Level 1 Zone A | +64 wd | 1 |
| A2720 | Final paint and finishes Level 1 Zone A | +64 wd | 1 |
| A3740 | Flooring Level 3 Zone A | +64 wd | 1 |
| A3750 | Doors, hardware and millwork Level 3 Zone A | +64 wd | 1 |
| A3760 | Final paint and finishes Level 3 Zone A | +64 wd | 1 |
| A1020 CP | Building Weathertight | +63 wd | 1 |
| A2380 CP | Curtain wall and windows, West elevation | +63 wd | 1 |
| A2660 CP | Drywall board Level 1 Zone A | +63 wd | 1 |
| A2670 CP | Tape, mud and sand Level 1 Zone A | +63 wd | 1 |
| A2680 CP | Prime paint Level 1 Zone A | +63 wd | 1 |
| A2790 | Drywall board Level 1 Zone B | +63 wd | 1 |
| A2800 | Tape, mud and sand Level 1 Zone B | +63 wd | 1 |
| A2810 | Prime paint Level 1 Zone B | +63 wd | 1 |
| A2920 | Drywall board Level 1 Zone C | +63 wd | 1 |
| A2930 | Tape, mud and sand Level 1 Zone C | +63 wd | 1 |
| A2940 | Prime paint Level 1 Zone C | +63 wd | 1 |
| A3050 | Drywall board Level 1 Zone D | +63 wd | 1 |
| A3060 | Tape, mud and sand Level 1 Zone D | +63 wd | 1 |
| A3070 | Prime paint Level 1 Zone D | +63 wd | 1 |
| A3700 | Drywall board Level 3 Zone A | +63 wd | 1 |
| A3710 | Tape, mud and sand Level 3 Zone A | +63 wd | 1 |
| A3720 | Prime paint Level 3 Zone A | +63 wd | 1 |
| A3830 | Drywall board Level 3 Zone B | +63 wd | 1 |
| A3840 | Tape, mud and sand Level 3 Zone B | +63 wd | 1 |
| A3850 | Prime paint Level 3 Zone B | +63 wd | 1 |
| A3960 | Drywall board Level 3 Zone C | +63 wd | 1 |
| A3970 | Tape, mud and sand Level 3 Zone C | +63 wd | 1 |
| A3980 | Prime paint Level 3 Zone C | +63 wd | 1 |
| A4090 | Drywall board Level 3 Zone D | +63 wd | 1 |
| A4100 | Tape, mud and sand Level 3 Zone D | +63 wd | 1 |
| A4110 | Prime paint Level 3 Zone D | +63 wd | 1 |
| A2340 CP | Curtain wall and windows, South elevation | +60 wd | 1 |
| A2300 CP | Curtain wall and windows, East elevation | +57 wd | 1 |
| A2260 CP | Curtain wall and windows, North elevation | +54 wd | 1 |
| A2020 CP | Erect structural steel Level 3 Zone A | +51 wd | 1 |
| A2030 | Metal deck Level 3 Zone A | +51 wd | 1 |
| A2040 | Concrete topping Level 3 Zone A | +51 wd | 1 |
| A2140 CP | Erect structural steel Roof Zone A | +51 wd | 1 |
| A2150 | Metal deck Roof Zone A | +51 wd | 1 |
| A2250 CP | Exterior sheathing and air/vapour barrier, North elevation | +51 wd | 1 |
| A2290 | Exterior sheathing and air/vapour barrier, East elevation | +51 wd | 1 |
| A2490 | Ductwork mains Level 2 | +51 wd | 1 |
| A2500 | Ductwork mains Level 3 | +51 wd | 1 |
| A3640 | Layout and partition framing Level 3 Zone A | +51 wd | 1 |
| A3650 | Mechanical in-wall rough-in Level 3 Zone A | +51 wd | 1 |
| A3660 | Plumbing in-wall rough-in Level 3 Zone A | +51 wd | 1 |
| A3670 | Electrical in-wall rough-in Level 3 Zone A | +51 wd | 1 |
| A3680 | Sprinkler branch piping Level 3 Zone A | +51 wd | 1 |
| A3690 | In-wall services inspection Level 3 Zone A | +51 wd | 1 |
| A2330 | Exterior sheathing and air/vapour barrier, South elevation | +50 wd | 1 |
| A3770 | Layout and partition framing Level 3 Zone B | +50 wd | 1 |
| A3780 | Mechanical in-wall rough-in Level 3 Zone B | +50 wd | 1 |
| A3790 | Plumbing in-wall rough-in Level 3 Zone B | +50 wd | 1 |
| A3800 | Electrical in-wall rough-in Level 3 Zone B | +50 wd | 1 |
| A3810 | Sprinkler branch piping Level 3 Zone B | +50 wd | 1 |
| A3820 | In-wall services inspection Level 3 Zone B | +50 wd | 1 |
| A2050 | Erect structural steel Level 3 Zone B | +48 wd | 1 |
| A2060 | Metal deck Level 3 Zone B | +48 wd | 1 |
| A2070 | Concrete topping Level 3 Zone B | +48 wd | 1 |
| A2160 | Erect structural steel Roof Zone B | +48 wd | 1 |
| A2170 | Metal deck Roof Zone B | +48 wd | 1 |
| A2370 | Exterior sheathing and air/vapour barrier, West elevation | +48 wd | 1 |
| A2280 | Sealants and flashings, North elevation | +47 wd | 1 |
| A2320 | Sealants and flashings, East elevation | +47 wd | 1 |
| A2360 | Sealants and flashings, South elevation | +46 wd | 1 |
| A3900 | Layout and partition framing Level 3 Zone C | +46 wd | 1 |
| A3910 | Mechanical in-wall rough-in Level 3 Zone C | +46 wd | 1 |
| A3920 | Plumbing in-wall rough-in Level 3 Zone C | +46 wd | 1 |
| A3930 | Electrical in-wall rough-in Level 3 Zone C | +46 wd | 1 |
| A3940 | Sprinkler branch piping Level 3 Zone C | +46 wd | 1 |
| A3950 | In-wall services inspection Level 3 Zone C | +46 wd | 1 |
| A4220 | Exterior stairs and barrier-free ramp | +46 wd | 1 |
| A4230 | Entrance canopy steel and soffit | +46 wd | 1 |
| A2400 | Sealants and flashings, West elevation | +44 wd | 1 |
| A2080 | Erect structural steel Level 3 Zone C | +42 wd | 1 |
| A2090 | Metal deck Level 3 Zone C | +42 wd | 1 |
| A2100 | Concrete topping Level 3 Zone C | +42 wd | 1 |
| A2180 | Erect structural steel Roof Zone C | +42 wd | 1 |
| A2190 | Metal deck Roof Zone C | +42 wd | 1 |
| A4030 | Layout and partition framing Level 3 Zone D | +42 wd | 1 |
| A4040 | Mechanical in-wall rough-in Level 3 Zone D | +42 wd | 1 |
| A4050 | Plumbing in-wall rough-in Level 3 Zone D | +42 wd | 1 |
| A4060 | Electrical in-wall rough-in Level 3 Zone D | +42 wd | 1 |
| A4070 | Sprinkler branch piping Level 3 Zone D | +42 wd | 1 |
| A4080 | In-wall services inspection Level 3 Zone D | +42 wd | 1 |
| A4260 | Sprinkler flush and hydrostatic test | +42 wd | 1 |
| A2420 | Roof flashings and penetrations | +37 wd | 1 |
| A2110 | Erect structural steel Level 3 Zone D | +36 wd | 1 |
| A2120 | Metal deck Level 3 Zone D | +36 wd | 1 |
| A2130 | Concrete topping Level 3 Zone D | +36 wd | 1 |
| A2200 | Erect structural steel Roof Zone D | +36 wd | 1 |
| A2210 | Metal deck Roof Zone D | +36 wd | 1 |
| A2230 | Steel stairs and railings | +36 wd | 1 |
| A2410 | Roof insulation and membrane | +36 wd | 1 |
| A2430 | Rooftop unit curbs | +36 wd | 1 |
| A2440 | Set rooftop air handling units | +36 wd | 1 |
| A2450 | Roof drains and leaders | +36 wd | 1 |
| A4270 | Test, adjust and balance | +36 wd | 1 |
| A4280 | Building automation functional testing | +36 wd | 1 |
| A4290 | Mechanical commissioning | +36 wd | 1 |
| A4360 | Owner training | +36 wd | 1 |
| A4400 | Seasonal commissioning of heating and cooling | +36 wd | 1 |
| A1930 | Erect structural steel Level 2 Zone B | +35 wd | 1 |
| A1940 | Metal deck Level 2 Zone B | +34 wd | 1 |
| A1950 | Concrete topping Level 2 Zone B | +34 wd | 1 |
| A1900 | Erect structural steel Level 2 Zone A | +30 wd | 1 |
| A1910 | Metal deck Level 2 Zone A | +30 wd | 1 |
| A1920 | Concrete topping Level 2 Zone A | +30 wd | 1 |
| A2480 | Ductwork mains Level 1 | +30 wd | 1 |
| A2510 | Domestic water risers | +30 wd | 1 |
| A2520 | Sprinkler mains and risers | +30 wd | 1 |
| A2610 | Mechanical in-wall rough-in Level 1 Zone A | +30 wd | 1 |
| A2650 | In-wall services inspection Level 1 Zone A | +30 wd | 1 |
| A1960 CP | Erect structural steel Level 2 Zone C | +28 wd | 1 |
| A1970 | Metal deck Level 2 Zone C | +28 wd | 1 |
| A1980 | Concrete topping Level 2 Zone C | +28 wd | 1 |
| A1990 CP | Erect structural steel Level 2 Zone D | +22 wd | 1 |
| A2000 | Metal deck Level 2 Zone D | +22 wd | 1 |
| A2010 | Concrete topping Level 2 Zone D | +22 wd | 1 |
| A1590 | Shoring along the north property line | +21 wd | 1 |
| A2240 | Elevator shaft masonry | +19 wd | 1 |
| A2580 | Elevator rails, machine and car install | +19 wd | 1 |
| A2590 | Elevator inspection and licence (TSSA) | +19 wd | 1 |
| A1220 | Curtain wall and windows shop drawings: consultant review | +18 wd | 1 |
| A1230 | Curtain wall and windows: fabricate and deliver | +18 wd | 1 |
| A1790 | Footing inspection Zone C | +16 wd | 1 |
| A1780 | Footings Zone C | +15 wd | 1 |
| A1840 | Footings Zone D | +15 wd | 1 |
| A1850 | Footing inspection Zone D | +15 wd | 1 |
| A1800 | Foundation walls Zone C | +12 wd | 1 |
| A1810 | Waterproofing and perimeter drainage Zone C | +12 wd | 1 |
| A1820 | Underslab services Zone C | +12 wd | 1 |
| A1830 | Slab on grade Zone C | +12 wd | 1 |
| A1860 | Foundation walls Zone D | +12 wd | 1 |
| A1870 | Waterproofing and perimeter drainage Zone D | +12 wd | 1 |
| A1880 | Underslab services Zone D | +12 wd | 1 |
| A2860 | Layout and partition framing Level 1 Zone C | +12 wd | 1 |
| A2870 | Mechanical in-wall rough-in Level 1 Zone C | +12 wd | 1 |
| A2880 | Plumbing in-wall rough-in Level 1 Zone C | +12 wd | 1 |
| A2890 | Electrical in-wall rough-in Level 1 Zone C | +12 wd | 1 |
| A2900 | Sprinkler branch piping Level 1 Zone C | +12 wd | 1 |
| A2910 | In-wall services inspection Level 1 Zone C | +12 wd | 1 |
| A1650 | Backfill and compact at foundations | +11 wd | 1 |
| A1890 | Slab on grade Zone D | +11 wd | 1 |
| A2990 | Layout and partition framing Level 1 Zone D | +11 wd | 1 |
| A3000 | Mechanical in-wall rough-in Level 1 Zone D | +11 wd | 1 |
| A3010 | Plumbing in-wall rough-in Level 1 Zone D | +11 wd | 1 |
| A3020 | Electrical in-wall rough-in Level 1 Zone D | +11 wd | 1 |
| A3030 | Sprinkler branch piping Level 1 Zone D | +11 wd | 1 |
| A3040 | In-wall services inspection Level 1 Zone D | +11 wd | 1 |
| A4160 | Granular base for parking and drive | +11 wd | 1 |
| A4170 | Concrete curbs and sidewalks | +11 wd | 1 |
| A4180 | Site lighting bases and poles | +11 wd | 1 |
| A4190 | Asphalt paving | +11 wd | 1 |
| A4200 | Landscaping and sod | +11 wd | 1 |
| A4210 | Line painting and signage | +11 wd | 1 |
| A4390 | Landscape establishment and warranty maintenance | +11 wd | 1 |
| A1150 | Structural steel shop drawings: prepare and submit | +10 wd | 1 |
| A1160 | Structural steel shop drawings: consultant review | +10 wd | 1 |
| A1170 | Structural steel: fabricate and deliver | +10 wd | 1 |
| A1640 | Municipal service connection inspection | +3 wd | 1 |
| A1090 | Site survey and building layout | +2 wd | 1 |
Window 1: Baseline → Current
05-May-2025 → 15-Oct-2025 · shift +86 wd| Code | Activity | Prior Duration | Later Duration | Change (wd) |
|---|---|---|---|---|
| A2260 | Curtain wall and windows, North elevation | 12 wd | 15 wd | +3 wd |
| A2300 | Curtain wall and windows, East elevation | 12 wd | 15 wd | +3 wd |
| A2340 | Curtain wall and windows, South elevation | 12 wd | 15 wd | +3 wd |
| A2380 | Curtain wall and windows, West elevation | 12 wd | 15 wd | +3 wd |
| A3610 | Flooring Level 2 Zone D | 4 wd | 7 wd | +3 wd |
| A3620 | Doors, hardware and millwork Level 2 Zone D | 4 wd | 7 wd | +3 wd |
| A3630 | Final paint and finishes Level 2 Zone D | 3 wd | 5 wd | +2 wd |
| Code | Activity | Prior Finish | Later Finish | Slip | Responsible Party | Cause Notes |
|---|---|---|---|---|---|---|
| A1040 CP | Substantial Performance of the Work | 10-Apr-2026 | 13-Aug-2026 | +86 wd | cascade | |
| A1050 CP | Ready for Owner Takeover | 01-May-2026 | 03-Sep-2026 | +86 wd | cascade | |
| A1060 CP | Total Performance of the Work | 01-May-2026 | 03-Sep-2026 | +86 wd | cascade | |
| A4330 CP | Deficiency review with the consultant | 02-Apr-2026 | 06-Aug-2026 | +86 wd | cascade | |
| A4340 CP | Substantial performance certification | 10-Apr-2026 | 13-Aug-2026 | +86 wd | cascade | |
| A4370 | Operation and maintenance manuals | 17-Apr-2026 | 20-Aug-2026 | +86 wd | cascade | |
| A4380 CP | Deficiency correction | 01-May-2026 | 03-Sep-2026 | +86 wd | cascade | |
| A4410 CP | Owner furniture and fit-out (by others) | 01-May-2026 | 03-Sep-2026 | +86 wd | cascade | |
| A4420 | Owner IT and security installation (by others) | 24-Apr-2026 | 27-Aug-2026 | +86 wd | cascade | |
| A3630 CP | Final paint and finishes Level 2 Zone D | 26-Mar-2026 | 24-Jul-2026 | +83 wd | Contractor | Level 2 finishing re-planned: flooring crew shared with another project |
| A3620 CP | Doors, hardware and millwork Level 2 Zone D | 23-Mar-2026 | 17-Jul-2026 | +81 wd | Contractor | Level 2 finishing re-planned: flooring crew shared with another project |
| A3610 CP | Flooring Level 2 Zone D | 17-Mar-2026 | 08-Jul-2026 | +78 wd | Contractor | Level 2 finishing re-planned: flooring crew shared with another project |
| A3220 | Flooring Level 2 Zone A | 19-Feb-2026 | 08-Jun-2026 | +75 wd | cascade | |
| A3230 | Doors, hardware and millwork Level 2 Zone A | 25-Feb-2026 | 12-Jun-2026 | +75 wd | cascade | |
| A3240 | Final paint and finishes Level 2 Zone A | 02-Mar-2026 | 17-Jun-2026 | +75 wd | cascade | |
| A3350 | Flooring Level 2 Zone B | 27-Feb-2026 | 16-Jun-2026 | +75 wd | cascade | |
| A3360 | Doors, hardware and millwork Level 2 Zone B | 05-Mar-2026 | 22-Jun-2026 | +75 wd | cascade | |
| A3370 | Final paint and finishes Level 2 Zone B | 10-Mar-2026 | 25-Jun-2026 | +75 wd | cascade | |
| A3480 | Flooring Level 2 Zone C | 09-Mar-2026 | 24-Jun-2026 | +75 wd | cascade | |
| A3490 | Doors, hardware and millwork Level 2 Zone C | 13-Mar-2026 | 30-Jun-2026 | +75 wd | cascade | |
| A3500 | Final paint and finishes Level 2 Zone C | 18-Mar-2026 | 06-Jul-2026 | +75 wd | cascade | |
| A3180 CP | Drywall board Level 2 Zone A | 28-Jan-2026 | 14-May-2026 | +74 wd | Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope |
| A3190 CP | Tape, mud and sand Level 2 Zone A | 03-Feb-2026 | 21-May-2026 | +74 wd | Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope |
| A3200 CP | Prime paint Level 2 Zone A | 05-Feb-2026 | 25-May-2026 | +74 wd | Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope |
| A3310 | Drywall board Level 2 Zone B | 05-Feb-2026 | 22-May-2026 | +73 wd | cascade | |
| A3320 | Tape, mud and sand Level 2 Zone B | 11-Feb-2026 | 28-May-2026 | +73 wd | cascade | |
| A3330 | Prime paint Level 2 Zone B | 13-Feb-2026 | 01-Jun-2026 | +73 wd | cascade | |
| A3440 | Drywall board Level 2 Zone C | 13-Feb-2026 | 29-May-2026 | +72 wd | cascade | |
| A3450 | Tape, mud and sand Level 2 Zone C | 20-Feb-2026 | 04-Jun-2026 | +72 wd | cascade | |
| A3460 | Prime paint Level 2 Zone C | 24-Feb-2026 | 08-Jun-2026 | +72 wd | cascade | |
| A3570 | Drywall board Level 2 Zone D | 24-Feb-2026 | 05-Jun-2026 | +71 wd | cascade | |
| A3580 | Tape, mud and sand Level 2 Zone D | 02-Mar-2026 | 11-Jun-2026 | +71 wd | cascade | |
| A3590 | Prime paint Level 2 Zone D | 04-Mar-2026 | 15-Jun-2026 | +71 wd | cascade | |
| A3090 CP | Flooring Level 1 Zone D | 05-Jan-2026 | 10-Apr-2026 | +67 wd | Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope |
| A3100 CP | Doors, hardware and millwork Level 1 Zone D | 09-Jan-2026 | 16-Apr-2026 | +67 wd | Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope |
| A3110 CP | Final paint and finishes Level 1 Zone D | 14-Jan-2026 | 21-Apr-2026 | +67 wd | Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope |
| A3120 CP | Layout and partition framing Level 2 Zone A | 19-Jan-2026 | 24-Apr-2026 | +67 wd | Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope |
| A3130 | Mechanical in-wall rough-in Level 2 Zone A | 20-Jan-2026 | 27-Apr-2026 | +67 wd | cascade | |
| A3140 | Plumbing in-wall rough-in Level 2 Zone A | 19-Jan-2026 | 24-Apr-2026 | +67 wd | cascade | |
| A3150 CP | Electrical in-wall rough-in Level 2 Zone A | 20-Jan-2026 | 27-Apr-2026 | +67 wd | Contractor | Interior chain lengthened by the contractor's re-planned ceiling scope |
| A3160 | Sprinkler branch piping Level 2 Zone A | 19-Jan-2026 | 24-Apr-2026 | +67 wd | cascade | |
| A3170 | In-wall services inspection Level 2 Zone A | 21-Jan-2026 | 28-Apr-2026 | +67 wd | cascade | |
| A3250 | Layout and partition framing Level 2 Zone B | 27-Jan-2026 | 04-May-2026 | +67 wd | cascade | |
| A3260 | Mechanical in-wall rough-in Level 2 Zone B | 28-Jan-2026 | 05-May-2026 | +67 wd | cascade | |
| A3270 | Plumbing in-wall rough-in Level 2 Zone B | 27-Jan-2026 | 04-May-2026 | +67 wd | cascade | |
| A3280 | Electrical in-wall rough-in Level 2 Zone B | 28-Jan-2026 | 05-May-2026 | +67 wd | cascade | |
| A3290 | Sprinkler branch piping Level 2 Zone B | 27-Jan-2026 | 04-May-2026 | +67 wd | cascade | |
| A3300 | In-wall services inspection Level 2 Zone B | 29-Jan-2026 | 06-May-2026 | +67 wd | cascade | |
| A3380 | Layout and partition framing Level 2 Zone C | 04-Feb-2026 | 12-May-2026 | +67 wd | cascade | |
| A3390 | Mechanical in-wall rough-in Level 2 Zone C | 05-Feb-2026 | 13-May-2026 | +67 wd | cascade | |
| A3400 | Plumbing in-wall rough-in Level 2 Zone C | 04-Feb-2026 | 12-May-2026 | +67 wd | cascade | |
| A3410 | Electrical in-wall rough-in Level 2 Zone C | 05-Feb-2026 | 13-May-2026 | +67 wd | cascade | |
| A3420 | Sprinkler branch piping Level 2 Zone C | 04-Feb-2026 | 12-May-2026 | +67 wd | cascade | |
| A3430 | In-wall services inspection Level 2 Zone C | 06-Feb-2026 | 14-May-2026 | +67 wd | cascade | |
| A3510 | Layout and partition framing Level 2 Zone D | 12-Feb-2026 | 21-May-2026 | +67 wd | cascade | |
| A3520 | Mechanical in-wall rough-in Level 2 Zone D | 13-Feb-2026 | 22-May-2026 | +67 wd | cascade | |
| A3530 | Plumbing in-wall rough-in Level 2 Zone D | 12-Feb-2026 | 21-May-2026 | +67 wd | cascade | |
| A3540 | Electrical in-wall rough-in Level 2 Zone D | 13-Feb-2026 | 22-May-2026 | +67 wd | cascade | |
| A3550 | Sprinkler branch piping Level 2 Zone D | 12-Feb-2026 | 21-May-2026 | +67 wd | cascade | |
| A3560 | In-wall services inspection Level 2 Zone D | 17-Feb-2026 | 25-May-2026 | +67 wd | cascade | |
| A4130 | Flooring Level 3 Zone D | 05-Jan-2026 | 10-Apr-2026 | +67 wd | cascade | |
| A4140 | Doors, hardware and millwork Level 3 Zone D | 09-Jan-2026 | 16-Apr-2026 | +67 wd | cascade | |
| A4150 | Final paint and finishes Level 3 Zone D | 14-Jan-2026 | 21-Apr-2026 | +67 wd | cascade | |
| A4250 | Fire alarm verification | 19-Jan-2026 | 24-Apr-2026 | +67 wd | cascade | |
| A4310 | Fire department inspection | 21-Jan-2026 | 28-Apr-2026 | +67 wd | cascade | |
| A4320 | Occupancy permit inspection | 26-Jan-2026 | 01-May-2026 | +67 wd | cascade | |
| A4350 | Final cleaning | 21-Jan-2026 | 28-Apr-2026 | +67 wd | cascade | |
| A2960 | Flooring Level 1 Zone C | 24-Dec-2025 | 01-Apr-2026 | +66 wd | cascade | |
| A2970 | Doors, hardware and millwork Level 1 Zone C | 02-Jan-2026 | 08-Apr-2026 | +66 wd | cascade | |
| A2980 | Final paint and finishes Level 1 Zone C | 07-Jan-2026 | 13-Apr-2026 | +66 wd | cascade | |
| A4000 | Flooring Level 3 Zone C | 24-Dec-2025 | 01-Apr-2026 | +66 wd | cascade | |
| A4010 | Doors, hardware and millwork Level 3 Zone C | 02-Jan-2026 | 08-Apr-2026 | +66 wd | cascade | |
| A4020 | Final paint and finishes Level 3 Zone C | 07-Jan-2026 | 13-Apr-2026 | +66 wd | cascade | |
| A2830 | Flooring Level 1 Zone B | 17-Dec-2025 | 24-Mar-2026 | +65 wd | cascade | |
| A2840 | Doors, hardware and millwork Level 1 Zone B | 23-Dec-2025 | 30-Mar-2026 | +65 wd | cascade | |
| A2850 | Final paint and finishes Level 1 Zone B | 30-Dec-2025 | 02-Apr-2026 | +65 wd | cascade | |
| A3870 | Flooring Level 3 Zone B | 17-Dec-2025 | 24-Mar-2026 | +65 wd | cascade | |
| A3880 | Doors, hardware and millwork Level 3 Zone B | 23-Dec-2025 | 30-Mar-2026 | +65 wd | cascade | |
| A3890 | Final paint and finishes Level 3 Zone B | 30-Dec-2025 | 02-Apr-2026 | +65 wd | cascade | |
| A2700 | Flooring Level 1 Zone A | 10-Dec-2025 | 16-Mar-2026 | +64 wd | cascade | |
| A2710 | Doors, hardware and millwork Level 1 Zone A | 16-Dec-2025 | 20-Mar-2026 | +64 wd | cascade | |
| A2720 | Final paint and finishes Level 1 Zone A | 19-Dec-2025 | 25-Mar-2026 | +64 wd | cascade | |
| A3740 | Flooring Level 3 Zone A | 10-Dec-2025 | 16-Mar-2026 | +64 wd | cascade | |
| A3750 | Doors, hardware and millwork Level 3 Zone A | 16-Dec-2025 | 20-Mar-2026 | +64 wd | cascade | |
| A3760 | Final paint and finishes Level 3 Zone A | 19-Dec-2025 | 25-Mar-2026 | +64 wd | cascade | |
| A1020 CP | Building Weathertight | 12-Nov-2025 | 12-Feb-2026 | +63 wd | cascade | |
| A2380 CP | Curtain wall and windows, West elevation | 12-Nov-2025 | 12-Feb-2026 | +63 wd | Owner | Curtain wall: RFI-14 anchor and sill revision adds field work at every floor |
| A2660 CP | Drywall board Level 1 Zone A | 19-Nov-2025 | 20-Feb-2026 | +63 wd | Owner | Drywall waits on the weathertight date set by the envelope |
| A2670 CP | Tape, mud and sand Level 1 Zone A | 25-Nov-2025 | 26-Feb-2026 | +63 wd | Owner | Drywall waits on the weathertight date set by the envelope |
| A2680 CP | Prime paint Level 1 Zone A | 27-Nov-2025 | 02-Mar-2026 | +63 wd | Owner | Drywall waits on the weathertight date set by the envelope |
| A2790 | Drywall board Level 1 Zone B | 26-Nov-2025 | 27-Feb-2026 | +63 wd | cascade | |
| A2800 | Tape, mud and sand Level 1 Zone B | 02-Dec-2025 | 05-Mar-2026 | +63 wd | cascade | |
| A2810 | Prime paint Level 1 Zone B | 04-Dec-2025 | 09-Mar-2026 | +63 wd | cascade | |
| A2920 | Drywall board Level 1 Zone C | 03-Dec-2025 | 06-Mar-2026 | +63 wd | cascade | |
| A2930 | Tape, mud and sand Level 1 Zone C | 09-Dec-2025 | 12-Mar-2026 | +63 wd | cascade | |
| A2940 | Prime paint Level 1 Zone C | 11-Dec-2025 | 16-Mar-2026 | +63 wd | cascade | |
| A3050 | Drywall board Level 1 Zone D | 10-Dec-2025 | 13-Mar-2026 | +63 wd | cascade | |
| A3060 | Tape, mud and sand Level 1 Zone D | 16-Dec-2025 | 19-Mar-2026 | +63 wd | cascade | |
| A3070 | Prime paint Level 1 Zone D | 18-Dec-2025 | 23-Mar-2026 | +63 wd | cascade | |
| A3700 | Drywall board Level 3 Zone A | 19-Nov-2025 | 20-Feb-2026 | +63 wd | cascade | |
| A3710 | Tape, mud and sand Level 3 Zone A | 25-Nov-2025 | 26-Feb-2026 | +63 wd | cascade | |
| A3720 | Prime paint Level 3 Zone A | 27-Nov-2025 | 02-Mar-2026 | +63 wd | cascade | |
| A3830 | Drywall board Level 3 Zone B | 26-Nov-2025 | 27-Feb-2026 | +63 wd | cascade | |
| A3840 | Tape, mud and sand Level 3 Zone B | 02-Dec-2025 | 05-Mar-2026 | +63 wd | cascade | |
| A3850 | Prime paint Level 3 Zone B | 04-Dec-2025 | 09-Mar-2026 | +63 wd | cascade | |
| A3960 | Drywall board Level 3 Zone C | 03-Dec-2025 | 06-Mar-2026 | +63 wd | cascade | |
| A3970 | Tape, mud and sand Level 3 Zone C | 09-Dec-2025 | 12-Mar-2026 | +63 wd | cascade | |
| A3980 | Prime paint Level 3 Zone C | 11-Dec-2025 | 16-Mar-2026 | +63 wd | cascade | |
| A4090 | Drywall board Level 3 Zone D | 10-Dec-2025 | 13-Mar-2026 | +63 wd | cascade | |
| A4100 | Tape, mud and sand Level 3 Zone D | 16-Dec-2025 | 19-Mar-2026 | +63 wd | cascade | |
| A4110 | Prime paint Level 3 Zone D | 18-Dec-2025 | 23-Mar-2026 | +63 wd | cascade | |
| A2340 CP | Curtain wall and windows, South elevation | 27-Oct-2025 | 22-Jan-2026 | +60 wd | Owner | Curtain wall: RFI-14 anchor and sill revision adds field work at every floor |
| A2300 CP | Curtain wall and windows, East elevation | 08-Oct-2025 | 31-Dec-2025 | +57 wd | Owner | Curtain wall: RFI-14 anchor and sill revision adds field work at every floor |
| A2260 CP | Curtain wall and windows, North elevation | 22-Sep-2025 | 08-Dec-2025 | +54 wd | Owner | Curtain wall: RFI-14 anchor and sill revision adds field work at every floor |
| A2020 CP | Erect structural steel Level 3 Zone A | 18-Aug-2025 | 30-Oct-2025 | +51 wd | Owner | Follows the Level 2 erection held for CD-03 |
| A2030 | Metal deck Level 3 Zone A | 21-Aug-2025 | 04-Nov-2025 | +51 wd | cascade | |
| A2040 | Concrete topping Level 3 Zone A | 26-Aug-2025 | 07-Nov-2025 | +51 wd | cascade | |
| A2140 CP | Erect structural steel Roof Zone A | 22-Aug-2025 | 05-Nov-2025 | +51 wd | Owner | Follows the Level 2 erection held for CD-03 |
| A2150 | Metal deck Roof Zone A | 27-Aug-2025 | 10-Nov-2025 | +51 wd | cascade | |
| A2250 CP | Exterior sheathing and air/vapour barrier, North elevation | 04-Sep-2025 | 17-Nov-2025 | +51 wd | Owner | Envelope follows the roof steel held for CD-03 |
| A2290 | Exterior sheathing and air/vapour barrier, East elevation | 16-Sep-2025 | 27-Nov-2025 | +51 wd | Contractor | Envelope follows the roof steel delayed by the Zone B crew |
| A2490 | Ductwork mains Level 2 | 08-Sep-2025 | 19-Nov-2025 | +51 wd | cascade | |
| A2500 | Ductwork mains Level 3 | 09-Sep-2025 | 20-Nov-2025 | +51 wd | cascade | |
| A3640 | Layout and partition framing Level 3 Zone A | 04-Sep-2025 | 17-Nov-2025 | +51 wd | cascade | |
| A3650 | Mechanical in-wall rough-in Level 3 Zone A | 16-Sep-2025 | 27-Nov-2025 | +51 wd | cascade | |
| A3660 | Plumbing in-wall rough-in Level 3 Zone A | 04-Sep-2025 | 17-Nov-2025 | +51 wd | cascade | |
| A3670 | Electrical in-wall rough-in Level 3 Zone A | 05-Sep-2025 | 18-Nov-2025 | +51 wd | cascade | |
| A3680 | Sprinkler branch piping Level 3 Zone A | 04-Sep-2025 | 17-Nov-2025 | +51 wd | cascade | |
| A3690 | In-wall services inspection Level 3 Zone A | 17-Sep-2025 | 28-Nov-2025 | +51 wd | cascade | |
| A2330 | Exterior sheathing and air/vapour barrier, South elevation | 29-Sep-2025 | 09-Dec-2025 | +50 wd | Contractor | Envelope follows the roof steel delayed by the Zone B crew |
| A3770 | Layout and partition framing Level 3 Zone B | 15-Sep-2025 | 25-Nov-2025 | +50 wd | cascade | |
| A3780 | Mechanical in-wall rough-in Level 3 Zone B | 16-Sep-2025 | 26-Nov-2025 | +50 wd | cascade | |
| A3790 | Plumbing in-wall rough-in Level 3 Zone B | 15-Sep-2025 | 25-Nov-2025 | +50 wd | cascade | |
| A3800 | Electrical in-wall rough-in Level 3 Zone B | 16-Sep-2025 | 26-Nov-2025 | +50 wd | cascade | |
| A3810 | Sprinkler branch piping Level 3 Zone B | 15-Sep-2025 | 25-Nov-2025 | +50 wd | cascade | |
| A3820 | In-wall services inspection Level 3 Zone B | 17-Sep-2025 | 27-Nov-2025 | +50 wd | cascade | |
| A2050 | Erect structural steel Level 3 Zone B | 27-Aug-2025 | 05-Nov-2025 | +48 wd | Contractor | Follows Level 2 Zone B and its short-handed crew |
| A2060 | Metal deck Level 3 Zone B | 02-Sep-2025 | 10-Nov-2025 | +48 wd | cascade | |
| A2070 | Concrete topping Level 3 Zone B | 05-Sep-2025 | 13-Nov-2025 | +48 wd | cascade | |
| A2160 | Erect structural steel Roof Zone B | 03-Sep-2025 | 11-Nov-2025 | +48 wd | Contractor | Follows Level 2 Zone B and its short-handed crew |
| A2170 | Metal deck Roof Zone B | 08-Sep-2025 | 14-Nov-2025 | +48 wd | cascade | |
| A2370 | Exterior sheathing and air/vapour barrier, West elevation | 14-Oct-2025 | 19-Dec-2025 | +48 wd | cascade | |
| A2280 | Sealants and flashings, North elevation | 26-Sep-2025 | 03-Dec-2025 | +47 wd | cascade | |
| A2320 | Sealants and flashings, East elevation | 08-Oct-2025 | 15-Dec-2025 | +47 wd | cascade | |
| A2360 | Sealants and flashings, South elevation | 22-Oct-2025 | 29-Dec-2025 | +46 wd | cascade | |
| A3900 | Layout and partition framing Level 3 Zone C | 29-Sep-2025 | 03-Dec-2025 | +46 wd | cascade | |
| A3910 | Mechanical in-wall rough-in Level 3 Zone C | 30-Sep-2025 | 04-Dec-2025 | +46 wd | cascade | |
| A3920 | Plumbing in-wall rough-in Level 3 Zone C | 29-Sep-2025 | 03-Dec-2025 | +46 wd | cascade | |
| A3930 | Electrical in-wall rough-in Level 3 Zone C | 30-Sep-2025 | 04-Dec-2025 | +46 wd | cascade | |
| A3940 | Sprinkler branch piping Level 3 Zone C | 29-Sep-2025 | 03-Dec-2025 | +46 wd | cascade | |
| A3950 | In-wall services inspection Level 3 Zone C | 01-Oct-2025 | 05-Dec-2025 | +46 wd | cascade | |
| A4220 | Exterior stairs and barrier-free ramp | 24-Oct-2025 | 31-Dec-2025 | +46 wd | cascade | |
| A4230 | Entrance canopy steel and soffit | 23-Oct-2025 | 30-Dec-2025 | +46 wd | cascade | |
| A2400 | Sealants and flashings, West elevation | 05-Nov-2025 | 09-Jan-2026 | +44 wd | cascade | |
| A2080 | Erect structural steel Level 3 Zone C | 11-Sep-2025 | 11-Nov-2025 | +42 wd | Contractor | Follows Level 2 Zone B and its short-handed crew |
| A2090 | Metal deck Level 3 Zone C | 16-Sep-2025 | 14-Nov-2025 | +42 wd | cascade | |
| A2100 | Concrete topping Level 3 Zone C | 19-Sep-2025 | 19-Nov-2025 | +42 wd | cascade | |
| A2180 | Erect structural steel Roof Zone C | 17-Sep-2025 | 17-Nov-2025 | +42 wd | Contractor | Follows Level 2 Zone B and its short-handed crew |
| A2190 | Metal deck Roof Zone C | 22-Sep-2025 | 20-Nov-2025 | +42 wd | cascade | |
| A4030 | Layout and partition framing Level 3 Zone D | 14-Oct-2025 | 11-Dec-2025 | +42 wd | cascade | |
| A4040 | Mechanical in-wall rough-in Level 3 Zone D | 15-Oct-2025 | 12-Dec-2025 | +42 wd | cascade | |
| A4050 | Plumbing in-wall rough-in Level 3 Zone D | 14-Oct-2025 | 11-Dec-2025 | +42 wd | cascade | |
| A4060 | Electrical in-wall rough-in Level 3 Zone D | 15-Oct-2025 | 12-Dec-2025 | +42 wd | cascade | |
| A4070 | Sprinkler branch piping Level 3 Zone D | 14-Oct-2025 | 11-Dec-2025 | +42 wd | cascade | |
| A4080 | In-wall services inspection Level 3 Zone D | 16-Oct-2025 | 15-Dec-2025 | +42 wd | cascade | |
| A4260 | Sprinkler flush and hydrostatic test | 17-Oct-2025 | 16-Dec-2025 | +42 wd | cascade | |
| A2420 | Roof flashings and penetrations | 30-Oct-2025 | 22-Dec-2025 | +37 wd | cascade | |
| A2110 | Erect structural steel Level 3 Zone D | 25-Sep-2025 | 17-Nov-2025 | +36 wd | cascade | |
| A2120 | Metal deck Level 3 Zone D | 30-Sep-2025 | 20-Nov-2025 | +36 wd | cascade | |
| A2130 | Concrete topping Level 3 Zone D | 03-Oct-2025 | 25-Nov-2025 | +36 wd | cascade | |
| A2200 | Erect structural steel Roof Zone D | 01-Oct-2025 | 21-Nov-2025 | +36 wd | cascade | |
| A2210 | Metal deck Roof Zone D | 06-Oct-2025 | 26-Nov-2025 | +36 wd | cascade | |
| A2230 | Steel stairs and railings | 27-Oct-2025 | 16-Dec-2025 | +36 wd | cascade | |
| A2410 | Roof insulation and membrane | 23-Oct-2025 | 12-Dec-2025 | +36 wd | cascade | |
| A2430 | Rooftop unit curbs | 16-Oct-2025 | 05-Dec-2025 | +36 wd | cascade | |
| A2440 | Set rooftop air handling units | 21-Oct-2025 | 10-Dec-2025 | +36 wd | cascade | |
| A2450 | Roof drains and leaders | 15-Oct-2025 | 04-Dec-2025 | +36 wd | cascade | |
| A4270 | Test, adjust and balance | 18-Nov-2025 | 12-Jan-2026 | +36 wd | cascade | |
| A4280 | Building automation functional testing | 28-Nov-2025 | 22-Jan-2026 | +36 wd | cascade | |
| A4290 | Mechanical commissioning | 04-Nov-2025 | 24-Dec-2025 | +36 wd | cascade | |
| A4360 | Owner training | 05-Dec-2025 | 29-Jan-2026 | +36 wd | cascade | |
| A4400 | Seasonal commissioning of heating and cooling | 16-Jan-2026 | 10-Mar-2026 | +36 wd | cascade | |
| A1930 | Erect structural steel Level 2 Zone B | 21-Aug-2025 | 10-Oct-2025 | +35 wd | Contractor | Short-handed steel erection crew, Level 2 Zone B |
| A1940 | Metal deck Level 2 Zone B | 26-Aug-2025 | 15-Oct-2025 | +34 wd | cascade | |
| A1950 | Concrete topping Level 2 Zone B | 29-Aug-2025 | 20-Oct-2025 | +34 wd | cascade | |
| A1900 | Erect structural steel Level 2 Zone A | 12-Aug-2025 | 24-Sep-2025 | +30 wd | Owner | Level 2 erection held for the CD-03 atrium steel |
| A1910 | Metal deck Level 2 Zone A | 15-Aug-2025 | 29-Sep-2025 | +30 wd | cascade | |
| A1920 | Concrete topping Level 2 Zone A | 20-Aug-2025 | 02-Oct-2025 | +30 wd | cascade | |
| A2480 | Ductwork mains Level 1 | 02-Sep-2025 | 15-Oct-2025 | +30 wd | cascade | |
| A2510 | Domestic water risers | 28-Aug-2025 | 10-Oct-2025 | +30 wd | cascade | |
| A2520 | Sprinkler mains and risers | 02-Sep-2025 | 15-Oct-2025 | +30 wd | cascade | |
| A2610 | Mechanical in-wall rough-in Level 1 Zone A | 09-Sep-2025 | 22-Oct-2025 | +30 wd | cascade | |
| A2650 | In-wall services inspection Level 1 Zone A | 10-Sep-2025 | 23-Oct-2025 | +30 wd | cascade | |
| A1960 CP | Erect structural steel Level 2 Zone C | 05-Sep-2025 | 16-Oct-2025 | +28 wd | Contractor | Follows Level 2 Zone B and its short-handed crew |
| A1970 | Metal deck Level 2 Zone C | 10-Sep-2025 | 21-Oct-2025 | +28 wd | cascade | |
| A1980 | Concrete topping Level 2 Zone C | 15-Sep-2025 | 24-Oct-2025 | +28 wd | cascade | |
| A1990 CP | Erect structural steel Level 2 Zone D | 19-Sep-2025 | 22-Oct-2025 | +22 wd | Contractor | Follows Level 2 Zone B and its short-handed crew |
| A2000 | Metal deck Level 2 Zone D | 24-Sep-2025 | 27-Oct-2025 | +22 wd | cascade | |
| A2010 | Concrete topping Level 2 Zone D | 29-Sep-2025 | 30-Oct-2025 | +22 wd | cascade | |
| A1590 | Shoring along the north property line | 28-May-2025 | 26-Jun-2025 | +21 wd | cascade | |
| A2240 | Elevator shaft masonry | 17-Sep-2025 | 15-Oct-2025 | +19 wd | Contractor | Shaft masonry rework after a failed plumb check |
| A2580 | Elevator rails, machine and car install | 16-Oct-2025 | 12-Nov-2025 | +19 wd | cascade | |
| A2590 | Elevator inspection and licence (TSSA) | 20-Oct-2025 | 14-Nov-2025 | +19 wd | cascade | |
| A1220 | Curtain wall and windows shop drawings: consultant review | 16-Jun-2025 | 11-Jul-2025 | +18 wd | cascade | |
| A1230 | Curtain wall and windows: fabricate and deliver | 27-Aug-2025 | 23-Sep-2025 | +18 wd | cascade | |
| A1790 | Footing inspection Zone C | 11-Aug-2025 | 03-Sep-2025 | +16 wd | Owner | Unsuitable soil at Zone C; CD-02 engineered fill and re-inspection |
| A1780 | Footings Zone C | 08-Aug-2025 | 29-Aug-2025 | +15 wd | Owner | Unsuitable soil at Zone C; CD-02 engineered fill and re-inspection |
| A1840 | Footings Zone D | 20-Aug-2025 | 11-Sep-2025 | +15 wd | cascade | |
| A1850 | Footing inspection Zone D | 21-Aug-2025 | 12-Sep-2025 | +15 wd | cascade | |
| A1800 | Foundation walls Zone C | 29-Aug-2025 | 17-Sep-2025 | +12 wd | cascade | |
| A1810 | Waterproofing and perimeter drainage Zone C | 05-Sep-2025 | 23-Sep-2025 | +12 wd | cascade | |
| A1820 | Underslab services Zone C | 08-Sep-2025 | 24-Sep-2025 | +12 wd | cascade | |
| A1830 | Slab on grade Zone C | 15-Sep-2025 | 01-Oct-2025 | +12 wd | cascade | |
| A1860 | Foundation walls Zone D | 15-Sep-2025 | 01-Oct-2025 | +12 wd | cascade | |
| A1870 | Waterproofing and perimeter drainage Zone D | 19-Sep-2025 | 07-Oct-2025 | +12 wd | cascade | |
| A1880 | Underslab services Zone D | 22-Sep-2025 | 08-Oct-2025 | +12 wd | cascade | |
| A2860 | Layout and partition framing Level 1 Zone C | 23-Sep-2025 | 09-Oct-2025 | +12 wd | cascade | |
| A2870 | Mechanical in-wall rough-in Level 1 Zone C | 24-Sep-2025 | 10-Oct-2025 | +12 wd | cascade | |
| A2880 | Plumbing in-wall rough-in Level 1 Zone C | 23-Sep-2025 | 09-Oct-2025 | +12 wd | cascade | |
| A2890 | Electrical in-wall rough-in Level 1 Zone C | 24-Sep-2025 | 10-Oct-2025 | +12 wd | cascade | |
| A2900 | Sprinkler branch piping Level 1 Zone C | 23-Sep-2025 | 09-Oct-2025 | +12 wd | cascade | |
| A2910 | In-wall services inspection Level 1 Zone C | 25-Sep-2025 | 14-Oct-2025 | +12 wd | cascade | |
| A1650 | Backfill and compact at foundations | 29-Sep-2025 | 15-Oct-2025 | +11 wd | cascade | |
| A1890 | Slab on grade Zone D | 29-Sep-2025 | 15-Oct-2025 | +11 wd | cascade | |
| A2990 | Layout and partition framing Level 1 Zone D | 07-Oct-2025 | 23-Oct-2025 | +11 wd | cascade | |
| A3000 | Mechanical in-wall rough-in Level 1 Zone D | 08-Oct-2025 | 24-Oct-2025 | +11 wd | cascade | |
| A3010 | Plumbing in-wall rough-in Level 1 Zone D | 07-Oct-2025 | 23-Oct-2025 | +11 wd | cascade | |
| A3020 | Electrical in-wall rough-in Level 1 Zone D | 08-Oct-2025 | 24-Oct-2025 | +11 wd | cascade | |
| A3030 | Sprinkler branch piping Level 1 Zone D | 07-Oct-2025 | 23-Oct-2025 | +11 wd | cascade | |
| A3040 | In-wall services inspection Level 1 Zone D | 09-Oct-2025 | 27-Oct-2025 | +11 wd | cascade | |
| A4160 | Granular base for parking and drive | 07-Oct-2025 | 23-Oct-2025 | +11 wd | cascade | |
| A4170 | Concrete curbs and sidewalks | 20-Oct-2025 | 04-Nov-2025 | +11 wd | cascade | |
| A4180 | Site lighting bases and poles | 09-Oct-2025 | 27-Oct-2025 | +11 wd | cascade | |
| A4190 | Asphalt paving | 24-Oct-2025 | 10-Nov-2025 | +11 wd | cascade | |
| A4200 | Landscaping and sod | 30-Oct-2025 | 14-Nov-2025 | +11 wd | cascade | |
| A4210 | Line painting and signage | 28-Oct-2025 | 12-Nov-2025 | +11 wd | cascade | |
| A4390 | Landscape establishment and warranty maintenance | 27-Jan-2026 | 11-Feb-2026 | +11 wd | cascade | |
| A1150 | Structural steel shop drawings: prepare and submit | 02-Jun-2025 | 16-Jun-2025 | +10 wd | Contractor | Structural steel shop drawings submitted late by the fabricator |
| A1160 | Structural steel shop drawings: consultant review | 16-Jun-2025 | 30-Jun-2025 | +10 wd | cascade | |
| A1170 | Structural steel: fabricate and deliver | 06-Aug-2025 | 20-Aug-2025 | +10 wd | Contractor | Structural steel shop drawings submitted late by the fabricator |
| A1640 | Municipal service connection inspection | 09-Jul-2025 | 14-Jul-2025 | +3 wd | cascade | |
| A1090 | Site survey and building layout | 07-May-2025 | 09-May-2025 | +2 wd | cascade |