Ontario Community College - B2 (Demo Data) 1 window analyzed: Baseline → Current
Scheduled completion slipped 21 working days, from 31-Aug-2026 to 30-Sep-2026, measured across 1 window (01-Apr-2025 to 01-Jul-2025). Of that movement, the slip registers attribute 9 wd to the Owner, 12 wd to the Contractor; nothing remains unattributed. The finish driver at the final data date is A4240 (Minor Deficiencies & Touch-ups), at the end of the driving critical-path chain. On the critical path, 6 activities grew in scheduler-estimated duration (+24 wd) and 9 reduced (-304 wd); the full per-activity tables follow. 309 activities moved their finish dates over the period; every one is listed in the registers below, none omitted.
Windows Overview
per-window shift and cumulative vs baseline, working days| Window | Period | Shift (wd) | Cumulative vs Baseline (wd) | CP Activities | CP Duration Changes | Slipped Activities |
|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | +21 wd | +21 wd | 39 | 15 | 281 |
Window Shift Trend
signed completion shift per window (working days)Cumulative Attribution Summary
party share of project slip-daysConcurrent Delay Matrix
per-window × per-party attribution grid| Window | Period | Owner | Contractor | Concurrent | Force Majeure | Unattributed | Window Shift (wd) | Finish Driver |
|---|---|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | +9 wd | +12 wd | 0 | 0 | 0 | +21 wd | A4240 early_end_date |
| Cumulative | project totals | +9 wd | +12 wd | 0 wd | 0 wd | 0 wd | +21 wd | 0 |
Slip Velocity & Acceleration
per-window slip-rate trend| Window | Period | Duration (wd) | Shift (wd) | Velocity (wd/wd) | Δ Acceleration | Midpoint Date | Half-Period Slip (wd) |
|---|---|---|---|---|---|---|---|
| Baseline → Current | 01-Apr-2025 → 01-Jul-2025 | 62 wd | +21 wd | +0.339 | 16-May-2025 | +10.5 wd |
WOET: worked versus on-time execution timeline
4-state day classification| Code | Activity | Baseline Period | Actual Period | Progress (wd) | Gain (wd) | Extended (wd) | Void (wd) |
|---|---|---|---|---|---|---|---|
| A1160 | TPO Roofing Shop Drawings | 05-Jun-2025 to 19-Jun-2025 | 09-Jul-2025 to 26-Aug-2025 | 0 wd | 0 wd | 35 wd | 11 wd |
| A3930 | Interior Demolition | 13-Jun-2025 to 07-Jul-2025 | 21-Jul-2025 to 02-Sep-2025 | 0 wd | 0 wd | 31 wd | 16 wd |
| A1460 | 23 25 00 - Water Treatment (R0) | 26-Jun-2025 to 04-Jul-2025 | 26-Jun-2025 to 12-Aug-2025 | 6 wd | 0 wd | 27 wd | 0 wd |
| A1280 | ACT Data sheet and Sample | 11-Jul-2025 to 25-Jul-2025 | 23-Jul-2025 to 27-Aug-2025 | 3 wd | 0 wd | 23 wd | 8 wd |
| A2500 | Install Rebar for Piers | 31-Jul-2025 to 08-Aug-2025 | 29-Jul-2025 to 08-Sep-2025 | 7 wd | 2 wd | 20 wd | 0 wd |
| A1120 | Cold-formed Metal Framing Shop Drawings | 05-Jun-2025 to 19-Jun-2025 | 26-Jun-2025 to 23-Jul-2025 | 0 wd | 0 wd | 19 wd | 11 wd |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | 05-Jun-2025 to 19-Jun-2025 | 20-Jun-2025 to 14-Jul-2025 | 0 wd | 0 wd | 16 wd | 11 wd |
| A1090 | Masonry and Mortar Samples & Data Sheets | 11-Jul-2025 to 25-Jul-2025 | 10-Jun-2025 to 18-Aug-2025 | 11 wd | 22 wd | 16 wd | 0 wd |
| A2280 | Under Pinning Inspection | 19-Jun-2025 to 20-Jun-2025 | 23-Jun-2025 to 14-Jul-2025 | 0 wd | 0 wd | 15 wd | 2 wd |
| A2520 | Form and Pour Foundation Piers | 08-Aug-2025 to 15-Aug-2025 | 11-Aug-2025 to 08-Sep-2025 | 5 wd | 0 wd | 15 wd | 1 wd |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | 09-Jul-2025 to 23-Jul-2025 | 09-Jul-2025 to 12-Aug-2025 | 11 wd | 0 wd | 14 wd | 0 wd |
| A2530 | Backfilling to U/S of Grade Beams | 15-Aug-2025 to 22-Aug-2025 | 11-Aug-2025 to 12-Sep-2025 | 6 wd | 4 wd | 14 wd | 0 wd |
| A1230 | Coiling Doors | 11-Jul-2025 to 25-Jul-2025 | 05-Aug-2025 to 21-Aug-2025 | 0 wd | 0 wd | 13 wd | 11 wd |
| A1580 | 26 50 00 - Lighting Fixtures | 27-Jun-2025 to 14-Jul-2025 | 01-Aug-2025 to 18-Aug-2025 | 0 wd | 0 wd | 12 wd | 11 wd |
| A1590 | 26 09 23 - Lighting Control (R0) | 12-Jun-2025 to 26-Jun-2025 | 01-Aug-2025 to 18-Aug-2025 | 0 wd | 0 wd | 12 wd | 11 wd |
| A1060 | Foundation Concrete Rebar Shop Drawing | 05-Jun-2025 to 19-Jun-2025 | 29-May-2025 to 08-Jul-2025 | 11 wd | 5 wd | 12 wd | 0 wd |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | 15-Jul-2025 to 29-Jul-2025 | 15-Jul-2025 to 14-Aug-2025 | 11 wd | 0 wd | 12 wd | 0 wd |
| A1050 | Ductbank Underpinning Drawing | 29-May-2025 to 12-Jun-2025 | 16-Jun-2025 to 30-Jun-2025 | 0 wd | 0 wd | 11 wd | 11 wd |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | 27-Jun-2025 to 14-Jul-2025 | 27-Jun-2025 to 29-Jul-2025 | 11 wd | 0 wd | 11 wd | 0 wd |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 11-Jun-2025 to 24-Jun-2025 | 11-Jun-2025 to 08-Jul-2025 | 10 wd | 0 wd | 9 wd | 0 wd |
| A1080 | Bentonite Waterstop Data Sheet | 05-Jun-2025 to 19-Jun-2025 | 09-Jun-2025 to 02-Jul-2025 | 9 wd | 0 wd | 8 wd | 2 wd |
| A1370 | 23 74 13 - Air Handling Units (R0) | 26-Jun-2025 to 11-Jul-2025 | 26-Jun-2025 to 21-Jul-2025 | 11 wd | 0 wd | 6 wd | 0 wd |
| A1290 | Suspended Metal Soffits | 11-Jul-2025 to 25-Jul-2025 | 28-Aug-2025 to 04-Sep-2025 | 0 wd | 0 wd | 5 wd | 11 wd |
| A1660 | Bentonite Waterstop | 19-Jun-2025 to 26-Jun-2025 | 03-Jul-2025 to 09-Jul-2025 | 0 wd | 0 wd | 5 wd | 6 wd |
| A1420 | 23 57 00 - Heat Exchangers | 23-Jun-2025 to 25-Jun-2025 | 23-Jun-2025 to 03-Jul-2025 | 3 wd | 0 wd | 5 wd | 0 wd |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 11-Jul-2025 to 15-Jul-2025 | 11-Jul-2025 to 22-Jul-2025 | 3 wd | 0 wd | 5 wd | 0 wd |
| A1070 | Foundation Concrete Mix Design | 05-Jun-2025 to 19-Jun-2025 | 13-Jun-2025 to 25-Jun-2025 | 5 wd | 0 wd | 4 wd | 6 wd |
| A1510 | 23 00 00 - Wall Fin Heater | 22-Jul-2025 to 06-Aug-2025 | 22-Jul-2025 to 12-Aug-2025 | 12 wd | 0 wd | 4 wd | 0 wd |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | 11-Jul-2025 to 25-Jul-2025 | 11-Jul-2025 to 31-Jul-2025 | 11 wd | 0 wd | 4 wd | 0 wd |
| A1190 | Fire-resistive Material Data Sheet | 19-Jun-2025 to 04-Jul-2025 | 27-Jun-2025 to 09-Jul-2025 | 5 wd | 0 wd | 3 wd | 6 wd |
| A1150 | Built-up Roofing Shop Drawings | 19-Jun-2025 to 04-Jul-2025 | 19-Jun-2025 to 09-Jul-2025 | 11 wd | 0 wd | 3 wd | 0 wd |
| A1390 | 23 25 00 - Buffer Tanks | 24-Jun-2025 to 27-Jun-2025 | 24-Jun-2025 to 03-Jul-2025 | 4 wd | 0 wd | 3 wd | 0 wd |
| A1400 | 23 21 16 - Air Separator | 24-Jun-2025 to 27-Jun-2025 | 24-Jun-2025 to 03-Jul-2025 | 4 wd | 0 wd | 3 wd | 0 wd |
| A1410 | 23 21 16 - Expansion Tanks | 24-Jun-2025 to 27-Jun-2025 | 24-Jun-2025 to 03-Jul-2025 | 4 wd | 0 wd | 3 wd | 0 wd |
| A1220 | Flush Wood Doors Sample | 11-Jul-2025 to 25-Jul-2025 | 26-Aug-2025 to 27-Aug-2025 | 0 wd | 0 wd | 2 wd | 11 wd |
| A2240 | Construction Site Setup. Fencing and Temp Facilities | 05-Jun-2025 to 12-Jun-2025 | 10-Jun-2025 to 16-Jun-2025 | 3 wd | 0 wd | 2 wd | 3 wd |
| A2260 | Top Soil Stripping | 13-Jun-2025 to 18-Jun-2025 | 18-Jun-2025 to 20-Jun-2025 | 1 wd | 0 wd | 2 wd | 3 wd |
| A2300 | Setup Hoarding @ Vestibule F100 | 12-Jun-2025 to 16-Jun-2025 | 17-Jun-2025 to 18-Jun-2025 | 0 wd | 0 wd | 2 wd | 3 wd |
| A2290 | Existing Structure Under Pinning | 19-Jun-2025 to 11-Jul-2025 | 24-Jun-2025 to 15-Jul-2025 | 13 wd | 0 wd | 2 wd | 3 wd |
| A2330 | Gas Meter and Pipe Relocation Investigation | 12-Jun-2025 to 17-Jun-2025 | 17-Jun-2025 to 19-Jun-2025 | 1 wd | 0 wd | 2 wd | 3 wd |
| A2340 | Gas Meter and pipe Relocation | 17-Jun-2025 to 19-Jun-2025 | 20-Jun-2025 to 23-Jun-2025 | 0 wd | 0 wd | 2 wd | 3 wd |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | 18-Jun-2025 to 03-Jul-2025 | 23-Jun-2025 to 07-Jul-2025 | 8 wd | 0 wd | 2 wd | 3 wd |
| A1020 | Subcontract Award | 30-Apr-2025 to 29-May-2025 | 05-May-2025 to 02-Jun-2025 | 18 wd | 0 wd | 2 wd | 3 wd |
| A1650 | Foundation Concrete Mix Design | 19-Jun-2025 to 23-Jun-2025 | 26-Jun-2025 to 27-Jun-2025 | 0 wd | 0 wd | 2 wd | 3 wd |
| A2370 | Bulk Excavation to U/S of Footings | 11-Jul-2025 to 18-Jul-2025 | 16-Jul-2025 to 22-Jul-2025 | 3 wd | 0 wd | 2 wd | 3 wd |
| A2320 | Demolition of Existing Vestibule F100 | 16-Jun-2025 to 23-Jun-2025 | 18-Jun-2025 to 25-Jun-2025 | 4 wd | 0 wd | 2 wd | 2 wd |
| A2230 | Ontario Community College Auto Show | 30-Apr-2025 to 05-Jun-2025 | 09-Jun-2025 to 09-Jun-2025 | 0 wd | 0 wd | 1 wd | 26 wd |
| A1680 IN-PROGRESS | Structural Steel | 19-Jun-2025 to 25-Jul-2025 | 04-Sep-2025, open | 0 wd | 0 wd | 1 wd | 26 wd |
| A1130 IN-PROGRESS | Misc. Metals Shop Drawings | 04-Jul-2025 to 18-Jul-2025 | 26-Aug-2025, open | 0 wd | 0 wd | 1 wd | 11 wd |
| A1330 IN-PROGRESS | Fall Arrest Anchors and Horizontal Lines | 11-Jul-2025 to 25-Jul-2025 | 14-Aug-2025, open | 0 wd | 0 wd | 1 wd | 11 wd |
| A1110 | Structural Reinforcement + Decking Shop Drawings | 05-Jun-2025 to 19-Jun-2025 | 01-Aug-2025 to 01-Aug-2025 | 0 wd | 0 wd | 1 wd | 11 wd |
| A1500 IN-PROGRESS | 23 52 16 - Heating Boilers | 09-Jul-2025 to 23-Jul-2025 | 12-Sep-2025, open | 0 wd | 0 wd | 1 wd | 11 wd |
| A1040 | Permit (Not Required Per Ontario Community College) | 12-May-2025 to 13-May-2025 | 16-May-2025 to 16-May-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A1010 | Contract Award | 29-Apr-2025 to 30-Apr-2025 | 02-May-2025 to 02-May-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A1030 | IFC Drawings Released | 09-May-2025 to 12-May-2025 | 15-May-2025 to 15-May-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2270 | Excavation for Under Pinning | 18-Jun-2025 to 19-Jun-2025 | 23-Jun-2025 to 23-Jun-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2250 | Tree Removal, Protection and Equipment Mobilization | 12-Jun-2025 to 13-Jun-2025 | 17-Jun-2025 to 17-Jun-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2310 | Relocate FAA | 12-Jun-2025 to 16-Jun-2025 | 16-Jun-2025 to 17-Jun-2025 | 1 wd | 0 wd | 1 wd | 2 wd |
| A3920 | Setup Temporary Hoarding | 12-Jun-2025 to 13-Jun-2025 | 04-Jul-2025 to 04-Jul-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A3780 | Layout for Elevator Cylinder | 18-Jun-2025 to 19-Jun-2025 | 23-Jun-2025 to 23-Jun-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A3790 | Drilling Elevator Cylinder from Grade | 19-Jun-2025 to 20-Jun-2025 | 24-Jun-2025 to 24-Jun-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A3800 | Install Steel Casing into the ground | 20-Jun-2025 to 23-Jun-2025 | 25-Jun-2025 to 25-Jun-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2380 | Bulk Excavation to U/S North Stair Footing | 18-Jul-2025 to 21-Jul-2025 | 23-Jul-2025 to 23-Jul-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2510 | Supply of Embedment & Ankors | 19-Jun-2025 to 20-Jun-2025 | 22-Aug-2025 to 22-Aug-2025 | 0 wd | 0 wd | 1 wd | 2 wd |
| A2600 | Compaction Inspection | 01-Apr-2025 to 19-Sep-2025 | 15-Aug-2025 to 15-Aug-2025 | 1 wd | 0 wd | 0 wd | 95 wd |
| A2390 | Subgrade Inspection | 01-Apr-2025 to 25-Jul-2025 | 22-Jul-2025 to 22-Jul-2025 | 1 wd | 0 wd | 0 wd | 77 wd |
| A3320 | Blocking Installation | 01-Apr-2025 to 09-Apr-2026 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A3480 | Blocking Installation | 01-Apr-2025 to 23-Apr-2026 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A3610 | Blocking Installation | 01-Apr-2025 to 04-May-2026 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A2660 | Install Temporary Hoarding for Slab on Deck | 01-Apr-2025 to 03-Nov-2025 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A3180 | Roof Inspection | 01-Apr-2025 to 19-Dec-2025 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A2620 | Structural Steel Inspection | 01-Apr-2025 to 20-Oct-2025 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | 01-Apr-2025 to 25-Feb-2026 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A3250 | Fire Spraying & Intumescent Paint Inspection | 01-Apr-2025 to 25-Feb-2026 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A2540 | Compaction Inspection | 01-Apr-2025 to 22-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 63 wd |
| A2150 IN-PROGRESS | 26 50 00 - Lighting Fixtures | 14-Jul-2025 to 20-Nov-2025 | 19-Aug-2025, open | 1 wd | 0 wd | 0 wd | 26 wd |
| A1180 IN-PROGRESS | Exterior Wall Cladding Shop Drawings | 25-Jul-2025 to 11-Aug-2025 | 11-Aug-2025, open | 1 wd | 0 wd | 0 wd | 11 wd |
| A2450 | Rebar for Pad Footings | 08-Jul-2025 to 29-Jul-2025 | 23-Jul-2025 to 24-Jul-2025 | 2 wd | 0 wd | 0 wd | 11 wd |
| A1210 IN-PROGRESS | Interior Aluminum Screen | 11-Jul-2025 to 25-Jul-2025 | 25-Jul-2025, open | 1 wd | 0 wd | 0 wd | 10 wd |
| A1170 | Air Barrier System Data Sheet and Mockup | 19-Jun-2025 to 04-Jul-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A1700 | Cold-formed Metal Framing | 19-Jun-2025 to 04-Jul-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A1740 | TPO Roofing (Bridge) | 19-Jun-2025 to 04-Aug-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A1690 | Structural Reinforcement | 19-Jun-2025 to 16-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 8 wd |
| A2140 IN-PROGRESS | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 26-Jun-2025 to 05-Nov-2025 | 09-Jul-2025, open | 1 wd | 0 wd | 0 wd | 8 wd |
| A3940 | Existing Slab Removal and Trenching | 12-Jun-2025 to 19-Jun-2025 | none | 0 wd | 0 wd | 0 wd | 6 wd |
| A2160 IN-PROGRESS | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 15-Jul-2025 to 21-Apr-2026 | 23-Jul-2025, open | 1 wd | 0 wd | 0 wd | 6 wd |
| A2420 IN-PROGRESS | Form and Pour North Exit Stair | 29-Jul-2025 to 25-Sep-2025 | 04-Aug-2025, open | 1 wd | 0 wd | 0 wd | 4 wd |
| A1350 | Sprinkler & Standpipe Shop Drawings | 26-Jun-2025 to 11-Jul-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2180 | 26 09 23 - Lighting Control | 26-Jun-2025 to 05-Nov-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| A2220 | Testing and Inspection Cash Allowance Expenditure | 12-May-2025 to 13-May-2025 | none | 0 wd | 0 wd | 0 wd | 2 wd |
| A1000 | Tender Closing | 01-Apr-2025 to 29-Apr-2025 | 01-Apr-2025 to 29-Apr-2025 | 20 wd | 0 wd | 0 wd | 0 wd |
| A2360 | Ductbank Shoring | 03-Jul-2025 to 17-Jul-2025 | 23-Jun-2025 to 08-Jul-2025 | 4 wd | 7 wd | 0 wd | 0 wd |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | 07-Jul-2025 to 14-Jul-2025 | 07-Jul-2025 to 11-Jul-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A1340 | Hydraulic Lift Shop Drawings | 26-Jun-2025 to 11-Jul-2025 | 26-Jun-2025 to 09-Jul-2025 | 9 wd | 0 wd | 0 wd | 0 wd |
| A1630 | Ductbank Underpinning | 12-Jun-2025 to 19-Jun-2025 | 28-May-2025 to 28-May-2025 | 0 wd | 1 wd | 0 wd | 0 wd |
| A1640 | Foundation Concrete Rebar | 19-Jun-2025 to 04-Jul-2025 | 13-Jun-2025 to 13-Jun-2025 | 0 wd | 1 wd | 0 wd | 0 wd |
| A1360 | 23 82 19 - Fan Coil Units (R0) | 19-Jun-2025 to 04-Jul-2025 | 19-Jun-2025 to 03-Jul-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1380 | 23 21 23 - Pumps (R0) | 24-Jun-2025 to 09-Jul-2025 | 24-Jun-2025 to 04-Jul-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| A1430 | 22 33 00 - Electric Domestic Water Heaters | 19-Jun-2025 to 03-Jul-2025 | 19-Jun-2025 to 03-Jul-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| A1440 | 23 81 26 - Split System | 12-Jun-2025 to 30-Jun-2025 | 12-Jun-2025 to 30-Jun-2025 | 13 wd | 0 wd | 0 wd | 0 wd |
| A1450 | 22 13 29 - Sump Pumps (R0) | 09-Jun-2025 to 20-Jun-2025 | 27-May-2025 to 02-Jun-2025 | 0 wd | 5 wd | 0 wd | 0 wd |
| A1480 | 23 00 00 - Exhaust Fans (R0) | 22-Jul-2025 to 06-Aug-2025 | 22-Jul-2025 to 22-Jul-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1490 | 23 00 00 - Unit Heater | 22-Jul-2025 to 06-Aug-2025 | 22-Jul-2025 to 22-Jul-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| A1520 IN-PROGRESS | 23 74 13 - Air Source Heat Pump | 26-Jun-2025 to 10-Jul-2025 | 26-Jun-2025, open | 3 wd | 0 wd | 0 wd | 0 wd |
| A1980 IN-PROGRESS | 23 25 00 - Buffer Tanks | 04-Jul-2025 to 24-Dec-2025 | 04-Jul-2025, open | 1 wd | 0 wd | 0 wd | 0 wd |
| A1990 IN-PROGRESS | 23 21 16 - Air Separator | 04-Jul-2025 to 11-Nov-2025 | 04-Jul-2025, open | 1 wd | 0 wd | 0 wd | 0 wd |
| A2000 IN-PROGRESS | 23 21 16 - Expansion Tanks | 04-Jul-2025 to 11-Nov-2025 | 04-Jul-2025, open | 1 wd | 0 wd | 0 wd | 0 wd |
| A2010 IN-PROGRESS | 23 57 00 - Heat Exchangers | 04-Jul-2025 to 11-Nov-2025 | 04-Jul-2025, open | 1 wd | 0 wd | 0 wd | 0 wd |
| A2020 IN-PROGRESS | 22 33 00 - Electric Domestic Water Heaters | 04-Jul-2025 to 12-Nov-2025 | 04-Jul-2025, open | 1 wd | 0 wd | 0 wd | 0 wd |
| A2030 IN-PROGRESS | 23 81 26 - Split System | 10-Jul-2025 to 18-Nov-2025 | 10-Jul-2025, open | 1 wd | 0 wd | 0 wd | 0 wd |
| A2040 IN-PROGRESS | 22 13 29 - Sump Pumps | 19-Jun-2025 to 08-Aug-2025 | 19-Jun-2025, open | 8 wd | 0 wd | 0 wd | 0 wd |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | 11-Jun-2025 to 24-Jun-2025 | 11-Jun-2025 to 17-Jun-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| A2190 IN-PROGRESS | 28 31 00 - Fire Alarm | 26-Jun-2025 to 05-Nov-2025 | 18-Jun-2025, open | 3 wd | 6 wd | 0 wd | 0 wd |
| A2400 | Subgrade Preparation | 25-Jul-2025 to 28-Jul-2025 | 23-Jul-2025 to 23-Jul-2025 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2410 | Soil Bearing Capacity Inspection | 28-Jul-2025 to 29-Jul-2025 | 24-Jul-2025 to 24-Jul-2025 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | 25-Jul-2025 to 28-Jul-2025 | 23-Jul-2025 to 23-Jul-2025 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2460 | Rebar Inspection | 29-Jul-2025 to 30-Jul-2025 | 25-Jul-2025 to 25-Jul-2025 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | 30-Jul-2025 to 31-Jul-2025 | 28-Jul-2025 to 28-Jul-2025 | 0 wd | 1 wd | 0 wd | 0 wd |
| A2490 | Concrete Field Testing | 30-Jul-2025 to 31-Jul-2025 | 28-Jul-2025 to 28-Jul-2025 | 0 wd | 1 wd | 0 wd | 0 wd |
Float Burndown Across Windows
per-activity float-erosion register, drawing-sheet exhibitCriticality predates the window: 38 of 99 activities opened at TF ≤ 0 at Baseline, and 14 more demonstrably burned their float to zero as completion moved 21 working days later
Total float in working days (wd), read from the schedule of record at 2 CPM snapshots, Baseline through Current spanning 1 window, day math on the project working calendar. Criticality test: TF ≤ 0. Sign convention: negative Δ = float lost across the window. Finish driver A4240; completion Baseline → Current: 21 wd later. Register bands: TF ≤ 0 · 1-5 wd (near-critical) · 6-20 wd · over 20 wd.
36 further activities first appear with one observation only. No second reading exists, so a loss of float cannot be demonstrated for them and is not claimed here.
conservation: 38 + 14 + 36 + 11 = 99 · reconciles to the register below
Reading notes
- Not plotted above: 49 activities with zero net float movement · 35 held TF ≤ 0 at every observation (11 observed at multiple snapshots, 24 single-observation) · 14 held constant positive float. All 99 appear in the register below.
- Baseline band counts in the inset carry the register convention: the 36 single-observation entrants are imputed at their only reading. The movement panel plots observed pairs only.
- The horizontal scale breaks at 40 wd, marked with a drafting section break. Nothing is clipped: A2480 reaches 315 wd on the compressed segment.
- Band deltas conserve across the population: −13 − 10 + 22 + 1 = 0 over 99 activities.
- Engine-reported recovery events (TF increase between consecutive snapshots): 35.
- Method caveat (cite in any expert report): Float burndown is post-processing of analyst-supplied CPM snapshots. Accuracy depends on the quality of the underlying schedule updates. Recovery events (TF increase) may reflect legitimate scope removal, schedule optimization, or activity deletion, and the analyst must verify which. Slip velocity is a linear average; actual burndown may be non-linear. The per-activity float-timeline presentation is not yet published in AACE/SCL literature; it is disclosed here as a CPP enhancement to the cited observational method.
Activity register · all 99 activities TF FIRST / LAST · Δ · FIRST AT TF ≤ 0
| Activity | TF at Baseline (wd) | TF at Current (wd) | Δ (wd) | First at TF ≤ 0 | Movement |
|---|---|---|---|---|---|
| A1000 | 2 | 2 | 0 | never | single observation |
| A1010 | 2 | 2 | 0 | never | single observation |
| A1020 | 2 | 2 | 0 | never | single observation |
| A1060 | 2 | 2 | 0 | never | single observation |
| A1110.1 | 0 | 0 | 0 | Current | single observation |
| A1640 | 2 | 2 | 0 | never | single observation |
| A1690 | 7 | 0 | −7 | Current | lost |
| A2230 | 5 | 5 | 0 | never | single observation |
| A2240 | 5 | 5 | 0 | never | single observation |
| A2290 | 5 | 5 | 0 | never | single observation |
| A2300 | 5 | 5 | 0 | never | single observation |
| A2310 | 5 | 5 | 0 | never | single observation |
| A2320 | 5 | 5 | 0 | never | single observation |
| A2370 | 5 | 5 | 0 | never | single observation |
| A2390 | 0 | 0 | 0 | Baseline | single observation |
| A2400 | 0 | 0 | 0 | Baseline | single observation |
| A2430 | 0 | 0 | 0 | Baseline | single observation |
| A2440 | 5 | 14 | +9 | never | gained |
| A2450 | 0 | 0 | 0 | Baseline | single observation |
| A2460 | 0 | 0 | 0 | Baseline | single observation |
| A2470 | 0 | 0 | 0 | Baseline | single observation |
| A2480 | 5 | 315 | +310 | never | gained |
| A2490 | 0 | 0 | 0 | Baseline | single observation |
| A2500 | 0 | 0 | 0 | Baseline | single observation |
| A2520 | 0 | 0 | 0 | Baseline | single observation |
| A2530 | 0 | 0 | 0 | Baseline | single observation |
| A2540 | 0 | 20 | +20 | Baseline | gained |
| A2550 | 0 | 14 | +14 | Baseline | gained |
| A2560 | 3 | 42 | +39 | never | gained |
| A2570 | 0 | 39 | +39 | Baseline | gained |
| A2580 | 4 | 16 | +12 | never | gained |
| A2590 | 0 | 16 | +16 | Baseline | gained |
| A2610 | 0 | 12 | +12 | Baseline | gained |
| A2620 | 0 | 12 | +12 | Baseline | gained |
| A2650 | 0 | 12 | +12 | Baseline | gained |
| A2660 | 0 | 12 | +12 | Baseline | gained |
| A2670 | 0 | 12 | +12 | Baseline | gained |
| A2680 | 0 | 12 | +12 | Baseline | gained |
| A2690 | 0 | 12 | +12 | Baseline | gained |
| A2700 | 0 | 12 | +12 | Baseline | gained |
| A2710 | 0 | 12 | +12 | Baseline | gained |
| A2740 | 4 | 4 | 0 | never | no movement |
| A2750 | 0 | 0 | 0 | Baseline | no movement |
| A2880 | 0 | 0 | 0 | Baseline | no movement |
| A2970 | 0 | 0 | 0 | Baseline | no movement |
| A3060 | 0 | 0 | 0 | Baseline | no movement |
| A3070 | 5 | 10 | +5 | never | gained |
| A3210 | 0 | 21 | +21 | Baseline | gained |
| A3220 | 0 | 21 | +21 | Baseline | gained |
| A3240 | 5 | 0 | −5 | Current | lost |
| A3250 | 5 | 0 | −5 | Current | lost |
| A3260 | 5 | 0 | −5 | Current | lost |
| A3280 | 5 | 15 | +10 | never | gained |
| A3290 | 0 | 15 | +15 | Baseline | gained |
| A3450 | 0 | 15 | +15 | Baseline | gained |
| A3580 | 0 | 15 | +15 | Baseline | gained |
| A3590 | 0 | 15 | +15 | Baseline | gained |
| A3610 | 0 | 15 | +15 | Baseline | gained |
| A3630 | 0 | 15 | +15 | Baseline | gained |
| A3640 | 0 | 15 | +15 | Baseline | gained |
| A3650 | 0 | 15 | +15 | Baseline | gained |
| A3660 | 5 | 20 | +15 | never | gained |
| A3670 | 0 | 15 | +15 | Baseline | gained |
| A3710 | 0 | 15 | +15 | Baseline | gained |
| A3720 | 5 | 20 | +15 | never | gained |
| A3750 | 0 | 15 | +15 | Baseline | gained |
| A3760 | 0 | 15 | +15 | Baseline | gained |
| A4030 | 119 | 0 | −119 | Current | lost |
| A4040 | 12 | 0 | −12 | Current | lost |
| A4040x | 0 | 0 | 0 | Current | single observation |
| A4050 | 184 | 0 | −184 | Current | lost |
| A4060 | 128 | 0 | −128 | Current | lost |
| A4070 | 133 | 0 | −133 | Current | lost |
| A4080 | 12 | 0 | −12 | Current | lost |
| A4090 | 12 | 0 | −12 | Current | lost |
| A4100 | 12 | 0 | −12 | Current | lost |
| A4110 | 12 | 0 | −12 | Current | lost |
| A4120 | 12 | 0 | −12 | Current | lost |
| A4170 | 16 | 5 | −11 | never | lost |
| A4180 | 0 | 0 | 0 | Baseline | no movement |
| A4190 | 0 | 0 | 0 | Baseline | no movement |
| A4200 | 0 | 0 | 0 | Baseline | no movement |
| A4210 | 0 | 0 | 0 | Baseline | no movement |
| A4220 | 5 | 5 | 0 | never | no movement |
| A4240 | 0 | 0 | 0 | Baseline | no movement |
| A4250 | 0 | 0 | 0 | Baseline | no movement |
| A4260 | 0 | 0 | 0 | Baseline | no movement |
| A4400 | 0 | 0 | 0 | Current | single observation |
| A4420 | 0 | 0 | 0 | Current | single observation |
| A4430 | 0 | 0 | 0 | Current | single observation |
| A4450 | 0 | 0 | 0 | Current | single observation |
| A4460 | 0 | 0 | 0 | Current | single observation |
| A4470 | 0 | 0 | 0 | Current | single observation |
| A4480 | 0 | 0 | 0 | Current | single observation |
| A4490 | 0 | 0 | 0 | Current | single observation |
| A4500 | 0 | 0 | 0 | Current | single observation |
| A4520 | 0 | 0 | 0 | Current | single observation |
| A4590 | 0 | 0 | 0 | Current | single observation |
| A4820 | 0 | 0 | 0 | Current | single observation |
Cumulative Activity Slip Register
sum of signed slip across all windows| Code | Activity | Total Slip | Windows Touched |
|---|---|---|---|
| A4070 CP | Frames installation | +182 wd | 1 |
| A4060 CP | Blocking | +169 wd | 1 |
| A4050 CP | Sprinkler Rough-ins | +162 wd | 1 |
| A4030 CP | New Partition Framing | +136 wd | 1 |
| A3850 | Foundations | +126 wd | 1 |
| A3860 | Concrete Vertical Piers | +126 wd | 1 |
| A3870 | Removal of Existing Facade for Tie In | +126 wd | 1 |
| A3880 | Structural Steel erection including expansion plates | +94 wd | 1 |
| A3890 | Envelope | +94 wd | 1 |
| A4150 | New Exterior Paved Areas and Sidewalks | +94 wd | 1 |
| A4160 | Landscape Installations | +94 wd | 1 |
| A3940 | Existing Slab Removal and Trenching | +90 wd | 1 |
| A3900 | Interior M&E Rough in | +84 wd | 1 |
| A2090 | 23 52 16 - Heating Boilers | +71 wd | 1 |
| A3910 | Interior Finishes | +65 wd | 1 |
| A2730 | Stairs B Installation @ North Side | +62 wd | 1 |
| A1710 | Misc. Metals | +62 wd | 1 |
| A2720 | Tactile Attention Indicators Mock-up | +62 wd | 1 |
| A1500 | 23 52 16 - Heating Boilers | +62 wd | 1 |
| A1950 | 23 82 19 - Fan Coil Units | +62 wd | 1 |
| A2050 | 23 25 00 - Water Treatment | +61 wd | 1 |
| A2060 | 23 37 13 - Diffuser and Grilles | +60 wd | 1 |
| A3270 | New Stair A Installation | +59 wd | 1 |
| A2540 | Compaction Inspection | +58 wd | 1 |
| A2180 | 26 09 23 - Lighting Control | +55 wd | 1 |
| A3170 | Install Built-up Roof | +54 wd | 1 |
| A1130 | Misc. Metals Shop Drawings | +53 wd | 1 |
| A3180 | Roof Inspection | +52 wd | 1 |
| A1680 | Structural Steel | +48 wd | 1 |
| A1160 | TPO Roofing Shop Drawings | +47 wd | 1 |
| A1740 | TPO Roofing (Bridge) | +46 wd | 1 |
| A1330 | Fall Arrest Anchors and Horizontal Lines | +45 wd | 1 |
| A2640 | Install Roof Decking | +44 wd | 1 |
| A2630 | Install Roof Anchors | +44 wd | 1 |
| A1920 | Fall Arrest Anchors and Horizontal Lines | +44 wd | 1 |
| A3150 | Roof Parapet Framing | +44 wd | 1 |
| A3160 | Roof Penetration Layout | +44 wd | 1 |
| A2510 | Supply of Embedment & Ankors | +44 wd | 1 |
| A2580 | Underground Drainage | +43 wd | 1 |
| A2130 | 22 40 00 - Plumbing Fixtures | +42 wd | 1 |
| A3930 | Interior Demolition | +40 wd | 1 |
| A2590 | Backfilling to U/S of SOG | +39 wd | 1 |
| A1970 | 23 21 23 - Pumps | +38 wd | 1 |
| A1590 | 26 09 23 - Lighting Control (R0) | +36 wd | 1 |
| A2150 | 26 50 00 - Lighting Fixtures | +35 wd | 1 |
| A2220 | Testing and Inspection Cash Allowance Expenditure | +34 wd | 1 |
| A1960 | 23 74 13 - Air Handling Units | +34 wd | 1 |
| A2440 | Formwork Remaining Pad Footing (Ramp) | +34 wd | 1 |
| A4040 CP | MEP Rough-ins | +33 wd | 1 |
| A4080 CP | Drywall/Sheathing Installation | +33 wd | 1 |
| A4090 CP | Taping and mudding | +33 wd | 1 |
| A4110 CP | Tile and Rubber Flooring Installation | +33 wd | 1 |
| A4100 CP | Painting | +33 wd | 1 |
| A4120 CP | Final Terminations and Fixtures Installation | +33 wd | 1 |
| A2120 | 20 05 10 - Electric Heat Tracing | +33 wd | 1 |
| A4170 | Fire Alarm Verification | +32 wd | 1 |
| A1110 | Structural Reinforcement + Decking Shop Drawings | +30 wd | 1 |
| A1290 | Suspended Metal Soffits | +28 wd | 1 |
| A1820 | Coiling Doors | +28 wd | 1 |
| A1870 | ACT & ACB | +27 wd | 1 |
| A1460 | 23 25 00 - Water Treatment (R0) | +27 wd | 1 |
| A1580 | 26 50 00 - Lighting Fixtures | +25 wd | 1 |
| A1700 | Cold-formed Metal Framing | +24 wd | 1 |
| A1120 | Cold-formed Metal Framing Shop Drawings | +23 wd | 1 |
| A1220 | Flush Wood Doors Sample | +23 wd | 1 |
| A1280 | ACT Data sheet and Sample | +23 wd | 1 |
| A4240 CP | Minor Deficiencies & Touch-ups | +22 wd | 1 |
| A1810 | Flush Wood Doors | +22 wd | 1 |
| A4260 CP | Total Completion | +21 wd | 1 |
| A4220 | Final Cleaning | +21 wd | 1 |
| A4180 CP | Mechanical, Electrical and Elevator Commissioning | +21 wd | 1 |
| A4190 CP | Integrated Testing | +21 wd | 1 |
| A4250 CP | Ready-To-Take Over | +21 wd | 1 |
| A4230 | Close-out Documents & Training | +21 wd | 1 |
| A4210 CP | Occupancy | +20 wd | 1 |
| A2500 | Install Rebar for Piers | +20 wd | 1 |
| A4200 CP | Substantial Performance | +19 wd | 1 |
| A1230 | Coiling Doors | +19 wd | 1 |
| A1180 | Exterior Wall Cladding Shop Drawings | +18 wd | 1 |
| A1210 | Interior Aluminum Screen | +18 wd | 1 |
| A1760 | Exterior Wall Cladding | +18 wd | 1 |
| A1800 | Interior Aluminum Screens | +17 wd | 1 |
| A1090 | Masonry and Mortar Samples & Data Sheets | +16 wd | 1 |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | +16 wd | 1 |
| A2550 | Form and Pour Grade Beams | +16 wd | 1 |
| A2560 | Below Grade Vapour Barrier Mock-up | +16 wd | 1 |
| A2570 | Footing Vapor Barrier & Insulation | +16 wd | 1 |
| A2750 CP | L1, L2 & L3 Framing and Sheathing Installation | +15 wd | 1 |
| A2880 CP | L1, L2 & L3 Framing and Sheathing Installation | +15 wd | 1 |
| A2890 | L1 Masonry Wall Installation | +15 wd | 1 |
| A2770 | L1 Masonry Wall installation | +15 wd | 1 |
| A2790 | L1, L2 & L3 Air Vapour Barrier Installation | +15 wd | 1 |
| A3260 CP | Seal Concrete Floor | +15 wd | 1 |
| A3430 | Seal concrete Floor | +15 wd | 1 |
| A3280 | New partition framing | +15 wd | 1 |
| A3330 | Door frames Installation | +15 wd | 1 |
| A3440 | New partition framing | +15 wd | 1 |
| A3560 | Seal concrete Floor | +15 wd | 1 |
| A1670 | Masonry and Mortar | +15 wd | 1 |
| A3420 | Fire Spraying & Intumescent Paint | +15 wd | 1 |
| A3550 | Fire Spraying & Intumescent Paint | +15 wd | 1 |
| A2820 | Glazing Site Measure and Scanning | +15 wd | 1 |
| A2280 | Under Pinning Inspection | +15 wd | 1 |
| A2760 | Masonry Mock-up | +15 wd | 1 |
| A2740 | Cold-Formed Metal Framing Mock | +15 wd | 1 |
| A3680 | Misc. Metals Mock-up | +15 wd | 1 |
| A2780 | Above Grade Vapour Mock-up | +15 wd | 1 |
| A2800 | AVB Inspection | +15 wd | 1 |
| A3250 CP | Fire Spraying & Intumescent Paint Inspection | +15 wd | 1 |
| A2520 | Form and Pour Foundation Piers | +15 wd | 1 |
| A3490 | Door frames Installation | +14 wd | 1 |
| A3520 | Door and Hardware Installation | +14 wd | 1 |
| A3620 | Door frames Installation | +14 wd | 1 |
| A3570 | New wall partition framing | +14 wd | 1 |
| A3920 | Setup Temporary Hoarding | +14 wd | 1 |
| A3240 CP | Fire Spraying & Intumescent Paint | +14 wd | 1 |
| A3210 | Electrical and Mechanical Room | +14 wd | 1 |
| A3690 | Misc. Metals installation | +14 wd | 1 |
| A3220 | Mech. and Elec. Equipment Installation | +14 wd | 1 |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | +14 wd | 1 |
| A2530 | Backfilling to U/S of Grade Beams | +14 wd | 1 |
| A1060 | Foundation Concrete Rebar Shop Drawing | +12 wd | 1 |
| A1050 | Ductbank Underpinning Drawing | +12 wd | 1 |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | +12 wd | 1 |
| A3410 | Painting | +11 wd | 1 |
| A3300 | Electrical, FA & Comms rough-ins | +11 wd | 1 |
| A3320 | Blocking Installation | +11 wd | 1 |
| A3350 | Gypsum board Installation | +11 wd | 1 |
| A3360 | Drywall Taping and Mudding | +11 wd | 1 |
| A3390 | Interior Aluminum/Glazing Screens Installation | +11 wd | 1 |
| A3370 | Door and Hardware Installation | +11 wd | 1 |
| A3810 | Install Controller at Machine Room | +11 wd | 1 |
| A3820 | Rails and Elevator Car installation | +11 wd | 1 |
| A3830 | Power to controller, Phone lines and Comms | +11 wd | 1 |
| A3840 | Elevator Testing and Commissioning | +11 wd | 1 |
| A3380 | Interior Aluminum/Glazing Screens Mock-up | +11 wd | 1 |
| A3340 | ACT Baffles Mock-ups | +11 wd | 1 |
| A3400 | Paint Mock-up | +11 wd | 1 |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | +11 wd | 1 |
| A3290 | Mech. & Plumbing rough-ins | +10 wd | 1 |
| A3310 | Sprinkler Rough-ins | +10 wd | 1 |
| A3540 | Painting | +9 wd | 1 |
| A2610 | Erect Structural Steel | +9 wd | 1 |
| A2650 | Install Level 2 & 3 Decking | +9 wd | 1 |
| A3450 | Mech. & Plumbing rough-ins | +9 wd | 1 |
| A3480 | Blocking Installation | +9 wd | 1 |
| A3500 | Gypsum board Installation | +9 wd | 1 |
| A3460 | Electrical, FA & Comms rough-ins | +9 wd | 1 |
| A3510 | Drywall Taping and Mudding | +9 wd | 1 |
| A3530 | Interior Glazing Installation | +9 wd | 1 |
| A3590 | Electrical, FA & Comms rough-ins | +9 wd | 1 |
| A3580 | Mech. & Plumbing rough-ins | +9 wd | 1 |
| A3610 | Blocking Installation | +9 wd | 1 |
| A3470 | Sprinkler Rough-ins | +9 wd | 1 |
| A3600 | Sprinkler Rough-ins | +9 wd | 1 |
| A2660 | Install Temporary Hoarding for Slab on Deck | +9 wd | 1 |
| A2620 | Structural Steel Inspection | +9 wd | 1 |
| A1080 | Bentonite Waterstop Data Sheet | +8 wd | 1 |
| A1660 | Bentonite Waterstop | +8 wd | 1 |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | +8 wd | 1 |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | +7 wd | 1 |
| A3750 | Washroom Partitions and Accessories Installation | +6 wd | 1 |
| A2670 | Rebar and Prep Work for Slab on Deck | +6 wd | 1 |
| A3110 | L1, L2 & L3 Exterior Glazing Installation (W09a, W09b) | +6 wd | 1 |
| A2930 | L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) | +6 wd | 1 |
| A2840 | L1, L2, L3 Exterior Glazing Installation (W05) | +6 wd | 1 |
| A3010 | L2 & L3 Exterior Glazing Installation (W08a, W08b) | +6 wd | 1 |
| A3720 | Ceiling/Wall Fixtures Installation | +6 wd | 1 |
| A3740 | Millwork Installation | +6 wd | 1 |
| A3710 | Tiling and rubber flooring Installation | +6 wd | 1 |
| A3670 | Painting | +6 wd | 1 |
| A3770 | Corner Guards and Wall Protection Installation | +6 wd | 1 |
| A3660 | Interior Glazing Installation | +6 wd | 1 |
| A3650 | Door and Hardware Installation | +6 wd | 1 |
| A3630 | Gypsum board Installation | +6 wd | 1 |
| A3640 | Drywall Taping and Mudding | +6 wd | 1 |
| A2850 | Exterior Cladding Site Measure and Scanning | +6 wd | 1 |
| A2940 | Exterior Cladding Site Measure and Scanning | +6 wd | 1 |
| A3020 | Exterior Cladding Site Measure and Scanning | +6 wd | 1 |
| A3100 | Glazing Shop Fabrication | +6 wd | 1 |
| A3120 | Exterior Cladding Site Measure and Scanning | +6 wd | 1 |
| A3760 | Plumbing Washroom Fixtures Installation | +6 wd | 1 |
| A3730 | Millwork Mock-up | +6 wd | 1 |
| A2810 | Aluminum & Metal Panel Cladding Mock-up | +6 wd | 1 |
| A3700 | Tiling & Rubber & Carpet Flooring Mock-up | +6 wd | 1 |
| A1370 | 23 74 13 - Air Handling Units (R0) | +6 wd | 1 |
| A2030 | 23 81 26 - Split System | +6 wd | 1 |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | +6 wd | 1 |
| A2680 | Concrete pour for slab on deck level 2 & 3 | +5 wd | 1 |
| A2960 | L2 & L3 Cladding Installation (EW2) | +5 wd | 1 |
| A2870 | L1, L2 & L3 Cladding Installation (EW2a) | +5 wd | 1 |
| A3040 | L2 & L3 Cladding Installation (EW2) | +5 wd | 1 |
| A3050 | Horizontal Shading Louvers | +5 wd | 1 |
| A2900 | Air Vapor Barrier Installation | +5 wd | 1 |
| A3140 | L1, L2 & L3 Cladding Installation (EW2, EW2A) | +5 wd | 1 |
| A3070 | L1, L2 & L3 Air Vapor Barrier Installation | +5 wd | 1 |
| A2690 | Final Grading and Vapor Barrier for SOG | +5 wd | 1 |
| A2860 | Exterior Cladding Shop Fabrication | +5 wd | 1 |
| A2910 | Glazing Site Measure and Scanning | +5 wd | 1 |
| A2950 | Exterior Cladding Shop Fabrication | +5 wd | 1 |
| A3000 | Glazing Shop Fabrication | +5 wd | 1 |
| A3030 | Exterior Cladding Shop Fabrication | +5 wd | 1 |
| A3130 | Exterior Cladding Shop Fabrication | +5 wd | 1 |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | +5 wd | 1 |
| A1420 | 23 57 00 - Heat Exchangers | +5 wd | 1 |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | +5 wd | 1 |
| A2970 CP | L2 & L3 Framing and Sheathing Installation | +4 wd | 1 |
| A3060 CP | L1, L2 & L3 Framing and Sheathing Installation | +4 wd | 1 |
| A2980 | L2 & L3 Air Vapor Barrier Installation | +4 wd | 1 |
| A1070 | Foundation Concrete Mix Design | +4 wd | 1 |
| A1650 | Foundation Concrete Mix Design | +4 wd | 1 |
| A2830 | Glazing Shop Fabrication | +4 wd | 1 |
| A2920 | Glazing Shop Fabrication | +4 wd | 1 |
| A2990 | Glazing Site Measure and Scanning | +4 wd | 1 |
| A3090 | Glazing Site Measure and Scanning | +4 wd | 1 |
| A3230 | Fire Spraying & Intumescent Paint Mock-up | +4 wd | 1 |
| A1510 | 23 00 00 - Wall Fin Heater | +4 wd | 1 |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | +4 wd | 1 |
| A2100 | 23 00 00 - Wall Fin Heater | +4 wd | 1 |
| A1040 | Permit (Not Required Per Ontario Community College) | +3 wd | 1 |
| A1030 | IFC Drawings Released | +3 wd | 1 |
| A1150 | Built-up Roofing Shop Drawings | +3 wd | 1 |
| A1170 | Air Barrier System Data Sheet and Mockup | +3 wd | 1 |
| A1190 | Fire-resistive Material Data Sheet | +3 wd | 1 |
| A1350 | Sprinkler & Standpipe Shop Drawings | +3 wd | 1 |
| A1730 | Built-up Roofing | +3 wd | 1 |
| A1750 | Air Barrier System | +3 wd | 1 |
| A1770 | Fire-resistive Material | +3 wd | 1 |
| A1940 | Sprinkler & Standpipe Shop Drawings | +3 wd | 1 |
| A2710 | Concrete Pour and Curing for SOG | +3 wd | 1 |
| A2700 | Rebar Installation for SOG | +3 wd | 1 |
| A3190 | Hoisting Roof Equipment | +3 wd | 1 |
| A3200 | Roof Anchor System Installation | +3 wd | 1 |
| A1390 | 23 25 00 - Buffer Tanks | +3 wd | 1 |
| A1400 | 23 21 16 - Air Separator | +3 wd | 1 |
| A1410 | 23 21 16 - Expansion Tanks | +3 wd | 1 |
| A1520 | 23 74 13 - Air Source Heat Pump | +3 wd | 1 |
| A2110 | 23 74 13 - Air Source Heat Pump | +3 wd | 1 |
| A2240 | Construction Site Setup. Fencing and Temp Facilities | +2 wd | 1 |
| A1010 | Contract Award | +2 wd | 1 |
| A2230 | Ontario Community College Auto Show | +2 wd | 1 |
| A2270 | Excavation for Under Pinning | +2 wd | 1 |
| A2250 | Tree Removal, Protection and Equipment Mobilization | +2 wd | 1 |
| A2260 | Top Soil Stripping | +2 wd | 1 |
| A2300 | Setup Hoarding @ Vestibule F100 | +2 wd | 1 |
| A2320 | Demolition of Existing Vestibule F100 | +2 wd | 1 |
| A2290 | Existing Structure Under Pinning | +2 wd | 1 |
| A2330 | Gas Meter and Pipe Relocation Investigation | +2 wd | 1 |
| A2340 | Gas Meter and pipe Relocation | +2 wd | 1 |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | +2 wd | 1 |
| A1020 | Subcontract Award | +2 wd | 1 |
| A1140 | Millwork Shop Drawings | +2 wd | 1 |
| A1200 | Hollow Metal Frames & Doors Shop Drawings | +2 wd | 1 |
| A1240 | Aluminum Framed Glazing System Shop Drawings | +2 wd | 1 |
| A1250 | Finished Hardware Schedule | +2 wd | 1 |
| A1260 | Stud framing and Gypsum Board Data Sheets | +2 wd | 1 |
| A1270 | Tiling Data sheet and samples | +2 wd | 1 |
| A1300 | Flooring Data Sheets and Samples | +2 wd | 1 |
| A1310 | Paint Drawdowns | +2 wd | 1 |
| A1320 | Washroom accessories and Partitions Shop Drawings | +2 wd | 1 |
| A1610 | Concrete Mix for Hardscapes | +2 wd | 1 |
| A1620 | Landscape Shop Drawings | +2 wd | 1 |
| A1720 | Millwork | +2 wd | 1 |
| A1780 | Hollow Metal Frames | +2 wd | 1 |
| A1830 | Aluminum Framed Glazing Systems | +2 wd | 1 |
| A1840 | Finished Hardware | +2 wd | 1 |
| A1850 | Stud framing & gypsum board | +2 wd | 1 |
| A1860 | Tiling | +2 wd | 1 |
| A1890 | Flooring | +2 wd | 1 |
| A1900 | Paint Drawdowns | +2 wd | 1 |
| A1910 | Washroom accessories and Partitions | +2 wd | 1 |
| A2200 | Concrete for Hardscape | +2 wd | 1 |
| A2210 | Landscape (unit pavers, furniture, etc) | +2 wd | 1 |
| A3780 | Layout for Elevator Cylinder | +2 wd | 1 |
| A3790 | Drilling Elevator Cylinder from Grade | +2 wd | 1 |
| A3800 | Install Steel Casing into the ground | +2 wd | 1 |
| A1690 CP | Structural Reinforcement | +2 wd | 1 |
| A1790 | Hollow Metal Doors | +2 wd | 1 |
| A2370 | Bulk Excavation to U/S of Footings | +2 wd | 1 |
| A2380 | Bulk Excavation to U/S North Stair Footing | +2 wd | 1 |
| A2310 | Relocate FAA | +1 wd | 1 |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | -1 wd | 1 |
| A1360 | 23 82 19 - Fan Coil Units (R0) | -1 wd | 1 |
| A1340 | Hydraulic Lift Shop Drawings | -2 wd | 1 |
| A1930 | Hydraulic Lift | -2 wd | 1 |
| A4010 | Underground Plumbing Rough-ins | -3 wd | 1 |
| A1380 | 23 21 23 - Pumps (R0) | -3 wd | 1 |
| A2390 | Subgrade Inspection | -3 wd | 1 |
| A2400 | Subgrade Preparation | -3 wd | 1 |
| A2410 | Soil Bearing Capacity Inspection | -3 wd | 1 |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | -3 wd | 1 |
| A2450 | Rebar for Pad Footings | -3 wd | 1 |
| A2460 | Rebar Inspection | -3 wd | 1 |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | -3 wd | 1 |
| A2490 | Concrete Field Testing | -3 wd | 1 |
| A2040 | 22 13 29 - Sump Pumps | -4 wd | 1 |
| A2360 | Ductbank Shoring | -7 wd | 1 |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | -7 wd | 1 |
| A2190 | 28 31 00 - Fire Alarm | -7 wd | 1 |
| A1480 | 23 00 00 - Exhaust Fans (R0) | -11 wd | 1 |
| A1490 | 23 00 00 - Unit Heater | -11 wd | 1 |
| A1640 | Foundation Concrete Rebar | -14 wd | 1 |
| A2420 | Form and Pour North Exit Stair | -14 wd | 1 |
| A1630 | Ductbank Underpinning | -16 wd | 1 |
| A1450 | 22 13 29 - Sump Pumps (R0) | -16 wd | 1 |
| A2480 | Concrete for Remaining Pad Footings (Ramp) | -21 wd | 1 |
| A2080 | 23 00 00 - Unit Heater | -23 wd | 1 |
| A2600 | Compaction Inspection | -24 wd | 1 |
| A2070 | 23 00 00 - Exhaust Fans | -29 wd | 1 |
Window 1: Baseline → Current
01-Apr-2025 → 01-Jul-2025 · shift +21 wd| Code | Activity | Prior Duration | Later Duration | Change (wd) |
|---|---|---|---|---|
| A3240 | Fire Spraying & Intumescent Paint | 5 wd | 15 wd | +10 wd |
| A4040 | MEP Rough-ins | 19 wd | 23 wd | +4 wd |
| A4030 | New Partition Framing | 10 wd | 13 wd | +3 wd |
| A4070 | Frames installation | 5 wd | 8 wd | +3 wd |
| A4050 | Sprinkler Rough-ins | 10 wd | 13 wd | +3 wd |
| A4240 | Minor Deficiencies & Touch-ups | 10 wd | 11 wd | +1 wd |
| A4200 | Substantial Performance | 1 wd | 0 wd | -1 wd |
| A4260 | Total Completion | 1 wd | 0 wd | -1 wd |
| A4210 | Occupancy | 1 wd | 0 wd | -1 wd |
| A4250 | Ready-To-Take Over | 1 wd | 0 wd | -1 wd |
| A4060 | Blocking | 10 wd | 7 wd | -3 wd |
| A2970 | L2 & L3 Framing and Sheathing Installation | 25 wd | 14 wd | -11 wd |
| A4080 | Drywall/Sheathing Installation | 38 wd | 10 wd | -28 wd |
| A1690 | Structural Reinforcement | 61 wd | 30 wd | -31 wd |
| A3250 | Fire Spraying & Intumescent Paint Inspection | 228 wd | 1 wd | -227 wd |
| Code | Activity | Prior Finish | Later Finish | Slip | Responsible Party | Cause Notes |
|---|---|---|---|---|---|---|
| A4070 CP | Frames installation | 30-Sep-2025 | 19-Jun-2026 | +182 wd | Contractor | Frame installation at the end of the delayed interior chain |
| A4060 CP | Blocking | 07-Oct-2025 | 09-Jun-2026 | +169 wd | Contractor | Blocking follows sprinkler rough-in in the interior chain |
| A4050 CP | Sprinkler Rough-ins | 07-Oct-2025 | 29-May-2026 | +162 wd | Contractor | Sprinkler rough-in follows partition framing; trade stacking on remobilization |
| A4030 CP | New Partition Framing | 23-Sep-2025 | 08-Apr-2026 | +136 wd | Contractor | Framing crew availability following remobilization |
| A3850 | Foundations | 22-Aug-2025 | 23-Feb-2026 | +126 wd | Owner | Differing site condition at the existing facade tie-in |
| A3860 | Concrete Vertical Piers | 29-Aug-2025 | 02-Mar-2026 | +126 wd | Owner | Follows delayed foundations at the tie-in |
| A3870 | Removal of Existing Facade for Tie In | 03-Sep-2025 | 05-Mar-2026 | +126 wd | Owner | Existing facade removal held for tie-in condition resolution |
| A3880 | Structural Steel erection including expansion plates | 10-Nov-2025 | 26-Mar-2026 | +94 wd | cascade | |
| A3890 | Envelope | 15-Dec-2025 | 30-Apr-2026 | +94 wd | cascade | |
| A4150 | New Exterior Paved Areas and Sidewalks | 14-Jan-2026 | 29-May-2026 | +94 wd | cascade | |
| A4160 | Landscape Installations | 28-Jan-2026 | 12-Jun-2026 | +94 wd | cascade | |
| A3940 | Existing Slab Removal and Trenching | 19-Jun-2025 | 28-Oct-2025 | +90 wd | Contractor | Resequenced slab removal and trenching |
| A3900 | Interior M&E Rough in | 14-Jan-2026 | 14-May-2026 | +84 wd | cascade | |
| A2090 | 23 52 16 - Heating Boilers | 01-Dec-2025 | 16-Mar-2026 | +71 wd | cascade | |
| A3910 | Interior Finishes | 11-Feb-2026 | 15-May-2026 | +65 wd | cascade | |
| A2730 | Stairs B Installation @ North Side | 19-Nov-2025 | 18-Feb-2026 | +62 wd | cascade | |
| A1710 | Misc. Metals | 29-Oct-2025 | 27-Jan-2026 | +62 wd | cascade | |
| A2720 | Tactile Attention Indicators Mock-up | 30-Oct-2025 | 28-Jan-2026 | +62 wd | cascade | |
| A1500 | 23 52 16 - Heating Boilers | 23-Jul-2025 | 21-Oct-2025 | +62 wd | cascade | |
| A1950 | 23 82 19 - Fan Coil Units | 26-Nov-2025 | 25-Feb-2026 | +62 wd | cascade | |
| A2050 | 23 25 00 - Water Treatment | 12-Nov-2025 | 09-Feb-2026 | +61 wd | cascade | |
| A2060 | 23 37 13 - Diffuser and Grilles | 05-Dec-2025 | 05-Mar-2026 | +60 wd | cascade | |
| A3270 | New Stair A Installation | 17-Nov-2025 | 10-Feb-2026 | +59 wd | cascade | |
| A2540 | Compaction Inspection | 22-Aug-2025 | 14-Nov-2025 | +58 wd | cascade | |
| A2180 | 26 09 23 - Lighting Control | 05-Nov-2025 | 23-Jan-2026 | +55 wd | cascade | |
| A3170 | Install Built-up Roof | 17-Dec-2025 | 09-Mar-2026 | +54 wd | cascade | |
| A1130 | Misc. Metals Shop Drawings | 18-Jul-2025 | 02-Oct-2025 | +53 wd | Contractor | Late misc. metals submittal |
| A3180 | Roof Inspection | 19-Dec-2025 | 09-Mar-2026 | +52 wd | cascade | |
| A1680 | Structural Steel | 25-Jul-2025 | 02-Oct-2025 | +48 wd | cascade | |
| A1160 | TPO Roofing Shop Drawings | 19-Jun-2025 | 26-Aug-2025 | +47 wd | Owner | Owner-directed revision to the roofing assembly; resubmittal and re-review cycle |
| A1740 | TPO Roofing (Bridge) | 04-Aug-2025 | 08-Oct-2025 | +46 wd | cascade | |
| A1330 | Fall Arrest Anchors and Horizontal Lines | 25-Jul-2025 | 29-Sep-2025 | +45 wd | cascade | |
| A2640 | Install Roof Decking | 12-Nov-2025 | 15-Jan-2026 | +44 wd | cascade | |
| A2630 | Install Roof Anchors | 05-Nov-2025 | 08-Jan-2026 | +44 wd | cascade | |
| A1920 | Fall Arrest Anchors and Horizontal Lines | 22-Oct-2025 | 23-Dec-2025 | +44 wd | cascade | |
| A3150 | Roof Parapet Framing | 19-Nov-2025 | 22-Jan-2026 | +44 wd | cascade | |
| A3160 | Roof Penetration Layout | 14-Nov-2025 | 19-Jan-2026 | +44 wd | cascade | |
| A2510 | Supply of Embedment & Ankors | 20-Jun-2025 | 22-Aug-2025 | +44 wd | cascade | |
| A2580 | Underground Drainage | 08-Sep-2025 | 07-Nov-2025 | +43 wd | cascade | |
| A2130 | 22 40 00 - Plumbing Fixtures | 03-Dec-2025 | 03-Feb-2026 | +42 wd | cascade | |
| A3930 | Interior Demolition | 07-Jul-2025 | 02-Sep-2025 | +40 wd | cascade | |
| A2590 | Backfilling to U/S of SOG | 19-Sep-2025 | 14-Nov-2025 | +39 wd | cascade | |
| A1970 | 23 21 23 - Pumps | 17-Nov-2025 | 12-Jan-2026 | +38 wd | cascade | |
| A1590 | 26 09 23 - Lighting Control (R0) | 26-Jun-2025 | 18-Aug-2025 | +36 wd | cascade | |
| A2150 | 26 50 00 - Lighting Fixtures | 20-Nov-2025 | 12-Jan-2026 | +35 wd | cascade | |
| A2220 | Testing and Inspection Cash Allowance Expenditure | 13-May-2025 | 02-Jul-2025 | +34 wd | cascade | |
| A1960 | 23 74 13 - Air Handling Units | 30-Mar-2026 | 15-May-2026 | +34 wd | cascade | |
| A2440 | Formwork Remaining Pad Footing (Ramp) | 30-Jul-2025 | 17-Sep-2025 | +34 wd | cascade | |
| A4040 CP | MEP Rough-ins | 25-Mar-2026 | 11-May-2026 | +33 wd | Contractor | MEP rough-in trade coordination; stacked trades after remobilization |
| A4080 CP | Drywall/Sheathing Installation | 19-May-2026 | 06-Jul-2026 | +33 wd | cascade | |
| A4090 CP | Taping and mudding | 02-Jun-2026 | 20-Jul-2026 | +33 wd | cascade | |
| A4110 CP | Tile and Rubber Flooring Installation | 12-Jun-2026 | 30-Jul-2026 | +33 wd | cascade | |
| A4100 CP | Painting | 05-Jun-2026 | 23-Jul-2026 | +33 wd | cascade | |
| A4120 CP | Final Terminations and Fixtures Installation | 19-Jun-2026 | 06-Aug-2026 | +33 wd | cascade | |
| A2120 | 20 05 10 - Electric Heat Tracing | 01-Dec-2025 | 19-Jan-2026 | +33 wd | cascade | |
| A4170 | Fire Alarm Verification | 07-Jul-2026 | 20-Aug-2026 | +32 wd | cascade | |
| A1110 | Structural Reinforcement + Decking Shop Drawings | 19-Jun-2025 | 01-Aug-2025 | +30 wd | cascade | |
| A1290 | Suspended Metal Soffits | 25-Jul-2025 | 04-Sep-2025 | +28 wd | cascade | |
| A1820 | Coiling Doors | 03-Dec-2025 | 14-Jan-2026 | +28 wd | cascade | |
| A1870 | ACT & ACB | 09-Sep-2025 | 17-Oct-2025 | +27 wd | cascade | |
| A1460 | 23 25 00 - Water Treatment (R0) | 04-Jul-2025 | 12-Aug-2025 | +27 wd | cascade | |
| A1580 | 26 50 00 - Lighting Fixtures | 14-Jul-2025 | 18-Aug-2025 | +25 wd | cascade | |
| A1700 | Cold-formed Metal Framing | 04-Jul-2025 | 07-Aug-2025 | +24 wd | cascade | |
| A1120 | Cold-formed Metal Framing Shop Drawings | 19-Jun-2025 | 23-Jul-2025 | +23 wd | cascade | |
| A1220 | Flush Wood Doors Sample | 25-Jul-2025 | 27-Aug-2025 | +23 wd | cascade | |
| A1280 | ACT Data sheet and Sample | 25-Jul-2025 | 27-Aug-2025 | +23 wd | cascade | |
| A4240 CP | Minor Deficiencies & Touch-ups | 28-Aug-2026 | 30-Sep-2026 | +22 wd | Contractor | Deficiency and touch-up re-work extended by finishing crew quality issues |
| A1810 | Flush Wood Doors | 12-Nov-2025 | 12-Dec-2025 | +22 wd | cascade | |
| A4260 CP | Total Completion | 31-Aug-2026 | 30-Sep-2026 | +21 wd | cascade | |
| A4220 | Final Cleaning | 05-Aug-2026 | 03-Sep-2026 | +21 wd | cascade | |
| A4180 CP | Mechanical, Electrical and Elevator Commissioning | 29-Jul-2026 | 27-Aug-2026 | +21 wd | cascade | |
| A4190 CP | Integrated Testing | 12-Aug-2026 | 11-Sep-2026 | +21 wd | cascade | |
| A4250 CP | Ready-To-Take Over | 31-Aug-2026 | 30-Sep-2026 | +21 wd | cascade | |
| A4230 | Close-out Documents & Training | 05-Aug-2026 | 03-Sep-2026 | +21 wd | cascade | |
| A4210 CP | Occupancy | 13-Aug-2026 | 11-Sep-2026 | +20 wd | cascade | |
| A2500 | Install Rebar for Piers | 08-Aug-2025 | 08-Sep-2025 | +20 wd | cascade | |
| A4200 CP | Substantial Performance | 14-Aug-2026 | 11-Sep-2026 | +19 wd | cascade | |
| A1230 | Coiling Doors | 25-Jul-2025 | 21-Aug-2025 | +19 wd | cascade | |
| A1180 | Exterior Wall Cladding Shop Drawings | 11-Aug-2025 | 05-Sep-2025 | +18 wd | cascade | |
| A1210 | Interior Aluminum Screen | 25-Jul-2025 | 20-Aug-2025 | +18 wd | cascade | |
| A1760 | Exterior Wall Cladding | 05-Nov-2025 | 01-Dec-2025 | +18 wd | cascade | |
| A1800 | Interior Aluminum Screens | 03-Dec-2025 | 29-Dec-2025 | +17 wd | cascade | |
| A1090 | Masonry and Mortar Samples & Data Sheets | 25-Jul-2025 | 18-Aug-2025 | +16 wd | cascade | |
| A1100 | Structural Steel Framing and Steel Deck Shop Drawings (R0) | 19-Jun-2025 | 14-Jul-2025 | +16 wd | cascade | |
| A2550 | Form and Pour Grade Beams | 08-Sep-2025 | 30-Sep-2025 | +16 wd | cascade | |
| A2560 | Below Grade Vapour Barrier Mock-up | 09-Sep-2025 | 01-Oct-2025 | +16 wd | cascade | |
| A2570 | Footing Vapor Barrier & Insulation | 12-Sep-2025 | 06-Oct-2025 | +16 wd | cascade | |
| A2750 CP | L1, L2 & L3 Framing and Sheathing Installation | 05-Dec-2025 | 29-Dec-2025 | +15 wd | cascade | |
| A2880 CP | L1, L2 & L3 Framing and Sheathing Installation | 19-Dec-2025 | 13-Jan-2026 | +15 wd | cascade | |
| A2890 | L1 Masonry Wall Installation | 29-Dec-2025 | 20-Jan-2026 | +15 wd | cascade | |
| A2770 | L1 Masonry Wall installation | 09-Dec-2025 | 31-Dec-2025 | +15 wd | cascade | |
| A2790 | L1, L2 & L3 Air Vapour Barrier Installation | 12-Dec-2025 | 06-Jan-2026 | +15 wd | cascade | |
| A3260 CP | Seal Concrete Floor | 04-Mar-2026 | 25-Mar-2026 | +15 wd | cascade | |
| A3430 | Seal concrete Floor | 06-Mar-2026 | 27-Mar-2026 | +15 wd | cascade | |
| A3280 | New partition framing | 18-Mar-2026 | 08-Apr-2026 | +15 wd | cascade | |
| A3330 | Door frames Installation | 25-Mar-2026 | 15-Apr-2026 | +15 wd | cascade | |
| A3440 | New partition framing | 01-Apr-2026 | 22-Apr-2026 | +15 wd | cascade | |
| A3560 | Seal concrete Floor | 12-Mar-2026 | 02-Apr-2026 | +15 wd | cascade | |
| A1670 | Masonry and Mortar | 04-Aug-2025 | 25-Aug-2025 | +15 wd | cascade | |
| A3420 | Fire Spraying & Intumescent Paint | 04-Mar-2026 | 25-Mar-2026 | +15 wd | cascade | |
| A3550 | Fire Spraying & Intumescent Paint | 11-Mar-2026 | 01-Apr-2026 | +15 wd | cascade | |
| A2820 | Glazing Site Measure and Scanning | 08-Dec-2025 | 30-Dec-2025 | +15 wd | cascade | |
| A2280 | Under Pinning Inspection | 20-Jun-2025 | 14-Jul-2025 | +15 wd | cascade | |
| A2760 | Masonry Mock-up | 08-Dec-2025 | 30-Dec-2025 | +15 wd | cascade | |
| A2740 | Cold-Formed Metal Framing Mock | 01-Dec-2025 | 22-Dec-2025 | +15 wd | cascade | |
| A3680 | Misc. Metals Mock-up | 02-Apr-2026 | 23-Apr-2026 | +15 wd | cascade | |
| A2780 | Above Grade Vapour Mock-up | 08-Dec-2025 | 30-Dec-2025 | +15 wd | cascade | |
| A2800 | AVB Inspection | 08-Dec-2025 | 30-Dec-2025 | +15 wd | cascade | |
| A3250 CP | Fire Spraying & Intumescent Paint Inspection | 25-Feb-2026 | 19-Mar-2026 | +15 wd | cascade | |
| A2520 | Form and Pour Foundation Piers | 15-Aug-2025 | 08-Sep-2025 | +15 wd | cascade | |
| A3490 | Door frames Installation | 07-Apr-2026 | 27-Apr-2026 | +14 wd | cascade | |
| A3520 | Door and Hardware Installation | 21-Apr-2026 | 11-May-2026 | +14 wd | cascade | |
| A3620 | Door frames Installation | 23-Apr-2026 | 13-May-2026 | +14 wd | cascade | |
| A3570 | New wall partition framing | 16-Apr-2026 | 06-May-2026 | +14 wd | cascade | |
| A3920 | Setup Temporary Hoarding | 13-Jun-2025 | 04-Jul-2025 | +14 wd | cascade | |
| A3240 CP | Fire Spraying & Intumescent Paint | 25-Feb-2026 | 18-Mar-2026 | +14 wd | Owner | Fire-spray application held for owner inspector availability |
| A3210 | Electrical and Mechanical Room | 04-Mar-2026 | 24-Mar-2026 | +14 wd | cascade | |
| A3690 | Misc. Metals installation | 29-May-2026 | 18-Jun-2026 | +14 wd | cascade | |
| A3220 | Mech. and Elec. Equipment Installation | 18-Mar-2026 | 07-Apr-2026 | +14 wd | cascade | |
| A1530 | 20 05 10 - Electric Heat Tracing (R0) | 23-Jul-2025 | 12-Aug-2025 | +14 wd | cascade | |
| A2530 | Backfilling to U/S of Grade Beams | 22-Aug-2025 | 12-Sep-2025 | +14 wd | cascade | |
| A1060 | Foundation Concrete Rebar Shop Drawing | 19-Jun-2025 | 08-Jul-2025 | +12 wd | cascade | |
| A1050 | Ductbank Underpinning Drawing | 12-Jun-2025 | 30-Jun-2025 | +12 wd | cascade | |
| A1470 | 23 37 13 - Diffuser and Grilles Shop Drawings (R0) | 29-Jul-2025 | 14-Aug-2025 | +12 wd | cascade | |
| A3410 | Painting | 07-May-2026 | 25-May-2026 | +11 wd | cascade | |
| A3300 | Electrical, FA & Comms rough-ins | 06-Apr-2026 | 21-Apr-2026 | +11 wd | cascade | |
| A3320 | Blocking Installation | 09-Apr-2026 | 24-Apr-2026 | +11 wd | cascade | |
| A3350 | Gypsum board Installation | 16-Apr-2026 | 01-May-2026 | +11 wd | cascade | |
| A3360 | Drywall Taping and Mudding | 30-Apr-2026 | 15-May-2026 | +11 wd | cascade | |
| A3390 | Interior Aluminum/Glazing Screens Installation | 07-May-2026 | 25-May-2026 | +11 wd | cascade | |
| A3370 | Door and Hardware Installation | 07-May-2026 | 25-May-2026 | +11 wd | cascade | |
| A3810 | Install Controller at Machine Room | 08-May-2026 | 26-May-2026 | +11 wd | cascade | |
| A3820 | Rails and Elevator Car installation | 25-May-2026 | 09-Jun-2026 | +11 wd | cascade | |
| A3830 | Power to controller, Phone lines and Comms | 01-Jun-2026 | 16-Jun-2026 | +11 wd | cascade | |
| A3840 | Elevator Testing and Commissioning | 22-Jun-2026 | 08-Jul-2026 | +11 wd | cascade | |
| A3380 | Interior Aluminum/Glazing Screens Mock-up | 01-May-2026 | 19-May-2026 | +11 wd | cascade | |
| A3340 | ACT Baffles Mock-ups | 10-Apr-2026 | 27-Apr-2026 | +11 wd | cascade | |
| A3400 | Paint Mock-up | 05-May-2026 | 21-May-2026 | +11 wd | cascade | |
| A1560 | 26 50 00 - Emergency Lighting & Exit Signs | 14-Jul-2025 | 29-Jul-2025 | +11 wd | cascade | |
| A3290 | Mech. & Plumbing rough-ins | 01-Apr-2026 | 15-Apr-2026 | +10 wd | cascade | |
| A3310 | Sprinkler Rough-ins | 01-Apr-2026 | 15-Apr-2026 | +10 wd | cascade | |
| A3540 | Painting | 20-May-2026 | 02-Jun-2026 | +9 wd | cascade | |
| A2610 | Erect Structural Steel | 20-Oct-2025 | 31-Oct-2025 | +9 wd | cascade | |
| A2650 | Install Level 2 & 3 Decking | 03-Nov-2025 | 14-Nov-2025 | +9 wd | cascade | |
| A3450 | Mech. & Plumbing rough-ins | 16-Apr-2026 | 29-Apr-2026 | +9 wd | cascade | |
| A3480 | Blocking Installation | 23-Apr-2026 | 06-May-2026 | +9 wd | cascade | |
| A3500 | Gypsum board Installation | 30-Apr-2026 | 13-May-2026 | +9 wd | cascade | |
| A3460 | Electrical, FA & Comms rough-ins | 20-Apr-2026 | 01-May-2026 | +9 wd | cascade | |
| A3510 | Drywall Taping and Mudding | 14-May-2026 | 28-May-2026 | +9 wd | cascade | |
| A3530 | Interior Glazing Installation | 22-May-2026 | 04-Jun-2026 | +9 wd | cascade | |
| A3590 | Electrical, FA & Comms rough-ins | 27-Apr-2026 | 08-May-2026 | +9 wd | cascade | |
| A3580 | Mech. & Plumbing rough-ins | 09-Apr-2026 | 22-Apr-2026 | +9 wd | cascade | |
| A3610 | Blocking Installation | 04-May-2026 | 15-May-2026 | +9 wd | cascade | |
| A3470 | Sprinkler Rough-ins | 16-Apr-2026 | 29-Apr-2026 | +9 wd | cascade | |
| A3600 | Sprinkler Rough-ins | 09-Apr-2026 | 22-Apr-2026 | +9 wd | cascade | |
| A2660 | Install Temporary Hoarding for Slab on Deck | 03-Nov-2025 | 14-Nov-2025 | +9 wd | cascade | |
| A2620 | Structural Steel Inspection | 20-Oct-2025 | 31-Oct-2025 | +9 wd | cascade | |
| A1080 | Bentonite Waterstop Data Sheet | 19-Jun-2025 | 02-Jul-2025 | +8 wd | cascade | |
| A1660 | Bentonite Waterstop | 26-Jun-2025 | 09-Jul-2025 | +8 wd | cascade | |
| A2140 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 05-Nov-2025 | 17-Nov-2025 | +8 wd | cascade | |
| A1550 | 26 27 26 - Wiring Devices, Service Poles, & Floor Boxes | 26-Jun-2025 | 08-Jul-2025 | +7 wd | cascade | |
| A3750 | Washroom Partitions and Accessories Installation | 08-Jul-2026 | 16-Jul-2026 | +6 wd | cascade | |
| A2670 | Rebar and Prep Work for Slab on Deck | 10-Nov-2025 | 18-Nov-2025 | +6 wd | cascade | |
| A3110 | L1, L2 & L3 Exterior Glazing Installation (W09a, W09b) | 26-Mar-2026 | 03-Apr-2026 | +6 wd | cascade | |
| A2930 | L1, L2 & L3 Exterior Glazing Installation (W07a, W07b, W01, W02 & W03) | 12-Mar-2026 | 20-Mar-2026 | +6 wd | cascade | |
| A2840 | L1, L2, L3 Exterior Glazing Installation (W05) | 05-Mar-2026 | 13-Mar-2026 | +6 wd | cascade | |
| A3010 | L2 & L3 Exterior Glazing Installation (W08a, W08b) | 05-Mar-2026 | 13-Mar-2026 | +6 wd | cascade | |
| A3720 | Ceiling/Wall Fixtures Installation | 30-Jun-2026 | 09-Jul-2026 | +6 wd | cascade | |
| A3740 | Millwork Installation | 23-Jun-2026 | 02-Jul-2026 | +6 wd | cascade | |
| A3710 | Tiling and rubber flooring Installation | 30-Jun-2026 | 09-Jul-2026 | +6 wd | cascade | |
| A3670 | Painting | 16-Jun-2026 | 24-Jun-2026 | +6 wd | cascade | |
| A3770 | Corner Guards and Wall Protection Installation | 06-Jul-2026 | 14-Jul-2026 | +6 wd | cascade | |
| A3660 | Interior Glazing Installation | 09-Jun-2026 | 17-Jun-2026 | +6 wd | cascade | |
| A3650 | Door and Hardware Installation | 16-Jun-2026 | 24-Jun-2026 | +6 wd | cascade | |
| A3630 | Gypsum board Installation | 19-May-2026 | 27-May-2026 | +6 wd | cascade | |
| A3640 | Drywall Taping and Mudding | 02-Jun-2026 | 10-Jun-2026 | +6 wd | cascade | |
| A2850 | Exterior Cladding Site Measure and Scanning | 06-Mar-2026 | 16-Mar-2026 | +6 wd | cascade | |
| A2940 | Exterior Cladding Site Measure and Scanning | 13-Mar-2026 | 23-Mar-2026 | +6 wd | cascade | |
| A3020 | Exterior Cladding Site Measure and Scanning | 06-Mar-2026 | 16-Mar-2026 | +6 wd | cascade | |
| A3100 | Glazing Shop Fabrication | 19-Mar-2026 | 27-Mar-2026 | +6 wd | cascade | |
| A3120 | Exterior Cladding Site Measure and Scanning | 27-Mar-2026 | 06-Apr-2026 | +6 wd | cascade | |
| A3760 | Plumbing Washroom Fixtures Installation | 08-Jul-2026 | 16-Jul-2026 | +6 wd | cascade | |
| A3730 | Millwork Mock-up | 17-Jun-2026 | 25-Jun-2026 | +6 wd | cascade | |
| A2810 | Aluminum & Metal Panel Cladding Mock-up | 06-Mar-2026 | 16-Mar-2026 | +6 wd | cascade | |
| A3700 | Tiling & Rubber & Carpet Flooring Mock-up | 17-Jun-2026 | 25-Jun-2026 | +6 wd | cascade | |
| A1370 | 23 74 13 - Air Handling Units (R0) | 11-Jul-2025 | 21-Jul-2025 | +6 wd | cascade | |
| A2030 | 23 81 26 - Split System | 18-Nov-2025 | 26-Nov-2025 | +6 wd | cascade | |
| A2160 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 21-Apr-2026 | 29-Apr-2026 | +6 wd | cascade | |
| A2680 | Concrete pour for slab on deck level 2 & 3 | 13-Nov-2025 | 20-Nov-2025 | +5 wd | cascade | |
| A2960 | L2 & L3 Cladding Installation (EW2) | 11-May-2026 | 19-May-2026 | +5 wd | cascade | |
| A2870 | L1, L2 & L3 Cladding Installation (EW2a) | 04-May-2026 | 11-May-2026 | +5 wd | cascade | |
| A3040 | L2 & L3 Cladding Installation (EW2) | 04-May-2026 | 11-May-2026 | +5 wd | cascade | |
| A3050 | Horizontal Shading Louvers | 11-May-2026 | 19-May-2026 | +5 wd | cascade | |
| A2900 | Air Vapor Barrier Installation | 13-Jan-2026 | 20-Jan-2026 | +5 wd | cascade | |
| A3140 | L1, L2 & L3 Cladding Installation (EW2, EW2A) | 02-Jun-2026 | 09-Jun-2026 | +5 wd | cascade | |
| A3070 | L1, L2 & L3 Air Vapor Barrier Installation | 25-Feb-2026 | 05-Mar-2026 | +5 wd | cascade | |
| A2690 | Final Grading and Vapor Barrier for SOG | 18-Nov-2025 | 25-Nov-2025 | +5 wd | cascade | |
| A2860 | Exterior Cladding Shop Fabrication | 06-Apr-2026 | 13-Apr-2026 | +5 wd | cascade | |
| A2910 | Glazing Site Measure and Scanning | 07-Jan-2026 | 14-Jan-2026 | +5 wd | cascade | |
| A2950 | Exterior Cladding Shop Fabrication | 13-Apr-2026 | 20-Apr-2026 | +5 wd | cascade | |
| A3000 | Glazing Shop Fabrication | 26-Feb-2026 | 06-Mar-2026 | +5 wd | cascade | |
| A3030 | Exterior Cladding Shop Fabrication | 06-Apr-2026 | 13-Apr-2026 | +5 wd | cascade | |
| A3130 | Exterior Cladding Shop Fabrication | 27-Apr-2026 | 04-May-2026 | +5 wd | cascade | |
| A3080 | L1, L2 & L3 Air Vapor Barrier Inspection | 25-Feb-2026 | 05-Mar-2026 | +5 wd | cascade | |
| A1420 | 23 57 00 - Heat Exchangers | 25-Jun-2025 | 03-Jul-2025 | +5 wd | cascade | |
| A1570 | 27 10 00 - Structural Cabling System (Fiber Optic Cable) | 15-Jul-2025 | 22-Jul-2025 | +5 wd | cascade | |
| A2970 CP | L2 & L3 Framing and Sheathing Installation | 27-Jan-2026 | 02-Feb-2026 | +4 wd | cascade | |
| A3060 CP | L1, L2 & L3 Framing and Sheathing Installation | 18-Feb-2026 | 24-Feb-2026 | +4 wd | cascade | |
| A2980 | L2 & L3 Air Vapor Barrier Installation | 03-Feb-2026 | 09-Feb-2026 | +4 wd | cascade | |
| A1070 | Foundation Concrete Mix Design | 19-Jun-2025 | 25-Jun-2025 | +4 wd | cascade | |
| A1650 | Foundation Concrete Mix Design | 23-Jun-2025 | 27-Jun-2025 | +4 wd | cascade | |
| A2830 | Glazing Shop Fabrication | 21-Jan-2026 | 27-Jan-2026 | +4 wd | cascade | |
| A2920 | Glazing Shop Fabrication | 04-Feb-2026 | 10-Feb-2026 | +4 wd | cascade | |
| A2990 | Glazing Site Measure and Scanning | 28-Jan-2026 | 03-Feb-2026 | +4 wd | cascade | |
| A3090 | Glazing Site Measure and Scanning | 19-Feb-2026 | 25-Feb-2026 | +4 wd | cascade | |
| A3230 | Fire Spraying & Intumescent Paint Mock-up | 19-Feb-2026 | 25-Feb-2026 | +4 wd | cascade | |
| A1510 | 23 00 00 - Wall Fin Heater | 06-Aug-2025 | 12-Aug-2025 | +4 wd | cascade | |
| A1540 | 22 40 00 - Plumbing Fixtures (R0) | 25-Jul-2025 | 31-Jul-2025 | +4 wd | cascade | |
| A2100 | 23 00 00 - Wall Fin Heater | 12-Dec-2025 | 18-Dec-2025 | +4 wd | cascade | |
| A1040 | Permit (Not Required Per Ontario Community College) | 13-May-2025 | 16-May-2025 | +3 wd | cascade | |
| A1030 | IFC Drawings Released | 12-May-2025 | 15-May-2025 | +3 wd | cascade | |
| A1150 | Built-up Roofing Shop Drawings | 04-Jul-2025 | 09-Jul-2025 | +3 wd | cascade | |
| A1170 | Air Barrier System Data Sheet and Mockup | 04-Jul-2025 | 09-Jul-2025 | +3 wd | cascade | |
| A1190 | Fire-resistive Material Data Sheet | 04-Jul-2025 | 09-Jul-2025 | +3 wd | cascade | |
| A1350 | Sprinkler & Standpipe Shop Drawings | 11-Jul-2025 | 16-Jul-2025 | +3 wd | cascade | |
| A1730 | Built-up Roofing | 18-Aug-2025 | 21-Aug-2025 | +3 wd | cascade | |
| A1750 | Air Barrier System | 18-Jul-2025 | 23-Jul-2025 | +3 wd | cascade | |
| A1770 | Fire-resistive Material | 04-Aug-2025 | 07-Aug-2025 | +3 wd | cascade | |
| A1940 | Sprinkler & Standpipe Shop Drawings | 04-Aug-2025 | 07-Aug-2025 | +3 wd | cascade | |
| A2710 | Concrete Pour and Curing for SOG | 28-Nov-2025 | 03-Dec-2025 | +3 wd | cascade | |
| A2700 | Rebar Installation for SOG | 21-Nov-2025 | 26-Nov-2025 | +3 wd | cascade | |
| A3190 | Hoisting Roof Equipment | 09-Jun-2026 | 12-Jun-2026 | +3 wd | cascade | |
| A3200 | Roof Anchor System Installation | 16-Jun-2026 | 19-Jun-2026 | +3 wd | cascade | |
| A1390 | 23 25 00 - Buffer Tanks | 27-Jun-2025 | 03-Jul-2025 | +3 wd | cascade | |
| A1400 | 23 21 16 - Air Separator | 27-Jun-2025 | 03-Jul-2025 | +3 wd | cascade | |
| A1410 | 23 21 16 - Expansion Tanks | 27-Jun-2025 | 03-Jul-2025 | +3 wd | cascade | |
| A1520 | 23 74 13 - Air Source Heat Pump | 14-Jul-2025 | 17-Jul-2025 | +3 wd | cascade | |
| A2110 | 23 74 13 - Air Source Heat Pump | 02-Jun-2026 | 05-Jun-2026 | +3 wd | cascade | |
| A2240 | Construction Site Setup. Fencing and Temp Facilities | 12-Jun-2025 | 16-Jun-2025 | +2 wd | cascade | |
| A1010 | Contract Award | 30-Apr-2025 | 02-May-2025 | +2 wd | cascade | |
| A2230 | Ontario Community College Auto Show | 05-Jun-2025 | 09-Jun-2025 | +2 wd | cascade | |
| A2270 | Excavation for Under Pinning | 19-Jun-2025 | 23-Jun-2025 | +2 wd | cascade | |
| A2250 | Tree Removal, Protection and Equipment Mobilization | 13-Jun-2025 | 17-Jun-2025 | +2 wd | cascade | |
| A2260 | Top Soil Stripping | 18-Jun-2025 | 20-Jun-2025 | +2 wd | cascade | |
| A2300 | Setup Hoarding @ Vestibule F100 | 16-Jun-2025 | 18-Jun-2025 | +2 wd | cascade | |
| A2320 | Demolition of Existing Vestibule F100 | 23-Jun-2025 | 25-Jun-2025 | +2 wd | cascade | |
| A2290 | Existing Structure Under Pinning | 11-Jul-2025 | 15-Jul-2025 | +2 wd | cascade | |
| A2330 | Gas Meter and Pipe Relocation Investigation | 17-Jun-2025 | 19-Jun-2025 | +2 wd | cascade | |
| A2340 | Gas Meter and pipe Relocation | 19-Jun-2025 | 23-Jun-2025 | +2 wd | cascade | |
| A2350 | Daylighting of Existing Hydro Ductbank & Services | 03-Jul-2025 | 07-Jul-2025 | +2 wd | cascade | |
| A1020 | Subcontract Award | 29-May-2025 | 02-Jun-2025 | +2 wd | cascade | |
| A1140 | Millwork Shop Drawings | 25-Jul-2025 | 29-Jul-2025 | +2 wd | cascade | |
| A1200 | Hollow Metal Frames & Doors Shop Drawings | 25-Jul-2025 | 29-Jul-2025 | +2 wd | cascade | |
| A1240 | Aluminum Framed Glazing System Shop Drawings | 04-Aug-2025 | 06-Aug-2025 | +2 wd | cascade | |
| A1250 | Finished Hardware Schedule | 25-Jul-2025 | 29-Jul-2025 | +2 wd | cascade | |
| A1260 | Stud framing and Gypsum Board Data Sheets | 25-Jul-2025 | 29-Jul-2025 | +2 wd | cascade | |
| A1270 | Tiling Data sheet and samples | 25-Jul-2025 | 29-Jul-2025 | +2 wd | cascade | |
| A1300 | Flooring Data Sheets and Samples | 25-Jul-2025 | 29-Jul-2025 | +2 wd | cascade | |
| A1310 | Paint Drawdowns | 25-Jul-2025 | 29-Jul-2025 | +2 wd | cascade | |
| A1320 | Washroom accessories and Partitions Shop Drawings | 25-Jul-2025 | 29-Jul-2025 | +2 wd | cascade | |
| A1610 | Concrete Mix for Hardscapes | 04-Aug-2025 | 06-Aug-2025 | +2 wd | cascade | |
| A1620 | Landscape Shop Drawings | 04-Aug-2025 | 06-Aug-2025 | +2 wd | cascade | |
| A1720 | Millwork | 07-Oct-2025 | 09-Oct-2025 | +2 wd | cascade | |
| A1780 | Hollow Metal Frames | 23-Sep-2025 | 25-Sep-2025 | +2 wd | cascade | |
| A1830 | Aluminum Framed Glazing Systems | 26-Nov-2025 | 28-Nov-2025 | +2 wd | cascade | |
| A1840 | Finished Hardware | 03-Dec-2025 | 05-Dec-2025 | +2 wd | cascade | |
| A1850 | Stud framing & gypsum board | 04-Aug-2025 | 06-Aug-2025 | +2 wd | cascade | |
| A1860 | Tiling | 09-Sep-2025 | 11-Sep-2025 | +2 wd | cascade | |
| A1890 | Flooring | 22-Oct-2025 | 24-Oct-2025 | +2 wd | cascade | |
| A1900 | Paint Drawdowns | 11-Aug-2025 | 13-Aug-2025 | +2 wd | cascade | |
| A1910 | Washroom accessories and Partitions | 02-Sep-2025 | 04-Sep-2025 | +2 wd | cascade | |
| A2200 | Concrete for Hardscape | 11-Aug-2025 | 13-Aug-2025 | +2 wd | cascade | |
| A2210 | Landscape (unit pavers, furniture, etc) | 29-Oct-2025 | 31-Oct-2025 | +2 wd | cascade | |
| A3780 | Layout for Elevator Cylinder | 19-Jun-2025 | 23-Jun-2025 | +2 wd | cascade | |
| A3790 | Drilling Elevator Cylinder from Grade | 20-Jun-2025 | 24-Jun-2025 | +2 wd | cascade | |
| A3800 | Install Steel Casing into the ground | 23-Jun-2025 | 25-Jun-2025 | +2 wd | cascade | |
| A1690 CP | Structural Reinforcement | 16-Sep-2025 | 18-Sep-2025 | +2 wd | cascade | |
| A1790 | Hollow Metal Doors | 22-Oct-2025 | 24-Oct-2025 | +2 wd | cascade | |
| A2370 | Bulk Excavation to U/S of Footings | 18-Jul-2025 | 22-Jul-2025 | +2 wd | cascade | |
| A2380 | Bulk Excavation to U/S North Stair Footing | 21-Jul-2025 | 23-Jul-2025 | +2 wd | cascade | |
| A2310 | Relocate FAA | 16-Jun-2025 | 17-Jun-2025 | +1 wd | cascade | |
| A3960 | Vinyl Flooring Abatement (Cash Allowance) | 14-Jul-2025 | 11-Jul-2025 | -1 wd | cascade | |
| A1360 | 23 82 19 - Fan Coil Units (R0) | 04-Jul-2025 | 03-Jul-2025 | -1 wd | cascade | |
| A1340 | Hydraulic Lift Shop Drawings | 11-Jul-2025 | 09-Jul-2025 | -2 wd | cascade | |
| A1930 | Hydraulic Lift | 03-Dec-2025 | 01-Dec-2025 | -2 wd | cascade | |
| A4010 | Underground Plumbing Rough-ins | 21-Jul-2025 | 16-Jul-2025 | -3 wd | cascade | |
| A1380 | 23 21 23 - Pumps (R0) | 09-Jul-2025 | 04-Jul-2025 | -3 wd | cascade | |
| A2390 | Subgrade Inspection | 25-Jul-2025 | 22-Jul-2025 | -3 wd | cascade | |
| A2400 | Subgrade Preparation | 28-Jul-2025 | 23-Jul-2025 | -3 wd | cascade | |
| A2410 | Soil Bearing Capacity Inspection | 29-Jul-2025 | 24-Jul-2025 | -3 wd | cascade | |
| A2430 | Formwork for Pad Footing (GL:AG-AC & X1-A5) | 28-Jul-2025 | 23-Jul-2025 | -3 wd | cascade | |
| A2450 | Rebar for Pad Footings | 29-Jul-2025 | 24-Jul-2025 | -3 wd | cascade | |
| A2460 | Rebar Inspection | 30-Jul-2025 | 25-Jul-2025 | -3 wd | cascade | |
| A2470 | Concrete for Pad Footings (GL:AG-AC & X1-A5) | 31-Jul-2025 | 28-Jul-2025 | -3 wd | cascade | |
| A2490 | Concrete Field Testing | 31-Jul-2025 | 28-Jul-2025 | -3 wd | cascade | |
| A2040 | 22 13 29 - Sump Pumps | 14-Aug-2025 | 08-Aug-2025 | -4 wd | cascade | |
| A2360 | Ductbank Shoring | 17-Jul-2025 | 08-Jul-2025 | -7 wd | cascade | |
| A1600 | 28 31 00 - Fire Alarm Shop Drawings and Data Sheets | 26-Jun-2025 | 17-Jun-2025 | -7 wd | cascade | |
| A2190 | 28 31 00 - Fire Alarm | 05-Nov-2025 | 27-Oct-2025 | -7 wd | cascade | |
| A1480 | 23 00 00 - Exhaust Fans (R0) | 06-Aug-2025 | 22-Jul-2025 | -11 wd | cascade | |
| A1490 | 23 00 00 - Unit Heater | 06-Aug-2025 | 22-Jul-2025 | -11 wd | cascade | |
| A1640 | Foundation Concrete Rebar | 04-Jul-2025 | 13-Jun-2025 | -14 wd | cascade | |
| A2420 | Form and Pour North Exit Stair | 25-Sep-2025 | 05-Sep-2025 | -14 wd | cascade | |
| A1630 | Ductbank Underpinning | 19-Jun-2025 | 28-May-2025 | -16 wd | cascade | |
| A1450 | 22 13 29 - Sump Pumps (R0) | 24-Jun-2025 | 02-Jun-2025 | -16 wd | cascade | |
| A2480 | Concrete for Remaining Pad Footings (Ramp) | 01-Aug-2025 | 03-Jul-2025 | -21 wd | cascade | |
| A2080 | 23 00 00 - Unit Heater | 12-Dec-2025 | 11-Nov-2025 | -23 wd | cascade | |
| A2600 | Compaction Inspection | 19-Sep-2025 | 15-Aug-2025 | -24 wd | cascade | |
| A2070 | 23 00 00 - Exhaust Fans | 12-Dec-2025 | 03-Nov-2025 | -29 wd | cascade |