Cedarline Pump Station Retrofit 3 windows analyzed: Baseline → Update 3
Summary of Findings
Completion moved 17 working days later than the baseline, from 11 September 2025 to 6 October 2025, across three windows. Of those, 17 are not explained by any attribution rule.
Each window’s movement is attributed as section 5 sets out.
What moved the finish: 17 working days
11 September 2025Forecast finish
6 October 2025
Movement by Window
The finish moved in three windows. The largest move was window 1, 8 working days later, from 3 February 2025 to 31 March 2025.
| Window | Period | Finish moved | Owner | Contractor | Not explained | Main causes |
|---|---|---|---|---|---|---|
| 1 | 3 February 2025 to 31 March 2025 | 8 working days later | 0 | 0 | 8 | - |
| 2 | 31 March 2025 to 30 June 2025 | 7 working days later | 0 | 0 | 7 | - |
| 3 | 30 June 2025 to 30 September 2025 | 2 working days later | 0 | 0 | 2 | - |
Why the Finish Moved
Without attribution rules for the causes, each window is attributed through the activities driving its finish, as section 5 sets out. Every one is listed below with how it moved the finish.
Drivers on the Driving Path
| Window | Activity | How it moved the finish | Its own working days | Party |
|---|---|---|---|---|
| 1 | CIV-BASE, Form Reinforce and Pour Base Slab | own growth | 8 | |
| 2 | nothing on the driving path moved | |||
| 3 | nothing on the driving path moved |
Who Is Responsible
17 are not explained by any attribution rule.
| Party | Working days | Share of the movement |
|---|---|---|
| Not explained | 17 | 100% |
| Total | 17 | 100% |
No working days are assigned to concurrent delay.
How Far the Figures Can Be Relied On
The attribution basis and every reading of the schedules are set out below.
Attribution basis: not stated.
Allocation Coverage
0% of the movement is allocated to a party; 17 working days are not explained by any rule.
Basis of Measurement
The Evidence
The exhibits behind these findings follow in full, each under its drawing code:
- A-01Windows Overview
- A-02Window Shift Trend
- A-03Cumulative Attribution Summary: every cause in each window
- A-04Concurrent Delay Matrix
- A-05Slip Velocity and Acceleration
- A-06Worked Versus On-Time Execution
- A-07Float Burndown Across Windows
- A-08Cumulative Activity Slip Register
- A-09Window 1 Detail: Baseline → Update 1
- A-10Window 2 Detail: Update 1 → Update 2
- A-11Window 3 Detail: Update 2 → Update 3
- A-12Provenance and Method
Windows Overview
per-window shift and cumulative vs baseline, working days| Window | Period | Shift (wd) | Cumulative vs Baseline (wd) | CP Activities | CP Duration Changes | Slipped Activities |
|---|---|---|---|---|---|---|
| Baseline → Update 1 | 03-Feb-2025 → 31-Mar-2025 | +8 wd | +8 wd | 17 | 1 | 26 |
| Update 1 → Update 2 | 31-Mar-2025 → 30-Jun-2025 | +7 wd | +15 wd | 11 | 0 | 24 |
| Update 2 → Update 3 | 30-Jun-2025 → 30-Sep-2025 | +2 wd | +17 wd | 3 | 0 | 14 |
Criticality test: TF ≤ 0, or the driving path in a schedule with negative float.
Window Shift Trend
signed completion shift per window (working days)Cumulative Attribution Summary
party share of project slip-daysConcurrent Delay Matrix
per-window × per-party attribution grid| Window | Period | Owner | Contractor | Concurrent | Force Majeure | Unattributed | Window Shift (wd) | Finish Driver |
|---|---|---|---|---|---|---|---|---|
| Baseline → Update 1 !UNATTRIBUTED | 03-Feb-2025 → 31-Mar-2025 | 0 | 0 | 0 | 0 | +8 wd | +8 wd | COM-DEMOB early_end_date |
| Update 1 → Update 2 ~CASCADE !UNATTRIBUTED | 31-Mar-2025 → 30-Jun-2025 | 0 | 0 | 0 | 0 | +7 wd | +7 wd | COM-DEMOB early_end_date |
| Update 2 → Update 3 ~CASCADE !UNATTRIBUTED | 30-Jun-2025 → 30-Sep-2025 | 0 | 0 | 0 | 0 | +2 wd | +2 wd | COM-DEMOB early_end_date |
| Cumulative | project totals | 0 wd | 0 wd | 0 wd | 0 wd | +17 wd | +17 wd | 0 |
Slip Velocity & Acceleration
per-window slip-rate trend| Window | Period | Duration (wd) | Shift (wd) | Velocity (wd/wd) | Δ Acceleration | Midpoint Date | Half-Period Slip (wd) |
|---|---|---|---|---|---|---|---|
| Baseline → Update 1 | 03-Feb-2025 → 31-Mar-2025 | 39 wd | +8 wd | +0.205 | 03-Mar-2025 | +4.0 wd | |
| Update 1 → Update 2 | 31-Mar-2025 → 30-Jun-2025 | 63 wd | +7 wd | +0.111 | ▼ -0.094 | 15-May-2025 | +3.5 wd |
| Update 2 → Update 3 | 30-Jun-2025 → 30-Sep-2025 | 63 wd | +2 wd | +0.032 | ▼ -0.079 | 15-Aug-2025 | +1.0 wd |
WOET: worked versus on-time execution timeline
4-state day classification| Code | Activity | Baseline Period | Actual Period | Progress (wd) | Gain (wd) | Extended (wd) | Void (wd) |
|---|---|---|---|---|---|---|---|
| MEC-PIPE | Internal Process Piping Install | 22-May-2025 to 16-Jun-2025 | 12-Jun-2025 to 16-Jul-2025 | 3 wd | 0 wd | 21 wd | 15 wd |
| ELE-COND | Conduit and Cable Tray Rough-In | 03-Jun-2025 to 20-Jun-2025 | 24-Jun-2025 to 22-Jul-2025 | 0 wd | 0 wd | 20 wd | 14 wd |
| CIV-WALL | Form Reinforce and Pour Wet Well Walls | 09-Apr-2025 to 29-Apr-2025 | 22-Apr-2025 to 21-May-2025 | 6 wd | 0 wd | 15 wd | 8 wd |
| ELE-CABLE | Power and Control Cable Pull | 30-Jun-2025 to 16-Jul-2025 | 30-Jul-2025 to 15-Aug-2025 | 0 wd | 0 wd | 12 wd | 12 wd |
| ELE-PROC | MCC and VFD Fabrication and Delivery | 03-Feb-2025 to 24-Mar-2025 | 03-Feb-2025 to 09-Apr-2025 | 35 wd | 0 wd | 12 wd | 0 wd |
| BLD-ERECT | Erect Pre-Engineered Building Frame | 09-May-2025 to 23-May-2025 | 02-Jun-2025 to 13-Jun-2025 | 0 wd | 0 wd | 10 wd | 10 wd |
| CIV-SLAB | Grade Slab and Equipment Pads | 20-May-2025 to 29-May-2025 | 10-Jun-2025 to 19-Jun-2025 | 0 wd | 0 wd | 8 wd | 8 wd |
| MEC-SET | Set Pump Skids and Grout Baseplates | 09-May-2025 to 21-May-2025 | 02-Jun-2025 to 11-Jun-2025 | 0 wd | 0 wd | 8 wd | 8 wd |
| ELE-TERM | Terminate and Point-to-Point Check | 17-Jul-2025 to 28-Jul-2025 | 18-Aug-2025 to 27-Aug-2025 | 0 wd | 0 wd | 8 wd | 8 wd |
| BLD-CLAD | Wall Cladding and Flashing | 03-Jun-2025 to 12-Jun-2025 | 24-Jun-2025 to 04-Jul-2025 | 0 wd | 0 wd | 8 wd | 8 wd |
| COM-LOOP | Instrument Loop Checks | 06-Aug-2025 to 15-Aug-2025 | 05-Sep-2025 to 16-Sep-2025 | 0 wd | 0 wd | 8 wd | 8 wd |
| CIV-BASE | Form Reinforce and Pour Base Slab | 24-Mar-2025 to 08-Apr-2025 | 24-Mar-2025 to 21-Apr-2025 | 12 wd | 0 wd | 8 wd | 0 wd |
| CIV-CURE | Wall Cure and Strip Formwork | 30-Apr-2025 to 08-May-2025 | 22-May-2025 to 30-May-2025 | 0 wd | 0 wd | 7 wd | 7 wd |
| COM-FUNC | Functional Testing All Modes | 18-Aug-2025 to 29-Aug-2025 | 17-Sep-2025 to 24-Sep-2025 | 0 wd | 0 wd | 6 wd | 10 wd |
| CIV-BKF | Backfill and Compact Around Structure | 09-May-2025 to 16-May-2025 | 02-Jun-2025 to 09-Jun-2025 | 0 wd | 0 wd | 6 wd | 6 wd |
| MEC-VALVE | Valve and Actuator Install | 17-Jun-2025 to 24-Jun-2025 | 17-Jul-2025 to 24-Jul-2025 | 0 wd | 0 wd | 6 wd | 6 wd |
| BLD-ROOF | Roof Deck and Membrane | 26-May-2025 to 02-Jun-2025 | 16-Jun-2025 to 23-Jun-2025 | 0 wd | 0 wd | 6 wd | 6 wd |
| MEC-TEST | Hydrostatic Test Process Piping | 25-Jun-2025 to 02-Jul-2025 | 25-Jul-2025 to 31-Jul-2025 | 0 wd | 0 wd | 5 wd | 5 wd |
| ELE-MCC | Set MCC and VFD Line-Up | 23-Jun-2025 to 27-Jun-2025 | 23-Jul-2025 to 29-Jul-2025 | 0 wd | 0 wd | 5 wd | 5 wd |
| COM-FLUSH | System Flush and Chlorination | 29-Jul-2025 to 05-Aug-2025 | 28-Aug-2025 to 04-Sep-2025 | 0 wd | 0 wd | 5 wd | 5 wd |
| COM-PERF IN-PROGRESS | Performance and Capacity Demonstration | 02-Sep-2025 to 08-Sep-2025 | 25-Sep-2025, open | 0 wd | 0 wd | 4 wd | 5 wd |
| BLD-DOOR | Overhead Doors and Louvres | 13-Jun-2025 to 18-Jun-2025 | 07-Jul-2025 to 10-Jul-2025 | 0 wd | 0 wd | 4 wd | 4 wd |
| MS-CONC | Concrete Structure Complete | 08-May-2025 to 08-May-2025 | 30-May-2025 to 30-May-2025 | 0 wd | 0 wd | 1 wd | 1 wd |
| MS-ENERG | Permanent Power Energized | 28-Jul-2025 to 28-Jul-2025 | 27-Aug-2025 to 27-Aug-2025 | 0 wd | 0 wd | 1 wd | 1 wd |
| COM-DEMOB | Demobilize and Turnover Documentation | 09-Sep-2025 to 11-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 3 wd |
| MS-SC | Substantial Completion | 11-Sep-2025 to 11-Sep-2025 | none | 0 wd | 0 wd | 0 wd | 1 wd |
| MS-NTP | Notice to Proceed | 03-Feb-2025 to 03-Feb-2025 | 03-Feb-2025 to 03-Feb-2025 | 1 wd | 0 wd | 0 wd | 0 wd |
| PRE-MOB | Mobilize Site Offices and Laydown | 03-Feb-2025 to 07-Feb-2025 | 03-Feb-2025 to 07-Feb-2025 | 5 wd | 0 wd | 0 wd | 0 wd |
| PRE-SHOP | Structural Shop Drawings and Review | 03-Feb-2025 to 24-Feb-2025 | 03-Feb-2025 to 24-Feb-2025 | 15 wd | 0 wd | 0 wd | 0 wd |
| PRE-PERMIT | Building Permit Issuance | 03-Feb-2025 to 03-Mar-2025 | 03-Feb-2025 to 03-Mar-2025 | 20 wd | 0 wd | 0 wd | 0 wd |
| CIV-EXC | Bulk Excavation Wet Well | 04-Mar-2025 to 17-Mar-2025 | 04-Mar-2025 to 17-Mar-2025 | 10 wd | 0 wd | 0 wd | 0 wd |
| CIV-SOE | Shoring and Dewatering Install | 10-Feb-2025 to 20-Feb-2025 | 10-Feb-2025 to 20-Feb-2025 | 8 wd | 0 wd | 0 wd | 0 wd |
| CIV-MUD | Mud Slab and Survey Layout | 18-Mar-2025 to 21-Mar-2025 | 18-Mar-2025 to 21-Mar-2025 | 4 wd | 0 wd | 0 wd | 0 wd |
| MEC-PROC | Pump Skid Fabrication and Delivery | 03-Feb-2025 to 31-Mar-2025 | 03-Feb-2025 to 31-Mar-2025 | 40 wd | 0 wd | 0 wd | 0 wd |
| BLD-PROC | Pre-Engineered Building Delivery | 03-Feb-2025 to 17-Mar-2025 | 03-Feb-2025 to 17-Mar-2025 | 30 wd | 0 wd | 0 wd | 0 wd |
Float Burndown Across Windows
per-activity float-erosion register, drawing-sheet exhibitCriticality predates the window: 17 of 23 activities opened at TF ≤ 0 at Baseline; none demonstrably crossed during 3 windows, while completion moved 17 working days later
Total float in working days (wd), read from the schedule of record at 4 CPM snapshots, Baseline through Update 3 spanning 3 windows, day math on the project working calendar. Criticality test: TF ≤ 0. Sign convention: negative Δ = float lost across the window. Finish driver COM-DEMOB; completion Baseline → Update 3: 17 wd later. Register bands: TF ≤ 0 · 1-5 wd (near-critical) · 6-20 wd · over 20 wd.
4 further activities first appear with one observation only. No second reading exists, so a loss of float cannot be demonstrated for them and is not claimed here.
conservation: 17 + 0 + 4 + 2 = 23 · reconciles to the register below
Reading notes
- Not plotted above: 23 activities with zero net float movement · 21 held TF ≤ 0 at every observation (17 observed at multiple snapshots, 4 single-observation) · 2 held constant positive float. All 23 appear in the register below.
- Baseline band counts in the inset carry the register convention: the 4 single-observation entrants are imputed at their only reading. The movement panel plots observed pairs only.
- The horizontal scale is linear to 5 wd; no section break is needed.
- Band deltas conserve across the population: 0 + 0 + 0 + 0 = 0 over 23 activities.
- 4 snapshots are plotted per row: the grey tick is the first observation, the dot the last, and small intermediate ticks mark each observation between them, so the trajectory is retained.
- Method caveat (cite in any expert report): Float burndown is post-processing of analyst-supplied CPM snapshots. Accuracy depends on the quality of the underlying schedule updates. Recovery events (TF increase) may reflect legitimate scope removal, schedule optimization, or activity deletion, and the register does not say which. Slip velocity is a linear average; actual burndown may be non-linear. The per-activity float-timeline presentation is not yet published in AACE/SCL literature; it is disclosed here as a CPP enhancement to the cited observational method.
Activity register · all 23 activities TF FIRST / LAST · Δ · FIRST AT TF ≤ 0
| Activity | TF at first obs (wd) | TF at last obs (wd) | Δ (wd) | First at TF ≤ 0 | Movement |
|---|---|---|---|---|---|
| BLD-ERECT | 0 | 0 | 0 | Baseline | no movement |
| BLD-ROOF | 0 | 0 | 0 | Baseline | no movement |
| CIV-BASE | 0 | 0 | 0 | Baseline | no movement |
| CIV-BKF | 2 | 2 | 0 | never | no movement |
| CIV-CURE | 0 | 0 | 0 | Baseline | no movement |
| CIV-EXC | 0 | 0 | 0 | Baseline | single observation |
| CIV-MUD | 0 | 0 | 0 | Baseline | single observation |
| CIV-SLAB | 2 | 2 | 0 | never | no movement |
| CIV-WALL | 0 | 0 | 0 | Baseline | no movement |
| COM-DEMOB | 0 | 0 | 0 | Baseline | no movement |
| COM-FLUSH | 0 | 0 | 0 | Baseline | no movement |
| COM-FUNC | 0 | 0 | 0 | Baseline | no movement |
| COM-LOOP | 0 | 0 | 0 | Baseline | no movement |
| COM-PERF | 0 | 0 | 0 | Baseline | no movement |
| ELE-CABLE | 0 | 0 | 0 | Baseline | no movement |
| ELE-COND | 0 | 0 | 0 | Baseline | no movement |
| ELE-MCC | 0 | 0 | 0 | Baseline | no movement |
| ELE-TERM | 0 | 0 | 0 | Baseline | no movement |
| MS-CONC | 0 | 0 | 0 | Baseline | no movement |
| MS-ENERG | 0 | 0 | 0 | Baseline | no movement |
| MS-NTP | 0 | 0 | 0 | Baseline | single observation |
| MS-SC | 0 | 0 | 0 | Baseline | no movement |
| PRE-PERMIT | 0 | 0 | 0 | Baseline | single observation |
Cumulative Activity Slip Register
sum of signed slip across all windows| Code | Activity | Total Slip | Windows Touched |
|---|---|---|---|
| MEC-PIPE | Internal Process Piping Install | +21 wd | 3 |
| MEC-VALVE | Valve and Actuator Install | +21 wd | 3 |
| MEC-TEST | Hydrostatic Test Process Piping | +21 wd | 3 |
| ELE-COND | Conduit and Cable Tray Rough-In | +21 wd | 3 |
| ELE-MCC | Set MCC and VFD Line-Up | +21 wd | 3 |
| ELE-CABLE | Power and Control Cable Pull | +21 wd | 3 |
| ELE-TERM | Terminate and Point-to-Point Check | +21 wd | 3 |
| MS-ENERG | Permanent Power Energized | +21 wd | 3 |
| COM-FLUSH | System Flush and Chlorination | +21 wd | 3 |
| COM-LOOP | Instrument Loop Checks | +21 wd | 3 |
| COM-FUNC | Functional Testing All Modes | +17 wd | 3 |
| COM-PERF CP | Performance and Capacity Demonstration | +17 wd | 3 |
| COM-DEMOB CP | Demobilize and Turnover Documentation | +17 wd | 3 |
| MS-SC CP | Substantial Completion | +17 wd | 3 |
| CIV-WALL | Form Reinforce and Pour Wet Well Walls | +15 wd | 2 |
| CIV-CURE | Wall Cure and Strip Formwork | +15 wd | 2 |
| MS-CONC | Concrete Structure Complete | +15 wd | 2 |
| CIV-BKF | Backfill and Compact Around Structure | +15 wd | 2 |
| CIV-SLAB | Grade Slab and Equipment Pads | +15 wd | 2 |
| MEC-SET | Set Pump Skids and Grout Baseplates | +15 wd | 2 |
| BLD-ERECT | Erect Pre-Engineered Building Frame | +15 wd | 2 |
| BLD-ROOF | Roof Deck and Membrane | +15 wd | 2 |
| BLD-CLAD | Wall Cladding and Flashing | +15 wd | 2 |
| BLD-DOOR | Overhead Doors and Louvres | +15 wd | 2 |
| ELE-PROC | MCC and VFD Fabrication and Delivery | +12 wd | 1 |
| CIV-BASE | Form Reinforce and Pour Base Slab | +8 wd | 1 |
Window 1: Baseline → Update 1
03-Feb-2025 → 31-Mar-2025 · shift +8 wd| Code | Activity | Prior Duration | Later Duration | Change (wd) |
|---|---|---|---|---|
| CIV-BASE | Form Reinforce and Pour Base Slab | 12 wd | 20 wd | +8 wd |
| Code | Activity | Prior Finish | Later Finish | Slip | Responsible Party | Cause Notes |
|---|---|---|---|---|---|---|
| ELE-PROC | MCC and VFD Fabrication and Delivery | 24-Mar-2025 | 09-Apr-2025 | +12 wd | assign | add notes |
| CIV-BASE CP | Form Reinforce and Pour Base Slab | 08-Apr-2025 | 21-Apr-2025 | +8 wd | assign | add notes |
| CIV-WALL CP | Form Reinforce and Pour Wet Well Walls | 29-Apr-2025 | 09-May-2025 | +8 wd | assign | add notes |
| CIV-CURE CP | Wall Cure and Strip Formwork | 08-May-2025 | 21-May-2025 | +8 wd | assign | add notes |
| MS-CONC CP | Concrete Structure Complete | 08-May-2025 | 21-May-2025 | +8 wd | assign | add notes |
| CIV-BKF | Backfill and Compact Around Structure | 16-May-2025 | 29-May-2025 | +8 wd | assign | add notes |
| CIV-SLAB | Grade Slab and Equipment Pads | 29-May-2025 | 10-Jun-2025 | +8 wd | assign | add notes |
| MEC-SET | Set Pump Skids and Grout Baseplates | 21-May-2025 | 02-Jun-2025 | +8 wd | assign | add notes |
| MEC-PIPE | Internal Process Piping Install | 16-Jun-2025 | 26-Jun-2025 | +8 wd | assign | add notes |
| MEC-VALVE | Valve and Actuator Install | 24-Jun-2025 | 07-Jul-2025 | +8 wd | assign | add notes |
| MEC-TEST | Hydrostatic Test Process Piping | 02-Jul-2025 | 14-Jul-2025 | +8 wd | assign | add notes |
| ELE-COND CP | Conduit and Cable Tray Rough-In | 20-Jun-2025 | 03-Jul-2025 | +8 wd | assign | add notes |
| ELE-MCC CP | Set MCC and VFD Line-Up | 27-Jun-2025 | 10-Jul-2025 | +8 wd | assign | add notes |
| ELE-CABLE CP | Power and Control Cable Pull | 16-Jul-2025 | 28-Jul-2025 | +8 wd | assign | add notes |
| ELE-TERM CP | Terminate and Point-to-Point Check | 28-Jul-2025 | 08-Aug-2025 | +8 wd | assign | add notes |
| MS-ENERG CP | Permanent Power Energized | 28-Jul-2025 | 08-Aug-2025 | +8 wd | assign | add notes |
| BLD-ERECT CP | Erect Pre-Engineered Building Frame | 23-May-2025 | 04-Jun-2025 | +8 wd | assign | add notes |
| BLD-ROOF CP | Roof Deck and Membrane | 02-Jun-2025 | 12-Jun-2025 | +8 wd | assign | add notes |
| BLD-CLAD | Wall Cladding and Flashing | 12-Jun-2025 | 24-Jun-2025 | +8 wd | assign | add notes |
| BLD-DOOR | Overhead Doors and Louvres | 18-Jun-2025 | 30-Jun-2025 | +8 wd | assign | add notes |
| COM-FLUSH CP | System Flush and Chlorination | 05-Aug-2025 | 15-Aug-2025 | +8 wd | assign | add notes |
| COM-LOOP CP | Instrument Loop Checks | 15-Aug-2025 | 27-Aug-2025 | +8 wd | assign | add notes |
| COM-FUNC CP | Functional Testing All Modes | 29-Aug-2025 | 11-Sep-2025 | +8 wd | assign | add notes |
| COM-PERF CP | Performance and Capacity Demonstration | 08-Sep-2025 | 18-Sep-2025 | +8 wd | assign | add notes |
| COM-DEMOB CP | Demobilize and Turnover Documentation | 11-Sep-2025 | 23-Sep-2025 | +8 wd | assign | add notes |
| MS-SC CP | Substantial Completion | 11-Sep-2025 | 23-Sep-2025 | +8 wd | assign | add notes |
Window 2: Update 1 → Update 2
31-Mar-2025 → 30-Jun-2025 · shift +7 wd| Code | Activity | Prior Finish | Later Finish | Slip | Responsible Party | Cause Notes |
|---|---|---|---|---|---|---|
| CIV-WALL | Form Reinforce and Pour Wet Well Walls | 09-May-2025 | 21-May-2025 | +7 wd | assign | add notes |
| CIV-CURE | Wall Cure and Strip Formwork | 21-May-2025 | 30-May-2025 | +7 wd | assign | add notes |
| MS-CONC | Concrete Structure Complete | 21-May-2025 | 30-May-2025 | +7 wd | assign | add notes |
| CIV-BKF | Backfill and Compact Around Structure | 29-May-2025 | 09-Jun-2025 | +7 wd | assign | add notes |
| CIV-SLAB | Grade Slab and Equipment Pads | 10-Jun-2025 | 19-Jun-2025 | +7 wd | assign | add notes |
| MEC-SET | Set Pump Skids and Grout Baseplates | 02-Jun-2025 | 11-Jun-2025 | +7 wd | assign | add notes |
| MEC-PIPE | Internal Process Piping Install | 26-Jun-2025 | 08-Jul-2025 | +7 wd | assign | add notes |
| MEC-VALVE | Valve and Actuator Install | 07-Jul-2025 | 16-Jul-2025 | +7 wd | assign | add notes |
| MEC-TEST | Hydrostatic Test Process Piping | 14-Jul-2025 | 23-Jul-2025 | +7 wd | assign | add notes |
| ELE-COND CP | Conduit and Cable Tray Rough-In | 03-Jul-2025 | 14-Jul-2025 | +7 wd | assign | add notes |
| ELE-MCC CP | Set MCC and VFD Line-Up | 10-Jul-2025 | 21-Jul-2025 | +7 wd | assign | add notes |
| ELE-CABLE CP | Power and Control Cable Pull | 28-Jul-2025 | 07-Aug-2025 | +7 wd | assign | add notes |
| ELE-TERM CP | Terminate and Point-to-Point Check | 08-Aug-2025 | 19-Aug-2025 | +7 wd | assign | add notes |
| MS-ENERG CP | Permanent Power Energized | 08-Aug-2025 | 19-Aug-2025 | +7 wd | assign | add notes |
| BLD-ERECT | Erect Pre-Engineered Building Frame | 04-Jun-2025 | 13-Jun-2025 | +7 wd | assign | add notes |
| BLD-ROOF | Roof Deck and Membrane | 12-Jun-2025 | 23-Jun-2025 | +7 wd | assign | add notes |
| BLD-CLAD | Wall Cladding and Flashing | 24-Jun-2025 | 04-Jul-2025 | +7 wd | assign | add notes |
| BLD-DOOR | Overhead Doors and Louvres | 30-Jun-2025 | 10-Jul-2025 | +7 wd | assign | add notes |
| COM-FLUSH CP | System Flush and Chlorination | 15-Aug-2025 | 26-Aug-2025 | +7 wd | assign | add notes |
| COM-LOOP CP | Instrument Loop Checks | 27-Aug-2025 | 08-Sep-2025 | +7 wd | assign | add notes |
| COM-FUNC CP | Functional Testing All Modes | 11-Sep-2025 | 22-Sep-2025 | +7 wd | assign | add notes |
| COM-PERF CP | Performance and Capacity Demonstration | 18-Sep-2025 | 29-Sep-2025 | +7 wd | assign | add notes |
| COM-DEMOB CP | Demobilize and Turnover Documentation | 23-Sep-2025 | 02-Oct-2025 | +7 wd | assign | add notes |
| MS-SC CP | Substantial Completion | 23-Sep-2025 | 02-Oct-2025 | +7 wd | assign | add notes |
Window 3: Update 2 → Update 3
30-Jun-2025 → 30-Sep-2025 · shift +2 wd| Code | Activity | Prior Finish | Later Finish | Slip | Responsible Party | Cause Notes |
|---|---|---|---|---|---|---|
| MEC-PIPE | Internal Process Piping Install | 08-Jul-2025 | 16-Jul-2025 | +6 wd | assign | add notes |
| MEC-VALVE | Valve and Actuator Install | 16-Jul-2025 | 24-Jul-2025 | +6 wd | assign | add notes |
| MEC-TEST | Hydrostatic Test Process Piping | 23-Jul-2025 | 31-Jul-2025 | +6 wd | assign | add notes |
| ELE-COND | Conduit and Cable Tray Rough-In | 14-Jul-2025 | 22-Jul-2025 | +6 wd | assign | add notes |
| ELE-MCC | Set MCC and VFD Line-Up | 21-Jul-2025 | 29-Jul-2025 | +6 wd | assign | add notes |
| ELE-CABLE | Power and Control Cable Pull | 07-Aug-2025 | 15-Aug-2025 | +6 wd | assign | add notes |
| ELE-TERM | Terminate and Point-to-Point Check | 19-Aug-2025 | 27-Aug-2025 | +6 wd | assign | add notes |
| MS-ENERG | Permanent Power Energized | 19-Aug-2025 | 27-Aug-2025 | +6 wd | assign | add notes |
| COM-FLUSH | System Flush and Chlorination | 26-Aug-2025 | 04-Sep-2025 | +6 wd | assign | add notes |
| COM-LOOP | Instrument Loop Checks | 08-Sep-2025 | 16-Sep-2025 | +6 wd | assign | add notes |
| COM-FUNC | Functional Testing All Modes | 22-Sep-2025 | 24-Sep-2025 | +2 wd | assign | add notes |
| COM-PERF CP | Performance and Capacity Demonstration | 29-Sep-2025 | 01-Oct-2025 | +2 wd | assign | add notes |
| COM-DEMOB CP | Demobilize and Turnover Documentation | 02-Oct-2025 | 06-Oct-2025 | +2 wd | assign | add notes |
| MS-SC CP | Substantial Completion | 02-Oct-2025 | 06-Oct-2025 | +2 wd | assign | add notes |