CPP
CRITICAL PATH PARTNERSForensic Schedule Analysis
DWG · FDA-01 / SHEET A-00
Windows Analysis · AACE MIP 3.3
Forensic Delay Analysis

CEDARLINE 3 windows analyzed: Baseline → Update 1

Project
CEDARLINE
Prepared By
Dana Fitkowski · Critical Path Partners
Window Period
03-Feb-2025 → 30-Sep-2025
Generated
19-Aug-2026
Baseline → Final Slip (wd)
+17wd
Completion delay · 17 slip-days unattributed
Window Shifts
+17 wd
Windows
3
Attribution
0.0%
Baseline → Final Slip (wd)
+17wd
Cumulative vs baseline completion (working days)
Sum of Window Shifts (wd)
+17wd
Signed shift across all windows (working days)
Windows Analyzed
3
Baseline → Update 1
Attribution Complete
0.0%
17 slip-days unattributed
Attribution required: 17 slip-days remain unattributed. Fill in the responsible_party column on the slip register (Owner / Contractor / Concurrent / Force Majeure) to populate the attribution chart.
Basis of measurementHow to read the numbers in this report
Day unit
Working days
Every day count in this deliverable is in working days. No calendar-day figure is displayed. Where a contract clause is quoted verbatim in calendar days, the computed equivalent is given in working days alongside.
Calendar
The activity's own P6 calendar
Deltas are counted on the activity's own P6 calendar via work_day_delta. Where no project calendar is available the documented fallback is Monday to Friday with no holidays, and that fallback is disclosed on the affected figure.
Date fields read
P6 Start and Finish columns only
A negative number means the contractor lost time
Convention: contractor-loss: negative = the contractor lost time
Variance
How it is computed
A negative value means
Start variance
contract start - subject start
started later than contract, prep time lost
Finish variance
subject finish - contract finish
finished earlier than contract, buffer lost
Window variance
subject window - contract window
window compressed
Milestone variance
subject date - contract date
date pulled in ahead of contract
The subtraction order is deliberately opposite between start and finish, so that a negative value means lost time in both columns. Reversing either order to make them look consistent would invert the sign of every finish variance in this report.
A-01

Windows Overview

per-window shift and cumulative vs baseline, working days
WindowPeriodShift (wd)Cumulative vs Baseline (wd)CP ActivitiesCP Duration GrowthSlipped Activities
Baseline → Update 103-Feb-2025 → 31-Mar-2025+8 wd+8 wd17126
Update 1 → Update 231-Mar-2025 → 30-Jun-2025+7 wd+15 wd11024
Update 2 → Update 330-Jun-2025 → 30-Sep-2025+2 wd+17 wd3014
A-02

Window Shift Trend

signed completion shift per window (working days)
Window slip (working days)3 windows
8 wd4 wd0 wd+8 wdBaseline → Update 1+7 wdUpdate 1 → Update 2+2 wdUpdate 2 → Update 3
Window slip (positive = delay)+17 wd total window shift
A-03

Cumulative Attribution Summary

party share of project slip-days
No attribution filled in yet. The chart will populate once responsible_party values are set on slip register entries. All 17 slip-days currently unattributed.
Attribution by responsible party (wd)17 wd total
Owner0 wdContractor0 wdConcurrent0 wdForce Majeure0 wdUnattributed17 wd
Unattributed pending analyst input17 wd awaiting attribution
Owner
0 wd
Contractor
0 wd
Concurrent
0 wd
Force Majeure
0 wd
A-04

Concurrent Delay Matrix

per-window × per-party attribution grid
Each cell = working days attributed to that party in that window (Window Shift (wd)). Column totals equal the cumulative party share across the project, which is a bookkeeping definition internal to this matrix rather than an AACE rule. The grand total equals the project completion shift in working days (CPP conservation check, per the AACE 29R-03 §3.3.E.13 requirement that the summed per-period net impacts equal the difference between the first and last schedule update in the evaluation). The Finish Driver column names the activity and date field the shift was measured on.
Unattributed dump: 100.0% of the project shift (working days) lands in the Unattributed column with no named responsible party. This matrix does NOT establish party responsibility for that share. It is not a finding that no party is responsible, only that the input slips carried no responsible_party. Assign responsible parties to the driving CP slips before relying on this attribution. Affected window(s): Baseline → Update 1, Update 1 → Update 2, Update 2 → Update 3.
WindowPeriodOwnerContractorConcurrentForce MajeureUnattributedWindow Shift (wd)Finish Driver
Baseline → Update 1 !UNATTRIBUTED03-Feb-2025 → 31-Mar-2025+8 wd+8 wdCOM-DEMOB
target_end_date
Update 1 → Update 2 ~CASCADE !UNATTRIBUTED31-Mar-2025 → 30-Jun-2025+7 wd+7 wdCOM-DEMOB
target_end_date
Update 2 → Update 3 ~CASCADE !UNATTRIBUTED30-Jun-2025 → 30-Sep-2025+2 wd+2 wdCOM-DEMOB
target_end_date
Cumulativeproject totals0 wd0 wd0 wd0 wd+17 wd+17 wd
~CASCADE = window had no CP duration growth; attribution inferred from dominant CP slip party. !UNATTRIBUTED = the dominant share of the window shift dropped to Unattributed (no named responsible party). Reference: AACE RP 29R-03 §3.3.I (apportionment) · §4.2 (concurrency).
A-05

Slip Velocity & Acceleration

per-window slip-rate trend
Velocity = signed completion shift (working days) ÷ window duration (working days on the same calendar). Acceleration = change in velocity vs the prior window. Half-period estimate (working days) assumes uniform deterioration within the window.
Mean Velocity (wd/wd)
+0.116
working-days slip / working-day elapsed
Max-Velocity Window
fastest deterioration
Accelerating Windows
0
velocity increasing
Decelerating Windows
2
velocity decreasing
WindowPeriodDuration (wd)Shift (wd)Velocity (wd/wd)Δ AccelerationMidpoint DateHalf-Period Slip (wd)
Baseline → Update 103-Feb-2025 → 31-Mar-202539 wd+8 wd+0.20503-Mar-2025+4.0 wd
Update 1 → Update 231-Mar-2025 → 30-Jun-202563 wd+7 wd+0.111▼ -0.09415-May-2025+3.5 wd
Update 2 → Update 330-Jun-2025 → 30-Sep-202563 wd+2 wd+0.032▼ -0.07915-Aug-2025+1.0 wd
Caveat (cite in any expert report): Slip velocity is a working-day/working-day rate: numerator = working-day completion shift, denominator = working days between data dates on the same calendar (see basis). Midpoint estimates assume uniform deterioration within the window. Actual slip events may have clustered at any point inside the window. The midpoint is a probabilistic centroid, not an observed event date. Cite this caveat in any expert report that quotes the half-period estimate. Velocity is a per-window average rate, not an instantaneous one; acceleration is a finite difference between successive averages and is sensitive to window-length disparity (sign and direction are reliable, magnitude less so).
Recovery windows (negative shift) detected: 0. Reference: AACE RP 29R-03 §3.3 (Windows Analysis: MIP 3.3 Observational / Dynamic).
A-06

WOET — Worked-vs-On-time Execution Timeline

4-state day classification
4-state day classification of as-built execution against the baseline plan. All day counts below are working days on each activity’s P6 calendar (weekends and holidays excluded). Reference date: 2025-09-30. Activities classified: 35. On-time-or-better: 33.8% (Progress 33.8% + Gain). Slipped: 66.2% (Extended + Void).
Progress (wd)
201 wd
33.8% on plan
Gain (wd)
0.0% ahead
Extended (wd)
211 wd
35.5% slipped
Void (wd)
183 wd
30.8% unrecovered
A-06Worst-affected activities (sorted Extended → Void — full list)
35 classified activities — all listedExport CSV
CodeActivityBaseline PeriodActual PeriodProgress (wd)Gain (wd)Extended (wd)Void (wd)
MEC-PIPEInternal Process Piping Install2025-05-22 → 2025-06-172025-06-12 → 2025-07-174 wd0 wd21 wd15 wd
ELE-CONDConduit and Cable Tray Rough-In2025-06-03 → 2025-06-232025-06-24 → 2025-07-230 wd0 wd21 wd15 wd
CIV-WALLForm Reinforce and Pour Wet Well Walls2025-04-09 → 2025-04-302025-04-22 → 2025-05-227 wd0 wd15 wd8 wd
ELE-CABLEPower and Control Cable Pull2025-06-30 → 2025-07-172025-07-30 → 2025-08-180 wd0 wd13 wd13 wd
ELE-PROCMCC and VFD Fabrication and Delivery2025-02-03 → 2025-03-252025-02-03 → 2025-04-1036 wd0 wd12 wd0 wd
BLD-ERECTErect Pre-Engineered Building Frame2025-05-09 → 2025-05-262025-06-02 → 2025-06-160 wd0 wd11 wd11 wd
CIV-SLABGrade Slab and Equipment Pads2025-05-20 → 2025-05-302025-06-10 → 2025-06-200 wd0 wd9 wd9 wd
MEC-SETSet Pump Skids and Grout Baseplates2025-05-09 → 2025-05-222025-06-02 → 2025-06-120 wd0 wd9 wd9 wd
ELE-TERMTerminate and Point-to-Point Check2025-07-17 → 2025-07-292025-08-18 → 2025-08-280 wd0 wd9 wd9 wd
BLD-CLADWall Cladding and Flashing2025-06-03 → 2025-06-132025-06-24 → 2025-07-070 wd0 wd9 wd9 wd
COM-LOOPInstrument Loop Checks2025-08-06 → 2025-08-182025-09-05 → 2025-09-170 wd0 wd9 wd9 wd
CIV-CUREWall Cure and Strip Formwork2025-04-30 → 2025-05-092025-05-22 → 2025-06-020 wd0 wd8 wd8 wd
CIV-BASEForm Reinforce and Pour Base Slab2025-03-24 → 2025-04-092025-03-24 → 2025-04-2213 wd0 wd8 wd0 wd
COM-FUNCFunctional Testing All Modes2025-08-18 → 2025-09-022025-09-17 → 2025-09-250 wd0 wd7 wd11 wd
CIV-BKFBackfill and Compact Around Structure2025-05-09 → 2025-05-202025-06-02 → 2025-06-100 wd0 wd7 wd7 wd
MEC-VALVEValve and Actuator Install2025-06-17 → 2025-06-252025-07-17 → 2025-07-250 wd0 wd7 wd7 wd
BLD-ROOFRoof Deck and Membrane2025-05-26 → 2025-06-032025-06-16 → 2025-06-240 wd0 wd7 wd7 wd
MEC-TESTHydrostatic Test Process Piping2025-06-25 → 2025-07-032025-07-25 → 2025-08-010 wd0 wd6 wd6 wd
ELE-MCCSet MCC and VFD Line-Up2025-06-23 → 2025-06-302025-07-23 → 2025-07-300 wd0 wd6 wd6 wd
COM-FLUSHSystem Flush and Chlorination2025-07-29 → 2025-08-062025-08-28 → 2025-09-050 wd0 wd6 wd6 wd
BLD-DOOROverhead Doors and Louvres2025-06-13 → 2025-06-192025-07-07 → 2025-07-110 wd0 wd5 wd5 wd
COM-PERF IN-PROGRESSPerformance and Capacity Demonstration2025-09-02 → 2025-09-092025-09-25 → —0 wd0 wd4 wd6 wd
MS-CONCConcrete Structure Complete2025-05-09 → 2025-05-092025-06-02 → 2025-06-020 wd0 wd1 wd1 wd
MS-ENERGPermanent Power Energized2025-07-29 → 2025-07-292025-08-28 → 2025-08-280 wd0 wd1 wd1 wd
COM-DEMOBDemobilize and Turnover Documentation2025-09-09 → 2025-09-12— → —0 wd0 wd0 wd4 wd
MS-SCSubstantial Completion2025-09-12 → 2025-09-12— → —0 wd0 wd0 wd1 wd
MS-NTPNotice to Proceed2025-02-03 → 2025-02-032025-02-03 → 2025-02-031 wd0 wd0 wd0 wd
PRE-MOBMobilize Site Offices and Laydown2025-02-03 → 2025-02-102025-02-03 → 2025-02-106 wd0 wd0 wd0 wd
PRE-SHOPStructural Shop Drawings and Review2025-02-03 → 2025-02-252025-02-03 → 2025-02-2516 wd0 wd0 wd0 wd
PRE-PERMITBuilding Permit Issuance2025-02-03 → 2025-03-042025-02-03 → 2025-03-0421 wd0 wd0 wd0 wd
CIV-EXCBulk Excavation Wet Well2025-03-04 → 2025-03-182025-03-04 → 2025-03-1811 wd0 wd0 wd0 wd
CIV-SOEShoring and Dewatering Install2025-02-10 → 2025-02-212025-02-10 → 2025-02-219 wd0 wd0 wd0 wd
CIV-MUDMud Slab and Survey Layout2025-03-18 → 2025-03-242025-03-18 → 2025-03-245 wd0 wd0 wd0 wd
MEC-PROCPump Skid Fabrication and Delivery2025-02-03 → 2025-04-012025-02-03 → 2025-04-0141 wd0 wd0 wd0 wd
BLD-PROCPre-Engineered Building Delivery2025-02-03 → 2025-03-182025-02-03 → 2025-03-1831 wd0 wd0 wd0 wd
35 classified activities — full list shown. Reference: Per-day execution-classification overlay on AACE RP 29R-03 §3.3 (Windows Analysis, MIP 3.3). A CPP-disclosed enhancement, NOT itself AACE-defined. Day counts are working days on each activity P6 calendar (weekends and holidays excluded), not calendar days.
A-07

Float Burndown Across Windows

per-activity float-erosion register, drawing-sheet exhibit
A-07

Criticality predates the window: 17 of 23 activities opened at TF ≤ 0 at Baseline; none demonstrably crossed during 3 windows, while completion moved 17 working days later

Total float in working days (wd), read from the schedule of record at 4 CPM snapshots, Baseline through Update 3 spanning 3 windows, day math on the project working calendar. Criticality test: TF ≤ 0. Sign convention: negative Δ = float lost across the window. Finish driver COM-DEMOB; completion Baseline → Update 3: 17 wd later. Register bands: TF ≤ 0 · 1-5 wd (near-critical) · 6-20 wd · over 20 wd.

FIRMCRITICAL PATH PARTNERS
EXHIBITFLOAT EROSION REGISTER
DWG NOA-07
REV1
DATE19-AUG-2026
SHEET1 OF 1
UNITSWORKING DAYS (WD)
SCALELINEAR
BASISAACE RP 29R-03
SNAPSHOTS4
Critical at Baseline
17
at TF ≤ 0 when the first window opened · no in-window crossing is claimed for them
Demonstrably lost float in window
0
a TF > 0 observation followed by TF ≤ 0 at a later snapshot
Never reached TF ≤ 0
2
positive float at every observation
Single-observation entrants: 4

4 further activities first appear with one observation only. No second reading exists, so a loss of float cannot be demonstrated for them and is not claimed here.

conservation: 17 + 0 + 4 + 2 = 23 · reconciles to the register below

KEYTF at first observationfloat lostfloat gainedTF ≤ 0 at last observation (critical)TF > 0 at last observationintermediate observation
TF = 0 (critical)near-critical band ≤ 5 wd, per register bandingFloat lost across 3 windows · 1 activity, sorted by lossFloat gained across 3 windows · 1 activity, sorted by gainCIV-SLABCIV-BKF+2 wd · 2 → 4Δ −2 wd · largest loss in the windowCIV-SLAB · TF 4 → 2 · never reached TF ≤ 0012345Total float at snapshot, working days · linear scale to 5 wd · nothing clipped
All 23 activities by float band · Baseline vs Update 3
counts of activities per register band at the first and last observation
BaselineUpdate 3
10202121TF ≤ 0Δ 0221-5 wdΔ 0006-20 wdΔ 000> 20 wdΔ 0

Reading notes

  1. Not plotted above: 21 activities with zero net float movement · 21 held TF ≤ 0 at every observation (17 observed at multiple snapshots, 4 single-observation) · 0 held constant positive float. All 23 appear in the register below.
  2. Baseline band counts in the inset carry the register convention: the 4 single-observation entrants are imputed at their only reading. The movement panel plots observed pairs only.
  3. The horizontal scale is linear to 5 wd; no section break is needed.
  4. Band deltas conserve across the population: 0 + 0 + 0 + 0 = 0 over 23 activities.
  5. 4 snapshots are plotted per row: the grey tick is the first observation, the dot the last, and small intermediate ticks mark each observation between them, so the trajectory is retained.
  6. Engine-reported recovery events (TF increase between consecutive snapshots): 1.
  7. Method caveat (cite in any expert report): Float burndown is post-processing of analyst-supplied CPM snapshots. Accuracy depends on the quality of the underlying schedule updates. Recovery events (TF increase) may reflect legitimate scope removal, schedule optimization, or activity deletion, and the analyst must verify which. Slip velocity is a linear average; actual burndown may be non-linear. CPP first-mover at per-activity float-timeline granularity (2026-05-09); methodology not yet formally published in AACE/SCL literature.
SOURCE · activity float register, 23 activities · CPM snapshots (data dates of record): Baseline → Update 3 (4 snapshots / 3 windows) · float and Δ in working days on the project working calendar · observational window basis per AACE RP 29R-03 · criticality counts analyst-verified only · finish driver COM-DEMOB · completion Baseline → Update 3: 17 wd later · buckets reconcile: 17 + 0 + 4 + 2 = 23 · method: compute_float_burndown v2.9.41
Activity register · all 23 activities TF FIRST / LAST · Δ · FIRST AT TF ≤ 0
ActivityTF at first obs (wd)TF at last obs (wd)Δ (wd)First at TF ≤ 0Movement
BLD-ERECT000Baselineno movement
BLD-ROOF000Baselineno movement
CIV-BASE000Baselineno movement
CIV-BKF24+2nevergained
CIV-CURE000Baselineno movement
CIV-EXC000Baselinesingle observation
CIV-MUD000Baselinesingle observation
CIV-SLAB42−2neverlost
CIV-WALL000Baselineno movement
COM-DEMOB000Baselineno movement
COM-FLUSH000Baselineno movement
COM-FUNC000Baselineno movement
COM-LOOP000Baselineno movement
COM-PERF000Baselineno movement
ELE-CABLE000Baselineno movement
ELE-COND000Baselineno movement
ELE-MCC000Baselineno movement
ELE-TERM000Baselineno movement
MS-CONC000Baselineno movement
MS-ENERG000Baselineno movement
MS-NTP000Baselinesingle observation
MS-SC000Baselineno movement
PRE-PERMIT000Baselinesingle observation
NOTE · for the 4 single-observation rows the register carries the only reading in both float columns; no other observation exists for them · engine order preserved (activity code ascending) · compute_float_burndown v2.9.41
A-08

Cumulative Activity Slip Register

sum of signed slip across all windows
A-08Most-slipped first — full list (26 activities)
26 rows — all listedExport CSV
Sum of signed slip across all windows per activity. Most-slipped first.
CodeActivityTotal SlipWindows Touched
MEC-PIPEInternal Process Piping Install+21 wd3
MEC-VALVEValve and Actuator Install+21 wd3
MEC-TESTHydrostatic Test Process Piping+21 wd3
ELE-CONDConduit and Cable Tray Rough-In+21 wd3
ELE-MCCSet MCC and VFD Line-Up+21 wd3
ELE-CABLEPower and Control Cable Pull+21 wd3
ELE-TERMTerminate and Point-to-Point Check+21 wd3
MS-ENERGPermanent Power Energized+21 wd3
COM-FLUSHSystem Flush and Chlorination+21 wd3
COM-LOOPInstrument Loop Checks+21 wd3
COM-FUNCFunctional Testing All Modes+17 wd3
COM-PERF CPPerformance and Capacity Demonstration+17 wd3
COM-DEMOB CPDemobilize and Turnover Documentation+17 wd3
MS-SC CPSubstantial Completion+17 wd3
CIV-WALLForm Reinforce and Pour Wet Well Walls+15 wd2
CIV-CUREWall Cure and Strip Formwork+15 wd2
MS-CONCConcrete Structure Complete+15 wd2
CIV-BKFBackfill and Compact Around Structure+15 wd2
CIV-SLABGrade Slab and Equipment Pads+15 wd2
MEC-SETSet Pump Skids and Grout Baseplates+15 wd2
BLD-ERECTErect Pre-Engineered Building Frame+15 wd2
BLD-ROOFRoof Deck and Membrane+15 wd2
BLD-CLADWall Cladding and Flashing+15 wd2
BLD-DOOROverhead Doors and Louvres+15 wd2
ELE-PROCMCC and VFD Fabrication and Delivery+12 wd1
CIV-BASE CPForm Reinforce and Pour Base Slab+8 wd1
26 rows — full list shown.
A-09

Window 1 — Baseline → Update 1

03-Feb-2025 → 31-Mar-2025 · shift +8 wd
Window Shift (wd)+8 wd · CRITICALPeriod03-Feb-2025 → 31-Mar-2025
Newly Critical
activities added to CP
No Longer Critical
activities left CP
Slipped Activities
26
finish dates later
CP Duration Growth
CP activities grew
Completion-shift basis
The window shift is measured on the finish driver shown below. Scheduled finish (scd_end_date) is cross-checked but never used as the shift basis.
Shift basis
Latest activity finish
Finish activity
COM-DEMOB
Date field used
target_end_date
Window shift (working days)
8 wd
Cumulative vs baseline (working days)
8 wd
Scheduled finish (prior)
12-Sep-2025
Scheduled finish (later)
24-Sep-2025
Basis vs project finish
Consistent
Critical-path duration growth (full list)
Direct delay — every day of duration growth on a CP activity is a day of project slip.
CodeActivityPrior DurationLater DurationGrowth
CIV-BASEForm Reinforce and Pour Base Slab12.0 wd20.0 wd+8.0 wd
Newly Critical (0)
None
No Longer Critical (4)
CIV-EXCBulk Excavation Wet Well
CIV-MUDMud Slab and Survey Layout
MS-NTPNotice to Proceed
PRE-PERMITBuilding Permit Issuance
A-09Slip register — 26 activities (full list) · assign responsible party
26 activities — all listedExport CSV
Fill in responsible_party and cause_notes for each slipped activity. Attribution drives the cumulative entitlement calculation.
CodeActivityPrior FinishLater FinishSlipResponsible PartyCause Notes
ELE-PROCMCC and VFD Fabrication and Delivery25-Mar-202510-Apr-2025+12 wd— assign —— add notes —
CIV-BASE CPForm Reinforce and Pour Base Slab09-Apr-202522-Apr-2025+8 wd— assign —— add notes —
CIV-WALL CPForm Reinforce and Pour Wet Well Walls30-Apr-202512-May-2025+8 wd— assign —— add notes —
CIV-CURE CPWall Cure and Strip Formwork09-May-202522-May-2025+8 wd— assign —— add notes —
MS-CONC CPConcrete Structure Complete09-May-202522-May-2025+8 wd— assign —— add notes —
CIV-BKFBackfill and Compact Around Structure20-May-202530-May-2025+8 wd— assign —— add notes —
CIV-SLABGrade Slab and Equipment Pads30-May-202511-Jun-2025+8 wd— assign —— add notes —
MEC-SETSet Pump Skids and Grout Baseplates22-May-202503-Jun-2025+8 wd— assign —— add notes —
MEC-PIPEInternal Process Piping Install17-Jun-202527-Jun-2025+8 wd— assign —— add notes —
MEC-VALVEValve and Actuator Install25-Jun-202508-Jul-2025+8 wd— assign —— add notes —
MEC-TESTHydrostatic Test Process Piping03-Jul-202515-Jul-2025+8 wd— assign —— add notes —
ELE-COND CPConduit and Cable Tray Rough-In23-Jun-202504-Jul-2025+8 wd— assign —— add notes —
ELE-MCC CPSet MCC and VFD Line-Up30-Jun-202511-Jul-2025+8 wd— assign —— add notes —
ELE-CABLE CPPower and Control Cable Pull17-Jul-202529-Jul-2025+8 wd— assign —— add notes —
ELE-TERM CPTerminate and Point-to-Point Check29-Jul-202511-Aug-2025+8 wd— assign —— add notes —
MS-ENERG CPPermanent Power Energized29-Jul-202511-Aug-2025+8 wd— assign —— add notes —
BLD-ERECT CPErect Pre-Engineered Building Frame26-May-202505-Jun-2025+8 wd— assign —— add notes —
BLD-ROOF CPRoof Deck and Membrane03-Jun-202513-Jun-2025+8 wd— assign —— add notes —
BLD-CLADWall Cladding and Flashing13-Jun-202525-Jun-2025+8 wd— assign —— add notes —
BLD-DOOROverhead Doors and Louvres19-Jun-202502-Jul-2025+8 wd— assign —— add notes —
COM-FLUSH CPSystem Flush and Chlorination06-Aug-202518-Aug-2025+8 wd— assign —— add notes —
COM-LOOP CPInstrument Loop Checks18-Aug-202528-Aug-2025+8 wd— assign —— add notes —
COM-FUNC CPFunctional Testing All Modes02-Sep-202512-Sep-2025+8 wd— assign —— add notes —
COM-PERF CPPerformance and Capacity Demonstration09-Sep-202519-Sep-2025+8 wd— assign —— add notes —
COM-DEMOB CPDemobilize and Turnover Documentation12-Sep-202524-Sep-2025+8 wd— assign —— add notes —
MS-SC CPSubstantial Completion12-Sep-202524-Sep-2025+8 wd— assign —— add notes —
A-10

Window 2 — Update 1 → Update 2

31-Mar-2025 → 30-Jun-2025 · shift +7 wd
Window Shift (wd)+7 wd · CRITICALPeriod31-Mar-2025 → 30-Jun-2025
Newly Critical
activities added to CP
No Longer Critical
activities left CP
Slipped Activities
24
finish dates later
CP Duration Growth
no CP growth this window
Completion-shift basis
The window shift is measured on the finish driver shown below. Scheduled finish (scd_end_date) is cross-checked but never used as the shift basis.
Shift basis
Latest activity finish
Finish activity
COM-DEMOB
Date field used
target_end_date
Window shift (working days)
7 wd
Cumulative vs baseline (working days)
15 wd
Scheduled finish (prior)
24-Sep-2025
Scheduled finish (later)
03-Oct-2025
Basis vs project finish
Consistent
Newly Critical (0)
None
No Longer Critical (6)
BLD-ERECTErect Pre-Engineered Building Frame
BLD-ROOFRoof Deck and Membrane
CIV-BASEForm Reinforce and Pour Base Slab
CIV-CUREWall Cure and Strip Formwork
CIV-WALLForm Reinforce and Pour Wet Well Walls
MS-CONCConcrete Structure Complete
A-10Slip register — 24 activities (full list) · assign responsible party
24 activities — all listedExport CSV
Fill in responsible_party and cause_notes for each slipped activity. Attribution drives the cumulative entitlement calculation.
CodeActivityPrior FinishLater FinishSlipResponsible PartyCause Notes
CIV-WALLForm Reinforce and Pour Wet Well Walls12-May-202522-May-2025+7 wd— assign —— add notes —
CIV-CUREWall Cure and Strip Formwork22-May-202502-Jun-2025+7 wd— assign —— add notes —
MS-CONCConcrete Structure Complete22-May-202502-Jun-2025+7 wd— assign —— add notes —
CIV-BKFBackfill and Compact Around Structure30-May-202510-Jun-2025+7 wd— assign —— add notes —
CIV-SLABGrade Slab and Equipment Pads11-Jun-202520-Jun-2025+7 wd— assign —— add notes —
MEC-SETSet Pump Skids and Grout Baseplates03-Jun-202512-Jun-2025+7 wd— assign —— add notes —
MEC-PIPEInternal Process Piping Install27-Jun-202509-Jul-2025+7 wd— assign —— add notes —
MEC-VALVEValve and Actuator Install08-Jul-202517-Jul-2025+7 wd— assign —— add notes —
MEC-TESTHydrostatic Test Process Piping15-Jul-202524-Jul-2025+7 wd— assign —— add notes —
ELE-COND CPConduit and Cable Tray Rough-In04-Jul-202515-Jul-2025+7 wd— assign —— add notes —
ELE-MCC CPSet MCC and VFD Line-Up11-Jul-202522-Jul-2025+7 wd— assign —— add notes —
ELE-CABLE CPPower and Control Cable Pull29-Jul-202508-Aug-2025+7 wd— assign —— add notes —
ELE-TERM CPTerminate and Point-to-Point Check11-Aug-202520-Aug-2025+7 wd— assign —— add notes —
MS-ENERG CPPermanent Power Energized11-Aug-202520-Aug-2025+7 wd— assign —— add notes —
BLD-ERECTErect Pre-Engineered Building Frame05-Jun-202516-Jun-2025+7 wd— assign —— add notes —
BLD-ROOFRoof Deck and Membrane13-Jun-202524-Jun-2025+7 wd— assign —— add notes —
BLD-CLADWall Cladding and Flashing25-Jun-202507-Jul-2025+7 wd— assign —— add notes —
BLD-DOOROverhead Doors and Louvres02-Jul-202511-Jul-2025+7 wd— assign —— add notes —
COM-FLUSH CPSystem Flush and Chlorination18-Aug-202527-Aug-2025+7 wd— assign —— add notes —
COM-LOOP CPInstrument Loop Checks28-Aug-202509-Sep-2025+7 wd— assign —— add notes —
COM-FUNC CPFunctional Testing All Modes12-Sep-202523-Sep-2025+7 wd— assign —— add notes —
COM-PERF CPPerformance and Capacity Demonstration19-Sep-202530-Sep-2025+7 wd— assign —— add notes —
COM-DEMOB CPDemobilize and Turnover Documentation24-Sep-202503-Oct-2025+7 wd— assign —— add notes —
MS-SC CPSubstantial Completion24-Sep-202503-Oct-2025+7 wd— assign —— add notes —
A-11

Window 3 — Update 2 → Update 3

30-Jun-2025 → 30-Sep-2025 · shift +2 wd
Window Shift (wd)+2 wd · WATCHPeriod30-Jun-2025 → 30-Sep-2025
Newly Critical
activities added to CP
No Longer Critical
activities left CP
Slipped Activities
14
finish dates later
CP Duration Growth
no CP growth this window
Completion-shift basis
The window shift is measured on the finish driver shown below. Scheduled finish (scd_end_date) is cross-checked but never used as the shift basis.
Shift basis
Latest activity finish
Finish activity
COM-DEMOB
Date field used
target_end_date
Window shift (working days)
2 wd
Cumulative vs baseline (working days)
17 wd
Scheduled finish (prior)
03-Oct-2025
Scheduled finish (later)
07-Oct-2025
Basis vs project finish
Consistent
Newly Critical (0)
None
No Longer Critical (8)
COM-FLUSHSystem Flush and Chlorination
COM-FUNCFunctional Testing All Modes
COM-LOOPInstrument Loop Checks
ELE-CABLEPower and Control Cable Pull
ELE-CONDConduit and Cable Tray Rough-In
ELE-MCCSet MCC and VFD Line-Up
ELE-TERMTerminate and Point-to-Point Check
MS-ENERGPermanent Power Energized
A-11Slip register — 14 activities (full list) · assign responsible party
14 activities — all listedExport CSV
Fill in responsible_party and cause_notes for each slipped activity. Attribution drives the cumulative entitlement calculation.
CodeActivityPrior FinishLater FinishSlipResponsible PartyCause Notes
MEC-PIPEInternal Process Piping Install09-Jul-202517-Jul-2025+6 wd— assign —— add notes —
MEC-VALVEValve and Actuator Install17-Jul-202525-Jul-2025+6 wd— assign —— add notes —
MEC-TESTHydrostatic Test Process Piping24-Jul-202501-Aug-2025+6 wd— assign —— add notes —
ELE-CONDConduit and Cable Tray Rough-In15-Jul-202523-Jul-2025+6 wd— assign —— add notes —
ELE-MCCSet MCC and VFD Line-Up22-Jul-202530-Jul-2025+6 wd— assign —— add notes —
ELE-CABLEPower and Control Cable Pull08-Aug-202518-Aug-2025+6 wd— assign —— add notes —
ELE-TERMTerminate and Point-to-Point Check20-Aug-202528-Aug-2025+6 wd— assign —— add notes —
MS-ENERGPermanent Power Energized20-Aug-202528-Aug-2025+6 wd— assign —— add notes —
COM-FLUSHSystem Flush and Chlorination27-Aug-202505-Sep-2025+6 wd— assign —— add notes —
COM-LOOPInstrument Loop Checks09-Sep-202517-Sep-2025+6 wd— assign —— add notes —
COM-FUNCFunctional Testing All Modes23-Sep-202525-Sep-2025+2 wd— assign —— add notes —
COM-PERF CPPerformance and Capacity Demonstration30-Sep-202502-Oct-2025+2 wd— assign —— add notes —
COM-DEMOB CPDemobilize and Turnover Documentation03-Oct-202507-Oct-2025+2 wd— assign —— add notes —
MS-SC CPSubstantial Completion03-Oct-202507-Oct-2025+2 wd— assign —— add notes —
A-12

Provenance & Method

reproducibility manifest
Generated
19-Aug-2026
Method
Windows Analysis — AACE MIP 3.3
Engine
CPP cpm-engine v2.9.41
Prepared By
Dana Fitkowski
Organization
Critical Path Partners
Windows Analyzed
3 (Baseline → Update 1)
Prepared by Dana Fitkowski · Source: Critical Path Partners · Generated 19-Aug-2026 · CPP Engine v2.9.41Method: AACE 29R-03 MIP 3.3 · SCL Delay and Disruption Protocol 2nd ed., Part B 11.6(c) time slice windows