The general contractor on a multi-phase recreation and community centre project was experiencing persistent schedule slippage across multiple work areas. The project completion date had drifted significantly from the original baseline, but the contractor had no clear documentation tying the delays to specific causes or responsible parties.
Without that analysis, pursuing a delay claim felt like a gamble — and doing nothing meant absorbing the costs.
Critical Path Partners performed a full contemporaneous windows analysis across 7 analysis periods, parsing 8 schedule updates from the contractor's Primavera P6 data. The analysis followed AACE RP 29R-03 methodology — the industry standard for forensic delay analysis — ensuring the findings would hold up in mediation, arbitration, or litigation.
The analysis revealed 85 working days of cumulative, unmitigated delay with zero recovery across any analysis window. Every delay was traceable to specific work areas and schedule updates — not assumptions or estimates. The contractor received a clear, defensible picture of what happened, when, and why.
Armed with that analysis, they had the documentation needed to pursue a formal Extension of Time claim with confidence, backed by methodology that would withstand independent review.
We offer a fixed-fee preliminary assessment — a straight answer in as little as two weeks. No long-term commitment. No hourly burn. Just a clear picture.
Schedule a 15-Minute Consultation → Or email Dana directly →