Window,Activity,Name,Type,EF Slip (d),Duration Delta (d),On CP,TF Before (d),TF After (d) W1,ELE-PROC,MCC and VFD Fabrication and Delivery,Duration Growth,12,12.0,false,90.0,85.0 W1,CIV-BASE,Form Reinforce and Pour Base Slab,Duration Growth (CP),8,8.0,true,0.0,0.0 W1,CIV-WALL,Form Reinforce and Pour Wet Well Walls,Critical Slip,8,0.0,true,0.0,0.0 W1,CIV-CURE,Wall Cure and Strip Formwork,Critical Slip,8,0.0,true,0.0,0.0 W1,MS-CONC,Concrete Structure Complete,Critical Slip,8,0.0,true,0.0,0.0 W1,CIV-BKF,Backfill and Compact Around Structure,Near-Critical Slip,8,0.0,false,2.0,4.0 W1,CIV-SLAB,Grade Slab and Equipment Pads,Near-Critical Slip,8,0.0,false,4.0,2.0 W1,MEC-SET,Set Pump Skids and Grout Baseplates,Activity Slip,8,0.0,false,26.0,24.0 W1,MEC-PIPE,Internal Process Piping Install,Activity Slip,8,0.0,false,27.0,27.0 W1,MEC-VALVE,Valve and Actuator Install,Activity Slip,8,0.0,false,27.0,24.0 W1,MEC-TEST,Hydrostatic Test Process Piping,Activity Slip,8,0.0,false,26.0,27.0 W1,ELE-COND,Conduit and Cable Tray Rough-In,Critical Slip,8,0.0,true,0.0,0.0 W1,ELE-MCC,Set MCC and VFD Line-Up,Critical Slip,8,0.0,true,0.0,0.0 W1,ELE-CABLE,Power and Control Cable Pull,Critical Slip,8,0.0,true,0.0,0.0 W1,ELE-TERM,Terminate and Point-to-Point Check,Critical Slip,8,0.0,true,0.0,0.0 W1,MS-ENERG,Permanent Power Energized,Critical Slip,8,0.0,true,0.0,0.0 W1,BLD-ERECT,Erect Pre-Engineered Building Frame,Critical Slip,8,0.0,true,0.0,0.0 W1,BLD-ROOF,Roof Deck and Membrane,Critical Slip,8,0.0,true,0.0,0.0 W1,BLD-CLAD,Wall Cladding and Flashing,Activity Slip,8,0.0,false,87.0,85.0 W1,BLD-DOOR,Overhead Doors and Louvres,Activity Slip,8,0.0,false,85.0,84.0 W1,COM-FLUSH,System Flush and Chlorination,Critical Slip,8,0.0,true,0.0,0.0 W1,COM-LOOP,Instrument Loop Checks,Critical Slip,8,0.0,true,0.0,0.0 W1,COM-FUNC,Functional Testing All Modes,Critical Slip,8,0.0,true,0.0,0.0 W1,COM-PERF,Performance and Capacity Demonstration,Critical Slip,8,0.0,true,0.0,0.0 W1,COM-DEMOB,Demobilize and Turnover Documentation,Critical Slip,8,0.0,true,0.0,0.0 W1,MS-SC,Substantial Completion,Critical Slip,8,0.0,true,0.0,0.0 W2,CIV-WALL,Form Reinforce and Pour Wet Well Walls,Duration Growth,7,7.0,false,0.0,0.0 W2,CIV-CURE,Wall Cure and Strip Formwork,Near-Critical Slip,7,0.0,false,0.0,0.0 W2,MS-CONC,Concrete Structure Complete,Near-Critical Slip,7,0.0,false,0.0,0.0 W2,CIV-BKF,Backfill and Compact Around Structure,Near-Critical Slip,7,0.0,false,4.0,0.0 W2,CIV-SLAB,Grade Slab and Equipment Pads,Near-Critical Slip,7,0.0,false,2.0,0.0 W2,MEC-SET,Set Pump Skids and Grout Baseplates,Near-Critical Slip,7,0.0,false,24.0,0.0 W2,MEC-PIPE,Internal Process Piping Install,Activity Slip,7,0.0,false,27.0,27.0 W2,MEC-VALVE,Valve and Actuator Install,Activity Slip,7,0.0,false,24.0,27.0 W2,MEC-TEST,Hydrostatic Test Process Piping,Activity Slip,7,0.0,false,27.0,27.0 W2,ELE-COND,Conduit and Cable Tray Rough-In,Critical Slip,7,0.0,true,0.0,0.0 W2,ELE-MCC,Set MCC and VFD Line-Up,Critical Slip,7,0.0,true,0.0,0.0 W2,ELE-CABLE,Power and Control Cable Pull,Critical Slip,7,0.0,true,0.0,0.0 W2,ELE-TERM,Terminate and Point-to-Point Check,Critical Slip,7,0.0,true,0.0,0.0 W2,MS-ENERG,Permanent Power Energized,Critical Slip,7,0.0,true,0.0,0.0 W2,BLD-ERECT,Erect Pre-Engineered Building Frame,Near-Critical Slip,7,0.0,false,0.0,0.0 W2,BLD-ROOF,Roof Deck and Membrane,Near-Critical Slip,7,0.0,false,0.0,0.0 W2,BLD-CLAD,Wall Cladding and Flashing,Activity Slip,7,0.0,false,85.0,84.0 W2,BLD-DOOR,Overhead Doors and Louvres,Activity Slip,7,0.0,false,84.0,84.0 W2,COM-FLUSH,System Flush and Chlorination,Critical Slip,7,0.0,true,0.0,0.0 W2,COM-LOOP,Instrument Loop Checks,Critical Slip,7,0.0,true,0.0,0.0 W2,COM-FUNC,Functional Testing All Modes,Critical Slip,7,0.0,true,0.0,0.0 W2,COM-PERF,Performance and Capacity Demonstration,Critical Slip,7,0.0,true,0.0,0.0 W2,COM-DEMOB,Demobilize and Turnover Documentation,Critical Slip,7,0.0,true,0.0,0.0 W2,MS-SC,Substantial Completion,Critical Slip,7,0.0,true,0.0,0.0 W3,MEC-PIPE,Internal Process Piping Install,Duration Growth,6,6.0,false,27.0,0.0 W3,MEC-VALVE,Valve and Actuator Install,Near-Critical Slip,6,0.0,false,27.0,0.0 W3,MEC-TEST,Hydrostatic Test Process Piping,Near-Critical Slip,6,0.0,false,27.0,0.0 W3,ELE-COND,Conduit and Cable Tray Rough-In,Duration Growth,6,6.0,false,0.0,0.0 W3,ELE-MCC,Set MCC and VFD Line-Up,Near-Critical Slip,6,0.0,false,0.0,0.0 W3,ELE-CABLE,Power and Control Cable Pull,Near-Critical Slip,6,0.0,false,0.0,0.0 W3,ELE-TERM,Terminate and Point-to-Point Check,Near-Critical Slip,6,0.0,false,0.0,0.0 W3,MS-ENERG,Permanent Power Energized,Near-Critical Slip,6,0.0,false,0.0,0.0 W3,COM-FLUSH,System Flush and Chlorination,Near-Critical Slip,6,0.0,false,0.0,0.0 W3,COM-LOOP,Instrument Loop Checks,Near-Critical Slip,6,0.0,false,0.0,0.0 W3,COM-FUNC,Functional Testing All Modes,Near-Critical Slip,2,-4.0,false,0.0,0.0 W3,COM-PERF,Performance and Capacity Demonstration,Critical Slip,2,0.0,true,0.0,0.0 W3,COM-DEMOB,Demobilize and Turnover Documentation,Critical Slip,2,0.0,true,0.0,0.0 W3,MS-SC,Substantial Completion,Critical Slip,2,0.0,true,0.0,0.0