FORENSIC SCHEDULE DELAY ANALYSIS REPORT
════════════════════════════════════════════════════════════════════════════
Prepared in Accordance with AACE International Recommended Practice 29R-03
────────────────────────────────────────────────────────────────────────────
Project:           CEDARLINE
Schedule Updates:  4
Analysis Windows:  3
Analysis Engine:   Critical Path Partners Forensic Claims Engine (Python skill)
Methodology:       Contemporaneous Period Analysis (Windows Analysis)
Delay Units:       Work days (per project calendar)

════════════════════════════════════════════════════════════════════════════
EXECUTIVE SUMMARY
════════════════════════════════════════════════════════════════════════════

This report presents the findings of a contemporaneous period analysis
(windows analysis) of the CEDARLINE project schedule. The analysis
examines 4 schedule updates spanning 3 discrete analysis windows
to identify, quantify, and attribute project delay to its root causes.

  Baseline Completion:    2025-09-12
  Current Forecast:       2025-10-07
  Net Project Delay:      +17 work days
  Gross Delay:            +17 work days
  Recovery:               0 work days
  Delay Drivers:          64 (31 critical path)
  Critical Path Shifts:   18
  Duration Growth Events: 1

════════════════════════════════════════════════════════════════════════════
WINDOW-BY-WINDOW ANALYSIS
════════════════════════════════════════════════════════════════════════════

────────────────────────────────────────────────────────────────────────────
WINDOW 1: Baseline --> Update 1
Period: 2025-02-03 through 2025-03-31
Impact: +8 work days slip
Cumulative Position: +8 work days
────────────────────────────────────────────────────────────────────────────

All 26 drivers this window:
  - ELE-PROC "MCC and VFD Fabrication and Delivery": 12d slip, off CP, TF after=85.0d, type=Duration Growth
  - CIV-BASE "Form Reinforce and Pour Base Slab": 8d slip, on CP, TF after=0.0d, type=Duration Growth (CP)
  - CIV-WALL "Form Reinforce and Pour Wet Well Walls": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - CIV-CURE "Wall Cure and Strip Formwork": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - MS-CONC "Concrete Structure Complete": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - CIV-BKF "Backfill and Compact Around Structure": 8d slip, off CP, TF after=4.0d, type=Near-Critical Slip
  - CIV-SLAB "Grade Slab and Equipment Pads": 8d slip, off CP, TF after=2.0d, type=Near-Critical Slip
  - MEC-SET "Set Pump Skids and Grout Baseplates": 8d slip, off CP, TF after=24.0d, type=Activity Slip
  - MEC-PIPE "Internal Process Piping Install": 8d slip, off CP, TF after=27.0d, type=Activity Slip
  - MEC-VALVE "Valve and Actuator Install": 8d slip, off CP, TF after=24.0d, type=Activity Slip
  - MEC-TEST "Hydrostatic Test Process Piping": 8d slip, off CP, TF after=27.0d, type=Activity Slip
  - ELE-COND "Conduit and Cable Tray Rough-In": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - ELE-MCC "Set MCC and VFD Line-Up": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - ELE-CABLE "Power and Control Cable Pull": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - ELE-TERM "Terminate and Point-to-Point Check": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - MS-ENERG "Permanent Power Energized": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - BLD-ERECT "Erect Pre-Engineered Building Frame": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - BLD-ROOF "Roof Deck and Membrane": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - BLD-CLAD "Wall Cladding and Flashing": 8d slip, off CP, TF after=85.0d, type=Activity Slip
  - BLD-DOOR "Overhead Doors and Louvres": 8d slip, off CP, TF after=84.0d, type=Activity Slip
  - COM-FLUSH "System Flush and Chlorination": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-LOOP "Instrument Loop Checks": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-FUNC "Functional Testing All Modes": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-PERF "Performance and Capacity Demonstration": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-DEMOB "Demobilize and Turnover Documentation": 8d slip, on CP, TF after=0.0d, type=Critical Slip
  - MS-SC "Substantial Completion": 8d slip, on CP, TF after=0.0d, type=Critical Slip

────────────────────────────────────────────────────────────────────────────
WINDOW 2: Update 1 --> Update 2
Period: 2025-03-31 through 2025-06-30
Impact: +7 work days slip
Cumulative Position: +15 work days
────────────────────────────────────────────────────────────────────────────

All 24 drivers this window:
  - CIV-WALL "Form Reinforce and Pour Wet Well Walls": 7d slip, off CP, TF after=0.0d, type=Duration Growth
  - CIV-CURE "Wall Cure and Strip Formwork": 7d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - MS-CONC "Concrete Structure Complete": 7d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - CIV-BKF "Backfill and Compact Around Structure": 7d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - CIV-SLAB "Grade Slab and Equipment Pads": 7d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - MEC-SET "Set Pump Skids and Grout Baseplates": 7d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - MEC-PIPE "Internal Process Piping Install": 7d slip, off CP, TF after=27.0d, type=Activity Slip
  - MEC-VALVE "Valve and Actuator Install": 7d slip, off CP, TF after=27.0d, type=Activity Slip
  - MEC-TEST "Hydrostatic Test Process Piping": 7d slip, off CP, TF after=27.0d, type=Activity Slip
  - ELE-COND "Conduit and Cable Tray Rough-In": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - ELE-MCC "Set MCC and VFD Line-Up": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - ELE-CABLE "Power and Control Cable Pull": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - ELE-TERM "Terminate and Point-to-Point Check": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - MS-ENERG "Permanent Power Energized": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - BLD-ERECT "Erect Pre-Engineered Building Frame": 7d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - BLD-ROOF "Roof Deck and Membrane": 7d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - BLD-CLAD "Wall Cladding and Flashing": 7d slip, off CP, TF after=84.0d, type=Activity Slip
  - BLD-DOOR "Overhead Doors and Louvres": 7d slip, off CP, TF after=84.0d, type=Activity Slip
  - COM-FLUSH "System Flush and Chlorination": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-LOOP "Instrument Loop Checks": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-FUNC "Functional Testing All Modes": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-PERF "Performance and Capacity Demonstration": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-DEMOB "Demobilize and Turnover Documentation": 7d slip, on CP, TF after=0.0d, type=Critical Slip
  - MS-SC "Substantial Completion": 7d slip, on CP, TF after=0.0d, type=Critical Slip

────────────────────────────────────────────────────────────────────────────
WINDOW 3: Update 2 --> Update 3
Period: 2025-06-30 through 2025-09-30
Impact: +2 work days slip
Cumulative Position: +17 work days
────────────────────────────────────────────────────────────────────────────

All 14 drivers this window:
  - MEC-PIPE "Internal Process Piping Install": 6d slip, off CP, TF after=0.0d, type=Duration Growth
  - MEC-VALVE "Valve and Actuator Install": 6d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - MEC-TEST "Hydrostatic Test Process Piping": 6d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - ELE-COND "Conduit and Cable Tray Rough-In": 6d slip, off CP, TF after=0.0d, type=Duration Growth
  - ELE-MCC "Set MCC and VFD Line-Up": 6d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - ELE-CABLE "Power and Control Cable Pull": 6d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - ELE-TERM "Terminate and Point-to-Point Check": 6d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - MS-ENERG "Permanent Power Energized": 6d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - COM-FLUSH "System Flush and Chlorination": 6d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - COM-LOOP "Instrument Loop Checks": 6d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - COM-FUNC "Functional Testing All Modes": 2d slip, off CP, TF after=0.0d, type=Near-Critical Slip
  - COM-PERF "Performance and Capacity Demonstration": 2d slip, on CP, TF after=0.0d, type=Critical Slip
  - COM-DEMOB "Demobilize and Turnover Documentation": 2d slip, on CP, TF after=0.0d, type=Critical Slip
  - MS-SC "Substantial Completion": 2d slip, on CP, TF after=0.0d, type=Critical Slip

════════════════════════════════════════════════════════════════════════════
END OF REPORT
════════════════════════════════════════════════════════════════════════════